Process Costing Module 9 Merged
Process Costing Module 9 Merged
Module 96
Process Costing – FIFO: Even and Uneven Application of Costs
Process costing refers to the product costing procedure whereby products are assigned costs by departments or
processes.
Allocation of manufacturing costs in every department to calculate the unit cost of the product for profit
determination and inventory costing purposes.
- During the production period, some of the units started will not be completed at the end of the period.
Therefore, each department must determine the total costs of the units still in process and the costs of the
units completed.
Example:
Assume that during the month 1,000 units were started in process in the Department 1. During the month, costs
were incurred as follows:
Direct materials P 150,000
Direct labor 50,000
Factory overhead 100,000
At the end of the month, 700 units were completed and transferred to Department 2.
- The objective of process cost system is to calculate how much of P 150,000 direct materials, P 50,000 of
direct labor, and P 100,000 of manufacturing overhead costs will be allocated to 700 units completed and
transferred to Department 2 and how much will be allocated to the 300 units still in process in Department
1.
SIMILARITIES
Page | 1
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
- Flow of costs.
o The accumulated manufacturing costs are assigned to the same accounts in both costing systems:
Work in Process, Finished Goods, and Cost of Goods Sold.
DIFFERENCES
The departmental accumulations of costs under process cost system are summarized below:
- Units completed in one department are transferred to the next department accompanied by their
corresponding costs
- Completed unit of one department becomes the raw materials of the next department until the units are
converted to finished products
- The output of Department 1 becomes the input of Department 2. Department 2 receives both the units
produced in Department 1 as well as its production costs
- Upon completion of the process in Department 2, the cost of units completed consists of the costs
received in Department 1 and cost incurred in Department 2
- The cost of a unit increases as it progresses from one department to the next.
Example:
TM Corporation manufactures office tables in three departments. Department 1 cuts the woods at an average cost
of P 100 per unit. The woods are then transferred to Department 2, where they are assembled at an average cost of
P 200 per unit. The last stop is in Department 3 where they are painted at an average cost of P 300 per unit. The
completed units are transferred from Department 3 to finished goods inventory.
The total unit cost of one finished table is P 600, computed as follows:
1 P 100
2 200
3 300
Total unit cost P 600
NOTE:
- In general, the cost per unit increases as units follow through each department.
o However, the unit cost decrease when volume is added to the units that pass through a
department.
ASSIGNMENT OF MANUFACTURING COSTS
For each producing department, a work in process accounts is used. Manufacturing costs incurred by a
department are charged to its own work in process account.
Process cost system accumulates the three elements of costs using either the following cost procedures:
- Normal costing.
o Direct materials and direct labor are applied at actual cost while factory overhead is applied at a
predetermined rate
Page | 2
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
- Standard costing
o Direct materials, direct labor and factory overhead are applied at standard cost or estimated cost.
In this chapter and in the following chapter process costing using the normal costing will be used.
Direct materials.
Usually direct materials are added to the first department, but they may also be added in the subsequent
departments.
Departmental charges for materials costs are based on stores requisitions and consumption reports.
Consumption reports is often required of department heads because not all of the materials issued during
a period are used during the same period.
The inventory of raw materials in the producing departments still form part of the raw materials
inventory.
Materials cost incurred were tallied with the expected amount thereof considering the actual volume of
production.
All materials used by a producing department (whether forming part of the finished product or not) are
charged to work in process.
Example:
Entry:
Work in Process – Mixing Dept. P 12,000
Work in Process – Brewing Dept. 10,000
Work in Process – Finishing Dept. 6,000
Factory Overhead Control 2,100
Stores/ Materials P 30,100
LABOR COST
- Labor costs per payroll (whether directly expended on goods in process or not) are charged to the payroll
account and subsequently charged to the different departments where they are incurred as indicated on
summary of daily time tickets or daily clock cards.
- Example:
Payroll amounted to P 32,000. The distribution is as follows:
Mixing Dept. P 11,000
Brewing Dept. 9,000
Finishing Dept. 8,000
Service Departments 4,000
Entry:
Work in Process – Mixing Dept. P 11,000
Work in Process – Brewing Dept. 9,000
Work in Process – Finishing Dept. 8,000
Factory Overhead Control 4,000
Payroll P 32,000
FACTORY OVERHEAD
- Factory overhead is accumulated in the Factory overhead (or Factory Overhead Control) account supported
by the subsidiary record – factory overhead analysis sheet
o If departmentalization is observed, departmental factory overhead analysis sheets (or standing orders)
are maintained also.
Page | 3
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
- Factory overhead may be charged to production at its actual amount or at a predetermined rate based on
normal capacity.
o Actual amounts may be used if overhead per unit is expected to remain at more or less the same level
and this holds true when
Production volume is more or less constant and
Factory overhead (particularly, fixed overhead) is not a significant portion of cost.
o If production volume fluctuates significantly and fixed factory overhead is a significant portion of cost,
application of factory overhead is preferably by the use of predetermined rate(s) based on normal
capacity.
- Example:
Applied factory overhead is P 33,800, while factory overhead as accumulated amounts to P 35,000. They
are analyzed as follows:
Factory overhead applied:
Mixing Department P 13,500
Brewing Department 9,200
Finishing Department 11,100
Total P 33,800
Entries:
Work in Process – Mixing Dept. P 13,500
Work in Process – Brewing Dept. 9,200
Work in Process – Finishing Dept. 11,100
Factory Overhead – Mixing Dept. P 33,800
Factory Overhead - Brewing Dept. 9,200
Factory Overhead - Finishing Dept. 11,100
Overhead charged to production
- After these entries, the balance of the factory overhead account for each department must be equal to the
departmental factory overhead variance.
