Camp Inspection
Camp Inspection
Camp Inspection
Page
Sl. No. Description Format No
numbers
1 First Aid Kit Checklist EHS-L&T-F001 3
Monthly Plant & Equipment & MEWP
2 EHS-L&T-F002 6
Inspection
Daily Plant & Equipment & MEWP Inspection
3 EHS-L&T-F003 7
Checklist
4 Fire Equipment EHS-L&T-F004 8
5 Crane Site Inspection EHS-L&T-F005 9
6 Site EHS Inspection EHS-L&T-F006 10
7 Sharp Hand tools & Tools Registries EHS-L&T-F007 12
8 Power Tools Inspection EHS-L&T-F008 13
9 Fall Protection EHS-L&T-F009 14
10 Lifting Equipment, Gears EHS-L&T-F010 15
11 Ladder Inspection EHS-L&T-F011 16
12 PPE EHS-L&T-F012 17
13 Scaffolding Inspection EHS-L&T-F013 18
14 Electrical Board & Extension Cables EHS-L&T-F014 19
15 Edge, Hole Protection EHS-L&T-F015 20
16 COSHH Assessment EHS-L&T-F016 21
17 Electrical Safety Inspection EHS-L&T-F017 24
18 Working at Height EHS-L&T-F018 25
19 Full Body Harness Inspection EHS-L&T-F019 27
20 Camp Inspection EHS-L&T-F020 28
21 Induction EHS-L&T-F021 31
22 Job Safety Task Instruction EHS-L&T-F022 33
23 Incident Preliminary Report EHS-L&T-F023 34
24 Incident Follow up form (Part 1&2) EHS-L&T-F024 35
25 Incident Investigation Personal form EHS-L&T-F025 37
26 Hot work Permit EHS-L&T-F026 38
27 EHS Training Attendance EHS-L&T-F027 39
Sl. No. Description Format No
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 2 of 76
REF.: EHS-L&T-F001
FIRST AID KIT CKECKLIST – PROJECT SITE /HIGH RISK AREAS
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 3 of 76
Exp No
S/ Qty Jan Feb Mar Apr May Jun Jul Aug Sep Oct
v
Dec
Item Date
N
STATUS
1 Guidance Card 1
2 Sterile Band Aid 40
Adhesive Tape : 1/2" x
1
10 yds
3
: 1” x
1
10 yds
Antiseptic Solution 250
4
ml
Gauze Bandage : 1
5 2
inch
:2 inch 2
:3inch 2
6 Gauze Pad 3” x 3” 4
Absorbent Sterile 250
7
Cotton Wool gms
8 Oval Eye Pad (Sterile) 15
Wrapped Sterile
9 2
Triangular Bandage
10 Disposable Gloves 3 Pairs
Wrapped Sterile
10
Unmediated Wound
11 Dressing : app. 12 cms
x 12 cms : app. 18 cms 3
x 18 cms
Individual Wrapped
12 4
Moist Cleaning Wipes
Cotton Tipped
13 20 pcs
Applicator(approx6”)
Eye Wash 250
14
ml
Resuscitation(CPR)
15 3
Training First Aid
16 Safety Pins 1 doz
17 Surgical Scissors 1
Signature & Date
REF.: EHS-L&T-F001 A
FIRST AID KIT CKECKLIST – FOR VEHICLE
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 4 of 76
Exp No
S/ Qty Jan Feb Mar Apr May Jun Jul Aug Sep Oct
v
Dec
Item Date
N
STATUS
1 Guidance Card 1
2 Sterile Band Aid 40
Adhesive Tape : 1/2" x
1
10 yds
3
: 1” x
1
10 yds
Antiseptic Solution 250
4
ml
Gauze Bandage : 1
5 1
inch
:2 inch 1
:3inch 1
6 Gauze Pad 3” x 3” 2
Absorbent Sterile 100
7
Cotton Wool gms
8 Oval Eye Pad (Sterile) 5
Wrapped Sterile
9 2
Triangular Bandage
10 Disposable Gloves 3 Pairs
Wrapped Sterile
6
Unmediated Wound
11 Dressing : app. 12 cms
x 12 cms : app. 18 cms 1
x 18 cms
Individual Wrapped
12 4
Moist Cleaning Wipes
Cotton Tipped
13 20 pcs
Applicator(approx6”)
Eye Wash 125
14
ml
Resuscitation(CPR)
15 2
Training First Aid
16 Safety Pins 1 doz
17 Surgical Scissors 1
Signature & Date
REF.: EHS-L&T-F001 B
FIRST AID KIT CKECKLIST – LOW RISK - OFFICE
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 5 of 76
Exp No
S/ Qty Jan Feb Mar Apr May Jun Jul Aug Sep Oct
v
Dec
Item Date
N
STATUS
1 Guidance Card 1
2 Sterile Band Aid 20
Adhesive Tape : 1/2" x
1
10 yds
3
: 1” x
1
10 yds
Antiseptic Solution 250
4
ml
Gauze Bandage : 1
5 1
inch
:2 inch 1
:3inch 1
6 Gauze Pad 3” x 3” 2
Absorbent Sterile 250
7
Cotton Wool gms
8 Oval Eye Pad (Sterile) 8
9 Disposable Gloves 3 Pairs
Individual Wrapped
10 4
Moist Cleaning Wipes
11 Safety Pins 1 doz
12 Surgical Scissors 1
Signature & Date
REF.: EHS-L&T-F02
Monthly Plant, Equipment, Vehicle & MEWP Checklist
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 6 of 76
Unit Model: __________________ Serial number: _____________________ Month Colour Code: _____
