Hydrotest and Pneumatic Test of Piping Systems-Hydrotest Vs Pneumatic Test With PDF
Hydrotest and Pneumatic Test of Piping Systems-Hydrotest Vs Pneumatic Test With PDF
Hydrotest and Pneumatic Test of Piping Systems-Hydrotest Vs Pneumatic Test With PDF
A pressure test is always required for a new pressure system before use or an
existing pressure system after repair or alteration to ensure the following:
Safety
Reliability of operation
and leak tightness of pressure systems
Also The last physical quality test in the fabrication process
1/16
Hydro test or Hydrostatic test is a type of pressure test performed on piping and
pressure vessels to check system integrity under pressure conditions. A
hydrostatic test is performed by using water as the test medium.
Pressure tests (both hydrostatic and pneumatic) must always be performed under
controlled conditions, following an approved test plan, and documented in a test record. A
single approved test plan could be used for several similar tests, but for each test a
separate test record is required.
In case after carrying out pressure testing, some modification has to be made requiring
hot work, it calls for a retest as per code. Here code specifies that the minor
repairs/modifications may be waived off provided adequate measures have been taken to
ensure sound construction. Now taking this decision as to which repairs or modifications
may be waived off should be taken very carefully. Normally, the maximum extent of
repairs not requiring retesting shall be the tack welding of any piping support or pad.
Anything else shall be done following a retest.
Advertisements
Pressure testing and conducting 100% radiography or ultrasonic inspection shall not be
interchanged. In case carrying out of hydrostatic or pneumatic test stands impractical
then 100% radiography or ultrasonic testing may be performed but in addition to this it is
advisable to check that the whole piping and its components have been supplied against
acceptable ASTM standards and required test certificates are available.
Conducting 100% radiography of all the weld joints assure that your weld
joints are defect-free but can never provide you with the assurance of
mechanical integrity of a system.
This is also to be noted that radiography / ultrasonic inspection shall also not be waived
off if the pipeline is to be hydrostatically tested. This may pose an additional safety risk
during the test. Moreover, some defects in the weld zones may prove to be detrimental
way after being taken in service due to severe extended service conditions.
2/16
Comparison of Hydrostatic and Pneumatic Testing
The following table lists down the major differences between hydrostatic and pneumatic
testing.
3/16
Hydrostatic Testing Pneumatic Testing
In a hydro test, the test media (Water) used In a pneumatic test, the test media,
is not compressible by pressure application. Air is compressible by pressure
application.
In hydrostatic testing, the energy stored per The energy stored per unit volume
unit volume of water under test pressure is of compressed air under test
negligible. pressure in the case of a pneumatic
test is very high.
Pressure Relief devices are usually Pressure relief devices are a must
recommended to control a sudden increase during the pneumatic test to ensure
in pressure during hydro testing. no over-pressurization.
Weight of equipment along with hydro test Weight of equipment with the
medium as water is high hence special pneumatic test medium as air is
attention should be given to floor and comparatively less.
supporting arrangements.
In hydrostatic testing, the test media can be In pneumatic testing, the test media
reused or transferred to other places after can not be reused or transferred to
testing. other places after testing.
4/16
Hydrotest is a regular day-to-day practice Needs special attention and safety
and safe procedure and it can be followed in precautions for performing a
any worksite. pneumatic test.
Pneumatic tests could be performed only when at least one of the following conditions
exists:
When the systems are designed in such a way that it cannot be filled with water.
When the systems are such that it is to be used in services where traces of the
testing medium cannot be tolerated.
Pt=1.5*Pd*(St/Sd)
Here,
5/16
St=allowable stress value at the test temperature
Sd=allowable stress value at design temperature.
Pt=1.1*Pd
1. If the fluid handled by the piping system is liquid then the pipe must be hydro
tested.
2. If the fluid handled is vapor or gas then the internal design pressure dictates
the testing method. For pipe design pressure 10 bar and above the pipe is
hydro tested. For pipe design pressure below 10 bar pipe is pneumatically
tested.