INTERDEPARTMENTAL TRANSFERS
- Transfers from one department to another are recorded by debiting the work in process account of the
transferee department and crediting that of the transferor department.
o Upon completion, the accumulated cost of the finished goods is charged to the finished goods accounts
and credited to the work in process account. The goods still in process in the different departments
comprise the ending inventory of work in process for the entire factory.
- Example:
Goods completed in Dept. A (cost, P 38,000) are transferred to Dept. B. During the same period, Dept. B.
completed goods with accumulated cost of P 64,200 and transferred these to the finished goods
stockroom.
Page | 4
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Entries:
At the end of each month a production report is prepared for each department by the cost accountant.
Production report – shows the number of units that were in process in the department at the start of the month,
the number of units started during the month, the number of units transferred out of the
department during the month, the number of units still in work in process at the end of
the month, and the percentage of completion of the units still in process at the end of the
month.
Warehousing
- Cost procedures related to warehousing are almost the same as those in job order costing.
- A difference is that the cost of goods completed is transferred from the last departmental Work in Process
account to Finished Goods Inventory by an entry in the general journal rather than in a job cost sheet.
- One summary entry is made at the end of the month to record the cost of goods completed during the
month.
Selling
- All procedures in recording sales are similar to those used when goods are sold from stock under the job
order cost system. The Cost of Goods Sold account is debited and the Finished Goods Inventory account
is credited for cost of products sold.
Page | 5
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Procedures should be designed to
a) Accumulate factory costs by departments or processes,
b) Determine departmental unit costs
c) Transfer costs from one department to the next and subsequently, to finished goods, and
d) Assign cost to ending inventories of work in process.
Stores
Payroll
COSTING BY DEPARTMENTS
- Inasmuch as homogeneous products cannot be identified from one another and are processed in a continuous
flow, the different elements of cost (materials, labor and factory overhead) are accumulated by processes or
departments.
- Unit cost in each department is computed based on volume of work done and
- The total unit cost of a unit completed in all departments is the total of the unit costs in all the departments
in which it passed through.
- If it is partly done only in a department, the cost assigned is proportionate to the amount of work done.
Example: Ago-o Manufacturing Co. has three producing departments (A, B and C). For January 2014, the
unit costs in these departments are as follows:
Page | 6
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
o A unit of the product that was started on in January, completed in Dept. A and 1/5 done in Dept B shall
be assigned the unit cost of P 12.90 or:
Dept A P 10.00
Dept B (one unit x 1/5 x P 14.50) 2.90
P 12.90
- If there is an ending inventory of work in process, it is assumed to have come from those placed in process
during the month.
Example:
Assume that of the 3,000 units, only 500 units (1/4 done) are still in process as of January 31. The equivalent
production is computed as follows:
Actual Work Done This Equivalent
Month Production
Placed in process 3,000
Page | 7
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
The work in process as of March 31 of 5,000 units must be part of the 20,000 units placed in
process so that only 15,000 units of the latter must have been completed in March.
Dept. A Dept. B
Stage of Stage of
Units Completion Units Completion
In process, Feb. 1 5,000 1/4 2,000 1/5
Placed in process 20,000
Transferred to Dept. B 19,000
Transferred to stockroom 18,000
Work in process, Feb. 28 6,000 1/3 3,000 1/6
Department A Department B
Work Work
Done Done
This Equivalent This Equivalent
Actual Month Production Actual Month Production
In process, Feb. 1 5,000 2,000
Placed in process 20,000
Received from preceding
dept. 19,000
Units to be accounted for 25,000 21,000
In process, Feb. 1, finished and transferred 5,000 ¾ 3,750 2,000 4/5 1,600
Placed in process, finished and transferred 14,000 100% 14,000
Received, finished and transferred 16,000 100% 16,000
In process, Feb. 28 6,000 1/3 2,000 3,000 1/6 500
Units accounted for 25,000 19,750 21,000 18,100
Page | 8
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Notes:
- Department A:
o The 19,000 units transferred out consist of 5,000 units in process on February 1 st and 14,000 coming
from those just placed in process.
o The units still in process as of February 28 must have come from those placed in process during the
month.
- Department B:
o Inasmuch as 19,000 units were transferred out from Department A, these are part of the units to be
accounted for in Department B so that the total to be accounted for is 21,000.
o With 18,000 units given as transferred out, priority is given to work in process, February 1 st, of 2,000
units so that only the difference of 16,000 must have come from those received (or transferred in) from
Department A. Thus out of the 19,000 units received, 3,000 units are still in process as of February 28.
LAST-IN, FIRST-OUT
- Not used in process costing because the layering aspects of this technique would make process costing
applications quite difficult.
- May be used in valuing raw materials and finished goods inventories.
- Shows:
o Flow of units in process and their stages of completion
o Computation of equivalent units of production
o Costs charged to a producing department or costs to be accounted for
o Computation of cost per equivalent unit
o An accounting for total cost
2. Modified form – shows the computations after the total cost column.
- the column headings amount and unit cost are observed throughout the report by presenting
computations in the unit cost column. In so doing, errors can easily be traced.
- the consistency in the use of the columns makes it easier to computerize the report.
Regardless of the form being used, the quantity schedule may be shown separately. This has the advantage of
being able to emphasize cost analysis on a shorter cost of production report. In some cases, errors in one do not
require the revision of both.
ILLUSTRATIVE PROBLEM A
Page | 9
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Factory costs:
Materials P 25,000
Labor 20,000
Factory Overhead 15,000
Factory costs are applied evenly throughout the process.
