Chapter-5 Cost Establishment
Chapter-5 Cost Establishment
Chapter-5 Cost Establishment
CHAPTER- 4
PROJECT COST ESTIMATION AND VALUATION
November 2011
(NASIR B.)
CONTENTS
Introduction
3
4.1. Introduction Cont.
An estimate serves a number of different functions, depending on the
stage of the project, as shown below :
Feasibility: Initially feasibility of the project need to be determined
Feasibility Estimate (Conceptual).
Schematic Design (Conceptual design): Sketches are prepared.
Major elements are defined Use a preliminary method to
estimate cost. Cost of each element is established (cost plan).
Design Development: Progressively the scope of the project is
defined A series of preliminary estimates are done during this
phase to assure adherence to cost plan.
Contract Document: Finalize drawings & Specifications:
Designer’s estimate to anticipate and check contractor’s bid
prices.
4
4.1. Introduction Cont.
Bidding Phase: Contractors prepare detailed estimate to submit
bids.
Construction Phase: Estimates are prepared for cost for cost
Control and for change order evaluations.
Feasibility Estimate (Conceptual Estimate)
Needed to make decision go/no go with project
Costs include:
Land
Financing cost
Consultations/Studies
Engineering
Project Management
Construction
Operation & Maintenance
5
4.1. Introduction Cont.
Preliminary Estimates and Cost Planning
The Conceptual Estimate found during feasibility becomes the initial
project budget
Subsequent design development should remain within the limit of
this budget
For that purpose, several preliminary estimates are performed as
more details become available through the design.
Preliminary estimates assign cost to various assemblies (elements) of
the project (Cost Plan). {substructure, superstructure, interior
partitions & doors, exterior cladding ..etc.}
Preliminary estimates allow for Value Analysis – Compare value of
an element with its cost Consider alternatives Select desired
option.
6
4.1. Introduction Cont.
Over all the main purpose of cost estimation can be summarized as
follow:
know the volume of work in reference to the fund available
determine actual cost per unit of item
identifying engineering estimate of the work for bidding purpose
work out economical use of materials , labor and equipments
in cases of variations to determine the extra cost to be incurred
when there is escalation, to work out the escalation in cost
7
4.2. Information required for cost estimation
The following information is required to define cost per unit of work
Correct information of the market price of the materials at the
time of need to be used as a basic price
Correct information of the rates of various categories of skilled
and unskilled laborers as wage rates to be used for daily work
rate
Output of laborers per day for various types of items
(productivity)
Correct information of the rates of various categories of
equipments and tools as rental rates to be used for major items of
rates
Up-to-date knowledge of the construction methods.
8
4.3. Knowledge and managerial skills for cost estimation
The following knowledge, managerial talents, and degree of
construction experience make a good estimator.
Ability to read and understand contract documents, with special
skills in reading construction drawings for all specialties and
related specifications.
Ability to accurately take off the quantities of construction work
for which he or she is preparing the detail estimate.
Ability to visualize the future building from drawings, which
usually requires some years of construction site experience.
Knowledge of arithmetic, basic geometry, and statistics.
9
4.3. Knowledge and managerial skills for cost estimation
The following knowledge, managerial talents, and degree of
construction experience make a good estimator.
Familiarity with estimating software in depth and with available
building cost databases.
Knowledge of building construction methods.
Knowledge of labor productivity, crew composition, and impacts
of various forecasted site conditions on crew output.
Possession of office managerial skills in organizing project-
related cost information.
Ability to work under pressure and to meet all bid requirements
and deadlines.
10
4.4. Factors Affecting Cost Estimation
Factors which affect the cost estimation are summarized as follow:
11
4.5. Types of Costing or Estimation
Estimation can be broadly classified as preliminary (approximate)
and detailed.
Preliminary /approximate costing
This type of cost estimation is required to know the financial
position of the client before costly detailed designs are carried out.
