Contents
Contents
Contents
CONTENTS
PROJECT AT A GLANCE
EXECUTIVE SUMMARY
1. INVESTIGATIONS
1.2 Topography
1.3 Meteorology
1.4 Hydrology
2.4 Reservoir
2.5 Spillway
2.6 Outlet
3. DATA STATEMENTS
4 Flood Routing
6 Storage Calculations.
5. PROJECT COST
6. ECONOMIC ANALYSIS
7. APPENDICES
BACK GROUND
during the three monsoon months of summer, while the remaining nine months
are nearly dry and get only one – third. Moreover, the delayed monsoon and
erratic winter rain–fall, which is a common feature, make the crops very
uncertain. On the other hand the topography of the hilly areas with steep ground
slopes, helps the rain water to form into numerous streams running at high
velocities, which erode the good land. Apart from damaging the land and the
erosion of soil, the rain water thus does not get a chance to soak down and
depends entirely on rainfall, which at time is very meager. This cycle of drought is
conserve the rain reservoir run – off for Agriculture, the only solution is to build up
dam, which would also eliminate the hazards caused by delayed rains at the time
of sowing and growing when a little delay in rainfall may results into reduction of
tributary of Kanshi River which outfalls in Jhelum River. The dam site is at a
distance of about 1 K.M from village Domeli Maliaran. Drainage area up to the
dam site is 32.30 Sq. K. Meter. Mean annual rainfall in the Project area is 1100
mm (43.30 inches). However, the Project has been designed on the rainfall of
standard dry year i.e. August 1977 to July 1978 having 886.00 mm (34.88
inches) rainfall. As per yard stick equation given below is applicable for rainfall
run – off calculations, and the run – off has been calculated by the same
equation. Total run – off in standard dry year comes as 6.639 MCM (5381.80
Aft). Catchment area has been calculated from G.T. sheets prepared by Survey
of Pakistan at scale 1:50,000. The probable maximum flood (PMF) discharge has
Survey of dam site and pond area has been carried out by Small
Dams Organization on large scales. These large scale maps have been used in
The proposed project will bring about 1215.00 Ha. (3000 acres) of
land under irrigation. Command area is located on south of dam site. Area will be
irrigated by gravity flow. The whole canal system will be brick masonry
rectangular section. Lining of water courses has been provided as per yard stick
and crop water requirement has been calculated by Penman method. In view of
whole available water in standard dry year by trials on computer. Minimum live
Gross storage capacity of Dam is 7100 Aft including dead storage capacity of
1682 Aft. At the dead storage level of 535 M, the dead storage capacity is much
more than that sufficient to accommodate the sediments inflow of more than 50
DAM SECTION
and earth quake factor of 0.05 g has been taken in design of the dam. Following
proposed as Dam embankment. Central impervious Zone is 10 ft. wide at top and
has 1.0 V : 0.5 H slope on both sides. A cut off trench of 10 ft. depth and 20 ft.
Embankment fill from material available from near the Dam site has
been provided in the flanks. Flanks have 1.0 V : 2.5 H downstream and 1.0 V :
3.0 H upstream slope. Upstream slope has been protected by stone pitching.
A 142.00 Ft.(42.67 M) wide Spillway Channel has been provided.
The capacity of Spillway is 8089.70 Cusec (229.30 M 3/Sec) which is equal to the
highest designed flood of 1000 years return period after routing through
reservoir.
Outlet structure consists of RCC pipe laid in the right side abutment
with control on upstream side. The intake structure will have trash rack, stop log
arrangement and a sluice valve along with a gate valve at upstream side.
53200 feet has been provided to irrigate 3000.00 acres of barren land.
Rectangular section of brick masonry channel has been adopted for channel.
Livestock and Fisheries have been taken into account. The Project would,
however, give a number of other direct and indirect benefits like employment
opportunities, recreation facilities etc. Economic viability of this Project has been
first 50 years life of the Project. However, this project is likely to give benefit for
much longer time as live storage has been kept much higher than required for its
command area. Benefit cost ratio (BCR) and economic internal rate of return
INVESTIGATIONS
1.1 GEOGRAPHIC LOCATION
1.2 TOPOGRAPHY
1.3 METEOROLOGY
under the tropical semiarid with an average annual temperature above 18 0 C and
dry winter.
season from December to March, (2) hot season from April to June, (3) monsoon
season from July to September, and (4) autumn season of October and
temperature.
The climate of the area is also characterized by the extreme
condition in hot season. Relative humidity in May and June varies from about 50
percent in the morning to about 25 percent or less in the afternoon. The highest
day temperature have been recorded in May and June when the hot weather
continues unabated for days together with the mean daily max. temperature
1.4 HYDROLOGY
The Run – off for the catchment has been calculated on the basis
computer applying least square method to determine the rainfall run – off
relationship for the overall catchment of Kahan basin. Following equation has
Where,
1.4.2 Flood
by unit hydrograph method with the help of computer. The maximum probable 24
hours rainfall with 1000 year return period comes to 230 mm. PMF discharge
before routing comes to 1655.40 M3/Sec for 1000 years return period.
