4980weldingpiping Rev7-140915
4980weldingpiping Rev7-140915
4980weldingpiping Rev7-140915
Processes correspondence:
02.03 Well Operations Drilling, 02.04 Capital Projects, 02.05 Asset
Integrity, 02.06 Facility Operations, 02.08 Facility Maintenance, 02.09
Modification Projects, 02.10 Well Operations Intervention
Dicipline:
M-Material
Changes:
• Agreed cost cutting elements added (sect. 2.6 and 2.7)
Table of contents
Additional Technical Requirements to NORSOK Standards.................................................. 4
1 General ............................................................................................................................... 5
1.1 Purpose ....................................................................................................................... 5
1.2 Scope .......................................................................................................................... 5
1.3 Target group and responsibility ................................................................................... 5
1.4 Deviation management ............................................................................................... 5
1.5 Definitions / Abbreviations........................................................................................... 5
1.6 References .................................................................................................................. 6
2 Technical Requirements ..................................................................................................... 7
2.1 NORSOK M-601 4.1 General...................................................................................... 7
2.2 NORSOK M-601 4.3.4 Hardness Tests....................................................................... 7
2.3 NORSOK M-601 5.1 (Welding Requirements) General .............................................. 7
2.4 NORSOK M-601 5.5 Welder and Welding Operator Qualification .............................. 7
2.5 NORSOK M-601 5.7.2 Carbon and carbon manganese steels .................................. 8
2.6 NORSOK M-601 6.3 Extent of Non Destructive Testing ............................................. 8
2.7 NORSOK M-601 6.6 Acceptance Criteria ................................................................... 8
2.8 NORSOK M-601 7 Repair ........................................................................................... 8
2.9 NORSOK M-601 8 Positive Material Identification (PMI) ............................................ 8
1 General
1.1 Purpose
These additional technical requirements cover requirements additional to NORSOK standard
M-601, rev.5 “Welding & Inspection of Piping”.
1.2 Scope
This specification applies to all welding related activities to be performed onshore and
offshore.
This specification and M-601 also applies to other than piping fabrication when specified,
such as mechanical packages, etc.
1.6 References
COPSAS reference documents
2 Technical Requirements
2.1 NORSOK M-601 4.1 General
Distance between welds:
Normally the minimum distance between welds shall be 1x diameter of the pipe. If this for
practical reasons is not possible the minimum distance between the welds may be reduced to
2xWT or 50mm (between the weld toes) whichever is greatest.
Fillet welds and welds between support and piping with throat thickness less than 5mm do not
require minimum distance between welds, due to low heat input.
• NDT shall represent completed work (not representing future welds). Meaning that
the NDT shall be performed at regular intervals through the complete fabrication
phase and not only up front
• Highly critical welding (see definition in TCD 4951) - 100% of all welds
• Critical welding - spot check (5-10%)
• Non critical welding - no additional weld inspections
Acceptance criteria for RT inspection of olets: Lack of fusion, cold fusion or other root errors
that can reduce the fatigue life of the joint are not acceptable.