Such estimates are based on practical knowledge and cost of similar
previous works. Examples of approximate cost estimations are as
follows:
A. Cost per functional unit
Hospital =cost per bed, Dormitory = cost per student, Cinema or
theatre = cost per seat, residential buildings = cost per area, road
works = cost per kilometer length, culverts or bridges = cost per
meter span, water supply or sewerage projects = cost per head of
population.
12
4.5. Types of Costing or Estimation
Preliminary /approximate costing
B. Plinth area method – cost per m2
Based on Plinth Area- roof area or external dimensions at the plinth
level (Courtyard & open area shall not be included)
The rate per meter square is deduced from the cost of similar
building projects in the locality.
C. Cubical Content method – cost per m3
Based on cubical contents of various buildings, i.e. Plinth area of the
building x height x cubic content rate.
Height should be taken from the top of flat roof (or halfway of the
sloped roof) to the top of concrete in foundation.
13
4.5. Types of Costing or Estimation
Detailed Cost Estimate (Based on Item Rate)
This is the most reliable and accurate type of estimate.
The quantities of items are carefully prepared from the drawings and
the total cost worked out from up to date market rates.
A detail cost estimate thus requires:
Quantity surveying and
Analysis of the different rates for the quantities prepared.
14
4.6. Fundamental approach to construction cost Estimation
Efficient construction cost estimates shall address properly the
required project quality, time for completion of works and of course
the construction cost of the project.
In deciding to participate in the intended project tender, the
contractor shall carefully assess the impact of the following key
factors:
Type of project
Method of tendering
Type of construction contract
Number and progress of contracts already at hand
Resource availability i.e. skilled manpower, plants and
machineries
Financial position
15
4.6. Fundamental approach to construction cost Estimation
cont.
Once decision is made to participate in the intended tender, the
contractor shall give due attention to the following major items
listed below
General and particular conditions of contract contained in the
bidding documents
Technical specifications
Drawings
Estimated bill of quantities
Method of measurement
Supporting documents such as information regarding geological
formations and hydrological data
Site visits
Construction method statements
16
4.6. Fundamental approach to construction cost Estimation
cont.
A. General and particular conditions of contract
Proper understanding of the general and particular conditions of
contract is mainly important for construction cost estimation in
identifying the responsibilities and cost implications on the project
Amount and type of performance security
Amount of advance payment and type of advance repayment
guarantee
Time for completion of the whole project
Limit of liquidated damages
Retention money
Claims and disputes settlement
17
4.6. Fundamental approach to construction cost Estimation
cont.
A. General and particular conditions of contract
Price escalation
Tax exemptions
Insurance of the works
Owner’s risks
Applicable laws
18
4.6. Fundamental approach to construction cost Estimation
cont.
B. Technical Specification
Technical specifications specify the following crucial information to
the contractor and it is the sole basis both for the construction
methods to be adapted and the construction cost of the project.
Quality of materials
Quality of machineries and plants
Quality of workmanship
Erection and installation methods
Test and inspection requirements and methods
19
4.6. Fundamental approach to construction cost Estimation
cont.
B. Technical Specification
Technical specifications basically have restricted applications, which
usually define specific work items. Therefore, for a better
understanding and cost estimation of the project, the contractor must
check the given specifications for:
Technical accuracy and adequacy
Define and clear stipulations
Fair and equitable requirements
Formats which can be easily used during bidding and
construction
Legal enforceability
20
4.6. Fundamental approach to construction cost Estimation
C. Drawings
The contractor mainly understands from the drawings what type of
construction methods to be adapted during cost estimation as well as
construction of the project.
some of the construction methods which need to be addressed during
cost estimation of this building project are:
Concrete production
Concrete transportation and placement
Transportation of construction materials to different floors
Methods and type of scaffolding
Types and methods of shuttering works
Erection and installation of glazing works
Temporary access for manpower working at different floors
Skilled manpower requirement
21
4.6. Fundamental approach to construction cost Estimation
cont.
