Process Costing Complete
Process Costing Complete
Materials
+ = 1
Process 1 Wait
Materials
Transferred-In Process 2
Cost
Department 1 Department 2
WIP, beg 30% complete 70% complete
WIP, end 50% complete 30% complete
Stage when materials are added beginning when 60% complete
Department 1 Department 2
Units Cost Units Cost
WIP, beg 20,000 25,000
Direct Materials P 30,000 P 62,500
Conversion Cost 36,500 34,696
Trasferred in 121,500
Department 1 Department 2
WIP, beg 30% complete 70% complete
WIP, end 50% complete 30% complete
Stage when materials are added beginning when 60% complete
Department 1 Department 2
Units Cost Units Cost
WIP, beg 20,000 25,000
Direct Materials P 30,000 P 62,500
Conversion Cost 36,500 34,696
Trasferred in 121,500
For example:
In the manufacture of soft drinks, the syrup is often
produced in one department and carbonated water
added in a subsequent process. The addition of
carbonated water increases the total volume of liquid
product to be accounted for.
In the manufacture of soft drinks, the syrup is often produced in one
department and carbonated water added in a subsequent process. The
addition of carbonated water increases the total volume of liquid product
to be accounted for. The Mixing Department of Tiger Paint Company
receives paint dye from the Pigment Department; the dye is mixed with a
liquid latex to form paint in the Mixing Department for April are:
Based on the cost of production report for the month of March, work in-
process beginning was 25% complete as to conversion costs. The departmental
supervisor reported that the ending inventory of work in-process was 50%
complete as to conversion costs. Also, the materials are added here whenever
the process reaches 30% conversion.
WIP, beg.
Cost from preceding department 5,800
Materials -
Conversion costs 4,095
Current period manufacturing cost
Cost from preceding department 18,400
Materials 26,400
Conversion costs 21,105
PROCESS COSTING SYSTEM
with Losses
January 24, 2022
Accounting for Lost Units
Three Types of Production Losses
Spoilage
Rework
Scrap
Three Types of Production Losses
For example:
When Starbucks roasts coffee beans, Approximately 20 percent
of the original weight is lost from water evaporation. This situation
results in shrinkage.
For example:
Spoilage of meats and other perishable foods awaiting customer
purchases in supermarkets can be further prevented by covering
refrigeration cases each night.
At other times, errors in the production process (either by
humans or machines) cause a loss of units through rejection at
inspection for failure to meet appropriate quality standards or
designated product specifications.
Whether these lost units are considered defective or spoiled
depends on their ability to be economically reworked.
For example:
The weight loss in roasting coffee beans and the relatively
continual breakage of fragile glass ornaments can be considered
continuous losses because they occur fairly uniformly throughout
the production process.
Continuous and Discrete Losses
In contrast, a discrete loss is assumed to occur at a specific point.
For example:
Adding the wrong amount of vinegar to a recipe for salad dressing
or attaching a part to a motor upside down. The units are only
deemed lost and unacceptable when a quality check is performed.
NORMAL ABNORMAL
Do not include equivalent lost Must include equivalent lost units
units in EUP schedule. Units in EUP schedule. Assign cost to
CONTINUOUS effectively “disappear”; unit lost units and charge as loss of
costs of good production are period.
increased.
Must include equivalent lost Must include equivalent lost units
units in EUP schedule. Assign in EUP schedule. Assign cost to
cost to lost units. Determine lost units and charge as loss of
point of ending work in process: period.
a. if before inspection point,
DISCRETE assign cost of lost units only to
units transferred.
b. if after inspection, prorate
cost of spoiled units between
units transferred and units in
ending inventory.
Continuous versus Discrete Losses
Type Assumed to Occur May Be Cost handled Now? Cost Assigned To?