Katpp Project Report 17 August
Katpp Project Report 17 August
Katpp Project Report 17 August
Report
at
Kalisindh Thermal Power Plant
Jhalawar- Rajasthan
Submitted By:
Ramniwas Dhakar
19113070
IPE-Final year
1
CONTENTS
1. Introduction 3-14
7. References 39
2
1. INTRODUTION
3
1.1 Thermal Power Plant in India
In India, Thermal Power Plant contribute about 61% of the total
electricity produced.
Pie chart shows the electricity production percentage by different
sectors.
4
1.2 AN OVERVIEW OF KaTPP
5
Kalisindh Thermal Power Project is located in Jhalawar. The
proposed capacity of coal based Thermal Power Project is 1200
MW. The project site is about 12 km from Jhalawar (Distt. -Head
quarter) and NH-12. Site is comprising of 5 villages viz. Nimoda,
Undel, Motipura, Singharia and Deveri. It is 2km from state
highway No.19 and 8 km from Ramganjmandi Bhopal broad gauge
rail line
6
mining of coal blocks and new company started the work. Annual
coal requirement for the project is 56 Lacs TPA. GOR also decided
to setup two new units of2x660MW in next few years.
Owner • RVUNL
EPC
• BGR Energy System Ltd
Contractor
7
1.3 ENERGY GENERATED IN KaTPP
Number of units=2
Electricity generated by one unit=600 MW
Total electricity negated by plant=2x600=1200 MW
8
1.5 PRINCIPLE OF OPERATION
When all the above four cycles are combined, the cycle achieved is
called RANKINE CYCLE. Hence the working of a thermal power
plant is based upon Rankine Cycle with some modification
9
1.6 THERMAL PLANT OPERATION PROCEDURE
10
each stage, steam expands, pressure decreases and velocity
increases.
11
Monitor these margins and the plant conditions, and provide
immediate indications and permanent records. Draw the
attention of the operator by an alarm system to any
unacceptable reduction in the margins. Shut down the plant if
the operating constraints are violated.
12
delivered by train from Mines to the Coal Handing Plant (CHP). The
CHP unloads this it become more economical to unload the coal.
Then the coal stacked, reclaimed, crushed, and conveyed it to the
storage silos near the steam generator. Then it is fed through the
Feeder to the Pulverizer. Feeder is mainly used to weight the amount
of coal going to the Pulverizer per hour. From the Feeder the coal is
fed to the Pulverizer which powders it and then it is carried to the
steam generator using pressurized air. Within the steam generator
the coal is atomized and burned and the heat energy produced is used
for producing steam. Here two types of steam namely superheated
& reheated steam are produced in a cycle. The steam turbine
generator converts the thermal energy of superheated and reheated
steam to electrical energy. The first energy conversion is carried in
Boiler or steam generator; the second is carried out in Turbine and
the last one carried out in the Generator.
13
the steam generator and PA fans transports the coal into the steam
generator. ID fans remove the flue gases from the steam generator
and exhaust it through chimney. Cooling water for the condenser is
supplied by the circulating water system, which takes the heat
removed from the condenser and rejects it to the cooling towers or
other heat sink. This all working is controlled from a single place
called control room. It enables the operator to direct the plant
operation for reliable and efficient production of electrical energy.
This is achieved by the control system installed by the C & I group.
These are DAS (Data Acquisition System), ACS (Analog Control
System), FSSS (Furnace Safeguard Supervisory System), and other
relays governing numerous activities. Last but not the least is the
switching and transmission methods used here. The generated
power cannot be transmitted as such. It is stepped up to 132 KVA
or 400 KVA then passed through a series of three switches an
isolator, a circuit breaker and an isolator. Three phase system is used
for the power transmission. Each generator has its own switchyard
and transmission arrangement.
14
2. COAL HANDLING PLANT (CHP)
2.1 INTRODUCTION
The term coal handling plant means to store and to handle the coal
which is transported by the train and convey to the bunkers with the
help of belt conveyers. Through the bunkers coal is transferred to
the coal mill and drifted to the furnace. The coal handling plant
includes wagon tippler, conveyer belt, crusher house, stacker &
reclaimer, bunkers & coal mill.
15
2.2 STAGES OF COAL HANDLING PLANT
Capacity 90 tones
Types of Tipplers 1.Weighing type,
2.Non weighing type
Drive unit Motor 37.3 KW
Angle of Tip 30 to 35
Wire Ropes 1.Hoisting Ropes,
2.Counter Weight Ropes
Operating Cycle 10 wagons/Hour on 1 wagon
Tippler
Time consumes for one cycle 6 minutes
16
Capacity 500 Tonnes/hr.
Machine Weight 30 Tonnes
Motor 500 Tonnes/hr.
Max Feed Rate 720 r.p.m
Rotor Speed 550 H. P
Phase 606 Kv
Volts 3 Phase motor
PARTS OF CONVEYORS
17
9) Impact Idler-These Rubber idlers are provided under chutes
through which coal falls on conveyors.
10) Carrying Idlers-These are installed to run the conveyor.
18
Fig: - COAL HANDLING LAYOUT
19
3. IMPORTANT PARTS OF THERMAL POWER PLANT
3.1 BOILER
Boiler can simply define as the device where any liquid is boiled or
Boiler may be defined as a device that is used to transfer heat
energy being produced by burning of fuel to liquid, generally
water, contended in it to cause its vaporization. Boiler, in simple
terms, can be called “Steam Generator”.