SATISFACTORY
S/N ITEMS N Correction Remarks
YES N/A
O
1 Operator Driving license
2 Operator Third party Certificate
3 Medical Fitness certificate
4 Health Insurance
5 Vehicle License (Mulkiya)
6 Vehicle Third party Certificate
7 Maintenance Inspection Logbook
8 User manual
9 Seat belts
10 Air conditioning
11 Telescopic boom condition
12 Condition of outrigger / pads
13 Head light & indicators
14 Beacon light / Additional Lights
15 Reverse Alarm
16 Horn
17 Coolant water, brake oil, engine oil, etc.
18 Plant / Equipment Earthing
19 Tires
20 Gauges & warning devices
21 Clutch / Brakes
22 Mirrors (center and side)
23 Unusual damage
24 Unusual noise
25 Leakages on oils, fuel etc.
26 Guards / Covers / Doors
27 Fire Extinguisher
28 First aid box
29 Warning Triangle
30 Others:-
REF.: EHS-L&T-F03
Daily Plant, Equipment, Vehicle & MEWP Checklist
Unit Name: __________________ Plate number: _____________________ Job #:_____________
Unit Model: __________________ Serial number: _____________________ Month Colour Code: _____
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 7 of 76
S/ Month: ______________________________________________
ITEMS 3 3
N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
0 1
Operator Driving
1 license
Operator Third
2 party Certificate
Medical Fitness
3 certificate
4 Health Insurance
Vehicle License
5 (Mulkiya)
Vehicle Third party
6 Certificate
Maintenance
7 Inspection logbook
8 User manual
9 Seat belts
1 Air conditioning
0
1 Telescopic boom
1 condition
1 Condition of
2 outrigger / pads
1 Head light &
3 indicators
1 Beacon light /
4 Additional Lights
1 Reverse Alarm
5
1 Horn
6
Coolant water,
1 brake oil, engine
7 oil, etc.
1 Plant / Equipment
8 Earthing
1 Tires
9
2 Gauges & warning
0 devices
2 Clutch / Brakes
1
2 Mirrors (center and
2 side)
2 Unusual damage
3
2 Unusual noise
4
2 Leakages on oils,
5 fuel etc.
2 Guards / Covers /
6 Doors
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 8 of 76
2 Fire Extinguisher
7
2 First aid box
8
2 Warning Triangle
9
3 Others:-
0
REF.: EHS-L&T-F004
Fire Equipment Inspection Checklist
Gauge
SI. Type of 3rd party Pressure Hose "NO" Seal Tank "NO" "NO"
I.D.# Location Capacity Remarks
No. Extinguisher Expiry (GREEN) Damage Intact Damage Corrosion
10
11
12
13
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 9 of 76
14
15
REF.: EHS-L&T-F05
Crane Site Inspection
Crane ID & Registration #:__________________ Job #:________________
Sr. SATISFACTORY
No ITEMS Remarks
. YES NO N/A
Operator competency (TP & Fitness) certificate and
1
license validity
2 TPI certificate validity
3 Maintenance registry
4 Lifting Gears TPI Certificate
5 Engine Start-up Condition
6 Seat Belt
7 Wire Rope, Slings, Anchored, &Chain Condition
8 Hydraulic condition (leakage and damages)
9 Lubrication
10 Emergency Stopper
11 Tires Condition & Pressure
12 Stability of Crane
13 Swing, Propel, Hoist, Boom Brakes & Locks
14 Over Load Indicator, lights and alarm
15 Hoist Limit Switch and Hook Latch Condition
16 Engine Oil Leakage
17 Unwanted Sound
18 Engine Oil Level at Indicator
19 Fuel Level at Indicator
20 Outrigger condition
21 Crane load graph
22 Boom Condition
23 Boom length, angle indicator
24 Boom Switch & cut off Switch
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning
of UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN –All EHS Formats Page 10 of 76
4 Watchman/Security Requirements
6 Welfare Facilities
7 Workplace Ventilations
15 Storage Area
16 Permit Requirements
25 Miscellaneous
Inspected By : Signature:
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 13 of 76
REF.: EHS-L&T-F007
Sharp Hand tools & Tools Registries
Assigned To: ________________ Signature:________________ Job #: _______________ Color Code: ______________
MONTH: ____________________
Sr. Identification
Description Usage / Purpose
No Mark / Serial # 1 2 3 4 5 6 7 8 9 10 11 12
10
11
12
13
14
15
16
17
18
19
20
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 14 of 76
REF.: EHS-L&T-F008
REF.: EHS-L&T-F009
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 15 of 76
MISSING
Sr. No. ITEMS ID MARKS CERTIFICATE # BROKEN CUTS CORRODED DIRTY SWL FINAL STATUS
PARTS
1
10
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 16 of 76
REF.: EHS-L&T-F010
Lifting Equipment& Lifting Gears Checklist
10
11
12
13
14
15
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 17 of 76
REF.: EHS-L&T-F011
Ladder Inspection Checklist
Inspection Date: ________________ Colour Code:________________ Job #: _______________
"NO" "NO"
"NO" GOOD "NO" Corrective
Sl No. TYPE OF LADDER ID MARKS Missing Dirty or Remarks
Paint Rung Cracks Actions
Parts Oil
1
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
REF.: EHS-L&T-F012
Personal Protective Equipment (PPE) Inspection Checklist
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 18 of 76
10
11
12
13