The schedule of equivalent production and the cost of production report are presented on the next page:
Quantity Schedule
Work Done Equivalent
Actual This Month Production
Placed in process 60,000
Placed in process, finished and transferred 40,000 100% 40,000
In process, January 31 20,000 1/2 10,000
Units accounted for 60,000 50,000
Solo Mfg. Co
Cost of Production Report
For the Month Ended January 31, 2014
Based on the foregoing cost of production report, the postings to the work in process account would be as follows:
Work in Process
2014 2014
Jan 1-31 Materials 25,000 Jan 1-31 To finished goods 48,000
Labor 20,000
Factory Overhead 15,000
The ending balance of work in process of P 12,000 is the cost assigned to the 20,000 units that are still one-half
done as of January 31, per cost of production report.
Cost last month - refers to the accumulated cost as of the beginning of the month
Cost added this month – pertains to the factory cost added during the current costing period based on work done
during the same period.
Page | 10
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Example:
As of March 1, 2014, there were 6,000 units in process, 1/4 done, with accumulated cost of P 3,100. Factory costs
for March amount to P 40,000 and equivalent production is 20,000 units so that the unit cost for the month must
be P 2.00. The cost of the 6,000 units is computed as follows:
Cost last month may also be called cost, March,1 and cost added in March as cost this month.
The 6,000 units were 1/4 done as of March 1st so that to complete them this month, work done in March ought to
be the remaining 3/4.
ILLUSTRATIVE PROBLEM B:
EVEN APPLICATION OF COST, ONE DEPARTMENT FACTORY WITH BEGINNING WORK IN
PROCESS
The Manggahan Mfg. Co. has a one-department factory and uses the process costing method for its sole product.
Factory costs are applied evenly throughout the process. The following production data are given:
Cost data:
Work in process, March 1, 2014 P 17,600
Factory costs, March, 2014
Materials 50,000
Labor 25,000
Factory overhead 20,000
Quantity data:
In process, March 1 (5/8 done) 8,000 units
Placed in process, March 30,000 units
In process, March 31 (1/5 done) 10,000 units
The schedule of equivalent production and the cost of production report are shown below.
Quantity Schedule
Work Done Equivalent
Actual This Month Production
In process, March 1 8,000
Place in process 30,000
Units to be accounted for 38,000
In process, March 1, finished and transferred 8,000 3/8 3,000
Placed in process, finished
and transferred ( 30,000 - 10,000) 20,000 100% 20,000
In process, March 31 10,000 1/5 2,000
Units accounted for 38,000 25,000
Page | 11
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Work in Process
2014 2014
Mar 1 Balance 17,600
1-31 Materials 50,000 Mar 1-31 To finished goods 105,000
Labor 25,000
Factory Overhead 20,000
Based on the above postings, the ending balance must be P 7,600, the cost assigned to work in process per cost of
production report.
CONVENTIONAL FORM OF COST OF PRODUCTION REPORT
Manggahan Mfg. Co,
Cost of Production Report
For the Month Ended March 31, 2014
Quantity Schedule:
Work Done Equivalent
Actual This Month Production
In process, March 1 8,000
Place in process 30,000
Units to be accounted for 38,000
Page | 12
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
- When goods in process pass through consecutive departments, costs from preceding departments become part
of the cost to be accounted for in the succeeding departments.
- In the succeeding department, cost from preceding department is identified with the units transferred in during
the period.
- Thus, at the end of the current costing period, their cost shall be the sum of the costs from the preceding and
the current departments.
- Accordingly, the cost of units in process at the end shall be equal to:
ILLUSTRATIVE PROBLEM C:
EVEN APPLICATION OF COST, TWO-DEPARTMENT FACTORY
The sole product of Amapola Manufacturing Co. is processed in two consecutive departments A and B. The
production data for April, 2014 are as follows:
Cost data:
Work in process, April 1 P 305.00 P 2,502.00
Factory costs:
Materials P 5,350.00 1,600.50
Labor 2,140.00 3,201.00
Factory overhead 3,210.00 533.5
Department A Department B
Work Work
Done Done
This Equivalent This Equivalent
Actual Month Production Actual Month Production
In process, April. 1 1,000 2,000
Placed in process 10,000
Received from preceding dept. 10,500
Units to be accounted for 11,000 12,500
In process, April. 1, finished and transferred 1,000 80% 800 2,000 40% 800
Placed in process, finished and transferred 9,500 100% 9,500
Received, finished and transferred 9,800 100% 9,800
In process, April 30 500 80% 400 700 10% 70
Units accounted for 11,000 10,700 12,500 10,670
Page | 13
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Based on the cost of production report, the postings to the departmental work in process would be as follows:
JOURNAL ENTRIES
The journal entries for Amapola Mfg. Co. would be as follows:
Work in Process P 10,700.00
Materials P 5,350.00
Payroll 2,140.00
Factory Overhead 3,210.00
Dept. A’s factory costs in April 2014
Page | 14
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
After posting the foregoing entries to the respective work in process accounts, the balance in each should
be equal to the ending work in process per cost of production report.
Factory costs:
Materials P 6,950.50
Labor 5,341.00
Factory overhead 3,743.50 P 16,035.00
Work in process, April 1 2,807.00
Work in process, April 30 (1,142.00)
Cost of Goods manufactured P 17,700.00
Page | 15
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
- The computation for equivalent units of production for materials is illustrated in the following examples. It is
assumed that conversion costs are evenly applied throughout the process so that the computation for the
corresponding equivalent units of production remains the same.
