RFP FW
RFP FW
RFP FW
Item Rate
UNIT NO. 702-B, KONNECTUS TOWER, DMRC BUILDING, AJMERI GATE, NEW DELHI-
110002
Dated: 15.12.2022
1
TABLE OF CONTENTS
Clause Subject Page
Request for Proposal 9
Disclaimer 10
1 Introduction 11
1.1 Background 11
1.2 Brief description of Bidding Process 13
1.3 Schedule of Bidding Process 14
1.3 A Details to be filled in by Tenderer while uploading their offer 15
1.3 B Check list of documents to be uploaded while submitting offer 16
1.3 C Checklist of Documents attached with offer 17
1.3 D Precautions to be taken for preparing legal document 23
PART 1 Instructions to Tenderers (ITT) 24
1. 1.0 Applicability 24
1.01 Order of Precedence of Documents 24
1.1 Interpretation 25
1.2 Definition 25
1.3 Singular And Plural 26
Credentials of Contractors 26
2. Application for Registration and Approved list of contractors 26
Tenders for Works 27
3. Tender Form 27
4. Omissions and Discrepancies 28
5. Bid Security 28
6. Care in Submission of Tenders 29
6.1 Certificate by Contractor 30
6.2 Instructions on Accessing/Purchasing of Bid Documents and Submission thereof 30
6.3 Registration 31
6.4 Searching for Tender Document 31
6.5 Preparation of Bids 31
6.6 Submission of Bids 32
6.7 Assistance to Bidders 33
6.8 Clarification on Tender Documents 34
6.9 Amendment of Tender Document 34
6.10 Preparation and Submission of Bids 35
6.11 Points to be kept in mind while preparing bid 37
Consideration of Tenders 37
7. Right of RLDA to Deal with Tenders 38
7A. Two Packets System of Tendering 38
7B. Pre Bid Conference 38
7C. Make in India Policy 38
7D. Permission to Bid for a bidder from a country which shares Landboundary 38
2
with India
3
Technical Representative / Project/ Site / Planning / Billing Engineer
12. Additional Special Conditions 140
13. Site Laboratory 143
Third Sheet – Annexure-I (Bill of Quantities) 147
Annexure-II Agreement for RLDA Contract 148
Annexure-III Work Order Under RLDA Contract 149
Annexure-IV RLDA Contract Agreement of Works 151
Annexure-V Format for Certificate to be submitted / uploadedby Tenderer 152
along with the tender documents
Annexure-VI Tenderer’s Credentials (Bid Capacity) 154
PART - II
4
13 Relics and Treasures 167
14. Excavated Material 167
15. Indemnity by Contractors 167
16. (1) Security Deposit 167
(2) Refund of Security Deposit 168
(3) Interest on Amount 168
(4) Performance Guarantee 168
17. Force Majeure Clause 169
17-A. Extension of Time in Contracts 170
(i) Extension due to Modification 170
(ii) Extension for Delay not due to RLDA or Contractor 170
(iii) Extension for Delay due to RLDA 170
17B. Extension of Time with Liquidated Damages (LD) for delay due to 171
Contractor
17 C Bonus for Early Completion of Work 172
18. Illegal Gratification 172
Execution Of Works 172
19. (1) Contractor's Understanding 172
(2) Commencement of Works 173
(3) Accepted Programme of Works 173
(4) Setting out of Works 174
20. (1) Compliance to Engineer's Instructions 174
(2) Alterations to be Authorized 174
(3) Extra Works 174
(4) Separate Contracts in Connection with Works 174
21. Instructions of Engineer's Representative 174
22. (1) Adherence to Specification and Drawings 175
(2) Drawings and Specifications of the Works 175
(3) Ownership of Drawings and Specifications 175
(4) Compliance with Contractor's Request for Details 175
(5) Meaning and Intent of Specifications and Drawings 175
23. Working During Night 175
24. Damage to RLDA Property or Private Life and Property 175
25. Sheds, Stores-Houses and Yards 176
26. Provision of Efficient and Competent Staff at Work Sites by the 176
Contractor
26A. Deployment of Qualified Engineers at Work Sites by the Contractor 176
27. (1) Workmanship and Testing 177
(2) Removal of Improper Work and Materials 177
28. Facilities for Inspection 177
29. Examination of Works before Covering up 177
5
30. Temporary Works 177
31. (1) Contractor to Supply Water for Works 178
(2) Water Supply from Railway System 178
(3) Water Supply by Railway Transport 178
(4) (A) Contractor to Arrange Supply of Electric Power for Works 178
(B) Electric Supply from the Railway System 178
32. Property in Materials and Plant 178
33. (1) Tools, Plant and Materials Supplied by RLDA 179
(2) Hire of RLDA’s Plant 179
34. (1) Precautions During Progress of Works 179
(2) Roads and Water Courses 179
(3) Provision of Access to Premises 179
(4) Safety of Public 179
(5) Display Board 180