14
15
16
17
18
19
20
___________________________________________________
REF.: EHS-L&T-F013
Scaffolding Inspection Checklist
Erector Name / Company: _________________________ Scaffolding Tag number: ____________ Inspection Date: _________
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 19 of 76
Location:_________________________________________________________
In Charge: _____________________________ Signature: _______________
Inspected By: ___________________________ Signature: ________________
SATISFACTORY
S/N ITEMS Correction Remarks
YES NO N/A
1 Build by Competent Person
2 Tag Available / Green Tag / Red Tag
3 Sole board
4 Base Plate
5 Upright / Standard
6 Runner
7 Bearer
8 Diagonal Bracing
9 Cross Bracing
10 Mid Rail (47 cm from toe board top end)
11 Top Rail (95 cm from mid rail top end)
12 Toe Board (15 cm width)
13 Transom
14 Planks (No space in between)
15 Plank clamps
16 Outrigger
17 Tie
18 Tie Clamps
19 Ladder
20 Ladder clamps
21 Adjustable Leg / Scaffolding Level
22 Castor / Wheel
23 Tie ratio 4:1 height to base
24 Scaffold ratio 3:2 height to short base
25 Loose parts
26 Frequency of inspection
27 Ladder safety hatch
28 Ladder safety gate
29 (Others)
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 20 of 76
REF.: EHS-L&T-F014
Electrical Boards & Extension Inspection Checklist
Monthly Colour Code: ________________ Date of Inspection:________________ Job #: _______________
REF.: EHS-L&T-F015
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 21 of 76
1
2
10
Hazard Type
REF.: EHS-L&T-F016
Route of Exposure
Control Measures: (for example extraction, ventilation, training, supervision) Include special measures for vulnerable groups, such as disable people and pregnant workers. Take account of
those substances that are produced from activities undertaken by other employer’s employee.
Googles
Respirators
Gloves Overalls
Footwear Others
Storage
Approved By:
…………………………………………………………………….
Project Manager’s Name & Signature
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 25 of 76
REF.: EHS-L&T-F017
Electrical Inspection Checklist
Location: ________________ Job #: _______________
EVALUATION
SI.
Description Corrective Action Remarks
No. Satisfactory Failed N/A
1 Earthing
2 Neutral earthing
3 ELCB
4 Insulation
5 Cable Layout
7 Lightning Arrestor
Electrical safety at
installations containing
10
Inflammable & Explosive
substances
11 Safety guards
12 Metal Stand
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 26 of 76
REF.: EHS-L&T-F018
Working at Height Inspection Checklist
EVALUATIO
N
SI. Corrective
Description
Satisfy
Failed
No. Action
N/A
Points
7 Workmen provided with bag / box to carry bolt, nuts and hand tools.
Access / Egress
13 Are ladders inspected and whether they are maintained in good condition
Housekeeping
37 Crawler boards / Safety system for work on fragile roof are used
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 28 of 76
REF.: EHS-L&T-F019
Full body Harness Inspection Checklist
Storage Location: Date of Inspection:
Month: Year: Color Code:
identification no.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
of harness
of lanyard
Back Pads /
Serial /
Serial /
Upper back
Lower back
Upper back
Lower back
Lower front
Upper front
Lower front
Upper front
pelvic side
pelvic side
pelvic side
pelvic side
snap hook
chest side
chest side
chest side
chest side
(front side
Absorber
D - rings
Keepers
Lanyard
Lanyard
Lanyard
Buckles
Locking
Remarks
Double
Plastic
Shock
chest)
Inspected by: Report verified by:
Name: Name:
Signature: Signature:
Date: Date:
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 29 of 76
REF.: EHS-L&T-F020
Camp Inspection Checklist
Location: ________________ Job #: _______________Date of Inspection: _____________
EVALUATION
SI. Corrective
Satisfy
Failed
Description
N/A
No. Action
Are the entry, exit roads / walkways / passages to camp kept clear from
obstruction/ un safe?
Are the walkways & roads are even and free from water logging?
Is the entry inside workmen camp restricted? Documented?
Is Illumination level adequate in access / egress?
Is Security provided adequate in the camp?
Is there emergency exit located in the fence?
Is there adequate fire training to the security guards?
GENERAL
Satisfy
Failed
N/A
No. Action
LIVING AREA
Are all doors and windows having proper locking studs, hooks?
Are the doors and windows provided with fly mashes?
Are there all doors and windows cleaned regularly?
Are the floors cleaned daily and non-slippery?
Is there an Adequate sitting arrangement for camp members?
Are all furniture good?
Are there fly catchers provided?
Is there adequate ventilation and distribution counters?
FOOD STORAGE AREA
Satisfy
Failed
N/A
No. Action
Are all Food items kept on wooden pallets above the ground?
Is the Temperature maintained in the freezers to preserve the food?