Example A:
Lagundi Mfg. Co. adds all the materials at the start of the process. Conversion cost is applied evenly
throughout the process. The quantity data are as follows:
The equivalent units of production for materials should be different from those for the conversion cost. They
are computed as follows:
Materials
Work done Equivalent
Actual this month Production
Placed in process 20,000
- It may be noted that due to the addition of materials at the start of the process, the equivalent production of
ending work in process for materials is 100% despite the fact that it is 60% completed only.
- This is emphasized in the following diagram:
Start of the
process Manufacturing process
Materials ///////////////
///////////////
Conversion cost /////////////////////////////////////////////////////////////////
Example B:
Assume that in example A, there were 3,000 units in process on May 1 st, 30% done. The equivalent units of
production for materials must also be 20,000 units as arrived at in the following computation.
-
Work done Equivalent
Actual this month Production
In process, May 1 3,000
Placed in process 20,000
Units to be accounted for 23,000
- Despite the existence of beginning work in process, equivalent production for materials remains at 20,000, the
number of units started on during the current month.
o Reason: beginning work in process has zero equivalent production for materials because the required
materials for the lot were already added when it was started last month.
o Therefore, when materials are added at the start of the process, equivalent production for materials
(under the FIFO assumed flow of cost) must be equal to the number of units started on during the
current month.
Page | 16
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Example C:
Sixty percent of the materials are added at the start of the process and 40%, when the process is 4/5
completed.
The equivalent units of production for materials must be 30,400 as shown below.
Materials
Work done Equivalent
Actual this month Production
In process, May 1, finished and transferred out 6,000 40% 2,400
Placed in process, finished and transferred out 25,000 100% 25,000
In process, May 31 5,000 60% 3,000
Units accounted for 36,000 30,400
The following visual aids would make it easier to understand the percentage of work done for materials:
,
Manufacturing process
60% 40%
Addition of materials
- Work in process beginning was 30% done at the start so that 60% of the materials were added last month.
Only the remaining 40% are added this month.
- Work in process, end is 70% done only so that only 60% of the materials were added during the month. The
remaining 40% shall be added next month when it reaches 4/5 or 80% completion.
Example D:
Seventy percent of materials are added at the start of the process, 10% at the middle, and 20%, at the end.
Same quantity data as in Example C.
The equivalent units of production for materials are arrived at as follows:
Materials
Work done Equivalent
Actual this month Production
In process, May 1, finished and transferred out 6,000 30% 1,800
Placed in process, finished and transferred out 25,000 100% 25,000
In process, May 31 5,000 80% 4,000
Units accounted for 36,000 30,800
The following diagrams would be of help to understand how the equivalent units of production are arrived at:
Manufacturing process
Page | 17
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
- Equivalent production for work in process at the beginning is equal to 30%.
o Reason: inasmuch as they were placed in process last month, 70% of the materials were added last
month.
o For this month, 10% was added when it reached the middle of the process and the remaining 20%,
upon completion.
- For ending work in process, which is 7/10 done, equivalent production is 80%.
o Inasmuch as they were placed in process during the current month, 70% of the materials were
immediately added and 10%, when it reached the middle of the process.
Laguna Mfg. Co. provides the following data on its May, 2014 production:
Dept. I Dept. II
Quantity data:
In process, May 1, 2014 3,000 units 5,000 units
Stage of completion 30% 25%
Placed in process, May 2014 20,000 units
In process, May 31 5,000 units 7,000 units
Stage of completion 20% 5/7
Cost data:
Work in process, May 1 P 3,450 P 21,750
Prime costs, May 2014 50,000 24,000
Materials 18,100 11,850
Labor
- In Department I, all the materials are added at the start of the process and factory overhead rate is 50% of
labor cost.
- In Department II, 60% of the materials are added at the start of the process with the remainder applied when
the goods are 4/5 done. Factory overhead rate in Department II is P .40 per equivalent unit of production.
Page | 18
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
Page | 19
COST ACCOUNTING AND CONTROL
PROCESS COSTING: FIFO: EVEN AND UNEVEN APPLICATION OF COSTS
o In the first part of the Cost Schedule, total costs are assembled and the cost per equivalent unit of
production for each cost category (materials, labor, overhead, and transferred in cost) is computed. In
addition, the cumulative cost per equivalent unit is calculated.
o The second part of the Cost Schedule accounts for the costs. Some costs relate to units that are
transferred to the next department or to finished goods. The total of costs transferred out is computed
by multiplying the cumulative cost per equivalent unit by the number of units transferred out. Other
costs remain as part of the work in process. The cost of ending work in process is the unit cost of each
cost category multiplied by the number of equivalent units of that cost category still in process.
The total cost of goods transferred from one department to the next or to finished goods, as shown in the cost of
production report, is recorded by a journal entry and posted to the general ledger.
References:
Cost accounting by Nenita Mejorada, 3rd Edition.
Cost accounting by Guillermo M. De Leon Jr. And Norma D. De Leon.
Page | 20
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
Module 9.1
7
Process costing: FIFO
PROCESS COSTING: FIFO – INCREASE AND LOSS IN UNITS
The addition of materials may bring about an increase in the quantity being processed. In some cases, there may
be decreases in the number of units due to the nature of the materials being used or the manufacturing process involved.
Both increases and decreases in the number of units in process (except in the case of abnormal loss) have the
reverse effect on unit cost.
Addition of Materials – Its Effects
- Although materials are generally placed in process in the first department, additional materials are often required
in subsequent departments for the completion of the goods.
- These additions may result in an
o increase in unit cost or
The addition of materials results in an increase in unit cost when it does not result in an increase
in the number of units.
Examples:
use of bottles (or cans) for beverages,
bleach for textiles, and
plating mixture for metal parts.
o an increase in the number of units in process
The addition of materials in liquid form (such as water and oil) increases the quantity of goods
being processed.