35. Use Of Explosives 180
36. Suspension of Works 180
Suspension Lasting More Than Three Months 180
37. Rates for Items of Works 180
38. Demurrage and Wharfage Dues 181
39. Rates for Extra Items of Works 181
40. (1) Handing over of Works 182
(2) Clearance of Site on Completion 182
40A Offloading of Parts of work 183
Variations in Extent of Contract 183
41. Modification to Contract to be in Writing 183
42. Power of Modifications to Contract 183
Valuation of Variations 185
43. Claims 185
(1) Quarterly Statement of Claims 185
(2) Signing of ’No Claim Certificate’ 185
Measurement, Certificates and Payments 185
44. Quantities in Bill(s) of Quantities Annexed to Contract 185
45. Measurements of Works 185
46. (1) "On Account” Payments 187
(2) Rounding off Amounts 187
(3) "On Account” Payments not Prejudicial to Final Settlement 187
(4) Payment of Advances 187
(5) Manner of Payment 188
46A. Price Variation Clause (PVC) 188
47. Maintenance of Works 202
6
48. (1) Certificate of Completion of Works 202
(2) Contractor not Absolved by Completion Certificate 203
(3) Final Supplementry Agreement 203
49. Approval only by Maintenance Certificate 203
50. (1) Maintenance Certificate 203
(2) Cessation of RLDA’s Liability 204
(3) Unfulfilled Obligations 204
51. (1) Final Payment 204
(2) Post Payment Audit 204
51-A. Production of Vouchers etc. by the Contractor 204
52. Withholding and Lien in Respect of Sums Claimed 205
52-A. Lien in Respect of Claims in other Contracts 206
53. Signature on Receipts for Amounts 206
Labour 206
54. Wages to Labour 206
54-A. Apprentices Act 206
55. Provisions of Payments of Wages Act 207
55-A. Provisions of Contract Labour (Regulation and Abolition) Act, 1970 207
55-B. Provisions of Employees Provident Fund and Miscellaneous Provisions Act, 1952 208
55-C. Shramikkalyan Portal 208
55-D. Provisions of “The Building and Other Construction Workers (RECS) Act, 1996” 209
and “The Building and Other Construction Workers’ Welfare Cess Act, 1996” :
56. Reporting of Accidents 209
57. Provision of Workmen's Compensation Act 209
57-A. Provision of Mines Act 209
58. RLDA not to Provide Quarters for Contractors 209
59. (1) Labour Camps 209
(2) Compliance to Rules for Employment of Labour 210
(3) Preservation of Peace 210
(4) Sanitary Arrangements 210
(5) Outbreak of Infectious Diseases 210
(6) Treatment of Contractor's Staff in Railway Hospitals 210
(7) Medical Facilities at Site 210
(8) Use of intoxicants 211
(9) Restriction on the Employment of Retired Engineers of Govt. 211
Services within One Year of their Retirement
60. (1) Non-Employment of Labourers below the age of 15 Years 211
(2) Medical Certificate of Fitness for Labour 211
7
(3) Period of Validity of Medical Fitness Certificate 211
(4) Medical Re-Examination of Labourer 211
Determination of Contract 212
61. (1) Right of RLDA to Determine the Contract 212
(2) Payment on Determination of Contract 212
(3) No Claim on Compensation 212
62. (1) Determination of Contract owing to Default of Contractor 212
(2) Right of RLDA after Rescission of Contract owing to Default of 213
Contractor
Settlement of Disputes 214
63. Conciliation of Disputes 214
(1) Matters finally Determined by the RLDA 215
(2) Dispute Adjudication Board (DAB) 215
64. (1) Demand for Arbitration 217
(2) Obligations During Pendency of Arbitration 218
(3) Appointment of Arbitrator 218
(4), (5), (6) (7) & (8) - Arbitral Award & General 218-221
Annexures : 222
Annexure-VII Proforma for Time Extension 222
Annexure-VIIA Proforma for 14 Days Notice for Offloading of Part of 223
Contract work
Annexure-VIIB Proforma for Notice for Part of Contract work Offloaded 224
Annexure-VIII Certificate of Fitness 226
Annexure-IX Proforma of 7 Days’ Notice 227
Annexure-X Proforma of 48 Hrs. Notice 228
Annexure-XI Proforma of Termination Notice 229
Annexure-XII Proforma of 48 Hrs. Notice (Part Termination) 230
Annexure-XIII Proforma of termination Notice (Part Termination) 231
Annexure-XIV Final Supplementary Agreement 232
Annexure-XV Agreement towards Waiver Under Section 12(5) and 234
Section 31(A)(5) of Arbitration and Conciliation (Amendment) Act
Annexure-XVI Certification by Arbitrators appointed under Clause 63 & 235
64 of RLDA General Conditions of Contract
Annexure-B: List of Drawings 236
8
REQUEST FOR PROPOSAL
RFP for the work of Development of Bijwasan Railway Station at Bijwasan, New Delhi (Balance
Work) on Item Rate Tender.