Are specified brand of food ingredients purchased / stored?
Are Pest control arrangements adequate?
Is adequate ventilation & Room temp maintained in the food stuff storage
area?
Is the expiry date displayed and followed in the storage area?
Is Disposal of expired products, non-complyingproducts are documented?
Are All food stuff materials stored in reachable area?
Is General cleanliness in the storage area maintained?
UTILITIES AREA
Is the Wash area - Water tanks constructed as per the Design Drawing?
Are adequate toilets available?
Are the toilets, floors being cleaned on regular basis?
Is there adequate water facility available for toilet and bath?
Are the septic tanks and soak pit working properly?
Is area around bathrooms cleaned & kept dry and non-slippery?
Is proper drainage provided?
Is there cleaning schedule followed?
Is there all taps free from leak, damage?
Is there adequate mirrors provided for face washing, shaving? Maintained?
Are there locking pads, tower bolts in the toilets/ bath rooms?
Is there any shoe racks provided to keep them in order?
Is there any cooking takes place outside the kitchen area?
Any Other Information
Conducted by: ______________________________ Signature: _______________ Date: __________ Time From: _____To:____
3. Before starting the work check all guards, fencing, safety devices and equipment etc., and follow safe method of working .It will be checked even
after the closure of work.
“I, hereby acknowledge / accept that, the subject matter HSE communication which was made by the
trainer during HSE Induction / Awareness session / Tool box / Training session, has been fully understood
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 33 of 76
by me and was found suitable and sufficient as per subject / agenda of HSE Induction, Awareness session,
Tool box, Training session. I will comply the same HSE communication / guidelines during my work /
activities in the project”
Emirates ID # /
S.I. Name Designation Contact # Signature
Company ID #
10
11
12
13
14
15
Activity :
Sequence of Tools/Equipment/Material to Potential Hazards Hazard Elimination/Control
work: be used measures in place
PRELIMINARY REPORT
Incident No
INCIDENT (ACCIDENT / NEAR MISS) (To be filled H&SS DEWA)
(CONTRACTOR STAFF)
To: Manager – Safety/Health, H&SS,DEWA
Contract No………………………
1a. Name, ID No. & Designation of the Victim/ involved with Accident /Near Miss: …………………………………...
……………………………………………………………………………………………………… …………………………………….
1b. Equipment / Machinery / Vehicle etc. Involved in Accident / Near miss: ……………………………………………………………
8. Present Status of the Victim (Sick Leave/ Police Custody/ Hospitalized / Resumed Duty): …………………………………………...
9. Risk Assessment carried out for the activity (If yes, pl. attach the copies) Yes / No:
NB:
Please Fax to 2857415 Within 24 Hours of The Occurrence through DEWA Executing Department
Preliminary Form- Contractors-H&SS, DEWA/2014
* Document from DEWA SP-06 Annexure IV-A
REF.: EHS-L&T-F024
Incident Follow up Report Form
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 36 of 76
FOLLOW UP REPORT
INCIDENT (ACCIDENT / NEAR MISS) Incident No
(To be filled H&SS
(CONTRACTOR STAFF)
PART 1:To be filled by Contractor, Consultant & DEWA executing dept.as applicable.
To: Manager – Safety/Health, H&SS, DEWARef. No………………..
_______________________________________________________________________
________________________________________________________________________
b) Sr. Manager(DEWA):__________________________________________________________
_______________________________________________________________________
PART3: Status on Implementation of corrective action taken by the contractor concerned to be sent to H&SS,
DEWA with 15 days of receipt of above mentioned recommendation (s) from M- Safety, H&SS, DEWA.
………………………………………….. …………………………………….
Contractor Sign &dt Consultant & Sign &dt
11. Use of Personal Protective Products / Equipment: (Please Tick) Safety Shoes / Helmet / Gloves / Belt / Any
other………………………………..
12. Condition of working area: (Please Tick) confirmed / noisy / slippery / not guarded / any other……………………………..
13. Taken any safety measure: Yes / No. If yes then what?......................................................
Topics Covered:
“I, hereby acknowledge / accept that, the subject matter HSE communication which was made by the trainer during HSE
Induction / Awareness session / Tool box / Training session, has been fully understood by me and was found suitable
and sufficient as per subject / agenda of HSE Induction, Awareness session, Tool box, Training session. I will comply the
same HSE communication / guidelines during my work / activities in the project”
SL
NO
ATTENDEES NAME ID NUMBER DESIGNATION COMPANY SIGNATURE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Faculty:
Location:_______________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
NO. Of STARs Received
___________________________________________________________________ Before:
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
_____________________________________________________________________
Project Safety Officer and Project Manager Name and Signature with date
____________________________________________________________________
REF.: EHS-L&T-F029
FORMATION OF SITE EHS COMMITTEE
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 42 of 76
CIRCULAR
Committee
The following safety Committee is constituted with immediate effect:
Chairman : Mr.
Members :
1) Mr.
2) Mr.
3) Mr.
4) Mr.
5) Mr.
6) Mr.
Secretary : Mr.
Periodicity
The committee will meet fortnightly.
Agenda
Secretary will circulate agenda of the meeting at least a day in advance of the schedule date of the meeting.
