05 - 12 - 00 - 00 (05120) - Steel Framing
05 - 12 - 00 - 00 (05120) - Steel Framing
05 - 12 - 00 - 00 (05120) - Steel Framing
PART 1 - GENERAL
1.3 REFERENCES
A. Welders’ and tackers’ qualifications and welding procedures for structural elements not part of the
seismic force resisting system (SRFS) shall be in accordance with AWS D1.1. Welding procedures for
structural elements that are part of the SFRS shall be in accordance with AWS D1.8.
D. High-strength bolts, headed concrete anchors, and shear connector studs shall be ICC-approved.
A. Fabricator and their subcontractors are responsible for Quality Control and Quality Assurance at the
fabrication facility as defined in AWS D1.1 for weld and NDT inspection.
B. NDT testing shall be done by an independent testing agency sourced by the fabricator and their
subcontractors that have all appropriate certifications and accreditations, ASTM E329, SNT-TC-1A,
level II UT/MT, and shall be approved by the EOR/AHJ.
C. Fabricator and their subcontractors shall ensure all quality control and assurance is sourced, certification
is up to date, and records are available that fulfill design, code and specification requirements prior to
scheduling owner inspection.
D. Fabricator and their subcontractors shall maintain approved plans, specifications, and RFIs that are
readily available when requested for owner inspector’s reference at any point during the owner
inspection or fabrication.
E. Erector is responsible for Quality Control with personnel assigned or dedicated to the role.
A. Prior to performing any fabrication work, a preliminary plant inspection shall be performed by the EOR,
Owner, or the owner’s third-party quality assurance inspection agency, together with the steel
fabricator’s QA/QC personnel. This shall include any work that is subcontracted out to another
fabricator. All items of concern identified during the preliminary plant inspection shall be addressed
prior to start of fabrication at the Owner’s discretion.
B. Prior to start of structural steel erection, a preconstruction meeting shall be performed by the EOR,
Owner, and the owner’s third-party quality assurance inspection agency, authority having jurisdiction
(AHJ) and the structural steel erection contractor. The preconstruction meeting shall review the overall
scope of work, plans, specifications, pertinent submittals and shop drawings, subcontractor
A. Structural steel and fabricated accessories shall be delivered to the site and marked with a piece number.
B. Steel shall be stored on dunnage and covered as needed in order to avoid damage or decay to finished
product.
1.9 SUBMITTALS
A. Required submittals:
Table 1.1 – Required Submittals
NO. REQUIREMENT
1. Mill test reports indicating piece numbers and certifying physical and chemical
properties for each heat of Grade 50 structural steel.
2. Shop and erection drawings showing piece numbers, grades, profiles, sizes,
dimensions, fasteners, welds, holes, hole types, special painting, paint masking,
cambers, positions, spacing, welding processes, and connections.
3. For structural steel members and connections indicated to comply with design
loads, include structural analysis data and substantiating test data signed and sealed
by the qualified professional engineer responsible for their preparation.
Calculations, plans and details for Buckling Restrained Braces signed and sealed by
a Structural Engineer registered in the jurisdiction where project is located.
4. Mill test reports certifying physical and chemical properties for each lot of A325
and A490 bolts and accompanying nuts and washers.
5. A copy of welders’ certifications.
6. Inspection reports concerning fabrication and erection of structural steel.
7. Test and inspection reports concerning welding and high-strength bolt tightening.
8. Certification that welding electrodes, fluxes and shielding gasses comply with AWS
A5 requirements and any additional requirements.
9. Certification for headed concrete anchors.
10. Fastener installation procedures outlining pre-installation testing, installation,
snugging, pretensioning, and post-installation inspection of fasteners, complying
with all requirements of the RCSC specification.
11. Welding procedure specifications for all welding procedures, including supporting
procedure qualification records for procedures not prequalified, and including
product data sheets for all welding material to be used.
12. Written qualifications for all inspectors assigned Quality Control functions for the
structural steel work.
13. Written Quality Control plan.
14. Written qualifications for all inspectors assigned Quality Assurance functions for
the structural steel work.
15. Written Quality Assurance plan.
16. Meeting minutes of pre-fabrication and pre-erection conference.
PART 2 - PRODUCTS
2.1 MATERIALS
B. Steel Shapes (other than Wide Flange and Tees), Plates, and Bars: ASTM A36 or A572, Grade 50 as
shown on the Drawings. Plates greater than 2 inches in thickness shall be tested for Charpy V-notch
toughness in accordance with ASTM A6 supplementary requirement S5, and shall meet a minimum
average absorbed energy value of 20 ft-lb at 70 degrees F.