The President of India represented by the CPM/DLI/RLDA, (the “Authority”), having its principal
office at Unit No.-702, 7th Floor, Konnectus Tower-2, DMRC Building, Ajmeri Gate, Delhi-
110002, India has decided to carry out the work of work of Development of Bijwasan Railway
Station at Bijwasan, New Delhi (Balance Work) on Special Limited Tender Single Stage Two
Packet System (Item Rate Tender) for the selection of a Bidder to whom the Project may be
awarded.
The scope of work shall broadly cover Civil, MEPF and Development work of the Station Building
and circulation area. The brief particulars of the Project Work, bidding process and the Estimated
Project Cost is provided in Clause 1.1.5, SECTION-I of RFP Document.
The complete Bid document can be viewed/ downloaded from official portal of the RLDA e-
Procurement Portal. Bidder must submit its Financial Bid and Technical Bid at e-Procurement
Portal on or before the Bid Due Date. Bids received online shall be openedon the time as mentioned
in the Key Information Table (KIT) at Clause 1.1.5 of RFP.
Bid through any other mode shall not be entertained. However, Power of Attorney and Joint
Bidding Agreement etc. shall be submitted physically by the Bidder on or before the time
mentioned at Clause 1.1.5 of RFP. Please note that the [Ministry/Authority/ Executing Agency]
reserves the right to accept or reject all or any of the Bids without assigning any reason whatsoever.
9
DISCLAIMER
The information contained in this Request for Proposal document (the “RFP”) or subsequently
provided to Bidder(s), whether verbally or in documentary or any other form by or on behalf of the
Authority or any of its employees or advisors, is provided to Bidder(s) on the terms and conditions set
out in this RFP and such other terms and conditions subject to which such information is provided.
This RFP is not an Agreement and is neither an offer nor invitation by the Authority to the prospective
Bidders or any other person. The purpose of this RFP is to provide interested party/parties with
information that may be useful to them in making their financial offers (Bids) pursuant to this RFP.
This RFP includes statements, which reflect various assumptions and assessments arrived at by the
Authority in relation to the Project. Such assumptions, assessments and statements do not purport to
contain all the information that each Bidder may require. This RFP may not be appropriate for all
persons, and it is not possible for the Authority, its employees or advisors to consider the investment
objectives, financial situation and particular needs of each party who reads or uses this RFP.
Information provided in this RFP to the Bidder(s) is on a wide range of matters, some of which may
depend upon interpretation of law. The information given is not intended to be an exhaustive account
of statutory requirements and should not be regarded as a complete or authoritative statement of law.
The Authority accepts no responsibility for the accuracy or otherwise for any interpretation or opinion
on law expressed herein.
The Authority, its employees and advisors make no representation or warranty and shall have no
liability to any person, including any Bidder under any law, statute, rules or regulations or tort,
principles of restitution or unjust enrichment or otherwise for any loss, damages, cost or expense which
may arise from or be incurred or suffered on account of anything contained in this RFP or otherwise,
including the accuracy, adequacy, correctness, completeness or reliability of the RFP and any
assessment, assumption, statement or information contained therein or deemed to form part of this RFP
or arising in any way for participation in this RFP.
The Authority also accepts no liability of any nature whether resulting from negligence or otherwise
whatsoever arising from reliance of any Bidder upon the statements contained in this RFP. The
Authority may in its absolute discretion, but without being under any obligation to do so, update, amend
or supplement the information, assessment or assumptions contained in this RFP.
The issue of this RFP does not imply that the Authority is bound to select the Bidder or Contractor, as
the case may be, for the Project and the Authority reserves the right to reject all or any of the Bids
without assigning any reason whatsoever.
The Bidder shall bear all its costs associated with or relating to the preparation and submission of its Bid
including but not limited to preparation, copying, postage, delivery fees, expenses associated with any
demonstrations or presentations which may be required by the Authority or any other costs incurred in
connection with or relating to its Bid. All such costs and expenses will remain with the Bidder and the
Authority shall not be liable in any manner whatsoever for the same or for any other costs or other expenses
incurred by a Bidder in preparation/submission of the Bid, regardless of the conduct or outcome of the
Bidding Process.