D. Estimated Bill Quantities
Estimated quantities of work are also the basis to determine the type
and number of resources to be deployed during construction of the
project.
Moreover, construction methods shall be selected in such a way the
given quantity of works can be executed during the completion time
of the project.
22
4.6. Fundamental approach to construction cost Estimation
cont.
D. Estimated Bill Quantities
Based on the estimated quantity of works, the contractor shall decide
the method of construction to be adapted during executing of the
project such as:
Type and size of crushing plants
Type and size of mechanical mixers or batching plants
Type, size and number of machineries such as dozers, graders,
loaders, rollers, dump trucks and so on.
Skill and number of manpower requirement
Type and quantity of construction materials
And so on
23
4.6. Fundamental approach to construction cost Estimation
cont.
E. Supporting Documents
Supporting documents such as geological formations, hydrological
data and other technical reports like socio-economic studies are
usually provided by the owner to contractors for their own
interpretations for heavy construction projects.
Therefore, the contractor shall have the technical ability and
experience in interpreting the technical data provided to determine
construction methods to be adapted which directly affects the
construction cost estimates.
24
4.6. Fundamental approach to construction cost Estimation
cont.
F. Site Visit
In order to prepare competent and reasonable construction cost
estimates, the contractor must visit the project site unless the site is
familiar to the contractor with previous reliable site information.
Site visits are critically important especially when the contractor is
working with heavy construction project cost estimates such as road
works and hydropower projects.
The contractor shall prepare his own checklists during the site visit
which shall address, but not limited to, the following issues which
have direct impact on the construction costs of the intended project.
25
4.6. Fundamental approach to construction cost Estimation
cont.
F. Site Visit
i. Location of the site:
It helps to determine the mobilization and demobilization costs.
28
4.6. Fundamental approach to construction cost Estimation
cont.
G. Construction Method Statements
Construction method statements give the clear picture of each project
activity execution during the construction phase of the project.
The required quality of works as per the specifications, estimated
quantity of works, safety standards, as well as time for completion
are the sole basis in determining the construction method statements
of a project.
29
4.6. Fundamental approach to construction cost Estimation
cont.
G. Construction Method Statements
Construction method statements shall clearly indicate the following
crucial construction issues:
Skill and number of manpower required
Type and specification of equipments required
Quantity and quality of materials required
Proposed working crews
Estimated crew productivity
Estimated duration for completion
Expected defects and remedial measures
30
4.7. Basic Cost Components of a construction project
Basically the cost of any construction project comprises
Direct costs, which include the direct cost of materials, labor as
well as equipments and
Indirect costs, which include but not limited to head office and
site overhead costs.
A. Direct Construction Cost
Direct construction costs are all costs that can be specifically booked
with an activity in a project.
The current trend is to assign as much as possible costs to direct costs
as these costs can be budgeted, monitored and controlled far more
effectively than the indirect costs.
31
4.7. Basic Cost Components of a construction project
A. Direct Construction Cost
The direct costs mainly include material, labor, equipment and
subcontract costs as described below.
Direct material costs – These costs referring to the cost of
materials, consumables and components used for executing an
activity including the allowances for scrap and wastages.
Direct labor costs – All costs related to the workers working on a
specific activity such as carpenters, masons, erectors, painters,
plumbers and so on.
Direct equipment costs – These costs referring to the costs of
machineries and plants used in executing a specific activity.
Subcontract costs – In case some specific activities are
subcontracted, the subcontract price will be considered as the
direct cost of the activities to be executed by the subcontractor.
32
4.7. Basic Cost Components of a construction project
B. Indirect Construction Cost
Indirect construction costs are all costs, which can not be directly
booked under a specific activity in a construction project but required
to keep the whole project operational.
These costs are also called overhead costs, which mainly include the
head office and site overhead costs.
i. Head office overhead costs
Head office overhead costs are all costs required to run the whole
operation of the construction company, which usually administers
different projects at a time.