Equivalent Units of Production with Increase in Quantity
- An increase in quantity increases the number of units to be accounted for.
- Determine carefully at what point the increase occurs.
o If the increase occurs at the start of the process, the increase in quantity should be associated with the
units received during the month only.
o Uneven addition of materials requires computation for equivalent units of production different from those
for conversion cost.
- Example:
The addition of materials at the start of the process in Dept. B of Mid-way Mfg. Co. brings about an increase in
quantity by 25%. The quantity data are given as follows:
In process, beg 6,000 gals., 1/4 done
Received from Dept. A 20,000 gals.
In process, end 7,000 gals., 2/7 done
The equivalent units of (or effective) production is computed as follows:
Schedule of equivalent units of production:
- If the addition of materials brings about an increase in quantity but normal losses also occur, only the net
increase may be reflected in the cost of production report provided they are associated with the same group of
units as accounted for.
- If the increase occurs at a point different from the point of loss, the loss may be shown separately.
- An increase in the quantity being processed has the effect of spreading costs over a greater number of units.
- The unit cost from the preceding department is adjusted as follows:
Adjusted unit cost from preceding department = Cost from preceding department
Increased number of units
- Example:
Dept. B received 20,000 gallons from Dept. A costing P 5 per gallon. The addition of materials at the start of the
process in Dept. B increases the quantity by 25%. The adjusted unit cost is computed as follows:
Adjusted unit cost from Dept A = 20,000 gallons x P 5
20,000 gallons x 125%
= P 100,000
25,000 gals.
= P 4 per gallon
- The unit cost from preceding department is adjusted from P 5 to P 4 per gallon.
- Cost from preceding department for the 25,000 gallons shall be at P 4 regardless of their stage of completion as of
the end of the current costing period.
Example:
The following cost data are given in addition to the quantity data given for Mid-way Mfg. Co.:
In process, August 1 P 25,590
Received from Dept. A 100,000
Factory costs, August:
Materials 24,500
Labor 12,250
Factory overhead rate – 80% of labor cost
ILLUSTRATION:
INCREASE IN UNITS DUE TO ADDITION OF MATERIALS EVENLY THROUGHOUT THE PROCESS
LOSS IN UNITS
- There may be losses due to wastage, seepage, shrinkage, evaporation, accidents and fortuitous events.
- When loss is inherent in the manufacturing process, the normal percentage of loss is computed based on expected
yield percentage.
o When the yield is significantly below the expected level, the possible causes thereof are determined and
may require a separate computation of the abnormal portion of the loss.
ILLUSTRATIVE PROBLEM A:
LOST UNITS – EQUIVALENT UNITS OF PRODUCTION
Anahaw Mfg. Provides you with the following quantity data based on the production in Department A in September,
2014:
In process, Sept. 1 F and T 10,000 3/5 6,000 3/5 6,000 3/5 6,000 3/5 6,000
Received, F and T 37,000 100% 37,000 100% 37,000 100% 37,000 100% 37,000
In process, end 5,000 1/5 1,000 1/5 1,000 1/5 1,000 1/5 1,000
Loss 8,000 - - - - ¾ 6,000 100% 8,000
Units accounted for 60,000 44,000 44,000 50,000 52,000
- It may be noted that the losses in Nos. 1 and 2 have zero equivalent production.
- In No. 3, the loss is at a specific point during process, that is, when the goods are 3/4 done;
- In No. 4, the loss is 100% included in equivalent production because it occurred at the end of the process.
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
TREATMENT OF ABNORMAL LOSS
- Abnormal loss is treated as a period cost.
- The cost assigned to the lost units is removed from work in process by charging the appropriate loss account (
such as loss from substandard materials, loss from flood, and loss from factory accident)
- Therefore, the unit cost of the remaining units is not affected.
o If there is partial cost recovery as in the case of spoiled goods, only the unrecovered cost is charged to the
loss account.
(Note: To be able to balance the report immediately, six decimal places are maintained for unit costs that are not exact
because there are five digits in the number of units. The additional decimal place takes care of the carry-over.)
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
NORMAL LOSS – A PRODUCT COST
- Normal loss, being a product cost, is generally charged to the remaining units.
- What the remaining units are depends on the point of loss.
- Remaining units
o Refers to what are left of the particular group of units with which the loss is identified.
o The loss may be identified either with those placed in process, both of those in process at the beginning
and those placed in process, or only those completed during the period. `
o The different points of loss and the corresponding figures for remaining units are the following:
Point of Normal Loss Remaining units
Start of the process Units started in process minus lost unit
During process Method I – Units started in process minus lost units
Method II – Equivalent production for remaining units
At a specific point in process Units that passed through the specific point of loss during the current
period minus lost units
End of the process Completed units
- In case normal loss occurs during process, determine whether the said loss must be identified with beginning
work in process or with those started on during the period.
o In Method I, the loss is identified with those started during the period while in
o Method II, it is identified with both beginning work in process and units started during the period.
Method I is generally used for convenience inasmuch as beginning work in process must already
have its share in normal loss during the preceding costing period.
- If the loss is stated to occur progressively during process, it implies that it is related to both the beginning work in
process and the units received or started on during the period.
ADJUSTMENTS FOR LOST UNITS
- A normal loss is treated as an additional cost of the remaining units and the additional unit cost charged to the
latter is usually called adjustment for lost units.
- To have an adjustment for lost units, the lost units must have absorbed cost.
- In case lost units have market value, the adjustment for lost units is based on the unrecovered portion of their cost.