Circulation
Gist of the meeting will be Minute in the standard format and circulated to the following under the signature of the secretary ---
1. Chairman 3. Invitees
2. Members 4. Country Manager EHS
5. Others concerned
REF.: EHS-L&T-F030
MINUTES OF EHS MEETING
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 43 of 76
REPORT SENT TO
No. of No. of No. of
Name / Dept. Name / Dept. Name / Dept.
Copies Copies Copies
Item
Description of Discussion Action By Target Remarks
No.
7 Sub-contractor performance
REF.: EHS-L&T-F031
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 45 of 76
Safe access and egress Work at height Safety Hot works & Fire safety Excavation Safety Electrical Safety
Confined Space safety Chemical Safety Power tools Safety Hand tool safety Importance of PPE
Floor opening Adverse weather Manual handling working with moving plant Safe Lifting works
Compressed Cylinder Health Hazard Emergency Procedure Carpentry work safety Steel work safety
Masonry work Safety Housekeeping Scaffolding safety Others:-
“I, hereby acknowledge / accept that, the subject matter HSE communication which was made by the trainer during
HSE Induction / Awareness session / Tool box / Training session, has been fully understood by me and was found
suitable and sufficient as per subject / agenda of HSE Induction, Awareness session, Tool box, Training session. I will
comply the same HSE communication / guidelines during my work / activities in the project”
SL
ATTENDEES NAME ID NUMBER DESIGNATION COMPANY SIGNATURE
NO
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Conducted By: Signature: Date & Time:
__________________________________________________________________________________
Permit Requested from (date) _______ (time) _______ hrs. To (date) _________ (time) _________hrs.
I hear by declare that I accept responsibility for carrying out the above said work on the panel /equipment / unit/ plant details on this permit
and it is safe to carry out the specified work during the time mentioned below. All necessary precaution have been taken including Lock out Tag
Out (LOTO)
Authorized Person (Permit Applicant)
Date:
Section IV CLEARANCE
I hear by declare that work for which this permit was issued is now suspended /Completed and that all personnel under my control have been
withdrawn. The area has been cleared and tools have been removed and are safe.
Name: Name:
Section V CANCELLATION
Signature: Permit Issuing Authority
Comments of cancellation:____________________________________________________________________________________________
NOTE:
1. A permit copy shall be submitted to L&T HSE department before starting the work.
2. Permit has to be renewed / validated on daily basis.
3. It is the responsibility of the permit applicant to ensure all control measures are in place during the work and till closure of work
permit.
4. The applicant has to return the original permit to issuing authority after completion of the job or at the end of working hours.
5. Make sure that each worker on the job understand fully the prescribed conditions and the tool box talk points.
6. Stop working upon hearing fire/emergency siren/alarm or the instruction of the permit issuer or safety officer or fire warden and
assemble in the fire assembly point.
7. Log IN / OUT register shall be placed in each room where electrical equipment is placed. All the entrant should fill in the details.
8. Room door should be locked after the completion of the works and to ensure nobody left out in room.
9. Lone working not allowed in any work areas.
REF.: EHS-L&T-F033
RISK ASSESSMENT REGISTER
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 48 of 76
REF.: EHS-L&T-F034
ACTION NOTICE
Prohibitions – Stop Work, immediately notify Supervisor & CM
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 49 of 76
DETAILS
Inspector name Date
Violator Name Time
Resp Engineer S/C Company
Location /Zone Risk Rating H M L
ENVIRONMENTAL
Noise Waste Management Hazardous Material/Waste
Illumination Nature/Temp/Wind Dust & Air Emissions
Ventilation Chemicals Fuel Storage/Spillage
Radiation Waste Management Other
OCCUPATIONAL HEALTH
Welfare Facilities Manual Handling Vibration Personal /Spitting
SAFETY
PPE Scaffolding Electricity /Energy Plant / Machinery
Driving Fire protection Confined Spaces Fall Protection
Hot Work Housekeeping Night Work Edge Protection
Access/Egress Traffic Management Barricading Excavation
Permits / R/A’s Lifting Tools Equipment Work at Height
INCIDENT/CONDITION/OCCURRENCE DESCRIPTION Open /Close
Person Sign
REF.: EHS-L&T-F035
LOCK OUT – TAG OUT PERMIT
This permit is required whenever personnel will work on or near the equipment (Electrical, fluid, mechanical or other) and
could be injured as a result of unexpected release of energy or hazardous material.