D. Round and Rectangular Hollow Structural Sections: ASTM A500, Grade B or ASTM A1085.
E. Buckling Restrained Braced Frames: Materials complying with tested assemblies demonstrating
conformance with requirements of ANSI/AISC 341.
G. High-strength Hex Head Bolts with Heavy Hex Nuts: ASTM A325 or A490 as shown on the Drawings.
All A325 bolts used in exterior applications shall be hot dipped galvanized per ASTM A153.
All A490 bolts used in exterior applications shall be Dacromet coated per ASTM F1136.
H. Anchor Bolts: ASTM F1554 Grade 36, 55, or 105 as shown on the Drawings.
O. Direct Tension Indicator Washers: ASTM F959; Standard DTI or Squirter DTI by Applied Bolting
Technology.
Squirter DTIs shall not be used for steel that shall be in the clean air stream.
Q. Shear Connector Studs and Headed Concrete Anchors: ASTM A108, Grade 1015 through 1020, cold-
finished carbon steel in conformance with AWS D1.1 by Nelson Stud Welding, Inc., Stud Welding
Associates, Inc., Tru-Weld Division of TFP Corporation, or Continental Studwelding Ltd.
For shear reinforcing composed of stud rails made from plate and studs, use only PSR studs from Nelson Stud
Welding, Inc.
R. Welding Filler Metal: AWS A5.1 or A5.5 E70XX for SMAW welding process, AWS A5.18 or A5.28
ER70S-X for GMAW welding process, AWS A5.17 or A5.23 F7X-EXXX for SAW welding process,
and AWS A5.20 or A5.29 E7XT-X for FCAW welding process. Electrodes shall be low-hydrogen type
or equivalent. All weld filler metal used in the seismic force resisting system as noted on the drawings
shall satisfy the following additional requirements:
CVN toughness of 20 ft-lb at 0 degrees F or lower when tested in accordance with AWS A5.
For demand critical welds, CVN toughness of 40 ft-lb at 70 degrees F or lower when tested in accordance with
AWS D1.8 Annex A.
Yield strength of 58 ksi minimum when tested per AWS A5 for E70 electrodes and also when tested in
accordance with AWS D1.8.
Tensile strength of 70 ksi minimum when tested per AWS A5 for E70 electrodes and also when tested in
accordance with AWS D1.8.
Elongation of 22 percent minimum when tested per AWS A5 for E70 electrodes and also when tested in
accordance with AWS D1.8.
Hydrogen level meeting requirements for H16 as tested using the mercury or gas chromatograph method as
specified in AWS A4.3.
S. Standard Prime Paint: For steel not to receive fireproofing, as specified in Section 09_91_13_00(09915).
T. Fireproofing Prime Paint: For structural steel that is to receive spray applied fireproofing Type 5, primer
as specified in Section 09_91_13_00(09915), Painting Application Schedule for structural steel with
Type 5 fireproofing.
V. Zinc Compound for Field Repair of Hot-Dip Galvanized Surfaces: Must meet FS DOD-P-21035A with a
minimum zinc content of 94%; ZRC Cold Galvanizing Compound by ZRC Worldwide. This product is
not to be applied within the clean air stream.
A. Structural steel shall be completely shop fabricated, except as otherwise shown on the Drawings.
B. All steel other than A36 shall be clearly identified according to grade.
D. Structural steel shall conform accurately to the shape and dimensions as shown on the Drawings within
the allowable tolerances as defined in AISC Code of Standard Practice, except as shown on the
Drawings and as described in the following cases:
Craneway support girders:
Elevation: 1/4 inch in 20 feet and 3/8 inch above or below specified elevation.
Girder to Girder Elevation: 1/4 inch in 20 feet and 1/4 inch above or below the opposite girder.
Stocker bracing beams:
Horizontal sweep: No larger than AISC tolerance of 9/16 inch.
E. Cuts, holes, and openings shown on the Contract Documents shall also be shown on the shop drawings
for structural steel and shall be shop fabricated.
F. Sheared and thermal cut edges shall be true to line and free from rough corners and projections per
Chapter M of AISC 360.
G. Reentrant cuts or corners shall be filleted to a radius of not less than 1/2 inch.
H. Holes shall be punched, sub-punched and reamed, or drilled at right angles to the surface of the metal, in
accordance with AISC, “Specifications for Structural Steel Buildings.” Burrs that would prohibit solid
seating of the connected parts shall be removed. Holes made by flame, plasma or thermal cutting shall be
permitted so long as the surface roughness profile does not exceed 1000 micro-inches and gouges do not
exceed a depth of 1/16 inch.