These costs are not usually associated with specific project but rather
shared proportionally by all projects under the company.
33
4.7. Basic Cost Components of a construction project
B. Indirect Construction Cost
i. Head office overhead costs
Some of the checklists for head office overhead costs are given below
with further clarifications.
Senior management costs – These refer to costs related with salaries
and benefit packages of the senior management in the head office.
Indirect labor costs – Staffs other than the senior management
members working at the head office such as the technical,
administrative, marketing, finance and supply staffs.
Head office building costs – In both cases, costs are incurred in such
a way either rental costs will be paid, if the building is rented and
building depreciation will be considered, if the building is owned.
34
4.7. Basic Cost Components of a construction project
B. Indirect Construction Cost
i. Head office overhead costs
Bidding Expenses – These costs are usually associated with bid
document purchases, site visit expenses, bid bonds and so on. These
costs are sometimes called sunk costs.
Expertise service costs – These costs will be incurred when
professional services are required such as the services of external
auditors, lawyers, management consultants and external trainings.
Office furniture and equipments – Different office furniture and
equipments are required depending on the size and standard of the
company.
Office running expenses – The head office operation requires lots of
miscellaneous expenses such as telephones, fax, internet services,
stationery, mail services and so many others.
35
4.7. Basic Cost Components of a construction project
B. Indirect Construction Cost
i. Head office overhead costs
Workshops, garages and warehouses – Costs related to central
workshops, garages and warehouses such as the depreciation costs of
the buildings or rental expenses.
Bank charges – It is very natural that companies may borrow money
from banks. Therefore, the interest to be paid on the borrowed capital
shall be considered under the head office costs.
Insurance charges – Employees medical insurance, office building
and small vehicles insurance.
Transportation and travel expenses –costs related to transportation,
per diem and living expenses.
Sundry expenses – These are miscellaneous expenses such as
advertisement expenses, reception parties and donations.
36
4.7. Basic Cost Components of a construction project
B. Indirect Construction Cost
ii. Site overhead costs
Site overhead costs are all costs required to run the whole operation
of a specific construction project at site level.
These costs are not associated with specific activity in a project but
rather shared proportionally by all activities within the project. Some
of the site overhead costs are listed below with further clarifications.
Site management costs – These costs refer to costs related with
salaries and benefit packages of the site management members in the
project site.
Indirect labor costs – salaries and benefits of staffs other than the site
management members working at the project site such as site
engineers, office engineers, administrative and finance staffs, data
collectors and so on.
37
4.7. Basic Cost Components of a construction project
B. Indirect Construction Cost
ii. Site overhead costs
Mobilization and demobilization costs –These costs are mainly
transportation costs.
Tender Expenses – These costs are related with the costs of the
contract performance security, advance repayment guarantee,
contractor’s all risk insurance, insurance of the works and third party
insurance depending on the contract conditions agreed.
Site offices –site offices are constructed from different materials such
as corrugated iron sheets, prefabricated materials, material packing
steel containers, steel structure and normal hollow concrete blocks.
Expertise service costs – These costs will be incurred when
professional services are required at the project site such as lawyers,
claim experts and so on.
38
4.7. Basic Cost Components of a construction project
B. Indirect Construction Cost
ii. Site overhead costs
Office furniture and equipments – Different office furniture and
equipments are required depending on the size and location of the
project.
Office running expenses - The site office operation requires different
expenses such as telephones, fax, internet service, mail service and
stationery.
Radio communications - If the coverage area of the construction
project is vast, hand held and stationed radio communications may be
used within the site and with the head office.
39
4.7. Basic Cost Components of a construction project
B. Indirect Construction Cost
ii. Site overhead costs
Camp facilities – The costs of construction and operation of other
facilities such as restaurants, recreational centers and playgrounds are
also included under the camp facilities.
Access roads – Depending on the topography and location of the
project site, different access roads may be required to construct such
as detour roads, access roads to quarry and disposal areas, etc.