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 50 of 76
Time of issue:
REF.: EHS-L&T-F036
CUSTOMER SATISFACTION FEEDBACK
Name of Site :
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 51 of 76
Job No. :
Region :
Company: ________________
REF.: EHS-L&T-F037
LEGAL REGISTER
L&T
REF.: EHS-L&T-F038
WASTE GENERATION REPORT
Project & Location Reporting Month : Report Date :
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 53 of 76
JAN
FEB
MAR
APR
MAY
JUN
JULY
AUG
SEPT
OCT
NOV
DEC
Total
Remarks :
REF.: EHS-L&T-F039
Other Requirement Checklist
EHS Manager / Engineer: ________________ Project Manager: _______________
Sr. SATISFACTORY
ITEMS Remarks
No. YES NO N/A
CONTRACTUAL REQUIREMENT
1 Approval for L&T EHS Representatives
2 Approval of L&T EHS Plan
3 Sub-Contractor Approval
4 Sub-Contractor Approval for EHS Representatives
5 Sub-Contractor Approval for EHS Plan
ENGINEERING REQUIREMENT
6 Risk Assessment prepared for all activities
7 Risk Assessments are signed
8 All Activities have Method Statement
9 Approval of Method Statements
10 All Activities have work notification
11 Approval for Work Notifications
WORK REQUIREMENT
12 Approval of Client's NOC
13 Approval of Water & Electric Authority Work NOC
14 Approval of Water & Electric Authority Trial Pit NOC
15 Approval of Water & Electric Authority Excavation NOC
16 Approval of Town planning Authority NOC
17 Approval of Central Military Command
18 Approval for Municipality Work Permit
19 Approval for Etisalat/DU Work Permit
20 Approval for Agri Department Work Permit
21 Approval for RTA Permit
22 Approval of Electric Authority NOC for Sub-Station
23 Approval for Hot work Permit
24 Approval for Excavation Permit
25 Approval for Confine Space Permit
TRAFFIC REQUIREMENT
26 RTA / Client Signage's Standards
27 RTA / Client Barricade Standards
28 RTA / Client Lighting Standards
TRAINING REQUIREMENT
29 EHS Induction
30 EHS Plan Orientation
31 Supervisor's Training
32 Control Measures Toolbox Meetings
FIRE PREVENTION REQUIREMENT
33 Fire points available with fire extinguishers
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 55 of 76
REF.: EHS-L&T-F040
HEALTH CHECKUP PROGRAM
Project No: ________________
Project Name: _____________________________ Date: ________________
Male Nurse :
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 57 of 76
Permit Request
Please permit the confined space entry as per the following details:
Location: …………..………………………… Activity: ………………………………Company: ……………………………
Type of the Confined Space: Trench, Pit, Man-hole, Severe, Flue, Reinforcement cage, enclosed room, silo,
chamber, tank, tunnel, pipe, others (specify): …………………………………………………………
Number of Crew: ……………………………………………………. Team Leader: ………………………………………………………………
Entrant Name: ………………………………………………………... Attendant Name: …………………………………………………………….
Name of the Requester: ………………………………………… Designation: …………………… Signature: ………………………………
Mobile No: …………………………….. Permit requested from: ………………………………… to: …………………………………………
Potential Hazards in the Confined Space
Oxygen Deficiency Flammable gas Hot/ humid atmosphere Poor lighting
Oxygen enrichment Bacterial agents Cold atmosphere Poor ventilation
Toxic gas/atmosphere Limited access/ egress Dust/ fumes High Noise
Water ingress Gas/ fuel ingress Dangerous creatures Deep narrow entry/ exit
Limited work place Presence of sewer Falling materials Electrical hazard
Sharp objects/ surface Slippery surface Cave in Others:
Air Quality Monitoring
Frequency of monitoring: 10/ 15/20 /30 minutes. Note: Log air quality monitoring in attached sheet.
Monitored by: Name:
Details of Gas monitor:
Details of Rescue equipment
Tripod with accessories Yes / No. Safety/ rescue harness Yes / No.
Extractor Yes / No Rescue hauler Yes / No.
SCBA/ SAR / EBA Yes / No Rescue stretcher Yes / No.
Rescue trolley/ pulling device Yes / No Others(specify):
Means of Communication
Walkie-talky Yes/ No PA System Yes / No.
Whistle/ Air horns Yes / No. Alarm Yes / No.
Control of Entry & Training
Entry/ exit register available Yes / No. Task Briefing /TBT given Yes / No.
Entrants/ attendants are 3rd party trained Yes / No. Supervisor is competent Yes / No.
Rescue equipment are inspected Yes / No. Emergency response known to all Yes / No.
Site clinic is alerted Yes / No. Standby vehicle available Yes / No.
Documents Attached: Method statement/ RA (strike out whichever is inapplicable).
Permit Requested by: (Supervisor /Engineer)
Permit Issued by:
(Construction Manager)
Verified by:
(Contractor EHS Officer)
Work completed safely & Permit returned by:
(Supervisor / Foreman / Engineer)
Permit Closed by:
(Construction Manager)
Verified by:
(Contractor EHS Officer/ Engineer)
Name Signature Date & Time
Permit Closed out: The confined space work has been completed safely:
Name of In-charge: Sig: Date:
Note: 1. The scope of the permit is limited to the location mentioned above. The permit must be returned to the HSE office
upon expiry of the same.
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 58 of 76
2. Alteration/ correction after the approval will make the permit null & void.
Frequency
Time Time Time Initial of
Time & Time & Time & Time & Time & Time &
& & & the
Value Value Value Value Value Value
Description Value Value Value inspector
Oxygen %
O2
Carbon
dioxide CO2
Carbon
monoxide CO
Hydrogen
Sulphide H2S
Ammonia
NH4
Other
Respiratory
particles
Atmospheric
Temp.
Relative
Humidity
Entry
Name of the entrant Time - in Time – out Time - in Time - out Time - in Time - out
Attendant
Location / Area.
Name of the Lifting Supervisor / Foreman.
Equipment Details.