I. Holes shall be 1/16 inch larger than the nominal bolt diameter, except where short, slotted, long-slotted,
or oversize holes are permitted by AISC 360 and are indicated on the Drawings. Holes for cast-in-place
column base anchor bolts shall be a minimum of 5/16 inch larger than the nominal bolt diameter and
fitted with plate washers unless otherwise shown on the Drawings.
J. The use of oversize or slotted holes not shown on the Drawings shall be subject to prior review by the
EOR.
K. Bent plate shall be in accordance with AISC, Steel Construction Manual, Table 10-12.
L. Column ends bearing upon base and cap plates and beam ends with end plates shall be saw-cut,
thermally cut by machine or milled to true surfaces and correct bevels.
M. Column base plate bearing surfaces on plates 2 inches or more in thickness shall be milled to true
surfaces except at surfaces to be grouted against.
N. Column caps and base plates and beam end plates shall have full contact when assembled.
O. Welding shall conform to AWS D1.1 and shall be performed in accordance with the appropriate weld
procedure specification for the joint.
Q. For all complete joint penetration and partial joint penetration groove welds subjected to ultrasonic
testing, a visible mark, “for UT,” shall be accurately placed on the steel a distance of 4 inches away from
the edge preparation.
S. Headed concrete anchors shall be shop welded in accordance with AWS C5.4 and AWS D1.1, or field-
welded in accordance with AWS.
T. Fabrication (holes, notches, etc.) not required by or shown on the Drawings shall be subject to prior
review by the EOR.
U. Weld access holes shall comply with AWS D1.1 and the following:
Provide weld access holes of adequate size to insure access for welding and inspection.
Weld access holes shall be a minimum length from the toe of the weld preparation to the end of the hole of 1.5
inches and be a minimum height of one inch.
The radii of the weld access hole shall be smooth and free of notches per Chapter M of AISC 360.
V. Weld tabs shall comply with AWS D1.1 and the following:
Weld tabs shall extend beyond the edge of the joint a distance equal to a minimum of the part thickness, but
not less than one inch.
Weld tabs at splices of heavy sections shall be removed and ground smooth to a finish of 500 micro-inches or
better. Gouges or notches shall satisfy the requirement of AWS D1.1.
W. Backing bars shall comply with AWS D1.1 and the following:
All tack welds attaching backing bars to the steel shall be made within the joint.
Backing bars at splices of heavy sections shall be removed. Where fusible backing is used, the root pass area
shall be back-gouged and back-welded until flush or with slight reinforcement, then ground smooth to a
surface roughness not to exceed 500 micro-inches. Gouges and notches shall satisfy the requirements of
AWS D1.1.
Backing bars shall be removed where noted on the Drawings.
X. When notch-toughness is specified, the process consumables for all weld metal, tack welds, root pass
and subsequent passes, deposited in a joint shall be compatible to assure notch-tough composite weld
metal.
Y. Fillet welds and groove welds exposed to view shall have as-welded surfaces that meet the visually
acceptable requirements of AWS D1.1 except for groove welds in butt joints shall not project more than
1/16 inch above the exposed surface.
2.3 FINISHES
A. Structural steel shall be prime painted as shown on the Drawings and specified in Section
09_91_13_00(09915), System P-4, except for the following which shall be bare:
Surfaces and anchors encased in concrete.
Surfaces to be grouted against.
Faying surfaces at high-strength slip-critical bolted (A325SC or A490SC) connections.
Surfaces to be finish painted.
B. Faying surfaces, surfaces to be welded, etc. shall be touch-up painted with specified finish after bolting
and welding is complete.
C. Faying surfaces at high-strength slip-critical bolted connections shall be prepared as for Class A or better
slip-critical joints unless noted otherwise on the Drawings.
D. Structural steel, where shown on the Drawings to receive Type 5 spray-applied fireproofing shall be
painted as specified in Section 09_91_13_00(09915), System P-35.
E. Structural steel, where shown on the Drawings to be epoxy acrylic painted, shall be painted per Section
09_91_13_00(09915), System P-33.
F. Exterior exposed structural steel shall be Hot-Dip Galvanized unless otherwise indicated on the
Drawings:
Hot-dip galvanizing of metal fabrications shall be in conformance with ASTM A123 and A385.
Hot-dip galvanizing of metal fasteners shall be in conformance with ASTM A153 and A385.