Water and power supply – All the site offices, camp facilities, the
construction itself requires water and power supply for operating the
whole project properly.
Workshops garages and warehouses, Bank charges, Transportation
and travel expenses, Insurance charges, etc…
40
4.7. Basic Cost Components of a construction project
C. Risk Allowance
Usually contractors incorporate risk allowances in their tender prices
to compensate the negative impacts of different risks such as
contractual, technical, political and economic risks.
Contractual risks are usually stemming from the contract agreements
with the project owner, subcontractors and suppliers.
Technical risks are associated usually with the clarification of the
technical specifications, working drawings, construction technology
and difficulties in understanding new method of constructions.
Political and economic risks reflect the impact of political situations,
stability of economic policies, inflation and price escalation on the
execution of the intended construction project.
41
4.7. Basic Cost Components of a construction project
D. Profit and Income Tax
construction projects are executed by contractors whereby these
contractors will commit to invest their capital to get maximum
possible profit from the contracts to be performed.
A profit margin entirely depends on the market competitiveness and
company strategies.
Any construction company operating a profitable business in
Ethiopia shall pay 30% of its gross profit as an income tax as per the
income tax proclamation No. 286/2002.
If the contractor is registered for VAT, which is usually the case, the
contractor’s construction cost estimate shall also include Value Added
Tax which is 15% of the tender amount in accordance with the Value
Added Tax proclamation No. 285/2002.
42
4.8. Unit Rate Analysis
Rate Analysis is the process of fixing cost per unit of measurement
for the different item of works.
Total cost per unit of work (TC): Direct cost (DC) + Indirect cost
(IC)
Direct Cost (DC) includes cost due to material (MC), cost due to
labor (LC), cost due to equipment (EC)
Indirect Cost (IC) covers overhead costs, and contractor’s profit.
In order to facilitate estimation Material break down is essential
Different formats, Excel sheets and software (like CONMIS) are
used for rate analysis.
43
4.8. Unit Rate Analysis Cont.
It is advisable that contractors shall adapt suitable construction cost
estimation formats which enables to see all the detailed cost
breakdowns of the required:
Direct materials,
Labor and equipment
Head office and site overhead costs,
Risk allowances,
Profit,
Income tax and
Value Added Tax (VAT) or Turnover tax (TOT).
44
4.8. Unit Rate Analysis Cont.
construction cost estimation formats and procedures shall also serve
as the basis for different purposes as listed below in managing the
project during construction.
Construction planning
Project cash flow preparation
Productivity data collection
Material consumption data collection
Construction monitoring
Performance evaluation and controlling
Performance related pay
Subcontractor’s price evaluation
Variations and claims substantiation
Remedial measures and improvements
45
46
4.8. Unit Rate Analysis Cont.
I. Direct Material Unit Cost (E)
Direct material cost is the total cost of construction materials
required to execute a unit of specific activity in a project.
In estimating the direct material cost, the contractor shall obtain the
quantity and quality of materials required to produce the specific
unit of an activity
47
4.8. Unit Rate Analysis Cont.
I. Direct Material Unit Cost (E)
In order to have a better material cost estimation, contractors shall
develop their own material price database and the database should
contain, but not limited to, the following information:
Material price at place of delivery
Supplier’s address such as telephone, fax and mail address
Supplier’s contact person
Supplier’s email address and web site
Supplier’s credit facility
Country of origin
Material delivery time
Place of delivery such as at the supplier’s shop, project site,
Addis Ababa air port or Djibouti port
Transportation charges usually per ton-km as well as transporters
48
4.8. Unit Rate Analysis Cont.
I. Direct Material Unit Cost (E)
the contractor shall add the following costs to the material supplier’s
price to get the material unit cost at the project site:
Loading expenses at the supplier’s place of delivery
Transportation costs to the project site
Insurance charges during transportation to the project site
Unloading expenses at the project site
49
4.8. Unit Rate Analysis Cont.
I. Direct Material Unit Cost (E)
Unless otherwise stated on the contract conditions and investment
incentives, contractors shall add the following costs, but not limited,
to the CIF Djibouti price to get the final material unit cost at the
project site.