3. If fluid handled is steam then hydro testing is suggested.
4. If the fluid handled is two-phase flow then hydro testing is suggested.
However, for big size flare headers, pneumatic testing is performed.
6/16
Hydrotest Fluid
As the name signifies, the test has to be performed using clean potable water free from
suspended solids. However different codes specify different requirements for water
quality. Hence, hydro tests need to be performed following those instructions.
Piping systems that are normally open to the atmosphere, such as drains, vents,
discharge piping from pressure-relieving devices, sewers, and stack downstream of the
seal drum, need not be subjected to the piping test pressure.
For some
countries, The provincial local inspector shall be notified at least 48 hours
in
advance of pressure testing of piping under the jurisdiction of the
provincial safety code
for witnessing at his/her option.
The following equipment shall be excluded from all piping pressure tests:
Vessels and tanks
Heat exchangers
Rotating machinery, such as pumps, compressors, and turbines
Equipment and Supplier furnished piping specifically recommended by the
manufacturer not to be tested
Underground
portions of piping systems may be tested and covered before testing
aboveground
portions.
Roughly, The
following steps should be followed for preparing the piping system for
leakage
testing.
All sorts of ultrasonic and radiographic inspections or checks must be carried out before
the actual pressure test is started. Conducting 100% radiography of all the weld joints
assure that your weld joints are defect-free but can never provide you with the assurance
7/16
of mechanical integrity of a system. This is also to be noted that radiography / ultrasonic
inspection shall also not be waived off if the pipeline is to be hydrostatically tested.
If required Pipings designed for vapor or gas services shall be provided with additional
temporary supports, to support the weight of test liquid as the test liquid is heavier than
service fluid.
All Spring supports shall be kept in locked condition during hydrostatic testing. Holding
pins shall not be removed from spring supports until testing is completed and the system
is drained. Care shall be taken to avoid overloading any parts of the supporting structures
during hydrostatic testing.
Instruments
All in-line Instruments shall be either removed or blocked prior to hydro testing to
prevent damage during hydro testing (e.g. meters).
Instrument take-off piping and sampling system piping, up to the first block valve,
shall be tested with the piping to which it is connected.
Instrument lead lines, between the first block valve and the instruments to which
they are connected, shall be pressure tested to the test pressure of the associated
piping. Testing may be performed separately or at the same time as the piping is
tested, but the instruments shall be disconnected.
8/16
A sample figure showing hydro-testing scheme
If there is an expansion joint in the piping system under the leakage test, the following
criteria shall be applied.
1. An expansion joint that depends on external main anchors to restrain pressure end
load shall be tested in place in the piping system.
2. A self-restrained expansion joint previously shop-tested by the manufacturer
3. A piping system containing expansion joints shall be leak tested without temporary
joint or anchor restraint at the lesser of
4. 150 % of design pressure for a bellows-type expansion joint, or
5. the system test pressure determined in accordance with para. 345
When a system leak test at a pressure greater than the minimum test pressure
specified in (c), or greater than 150% of the design pressure within the limitations of
para. 345.2.1(a) is required, bellows-type expansion joints shall be removed from
the piping system or temporary restraints shall be added to limit main anchor loads
if necessary.
Rotating Machinery
9/16
For rotary machinery, such as pumps, compressors, or steam turbines, have lube and
seal oil systems that could be impaired by the presence of water. These systems shall not
be subjected to the piping test pressure.
Test Water
Clean water that will not corrode and/or damage the test system shall be used for
hydrostatic tests. If municipal water is not available, supply water may be obtained from a
native water supply. Water containing silt or suspended material shall not be used, and a
suitable filter with 40 mesh should be provided in the filling line. A mixture of glycol-water
shall be used where the ambient temperature may reach less than 0°C (32°F) during
testing or prior to dry-out
Check Valves
Check Valves shall have the piston or flap removed for testing, where pressure can not
be located on the upstream side of the valve. The locking device of the flap pivot pin shall
be reinstated together with the flap and a new cover gasket shall be installed after
completion of the test.