NORMAL LOSS IN THE FIRST DEPARTMENT
- When normal loss occurs at the start of the process or during the process in the first department, the lost
units do not absorb cost inasmuch as costing is based on equivalent units of production.
o Reason:
When normal loss occurs at the start of the process, nothing has been done yet in the current
department.
In the case of normal loss during the process, the specific point of loss is not determinable so that
it is not included in the equivalent units of production.
This has the effect of automatically charging the cost of lost units in the current department
to the remaining units based on work done during the period.
When normal loss occurs at the end of the process in the first department, the loss units must have
absorbed cost equal to the unit cost of a completed unit and must be identified with the completed units
only
Formula for adjustment for lost units
Adjustment for lost units = Cost of lost units
Completed units
NORMAL LOSS IN A SUBSEQUENT DEPT.
- A unit in a subsequent department has absorbed cost in the preceding department so that there is adjustment
for lost units regardless of the point of loss. The numerator must be the accumulated cost of the lost units.
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
o Normal loss at the Start of the Process
Accumulated cost of the lost units is equal to their cost from the preceding department.
The loss is identified with the units received during the current costing period.
Formula:
Normal loss at the start of the process:
Adjustment for lost units = Cost of lost units from preceding department
Units received – lost units
Adjustment for lost units, in this case
An additional cost of remaining units (out of those received) regardless of the latter’s stage
of completion as of the end of the period.
The following data are on the production of Department B of Sumilang Mfg. Co. for August, 2014:
The loss during process (Method II) is identified with the three groups (beginning work in process,
finished and transferred; units received, finished and transferred; and, ending work in process) so that
each of them shares in the cost of the lost units based on equivalent production. If method I were used,
the figures would be the same as in A (loss at the start).
The normal lost units, one-half done, absorb cost up to the middle of the process. The accumulated cost
is divided between the three groups because they all pass the middle of the process during the period.
Beginning work in process was not yet half done at the start so that it passed the middle of the process
this month. In the case of the ending work in process, it passed the middle of the process during the
same month because it was started during the month and was already 2/3 done as of August 31.
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
Normal Loss, Uneven Application of Cost
When there is normal loss and factory costs are applied unevenly thoroughout the process, the same
formula for adjustment for lost units are observed. The difference lies only in the costing of the normal
lost units.
ILLUSTRATIVE PROBLEM D:
NORMAL LOSS AND UNEVEN APPLICATION OF COST
Using the data per illustrative problem – C assume that materials are added at the start of the process. The
comparative presentation of costs and equivalent units of production is on the next page.
ILLUSTRATIVE PROBLEM E:
NORMAL AND ABNORMAL LOSSES; UNEVEN APPLICATION OF COST
The following data are on the production of Department B of Silangan Mfg. Co. for September, 2014:
Quantity data:
In process, September 1 10,000 units, 1/4 done
Received from preceding dept 40,000 units
In process, September 30 5,000 units, 1/5 done
Normal loss 2,000 units
Abnormal loss 3,000 units, 1/2 done
Cost data:
Factory costs, September:
Materials P 152,000
Labor 82,000
Factory overhead 32,800
Received from preceding dept 79,800
Work in process, Sept 1 41,400
Materials are added at the start of the process.
For comparative presentation of cost and equivalent units of production, the following independent assumptions
are observed:
Per solution given on the preceding pages, the following may be noted:
The abnormal loss, which occurred at the middle of the process, absorbs part of the cost of normal lost
units except when the latter occurs after the middle of the process.
The cost pertaining to normal loss at the middle of the process is charged to the different groups,
excluding work in process, end. The reason for this is that work in process (end) is only 1/5 done or it
did not reach the middle of the process, the point of normal loss. The abnormal loss shares also in the
cost of normal lost units because the abnormal loss occurred at the middle of the process, the point of
normal loss.
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
Evaporation
o The transformation of liquid into vapour, is a normal loss.
o It occurs due to the nature of materials being used and the type of manufacturing process involved.
o Inasmuch as the percentage of evaporation is generally stated based on the original quantity, beginning
work in process and month-end figures (which are already net of the evaporation that has taken place) are
converted to their original quantities.
Original quantities are used in accounting for total units and in determining the actual quantities
transferred of work in process beginning and of those received during the month.
ILLUSTRATIVE PROBLEM F:
EVAPORATION
In Dept. B of Jolly Mfg. Co., evaporation for 10 days is 5%. The following data are on the August, 2014
production:
Quantity data:
In process, August 1 5,910 gals., 3 days done
Received from Dept A 30,000 gals.
In process, August 31 7,760., 6 days done
Cost data:
In process, August 1 P 24,200
Received from Dept. A 90,000
Factory costs, August:
Materials P 59,092
Labor 29,546
Factory overhead 14,773
With evaporation of 5% for 10 days, evaporation for three days must be .015 or 1.5%. the 5,910 gallons of
beginning work in process must therefore be net of .015 evaporation or equal to 98.5% of original quantity.
The original quantities for beginning and ending goods in process are computed as follows:
Original quantity of work in process, August 1 = 5,910 / [1-(3/10 x .05)]
= 5,910/.985
= 6,000
Original quantity of work in process, August 31 = 7,760 / [1-(6/10 x .05)]
= 7,760/.97
= 8,000
With 6,000 as the original quantity of beginning work in process, the quantity upon completion (or net of the total
evaporation of 5%) must be 5,700 gals. Computed as follows:
Quantity of beginning work in process upon completion = 6,000 gals x (1 - .05)
= 6,000 gals. X .95
= 5,700*
Or 5,910 x (0.95/ .985) = 5,700
The equivalent units of (or effective) production are arrived at as follows:
Original Net Work Done This Equivalent
Month Production
In process, Aug. 1 (5,910/ .985) 6,000
Received from Dept A 30,000
Units to be accounted for 36,000
Department B
References:
Cost accounting by Nenita Mejorada, 3rd Edition.