Equipment Custodian / In-charge
Type of the Crane or Lifting Equipment Mobile crane / Tower crane / EOT crane / Chain block / Others:-
Capacity (SWL) & 3rd Party Certificate ref. no:
Maximum load to be lifted
Capacity of the lifting gears
Crane operator’s name & 3rd Party ID
Routine (normal)/ Non-routine (Critical/Heavy Lift/ Tandem lift etc.) Note: Lift
Type of Lifting
Plan required for non-routine lifting operations.
Type of hitch arrangements and condition
HSE Checklist for the Lifting Supervisor/ Foreman/Engineer
Task briefing delivered to the crew. Yes No Verified 3rd party certificates and found OK. Yes No
Visual inspection carried out on lifting Yes No The Crane operator has valid license and 3rd Yes No
equipment and accessories. party ID.
Trained rigger available Yes No The Rigger & the operator know correct Yes No
hand signals.
Outrigger pads are defect free Yes No The ground is compacted and levelled. Yes No
Swing area is barricaded Yes No Hazard warning signage placed. Yes No
Is there any U/G utility below the Yes No Is there any overhead electrical line etc. in Yes No
outriggers the swing area.
The Crane, vehicle, truck parked on road. Yes No NA Traffic control measures taken. Yes No NA
Lifting supervisor is available on site. Yes No Weather condition is satisfactory Yes No
Operator cabin have full visual clearance Yes No Is there any excavation nearby the crane Yes No
positioning area?
The crane is positioned away from Yes No NA If the excavation is deeper than 1.5 mts. the Yes No NA
excavation edge crane outrigger shall be Depth X 1.5 mts.
(2 meters away if depth is 1.5m or below) away from the edge.
Permit Requested by:
(Lifting supervisor / Engineer)
Permit Issued by:
(Construction / Site - Manager)
Verified by: (Contractor EHS Officer)
The work completed safely & Permit returned by:
(Lifting supervisor / Engineer)
Permit Closed by: (Construction / Site - Manager)
Verified by: (Contractor EHS Officer)
Signature with
Name Designation
Date & Time
Permit Validity: From: Hrs. To: Hrs. Permit Closed at: Hrs.
Note: 1) The permit shall be returned to HSE office on completion of the task.
2) Non-compliance to the permit conditions will lead to stoppage of work.
3) The lifting shall be stopped if the wind speed exceeds 35 Km/Hr. and during other inclement weather conditions
REF.: EHS-L&T-F043
CHEMICAL INVENTORY REGISTER
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 60 of 76
Hazardous
Chemical Quantity
Chemical Hazardous Property eg. Is the Chemical
S Abstracts Stored Is MSDS Is COSHH
Trade / Non - Toxic/ Labelled and
No. Service – (unit in Available Available
Name Hazardous Flammable/ stored safety?
(CAS No) Gallon )
Explosive
REF.: EHS-L&T-F044
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 62 of 76
REF.: EHS-L&T-F045
Target
Yearly Achiev
# INDICATOR Targe CONTRACTOR OH&S PERFORMANCE (CUMULATIVE) ement
t Level
(TAL)
Ja Fe Ma Apr M Jun Jul Aug Sep Oct Nov Dec
n b r ay
Average number of staff in the Month: Total number of new staffs joined in the Month:
Target Achievement level (for Positive Trend -Item 6 to8 = 100% + [Actual-Target] * 100%
Target Achievement level (for Negative Trend -Item 1 to5 = 100% + [Target-Actual] * 100%
REF.: EHS-L&T-F046
1.
2.
3.
4.
5.
6.
Referred by / References:
Screened by me. Certificates / Details verified / not verified.
________________________________________________________________
Referred to Mr. _________________ for on the job trial
Suitable for employment as ____________________
PROJECT MANAGER
Employment Card issued and details entered into Register of workmen.
Points to be checked
Sl. No Details Yes No NA
1. Is the area free from any falling materials?
2. Anybody working in down the floor opening
3. Is required to be wear safety harness and hook right place
4. Is adequate working platform provided with Access?
5. Proper barricades provided with sign boards
6. Are the operatives provided with adequate PPE and explained about open
floor during Tool Box Talk.
7. Any other precautions taken (specify)
8. Is adequate fall protection from basement provided?
9. Is Watcher made available for this job to guard the opening?
Please don’t issue any Floor open work if above points are not complied
Certified that the above quoted HSE precautions are ensured at the work location.
Permit Requested By (Foreman/Engineer)
Permit Issued By (Construction Manager)
Verified By (Contractor EHS Officer)
The work completed safely & Permit
returned by:
(Supervisor / Foreman / Engineer)
Permit Closed by:
(Construction Manager)
Verified By (Contractor EHS Officer)
Signature with
Designation
date & time
Permit Validity: From: ______ Hrs. To: ________Hrs. Permit Closed at: Hrs.
After Work Completion (Before Leaving the Location)
The openings have been protected and reinstate safely.
By Permit Requester: Name: Designation: Signature with date & time:
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 66 of 76
Details of Underground Utilities: Furnish Details & means of isolation and protection.
Are there any electrical cables/ services present: Yes / No.
Are there any data cables present: Yes / No.
Is there any pipe lines (fuel, gas, water etc.) present:Yes / No.
Are you verified below documents/ drawings/ Approvals?
Method Statement/ RA: Yes / No. Utility Drawings provided by Authorities Yes / No.