Wherever applicable All hot works, related to welding or the post-weld heat treatment
have to be completed before the Hydrostatic test.
Installation of Barriers
It is necessary to install safety barriers around the piping system under test prior to
starting pressurization related to testing. Public Address announcements and access
restriction procedures such as permits to work shall be implemented. Under no
circumstances should anyone other than an authorized person be allowed within the
safety barriers.
Control Valves
Prior to the leakage test, Control Valves and soft-seal block Valves shall be removed from
the piping and replaced with pipe spools. However, All welded Valves need to be tested
along with pipings otherwise Radiographic Testing of golden joints (welded) will be
required.
10/16
Physical Inspection
Hydrotesting Documentation
The individual system documentation i.e. test pack shall be available prior to any testing
and shall include information such as test limits, test pressure, test medium, duration, test
blinds, blind flanges, vents, and drains.
The use of marked-up P&IDs coupled with isolation registers should be utilized to identify
the locations of blinds, Valves, vents, and drains.
Records shall be
made of each piping system test. In general, these records shall include
the
following information:
Date of test
Identification of piping system
Test medium
Test pressure
Minimum ambient temperature
Test medium temperature
Certification by examiner
Test duration
Pipe standards or
specifications for the test
11/16
Pressure and temperature
recording charts and logs
Location and cause of
leaks/failures
Repair procedures used in the
event that the pipe leaked of failed
Test results
Name of test operator
Minimum metal temperature (if
applicable)
Test gauge calibration date
Forms, when
completed, shall be retained in the Construction Contractor’s QC file as a
permanent record.
Over pressurization
Operator error
Inadequate equipment
Poor component design
Improper isolation of the tested system from equipment or remaining parts of the
system.
Inadequate repairs
So it is always a good idea to follow safe work practices for Hydro testing. The below-
mentioned steps can be followed to avoid hazards of Pressure Testing:
Prepare a standard operating procedure (SOP) for the hydro test or pneumatic test
following the latest applicable code
Developing a checklist using the sop and sticking to it.
Train the involved personnel indicating the potential hazards and safety measures.
Develop a Pre-test safety plan and conduct a pre-test safety briefing just prior to
hydro testing.
Perform a Walk down inspection following the checklist to ensure all hydro test
checkpoints are taken care of.
After the hydrostatic test, gradually release the pressure and drain the system.
Hydrotest Checklist
12/16
The following section provides a sample of the hydro test checklist to inform the major
points that must be considered.
13/16
Hydrotesting Checklist
14/16
20 Working professional with all PPE
equipment
Post-Hydrotest Checklist
What is the difference between the Hydro test and the Hydrostatic test?
Both hydro test and hydrostatic test refers to the same pressure test method. Hence, both
are the same and there is no difference between Hydrotest and Hydrostatic test.
The hydrostatic test pressure considered for pipeline systems is 1.25 times the design
pressure.
A Hydrostatic test is done by filling the system with water and then pressurizing it to hydro
test pressure (usually 1.5 times of design pressure). The pressurized system is kept for a
predecided time and then visually all joints are checked for any leakage.
Yes, a hydrostatic test can cause damage. Some examples of hydro test hazards are
provided here.
15/16
Hydrostatic testing is the safest type of pressure testing as it generated considerably less
stored energy which in turn involves less risk to workers.
Most of the codes and standards prefer to use hydro testing as the best method for
pressure integrity checks. However, in some situations, the hydrostatic test may be
avoided. An example is a golded joint.
A golden joint is usually the final joint to weld the new pipe with the existing pipe.
As the Hydrostatic test is usually not feasible, NDE (ultrasonic or radiographic test)
is performed in place of pressure testing.
It depends on various factors like the governing codes, standards, and local procedures;
length of the system, number of joints to check, etc. Usually, the system should be
pressurized for a least 10 minutes.
16/16