In simple way, boiler is a device used for producing steam. There
are two types of boilers.
a) Fire tube boiler
b) Water tube boiler
20
Manufacturing Made in China
Motor rating 15 KW
Rated voltage 970 r.p.m
Speed 416 V
Rated current 28.4 A
Impedance voltage 80.0 %
Oil weight 20 Kg
Core+ winding weight 224 Kg
Temp rise 50-55 deg cel.
Total weight 600 Kg
21
BOILER AUXILIARIES-Efficiency of a system is of most
concerned. Thus, it is very important to maintain a system as
efficient as possible. So, Boiler auxiliaries help in improving
boiler’s efficiency. Following are the important auxiliaries used
22
3.2 TURBINE
23
Intermediate Pressure (IP) and Low Pressure (LP) cylinders. The
HP turbine is of Single Flow type while IP and LP turbines are of
Double Flow type. The turbine is condensing type with single
reheat. It is basically engineered on reaction principle with throttle
governing. The stages are arranged in HP, IP AND LP turbines
driving alternating current full capacity turbo generator. The
readily designed HP, IP and LP turbines are combined and sized to
required power output, steam parameters and cycle configuration
to give most economical turbine set. The design and constructional
feature have proved their reliability in service and ensure trouble
free operation over long operating periods and at the same time
ensuring high thermal efficiencies
24
TURBINE SPECIFICATION
25
3.3 GENERATOR
26
GENERATOR SPECIFICATION FOR UNIT I AND II: -
Make BY STAMFOARD
MAHARASTRA
INDIA
Rating 1900 KVA
Speed 1500 R.P.M
Rated Current 2643.37 A
Rated Temp Rated Temp
AMPS 3.6 A
27
3.4 CONDENSER
In condenser, the water passes through various tubes and steam
passes through a chamber containing a large number of water tubes
(about 20000)
The steam gets converted into water droplets, when steam comes in
contact with water tubes. The condensate is used again in boiler as
it is dematerialized water and 5-6 heats the water, which was in
tubes, during the process of condensation. This water is sent to
cooling tower.
Condenser is installed below the LP exhaust. The condenser is of
surface type made of fabricated construction in single shell. The
tube is of divided type double pass arrangement, having two
independent cooling water inlet, outlet and reverse and water boxes.
This arrangement facilitates the operation of one half of condenser
when the other half is under maintenance. The condenser is provided
with integral air-cooling zone at the center from where air and non-
condensable gases are continuously drawn out with the help of
mechanical vacuum pump.
Area of condenser = 9655 sq m
Cooling water flow rate = 2400 cubic m/Hr
28
3.5 COOLING TOWER
Fig-Cooling Tower
29
3.6 WATER TREATMENT PLANT
As everyone know that the cost of any thermal power plant is cores
of rupees. So major problem of any thermal power plant is that how
to prevent the corrosion. The water available can’t be used in boilers
as such. The objective of water treatment plant is to produce the
boiler feed water so that there shall be.
No scale formation
No corrosion
No priming or forming problems
30
It has high efficiency i.e., about 99%
Ability to treat large volume of gases at high temperature
Ability to cope with the corrosive atmosphere.
It offers low resistance to the flow of gases.
It requires less maintenance.
31
The whole ESP is divided into two parts-
Mechanical System
Electrical System
32
electrodes in the form of open spiral. The four suspension points are
supported on support insulators to give electrical insulation to the
emitting frame. The frame is designed to take up the retention forces
of the emitting electrode. The emitting electrode consists of hard
drawn spiral wires and are fastened with hooks to the discharge
frame. Collecting system mainly consists of collecting suspension
frame, collection electrodes and shock bars. Collecting electrode are
made of 1.6 mm thick Mild Steel sheets formed in ‘G’ Profile of
400mm width. Hook and guide are welded on one end and shock
iron on the dipped in rust preventive oil tank. Collecting electrodes
bundles are properly bundled in order to avoid any damage to
electrode.
Hoppers- Hoppers are seized to hold the ash for 8-hour collection
and is provided under the casing of ESP. It is of Pyramidal Shape
and is 56 in number. It is preferred to evacuate the hoppers at the
earliest as long storage of dust in hopper leads to clogging of hopper.
Also, at the bottom of hopper electrical heating is provided to avoid
any condensation, which could also lead to clogging of hopper.
Baffle plates are provided in each hopper to avoid gas leakage
33
4.2 ASH HANDLING PLANT (AHP)
34
FLY ASH SYSTEM-Even though ESP is very efficient, there is
still some ash, about 0.2%, left in flue gases. It is disposed to the
atmosphere along with flue gases through chimney
35
5. CONTROLLING, SWITCHING AND TRANSMISSION
36
From the circuit breaker the current is taken to the bus bars-
conductors, which run the length of the switching compound and
then to another circuit breaker with its associated isolates before
feeding to the grid.
Three wires are used in a ‘three=phase’ system for large power
transmission. The center of the power station is the control room.
Here engineers monitor the output of electricity, supervising and
controlling the operation of the generation plant and high voltage
switch gear and directing power to the grid system as required.
37
6. EFFICIENCY AND CONCLUSION
6.1 EFFICIENCY
38
6.2 CONCLUSION
7.REFERENCE
www.rvunl.com
www.googleindia.com
Generation of electrical power By B. R. Gupta, S CHAND
PUBLICATION
39
Thank You
40