1.4.3 Reservoir
storage of 5690 Aft (10.72 million cu. Meter) out of which live storage will be
3735 Aft (6.67 million cu. Meter). Capacity has been fixed higher than maximum
area. Surface area at normal pond level submerged by water shall be 101.21 Ha
(250.00 Acres).
(PMF) has been calculated for one thousand years return period.
computer. The clear water way of spillway has been adopted as 70 meter (230
ft). With this spillway (clear water way), high flood level (H.F.L.) worked out to be
1188.00 ft (362.20 meter). Top level of embankment section for dam is fixed
The maximum probable peak flood discharge for 1000 years return
period is 1655.40 CMS. After flood routing peak flood of 1655.40 CMS through
the reservoir it reduces to 1186 CMS as outflow. The spillway channel has been
proposed under this Project have been computed by Penman method adopted
for climatic conditions of Jhelum area. Monthly crop wise requirement has been
penman formula. Total project water requirement for cultivable command area
has been balanced with water supply from the reservoir storage, keeping in view
the evaporation from the pond surface. It has been estimated that 3735 Aft of live
storage would be required to irrigate 980 Ha of land. Reservoir balance study has
been carried out keeping in view irrigation requirement, evaporation and inflow.
Dead storage level has been kept at R.L. 1158.00 ft (353.0 M), which has been
4955 Aft, (6.11 MCM) which can accommodate incoming sediments in reservoir
for much longer than 50 year i.e. life adopted for economic analysis.
season.
Wheat is a major crop during Rabi season and Millets and Sorghum
are the minor crops during Kharif season which provide vegetation cover and
reduce the erosion. The present cropping intensity is about 102% and the land
different crops and soil structure and texture will improve creating conditions to
retain nutrients for successful growth of plants which helps to raise the crop yield
Like other rain – fed area, the traditional farming is practiced in the
project area. Therefore, the yield of Rabi as well as Kharif crops is low.
Wheat is the major Rabi crop and covers 54% of the total area
area grown in Kharif season. Jowar and Bajra are grown as fodder as well as
grain crop.
The life of the Dam reservoir depends upon the time it takes to silt
Dam type has been selected after studying all possible criteria to
achieve the most feasible, safe and stable structure at an economical cost. An
earth fill zoned Dam has been proposed for this site due to following reasons: -
impervious clay and semi impervious clay are available near the Dam site.
The site is quite suitable for Zoned type of dam as semi – impervious and
Dam.
deformation for Zoned Earth fill Dam, adopted as the dam type for this
Project.
capacity.
ii. The slopes of embankment must be stable during construction and
viii. The design must be such that most severe earth quake, which can
construction controls.
considering all the above criteria and after carrying out some trials to achieve the
embankment section, will have a 1.0 V : 3.0 H upstream slope. The stone
pitching from toe to top of dam has been provided on upstream slope. The
along dam axis is shown in drawing No.____. Typical section of the proposed
A section having 10 ft. width at top with 1.00 H 1.0 V side slope has
been proposed. Top level of this Zone has been kept at H.F.L. The main aim of
this Zone is to act as a barrier against seepage. A steeper slope has been kept
ii. A deep cut – off trench up to 10 ft has been provided. However its
iii. Bottom width of the cut – off trench has been kept 20 ft.
2.3.2 Embankment Fill Zone
the dam site. The use of this near by material in embankment fill zone is not only
zone on downstream side. Similarly sand filter has been provided in between
Upstream slope has been protected by 1.5 ft stone pitching and 1.0
ft graded filter from top of dam up to toe of dam. Downstream slope has been
2.4 RESERVOIR
storage of 8690 Acre feet (10.72 million cubic meter) out of which 3735.00 Acre
feet (4.61 million cubic meter) is live storage. The reservoir capacity has been
kept according to the inflow during the standard dry year of August 1977 to July
1978, to irrigate 2420.00 Acres (980.00 Ha) of land. Surface area at normal pond
2.5 SPILLWAY
Selection of site and type of spillway was also done after care–full
2.6 OUTLET
One outlet has been provided on the left side of Dam R.C.C. pipe
3.00 ft. dia shall be used. Control shall be by means of one sluice valve at
upstream side. The intake structure will have trash rack and stop log
Inspection Hut as per attached plan has been provided for the
facility of field staff and inspecting officers during construction and maintenance.
Minor with a length of 9200 ft. Following are main features of the system:
i. Syphons have been designed with water velocity of 4.0 ft. / Sec.
ii. Channels have been proposed along the natural slope i.e. with
iii. Canal capacity has been designed for 12 hour supply in a day.
HYDRAULIC FACTORS FOR DOMELI DAM
VOL. II
LIST OF DRAWINGS
1. Index plan
5. L-Section of Dam
6. X-Section of Dam
7. L-Section of Spillway
H.F.L. = 1188 ft
Q = 41800 Cs
H = 60 ft
B = 230 ft
d1 = Q / 0.95 B (2gh)1/2
= 3.08 ft
F1 = Q / B d1 ((gd1 )1/2
= 5.93
= 24.34 ft
L/ d2 = 2.45