Provide thickness of galvanizing specified in referenced standards not less than 2.0 ounces/square foot of
surface area or minimum thickness of 3.4 mils.
Fabricate units (including shearing, punching, bending, forming or welding) complete or in largest practical
sections before hot-dip galvanizing. Thoroughly clean welded areas prior to hot-dip galvanizing.
Remove weld spatter, burrs, oil, grease and other deleterious matter that would interfere with the
adherence of the zinc.
Safeguarding against warping and distortion during hot-dip galvanizing of metal fabrications shall be in
conformance with ASTM A384.Touch-up any areas where shop coat has been damaged in accordance
with ASTM A780 using approved material from Section 2.1.
Where new welded connections are made to existing galvanized steel, remove existing hot-dipped galvanized
finish prior to welding and repair after welding with galvanized repair compound.
Provide touch-up to existing galvanized finish where new holes are drilled into existing galvanized framing.
Seal weld cap plates and penetrations at galvanized exterior steel tubes to resist water infiltration and provide
weep holes at low points of tubes.
Plug galvanizing vent holes flush with tapered aluminum plugs.
G. Structural steel, where shown on the Drawings to be polyurethane painted, shall be painted per Section
09_91_13_00(09915), System P-13.
H. Structural steel, where shown on the Drawings to be powder-coated, shall be painted per Section
09_91_13_00(09915), System P-37.
I. Surfaces to be welded shall be protected from painting and galvanizing by use of masking unless a
weldable primer is used. Inadvertent overspray on surfaces to be welded shall be removed by wire
brushing.
B. All fabricator shops shall have a preliminary plant inspection conducted by the owner’s third-party
independent inspection agency. All non-conformances shall be corrected prior to start of fabrication.
Approved fabricator status is subject to the authority having jurisdiction (AHJ) approval.
C. Contractor shall cooperate fully with requests from inspection and testing personnel for access to
connections and joints to be inspected or tested, including turning members and removing backing
material where required or where a rejectable condition is indicated.
D. Inspection of headed concrete anchor welding shall be in accordance with AWS D1.1 and the IBC.
E. A minimum of 10 percent of headed concrete anchors shall be tested in accordance with AWS D1.1.
I. Contractor shall correct all deficiencies in material or workmanship. Where repairs alter the members as
dimensioned and detailed on the shop drawings by notching or removing base material, such repairs
shall be submitted for review by the EOR and Intel.
PART 3 - EXECUTION
3.1 PREPARATION
A. At the time of connecting, all bearing surfaces shall be free from loose or non-adherent rust, loose mill
scale, oil, grease, dirt, mud, and any foreign matter, coating, or defect that adversely affects the
connection.
B. Fasteners shall be stored in a protected place. Clean and re-lubricate bolts, nuts and washers that become
dry or rusty before use. Re-lubricate F1852 fastener components following the manufacturer’s written
instructions, and retest after lubrication and prior to use to verify suitability for installation.
C. Surface preparation for welding shall be in accordance with AWS D1.1, except loose or non-adherent
rust, loose mill scale, and paint shall be removed by wire brushing.
D. Structural steel shall be stored and handled in a manner that prevents damage or distortion.
A. Structural steel shall be located and erected/placed so as to conform accurately with the Drawings within
the allowable tolerances as defined in AISC Code of Standard Practice, except as shown on the
Drawings and as described in the following cases:
Craneway support girders:
Elevation: 1/4 inch in 20 feet, and 3/8 inch above or below specified elevation.
Girder-To-Girder Elevation: 1/4 inch in 20 feet, and 1/4 inch above or below the opposite girder.
Stocker bracing beams:
Horizontal: plus/minus 1/16 inch.
Vertical: plus/minus 1/4 inch.
Beams adjacent to elevator openings:
Horizontal: plus (towards opening) 1/2 inch, no limit on minus.
B. Where erection requires performing fabrication work on site, this work shall conform to applicable
standards for fabrication.
C. Connections shall be as shown on the Drawings. Connections and splices not shown on the Drawings
shall be subject to prior review by the EOR.
D. High-strength bolts shall be installed and tightened in accordance with RCSC/AISC Specification for
Structural Joints Using High Strength Bolts.
F. Connection parts in connections that are not slip joints or using load indicator washers shall be properly
drawn together and the bolts initially tightened to the snug-tight condition, with tightening in the
connection beginning at the most rigid or stiffest point and progressing toward the free edges. Load
indicator washers shall be installed and the bolts tightened so that the washer protrusions flatten in
accordance with the manufacturer’s written instructions and specifications.
