Cost Estimate Part 1 (Estimate)
Cost Estimate Part 1 (Estimate)
Cost Estimate Part 1 (Estimate)
CONSTRUCTION
BUILDING ESTIMATE
WITH AID OF MICROSOFT EXCEL & AUTOCAD
P R E S E N T E D B Y:
DAY ONE
JANUARY 17, 2021
EXPECTATIONS FOR THE TRAINING
❑ To learn professionally.
❑ To be able to create a
précised Bill of Materials
and Quantity.
❑ To learn the field of quantity
surveyor/estimator.
❑ To be able to minimize the
errors in construction
management.
PRINCIPLES
ESTIMATES
W H AT I S C O S T E S T I M AT E ? PROVIDE DESION MAKERS/ ALTERATIVES
FOR THE PROJECT
Cost estimation in project management is the
process of forecasting the cost and other resources
needed to complete a project within a defined scope.
Cost estimation accounts for each element required
for the project and calculates a total amount that PRECISE/DETAILED BASIS OF LIST OF
determines a project’s budget. COST
OF ESTIMATES • A preliminary estimate allows a contractor to figure out the budget for a
project and what to charge the client.
• Used to study the feasibility of the project also.
• Used when the design plans is 35% to 50 % complete and is used to
check if the proposed project is on budget.
For example, a roofer is asked by a client to redo the roof of his house. The
roofer did a very similar project three months ago. He uses the estimate from
his old project to make a preliminary estimate for his new project.
OF ESTIMATES the line items are added together to reach the final cost.
• It includes a list of quantities for all materials needed to complete a project.
Its purpose is to give the client a complete list of all the quantities required
for the project and what the cost will be for each quantity. It is a key
estimating method in construction.
• They are prepared from a complete or nearly complete set of drawings
and are the most accurate type of estimate.
• Besides these line items, detailed estimates can also include:
• Information on the rates used to calculate costs (see quantity estimate
below)
• Specifications
• Drawings for the areas included in the project (including an index
and key)
• Detailed estimates are often used as a contractor’s budget estimate.
This planning tool helps him know how much cash flow he needs and
whether he requires financing.
3. BID ESTIMATE
OF ESTIMATES method if she believes her chance of winning the bid is high. Otherwise,
it’s a waste of her time.
• A bid estimate can be drawn up based on plans provided by the client or
on standard industry costs. If the contractor wants more accurate
amounts, she will need to calculate specific labor, material and equipment
costs for the project.
• For example, a landscaper is hired to redo the backyard of a client’s
house. He uses his hourly wage and material costs to arrive at a total for a
bid estimate. The landscaper charges his standard hourly rate (Php 80
per hour) for 25 hours of work. However, he decides to mark up his
material costs less than he usually does to outbid a competitor.
METHODS/TECHNIQUES
IN ESTIMATION
❑KNOWING THE ACTUAL MARKET COST
❑PROJETING FEASIBLE TIMELINE
❑DETAILED ORIENTED ON SCOPE OF WORKS
❑KNOWING ALL THE CONSTRUCTION RISKS
❑ALLOCATING AVAILABLE RESOURCES
❑IMPLEMENTING QUALITY
ACTUAL CONSTRUCTION
CREATING A SAMPLE BOM
CREATING A BOM
❑STEP 1
LIST DOWN ALL THE REQUIRED SCOPE OF
WORKS (BE SPECIFIC AND DETAILED)
(BREAKDWOWN EVERYTHING FROM DIFFERENT
SET OF CATEGORIES)
▪ PLASTERING WORKS
▪ STAIRS
❑FORMWORKS
▪ SCAFFOLDINGS
3.ARCHITECTURAL WORKS
EXAMPLE:
TOTAL PLYWOOD : 10
X .10
TOTAL PLYWOOD : = 11 NO. OF PLYWOODS
CREATING A SAMPLE BOM
LABOR COST
❑WITH THE DIRECT COST IT IS ESTIMATED INTO
35% TO 50%.
EXAMPLE:
TOTAL DIRECT COST : PHP 1,000,000
X .35
TOTAL LABOR COST = PHP 350,000
CREATING A SAMPLE BOM
VATS/TAXES
❑WITH THE TOTAL OF DIRECT COST INTO 12%
AND ALSO IT WILL ALWAYS DEPENDS ON
OTHER SITUATIONS.
EXAMPLE:
TOTAL MATERIAL COST : PHP 1,000,000
X .12
VATS/TAXES COST = PHP 120,000
CREATING A SAMPLE BOM
MISCELLANEOUS/CONTINGENCY
❑WITH THE TOTAL OF DIRECT COST AND
INDIRECT COST INTO 3%-10%.
EXAMPLE:
TOTAL D + I COST : PHP 1,000,000
X .05
VATS/TAXES COST = PHP 50,000
CREATING A SAMPLE BOM
OVERHEAD/PROFIT
❑WITH THE TOTAL OF DIRECT COST AND
INDIRECT COST INTO 5%-30%
❑CAN BE ALSO COMPUTED WITH THE OTHER
COST ASSOCIATED FOR ADMIN.
EXAMPLE:
TOTAL D + I COST : PHP 1,000,000
X .05
VATS/TAXES COST = PHP 50,000
CREATING A SAMPLE BOM
CREATING A BOM
❑Last Step
“Indicate at the final amount:
The ff:
❖ Discounted Cost(if any)
❖ Exclusions
❖ Total working or calendar days.
EXAMPLE
ADDITIONAL INFORMATION
(GOOD BUILDING CONSTRUCTION)
INTRODUCTION TO THE
SAMPLE PLANS
ACTUAL SITE
INTERIORS
Dining Area
Kitchen Area
Master Bedroom
Bedroom 1
Bedroom 2
Bathroom
ACTUAL SET OF PLANS
THE END