Cost Plus Fixed Fee Agreement
Cost Plus Fixed Fee Agreement
Cost Plus Fixed Fee Agreement
CONTRACTOR’S NAME:
ADDRESS:
PHONE:
FAX:
E-MAIL:
LIC #:
DATE:
OWNER’S NAME:
ADDRESS:
PROJECT ADDRESS:
I. PARTIES
A. CONTRACTOR’S DUTIES
B. CONTRACT DOCUMENTS
1. This Agreement.
2. Any plans, specifications, or addenda referred to in the General
Scope of Work section above.
3. Other:
C. EXCLUSIONS
This Agreement does not include labor or materials for the following
work:
1. PROJECT-SPECIFIC EXCLUSIONS:
2. STANDARD EXCLUSIONS:
Owner (not Contractor) is to enter into contracts for all of the above-
mentioned services and provide direct payment to the people or
agencies contracted with for all of the services and permit fees in the
paragraph above.
If Owner requests that Contractor meet with Owner and architect or
other design professionals to review the construction plans and
specifications prior to completion of the final design documents,
Contractor will perform this work on an hourly basis at the hourly rate
of: PHP____________
Commence work:____________________.
Construction time through substantial completion:
Approximately ____ to ____ weeks/months, not including delays and
adjustments for delays caused by: holidays; inclement weather;
accidents; shortage of labor or material; additional time required for
Change Order and Additional Work; delays caused by Owner, Owner’s
design professionals, agents, and separate contractors; and other delays
unavoidable or beyond the control of the Contractor.
This Agreement will expire 15 days after the date at the top of page
one of this Agreement if not accepted in writing by Owner and returned
to Contractor within that time.
Owner will pay Contractor the Contract Sum consisting of the Cost of
the Work as defined in Section III.H of this Agreement, plus, as
compensation for Contractor’s profit and overhead, a fixed fee of:
PHP________*.
G. PROGRESS PAYMENTS
Add up the total Cost of the Work as defined in Section III.H., below,
which has been performed during the payment period, add the
appropriate percentage of Contractor’s Fee, and the total of these two
amounts will be due each Friday to Contractor.
H. COSTS TO BE REIMBURSED
Owner shall reimburse Contractor the Cost of the Work. The term
“Cost of the Work” shall mean costs necessarily incurred by Contractor in
good faith and in the proper performance of the work. The Cost of the
Work shall include the items set forth in this section.
WORKER RATE
4. SUBCONTRACT COSTS:
Payments made to Subcontractors to properly advance the project
work is part of the Cost of Work for the project.
c. Costs of removal of debris from the site, and hauling and dump fees.
e. The cost of all taxes on the project itself imposed by local, state, or
federal agencies related to the work (not including taxes on employees
The Cost of the Work shall also include any actions taken in case
of an emergency to prevent threatened damage, injury or loss to
persons and property on the job site.
1. Any general insurance costs and state and federal taxes of Contractor
(e.g., worker’s compensation, comprehensive general liability insurance,
auto insurance, health insurance, or labor burden expenses such as state
and federal employer taxes, etc.). Contractor has factored these costs
into the Rate Schedule for Contractor’s Personnel in Section III.H.1,
above, or these costs will be paid out of Contractor’s profit and overhead
percentage.
2. Travel time to and from the job site for Contractor and his employees.
Costs associated with travel time such as: gas, vehicle maintenance,
mileage payments, vehicle insurance, etc.
K. ACCOUNTING RECORDS
_____________________________________
_____________________________________
N. MISCELLANEOUS CONDITIONS
2. INTEREST CHARGES:
Interest in the amount of ____% per month will be charged on all
late payments under this Agreement. “Late Payments” are defined as
any payment not received within _____ days of receipt of invoice from
Contractor.
4. LIEN RELEASES:
Contractor shall have the right to stop all work on the project and
keep the job idle if payments are not made to Contractor strictly in
accordance with the Payment Schedule in this Agreement, or if Owner
repeatedly fails or refuses to furnish Contractor with access to the job
site and/or product selections or information necessary for the
advancement of Contractor’s work. Simultaneous with stopping work on
the project, Contractor must give Owner written notice of the nature of
Owner’s material breach of this Agreement and must also give Owner a
14-day period in which to cure this breach of contract. Owner to follow
this same notice procedure with Contractor if Owner alleges Contractor is
in material breach of this Agreement.
If work is stopped due to any of the above reasons (or for any other
material breach of contract by Owner) for a period of 14 days and Owner
has failed to take significant steps to cure his default, then Contractor
may — without prejudicing any other remedies Contractor may have —
give written notice of termination of the Agreement to Owner and
demand payment for all completed work and materials ordered through
the date of work stoppage and any other reasonable loss sustained by
Contractor, including Contractor’s Profit and Overhead at the rate of
____% on the balance of the incomplete work under the Agreement.
Thereafter, Contractor is relieved from all other contractual duties,
including all Punch List and warranty work.
Q. INSURANCE
R. WARRANTY
Thank you for choosing our company to perform this work for you.
Your satisfaction with our work is a high priority for us, however, not all
possible complaints are covered by our warranty. Contractor does
provide a limited warranty against material defects on all Contractor-
and subcontractor-supplied labor and materials used in this project for a
period of one year following Substantial Completion of all work. This
warranty covers normal usage only. You must contact the Contractor at
the address on page one of this Agreement in writing for warranty
service immediately upon discovering an item in need of warranty
service. If the matter is urgent, you must also call the Contractor and
send written notice of the need for warranty service. Failure to notify the
Contractor of the need for warranty service within ten days of discovery
of a warranty item may void this warranty. Additionally, Owner’s hiring
of others or direct actions by Owner or Owner’s separate contractors to
repair a warranty item are not covered by this warranty and will not be
reimbursed by Contractor.
Repair of the following items and related damages of every kind are
specifically excluded from Contractor’s warranty: problems caused by
lack of Owner maintenance; problems caused by Owner abuse, Owner
misuse, vandalism, Owner modification, or alteration; and ordinary wear
and tear. Damages resulting from mold, fungus, and other organic
pathogens are excluded from this warranty unless caused by the sole
and active negligence of contractor as a direct result of a construction
defect which caused sudden and significant amounts of water infiltration
into a part of the structure. Deviations that arise such as the minor
cracking of concrete, stucco, and plaster; minor stress fractures in
drywall due to the curing of lumber; warping and deflection of wood;
shrinking/cracking of grouts and caulking; fading of paints and finishes
exposed to sunlight are all typical (not material) defects in construction
and are strictly excluded from Contractor’s warranty.
I have read and understood, and I agree to, all of the terms and
conditions in the Agreement above.
_________ ______________________
DATE CONTRACTOR’S SIGNATURE
_________ ______________________
DATE OWNER’S SIGNATURE
_________ ______________________
DATE OWNER’S SIGNATURE