Port clearance
Duty
Excise tax
Value Added Tax
Customs clearance
Clearing Agent’s fee
Transportation cost from Port to the project site
Insurance, if required, during transportation
Unloading expenses at the project site
50
4.8. Unit Rate Analysis Cont.
I. Direct Material Unit Cost (E)
Example: Assume the CIF price at Djibouti Port for Re-bar is 4,115.53
Birr/ton
51
4.8. Unit Rate Analysis Cont.
I. Direct Material Unit Cost (E)
52
4.8. Unit Rate Analysis Cont.
I. Direct Material Unit Cost (E)
53
4.8. Unit Rate Analysis Cont.
II. Direct Labor Unit Cost (F)
In calculating the direct labor cost, contractors need to calculate the
direct labor hourly cost which is the total hourly cost of labor crew
required to execute a specific activity in the project.
In estimating the direct labor hourly cost, the contractor shall obtain
the:
Number of labor,
Skill and labor utilization factor (UF)
Labor basic salary and
Labor index from his previous records and the labor market.
54
4.8. Unit Rate Analysis Cont.
II. Direct Labor Unit Cost (F)
Labor index is a multiplying factor of the basic salary which
represents the additional benefits whereby a worker gets from the
contractor such as:
Severance pay
Annual leave
Occupational accident expenses
Occupational disease expenses
Overtime pay
Occupational safety, health and working environment
Benefits resulting from collective agreements
55
Labor Index Calculation
25.71 days/ mth
1. Regular Salary = = 1.00
25.71 days/ mth
2.0 days/ mth
2. Annual Leave = = 0.078
25.71 days/ mth
0.92 days/ mth
3.Public Holidays = = 0.036
25.71 days/ mth
1.5 days/ mth
4. Miscellaneous Leave = = 0.058
25.71 days/ mth
5 Benefits
0.08 days/ mth
5.1. Closing & supplies = = 0.003
25.71 days/ mth
3.43 days/ mth
5.2. Avg Annual Increase = = 0.133
25.71 days/ mth
5 days/ mth
6. Rainy Season Salary = = 0.1945
25.71 days/ mth
Sub Total 1.50
Contingency ( for work injury, dispute & labor union)
5 % of the total indexed cost = .05*1.46 0.08
Grand Total Indexed Factor 1.58
56
4.8. Unit Rate Analysis Cont.
III. Direct Equipment Cost (G)
In order to calculate the direct equipment cost, contractors need to
calculate the direct equipment hourly cost which is the total hourly
cost of equipment crew required to execute a specific activity in a
project.
In estimating the direct equipment hourly cost, the contractor shall
obtain
The number of equipments,
Capacity and equipment utilization factor (UF), and
The equipment hourly cost.
57
4.8. Unit Rate Analysis Cont.
IV. Site Overhead Cost (I)
It is easier to express the site overhead costs as a percentage of the
direct unit cost of an activity.
58
4.8. Unit Rate Analysis Cont.
VI. Risk Allowance (L)
Let’s assume the following factors represent the percentage cost
increment of each cost component and the risk allowance will be
calculated as follows:
59
4.8. Unit Rate Analysis Cont.
VII. Gross Profit (M)
As an illustration, if the net profit margin is assumed to be P% of
the breakeven cost (direct costs + indirect costs + risk allowances),
the gross profit (net profit + income tax) can be calculated as
follows, which is X% of the breakeven cost.
60
4.8. Unit Rate Analysis Cont.
VIII. Total unit price without VAT
If the contractor is registered for VAT but the contract is VAT
exempted, the contractor’s unit price in his tender is the sum of direct
unit cost (H), indirect unit cost (K), risk allowance (L) and gross
profit (M).
61
THANK YOU!
62