COST ACCOUNTING AND CONTROL
PROCESS COSTING FIFO INCREASE AND LOSS IN UNITS
Cost accounting by Guillermo M. De Leon Jr. And Norma D. De Leon.
Module 9.2
8
PROCESS COSTING: AVERAGE METHOD
- However, simplification of the costing process does not necessarily imply an improvement in cost estimates.
There are cases wherein the FIFO costing method ought to be used to arrive at fairer estimates of product cost.
- Also called weighted-average method because the quantity (or equivalent production) of each lost is considered
in computing for the average unit costs.
Materials average unit cost = Materials cost added last month to work in process beg. + materials cost Added this month
Equivalent production for materials
Labor average unit cost = Labor cost added last month to work in process beg. + Labor cost Added this month
Equivalent production for labor
Factory overhead average unit cost = FOH cost added last month to work in process beg. + FOH cost Added this month
Equivalent production for factory overhead
EQUIVALENT PRODUCTION
- Computed based on total work done so that, in general, it is equal to completed units plus work done on ending
work in process.
ILLUSTRATION:
1
Equivalent units of production:
2
CASE E : With normal loss during process
3
Per computations, total equivalent production for February is 40,000.
The horizontal and vertical forms for cost analysis are shown on the next page.
In the given illustration, the average unit cost from preceding department is arrived at by dividing the total cost from
preceding department of P 250,500 by the total number of units of 50,000.
When cost of production report is being prepared for the first department, only the department’s average unit cost for each
element is computed
ILLUSTRATIVE PROBLEM A
The Tiger Mfg. Co. has its product processed in two consecutive departments, A and B. For January, 2014, the production
data for te first department are as follows:
Quantity data:
In process, January 1 3,000 units, 1/4 done
Started in process 25,000 units
In process, January 31 2,000 units, 1/4 done
Cost data:
Work in process, January 1:
Materials P 840
Labor 500
Factory overhead 475
Factory cost, January:
Materials P 38,910
Labor 20,700
Factory overhead 19,400
4
Factory costs are applied evenly throughout the process.
The cost of production report is given below:
Tiger Mfg. Co
Cost of Production Report
January, 2014
Department A
Quantity Schedule
Actual Work Done Equivalent
Production
In process, Jan 1 3,000
Started in process 25,000
Units to be accounted for 28,000
Finished and transferred 26,000 100% 26,000
In process, Jan 31 2,000 1/4 500
Units accounted for 28,000 26,500
Cost Analysis: In process, Cost Added Total Cost Unit cost
January 1 this month
Materials P 840 P 38,910 P 39,750 ÷ 26,500 = P 1.50
Labor 500 20,700 21,200 ÷ 26,500 = 0.80
Factory Overhead 475 19,400 19,875 ÷ 26,500 = 0.75
P 1,815 P 79,010
Total cost to be accounted for P 80,825 P 3.05
Costs accounted for as follows:
Finished and transferred 26,000 units P 79,300 [ 26,000 x P 3.05]
In process, January 31 2,000 units
Materials P 750 [500 x P 1.50]
Labor 400 [500 x P 0.80]
Factory overhead 375 [500 x P 0.75]
P 1,525
Total cost accounted for P 80,825
- For a subsequent department, the total average unit cost is equal to the total of the average unit cost from
preceding department and the average unit cost in the department.
ILLUSTRATIVE PROBLEM B
The following data are on the production of Department II of Sumilang Mfg. Co. for March, 2014
Quantity data:
In process, March 1 8,000 units, 3/4 done
Received from Department I 30,000 units
In process, March 31 6,000 units, 1/3 done
Cost data:
Received from Department I P 90,000
In process, March I
Cost, Department I 24,240
Cost, Department II
Materials 3,090
Labor 2,390
Factory overhead 1,780
Factory cost, March
Materials 15,950
Labor 14,610
Factory overhead 11,820
The different elements of cost are applied evenly throughout the process.
The cost of production report is shown below:
5
Sumilang Mfg. Co
Cost of Production Report
March, 2014
Department II
Quantity Schedule
Actual Work Done Equivalent
Production
In process, March 1 8,000
Received from Dept I. 30,000
Units to be accounted for 38,000
Mutya Mfg. Co
Cost of Production Report
April, 2014
Department C
Note:
- With materials added at the start of the process, only the 20,000 units received during the period increased by 5%
or by P 1,000.
- The average unit cost from preceding department is accordingly adjusted by dividing the total cost from
preceding department (of beginning work in process and those received during the month) by the increased
quantity.
- Abnormal loss is costed as a separate lot using the average unit costs as arrived at and based on stage of
completion of the lost units.
ILLUSTRATIVE PROBLEM D
Laguna Mfg. Co. operates five producing departments (A, B, C, D and E). Department E’s production data for May 2014
are as follows:
In process, May 1 5,000 units, 2/5 done
Cost, preceding department P 27,225
Cost, this department
Materials 3,920
7
Labor 2,450
Factory overhead 1,029
Received from Department D ....50,000 units @ P 5.50
In process, May 31 6,000 units, 1/3 done
Abnormal loss 2,000 units, 1/2 done
Factory cost, May
Materials 92,120
Labor 34,790
Factory overhead 18,571
The cost of production report is shown below:
Laguna Mfg. Co
Cost of Production Report
May, 2014
Department E
Quantity Schedule
Actual Work Equivalent
Done Production
In process, May 1 5,000
Received from Dept D 50,000
Units to be accounted for 55,000
NORMAL LOSS
- The cost of lost units is computed and any unrecoverable portion thereof is charged as follows
Loss at the start Remaining units
8
Loss during process Remaining units (Method I)
Equivalent units of production for remaining units (Method II)
Finished units (Method III)
Loss at the end Finished units
- When the point of loss is not given, it may be assumed to have occurred at the start of the process.