Is IFC drawing is available Yes / No. Area clearance obtained by concerned Yes / No.
HSE Controls and precautions:
The crew undergone excavation safety training Yes / No. Necessary PPE are available Yes / No.
The area scanned using CAT scanner Yes / No Hazard warning signage/ Emergency no. Yes / No.
displayed.
Area is barricaded with hard barriers Yes / No Provision of access/ egress Give details:
Welfare facilities available at the Yes / No First aid box & first aider available. Yes / No.
location( toilet/ rest shed/ drinking water)
Type of side protection planned: Shoring/ Mention type. Any impact on road traffic. Yes / No.
benching/ sloping/ shield/ box shield.
Flashing lights are provided near vehicular Yes / No. Surface encumbrance are removed or Yes / No.
movement area/ adjacent to road. protected.
Full time supervision is ensured. Yes / No. Any plant/ equipment positioned Yes / No.
nearby.
Remarks(if any):
Documents Attached: Method statement/ Risk Assessment/ As built Drawing/ Utility Drawing/ IFC Drawing (strike out whichever is
not applicable
Permit Requested by: (Supervisor
/Engineer)
Permit Issued by:
(Construction Manager)
Verified by:
(Contractor EHS Officer)
Work completed safely & Permit
returned by:
(Supervisor / Foreman / Engineer)
Permit Closed by:
(Construction Manager)
Verified by:
(Contractor EHS Officer/ Engineer)
Name Designation Signature with date &time
Noncompliance to the permit conditions will lead to cancellation of the permit and stoppage of the work.
Cancelled by: Signature: Reason:
Validity of the Permit. From: ………………………………….. To: …………………………………………………….
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 67 of 76
Note: 1. The scope of the permit is limited to the location mentioned above. The permit must be returned to the HSE office upon
expiry of the same.
2. Alteration/ correction after the approval will make the permit null & void.
EXCAVATION PERMIT VALIDATION FORM
Daily HSE Check by the Supervisor Yes No HSE Engineer’s/ Officer’s Remarks
1) The excavation profile is intact.
2) Sign boards & barricades are in place.
3) No water ingress in the excavation.
4) Safe access/ egress provided.
5) U/G utilities are protected.
6) No plant/ equipment parked at the edge.
7) Workmen given daily toolbox talks.
8) Edge protection is intact.
9) Welfare facilities are provided.
10) Emergency No. displayed & known to all.
11) Good housekeeping is maintained on site.
12) First aid facility is available.
13) No oil leak in the equipment being used.
14) Workmen are using PPE.
15) MS/ RA available on site.
Request for Daily Validation of the Permit (To be filled by the Supervisor).
Date/ Time/ Date / Time/ Date / Time/ Date / Time/ Date / Time/ Date / Time/
Signature Signature. Signature. Signature. Signature. Signature.
Note:
1) The excavation work shall not commence until validating the permit.
2) Maximum days for validation are for six days. If the excavation is continuing beyond six days
a new permit shall be obtained.
3) HSE Engineer/ Officer to cancel the permit if deviations are observed during the daily
validation.
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 68 of 76
4) The permit and the daily validation sheet shall be returned to the HSE office upon expiry.
Date of cancelation / expiry:
Dept/Section:
Workshop Name & Location:
Method of Checking:Checking shall be carried out prior to use the equipment at least on daily basis.
Step 1: Switch on the equipment and allow to run fully; Step 2: Stop the equipment using emergency stop switch.
Action: If the running equipment not stopped by emergency switch immediately notify to the workshop in-charge and do not use the equipment
till corrective action has been completed.
REF.: EHS-L&T-51
HOUSKEEPING INSPECTION CHECKLIST
EHS In-Charge
REF.: EHS-L&T-52
Verified by:
Points to be checked
Sl. No Details Yes No NA
1. Is the area free from any falling materials?
2. Well Ventilated
3. Scaffolding inspected
4. Is required to be wear safety harness and hook right place
5. Is adequate working platform provided with Access?
6. Proper barricades provided with sign boards
7. Are the operatives provided with adequate PPE and explained about
hazard during Tool Box Talk.
8. Illumination intensity is acceptable.
9. Emergency light provided.
10. Others if any:
LONE WORKING IS NOT PERMITTED INSIDE CABLE RAISER ROOM- BY ORDER (HSE Dept)
Certified that the above quoted HSE precautions are ensured at the work location.
Permit Requested By (Foreman/Engineer)
Permit Issued By (Construction Manager)
Verified By (Contractor EHS Officer)
The work completed safely & Permit
returned by:
(Supervisor / Foreman / Engineer)
Permit Closed by:
(Construction Manager)
LARSEN & TOUBRO LIMITED
Power Transmission & Distribution (UAE)
Construction, Supply, Installation, Testing and Commissioning of
UMMDAMAN 132/11kV Substation and Associated works
PROJECT HSE PLAN- EHS Formats Page 74 of 76
Comments:
____________________________________________________________________________________________
PERMIT TO WORK for Civil / Electrical / MEP Works after handing over to T&C
Permit Applier/Holder:
The above points have been complied with and conditions rendered safe / hazards innocuous to undertake the Civil/ Electrical
/MEP work.
Permit Closeout:
Work area and adjacent area were inspected and were found safe.
Supervisor in charge:-
Name Sign Date_________