G. Load indicator washer protrusions shall face the bolt head or nut that it is under and bear against a
hardened surface bolt head or hardened washer. Bearing against the steel or nut is not permitted.
I. Standard bolt heads and nuts at oversized and slotted holes shall be provided with washers in accordance
with ANSI B13.22.1.
J. High-strength bolt heads and nuts at oversized and slotted holes shall be provided with hardened washers
in accordance with ASTM F436. Load indicator washers shall not be substituted for these required
washers.
K. Bolt heads and nuts at sloped surfaces shall be provided with beveled washers.
L. Welding shall conform to AWS D1.1 and shall be performed in accordance with the appropriate weld
procedure specification for the joint.
O. Shear connector stud spacing shall be as shown in the Drawings within the limits established by the
AISC Specifications for Structural Steel. Do not use more than one stud per rib where the number of
studs required is less than or equal to the number of ribs available. Where the number of studs required
exceeds the number of ribs available, place a minimum of one stud per rib full length of the beam and
place additional studs (no more than two per rib total) in each rib beginning at the supports at each end
and moving toward mid-span until required number of studs is supplied.
P. Holes that shall be enlarged to admit bolts shall be reamed. Do not enlarge holes by more than 1/32 inch
without approval of the EOR. Where holes are reamed beyond 1/32 inch, drill or ream to the next largest
hole size and use the next larger bolt size. If hole shall be enlarged by flame cutting, finished hole shall
be true to line and free from rough corners and projections per Chapter M of AISC 360.
Q. Field correcting by flame cutting shall be subject to prior review by the EOR.
R. No members of the seismic force resisting system shall be cut or altered to correct fabrication errors or
for the work of other trades without prior approval of the EOR. Submit detailed documentation outlining
exact location, reasons for change, and details of proposed work. Work shall be performed in accordance
with the requirements of the Contract Documents.
S. Filler or shim plates shall be furnished and installed by the subcontractor to provide alignment of
members where required due to mill or fabrication tolerances.
T. Weld tabs shall comply with AWS D1.1 and the following:
Weld tabs shall extend beyond the edge of the joint a distance equal to a minimum of the part thickness, but
not less than one inch.
Weld tabs at splices of heavy sections shall be removed and ground smooth to a finish of 500 micro-inches or
better. Gouges or notches shall satisfy the requirement of AWS D1.1.
U. Backing bars shall comply with AWS D1.1 and the following:
All tack welds attaching backing bars to the steel shall be made within the joint.
Backing bars at splices of heavy sections shall be removed. Where fusible backing is used, the root pass area
shall be back-gouged and back-welded until flush or with slight reinforcement, then ground smooth to a
surface roughness not to exceed 500 micro-inches. Gouges and notches shall satisfy the requirements of
AWS D1.1.
Backing bars shall be removed where noted on the Drawings.
V. When notch-toughness is specified, the process consumables for all weld metal, tack welds, root pass
and subsequent passes, deposited in a joint shall be compatible to assure notch-tough composite weld
metal.
W. Fillet welds and groove welds exposed to view shall have as-welded surfaces that meet the visually
acceptable requirements of AWS D1.1 except for groove welds in butt joints shall not project more than
1/16 inch above the exposed surface.
A. Structural steel shall be inspected by the special inspector as indicated on drawings after erection.
B. Inspection of welding shall be in accordance with AWS D1.1 and the IBC with all welds visually
C. Contractor shall cooperate fully with requests from inspection and testing personnel for access to
connections and joints to be inspected or tested, including removing backing material where required or
where a rejectable condition is indicated. Contractor shall provide access via lift, platforms, scaffolding
or other method as required to perform the inspection safely.
D. Welders and welding operators performing work on complete penetration demand-critical welds of
elements of the seismic force resisting system shall pass supplemental welder qualification testing as
required by AWS D1.8, under conditions and procedures comparable to the work, at the highest
deposition rate to be used in the work. FCAW-S and FCAW-G shall be considered separate processes for
welding personnel qualification
E. Inspection of shear connector stud welding shall be in accordance with AWS D1.1 and the IBC.
I. Contractor shall correct all deficiencies in material or workmanship. Where repairs alter the members as
dimensioned and detailed on the shop drawings by notching or removing base material, such repairs
shall be submitted for review by the EOR.
A. Abraded and scarred areas and connections on painted surfaces exposed to view shall be repaired with
the same kind of paint and with a minimum dry film thickness equal to that previously applied to the
steel. Conform to preparation, application and protection requirements of Section 09_91_13_00(09915).
END OF SECTION