- If it is normal loss during process,
o Method I – cost of lost units from preceding department is divided by the remaining good units so that even
ending work in process shares therein.
This is automatically adjusted the following costing period when the cost of lost units in that
period is again spread among all remaining good units.
o Method II – the higher the percentage of work done on a unit, the greater should be its share in the cost of
lost units.
o Method III – the cost of lost units is charged only to the finished units.
Ending work in process is to share in the cost of lost unit upon completion during the next costing
period.
- When loss occurs at a specific point, the FIFO method is preferably used because of the required
identification with the specific group that passed through the point of loss
- When normal loss occurs at the start, the lost units may be subtracted right away in the units’ column so that the
average unit cost from preceding department is automatically adjusted.
o The same is observed when using Method I for normal loss during process.
- Example:
Cost from preceding department of beginning work in process (3,000 units) is P 7,620 and transferred in
cost during the month (48,000 units) is P 122,430. Normal loss during process is 1,000 units.
The adjustment for lost units is based on the average unit cost computed as follows:
Without showing the adjustment for lost units separately, it is automatically included in the computation as follows:
ILLUSTRATIVE PROBLEM E
Rambutan Mfg. Co. has its product processed in three consecutive departments. The June, 2014 production data for the
last department are as follows:
(a) Normal Loss During Process (b) Normal Loss, End of Process
Equivalent Equivalent
Work Done Work Done
Production Production
Cost from Preceding Department: Units Total Cost Unit Cost Total Cost Unit Cost
Work in process, June 1 8,000 32,300.00 4.037500 32,300.00 4.037500
Received this month 40,000 160,000.00 4.000000 160,000.00 4.000000
48,000 192,300.00 4.006250 192,300.00 4.006250
Cost, this Department:
Work in process, June 1
Materials 11,994.00 11,994.00
Labor 6,060.00 6,060.00
Factory Overhead 4,880.00 4,880.00
Cost added this month:
Materials 79,000.00 1.999868 79,000.00 1.956860
Labor 39,500.00 1.001319 39,500.00 0.979785
Factory Overhead 31,600.00 0.801758 31,600.00 0.784516
Total cost added in this department 173,034.00 3.802945 173,034.00 3.721161
7.809195 7.727411
Adjustment for los t units
[(1,000 u. x P 4.00625) / 47,000] 0.085239
[(1,000 u. x P 7.727411) / 45,000] 0.17
Tota cost to be accounted for 365,334.00 7.894434 365,334.00 7.899131
EVAPORATION
- When goods being processed are subject to evaporation, original quantities for beginning and ending work in
process are computed to be assured that all units are accounted for.
- The computation for equivalent production is based on total work done on the end of the month (or net) figures.
- The average unit cost from preceding department is based on the original quantity for each lot.
10
ILLUSTRATIVE PROBLEM F
In Department Y of Masugid Mfg. Co. evaporation is 8% for 20 days. The production data for July, 2014 are as
follows:
In process, July 1 5,880 gals., 5 days done
Cost from preceding dept. P 12,072
Cost this department
Materials 310
Labor 920
Factory overhead 880
Received from preceding dept 30,000 gals. 60,648
Cost added in July:
Materials 5,686
Labor 17,068
Factory overhead 15,609
In process, July 31 8,568 gals. 12 days done
The cost of production report is presented below:
ILLUSTRATION F: EVAPORATION
Masugid Mfg. Co.
Cost of Production Report
July, 2014
Department Y
Net as of Equivalent
Quantity Schedule: Original Work Done
July 31 Production
In Process, July 1
[5,880 / 1 - (8%/20 x 5 days)] 6,000
Received from preceding dept 30,000
Units to be accounted for 36,000
Finished and transferred
(36,000 - 9,000) 27,000 24,840 100% 24,840.0
In Process, June 30 9,000 8,568 12/20 5,140.8
Units accounted for 36,000.00 29,980.80
Cost from Preceding Department: Total Cost Unit Cost
Work in process, July 1 6,000 12,072.00 2.0120
Received from preceding department 30,000 60,648.00 2.0216
36,000 72,720.00 2.0200
Cost added in this Department:
Work in process, June 1
Materials 310.00
Labor 920.00
Factory Overhead 880.00
Cost added this month:
Materials 5,686.00 0.2000
Labor 17,068.00 0.6000
Factory Overhead 15,609.00 0.5500
Total cost added in this department 40,474.00 1.3500
Total cost to be accounted for 113,194.00 3.3700
Cost accounted for as follows:
Finished and transferred 24,840 gals.
Cost preceding dept. 54,540.00 [27,000 x 2.02]
Cost this dept. 33,534.00 [24,840 x 1.35]
88,074.00
Work in Process, July 31 8,5686 gals.
Cost preceding department 18,180.00 [9,000 x 2.02]
Cost this department
Materials 1,028.00 [5,140.8 x 0.20]
Labor 3,084.00 [5,140.8 x 0.60]
Factory Overhead 2,828.00 [5,140.8 x 0.55]
25,120.00
Total cost accounted for 113,194.00
Reference:
Cost Accounting by Nenita Mejorada, 3rd Edition
Cost Accounting by Guillermo De Leon and Norma De Leon
11