10
RAIL LAND DEVELOPMENT AUTHORITY
(A STATUTORY AUTHORITY UNDER MINISTRY OF
RAILWAYS) UNIT NO. 702-B, KONNECTUS TOWER, DMRC
BUILDING, AJMERI GATE, NEW DELHI-110002
SECTION 1
INTRODUCTION
1.1 Background
1.1.1 The President of India represented by the CPM/DLI/RLDA (the “Authority”), having
its principal office at Unit No. 702-B, 7th Floor, Konnectus Tower-2, DMRC Building,
Ajmeri Gate, Delhi-110002, India has decided to undertake the Work for Development
of Bijwasan Railway Station at Bijwasan, New Delhi (Balance Work) on Special
Limited Tender Single Stage Two Packet System for selection of a Bidder to whom
the Project may be awarded.
1.1.2 The Invitation of Bid is for the selected bidders only.
1.1.3 Bid Document is “free of cost” for the selected bidders.
1.1.4 The brief scope of work involves;
a) Station Building Work including Concourse
b) MEPF Work
c) External Development including Roadwork
1.1.5 The brief particulars of the Project and the Bidding Process are as follows in the Key
Information Table (KIT):
S.N. Particular Details
11
7. Mode of tendering Special Limited Tender Single Stage Two Packet
System
13. Validity of the Bid 90 days from the Bid Due Date
18. Signing of Agreement Within 30 days from the date of issue of Letter of
Award (LOA)
19. Bank Account Details of the Account Name: Rail Land Development Authority
Authority
Name of bank and Branch: State Bank of India,
1.1.6 The Selected Bidder (the “Contractor”) shall be responsible for Construction of the Project
under and in accordance with the provisions of Contract agreement to be entered into between
the Selected Bidder and the Authority in the form provided by the Authority as part of the Bidding
12
Documents pursuant hereto.
1.1.7 The estimated cost of the Project (the “Estimated Project Cost”) has been specified in the
Clause 1.1.5 above. The assessment of actual costs, however, will have to be made by the Bidders.
1.1.8 The draft Agreement sets forth the detailed terms and conditions for award of the Project to the
Contractor, including the scope of the Contractor’s services and obligations.
1.1.9 The Authority shall receive Bid pursuant to this RFP in accordance with the terms set forth in
this RFP and other documents to be provided by the Authority pursuant to this RFP, as modified,
altered, amended and clarified from time to time by the Authority (collectively the "Bidding
Document"), and Bid shall be prepared and submitted in accordance with such terms on or before
the Bid Due Date as specified in the KIT and provided in Clause 1.1.5 for submission of Bid (the
“Bid Due Date”).
1.2.2 The Bid shall be valid for the period as per the Key Information Table.
1.2.3 The Bidding Documents including the draft Contract Agreement for the Project is enclosed for
the Bidders.
1.2.4 A Bidder is required to submit, along with its Bid, a Bid Security of the amount as mentioned
in the KIT (the "Bid Security"). The Bidder will have to provide Bid Security through e-
payment gateway OR in form of Bank Guarantee as per the format at Appendix VIA. The Bid
shall be summarily rejected if it is not accompanied by the prescribed amount of Bid Security.
1.2.5 Bidder is advised to examine the Project in greater detail, and to carry out, at their cost, such
studies as may be required for submitting his respective Bid for award of the contract including
implementation of the Project.
1.2.6 Bid will be evaluated for the Project on the basis of the lowest cost submitted by the Bidder
for implementing the Project (the "Bid Price"). The total time allowed for completion of
construction under the Agreement (the “Construction Period”) and the period during which
the Contractor shall be liable for rectification of any defect or deficiency in the Project after
completion of the Construction Period (the “Defect Liability Period”) shall be pre-determined,
and are specified in the draft Contract Agreement forming part of the Bidding Documents.
1.2.7 Other details of the process to be followed under this Bidding Process and the terms thereof are
spelt out in this RFP.
1.2.8 Any queries or request for additional information concerning this RFP shall be submitted in
writing by speed post/courier/special messenger or by e-mail by the specified date. The
13
envelopes/ communication shall clearly bear the following identification/ title:
"Queries / Request for Additional Information: RFP for the Work of Development of Bijwasan
Railway Station at Bijwasan, New Delhi (Balance Work).
14
(A) Details to be filled in by tenderer while uploading their offer:
4 PAN NO.
5 GSTIN No.
7 Address on which
correspondence regarding this
tender should be done
Name of signatory____________
15
(B) Check List of documents to be uploaded by the tenderer(s) while submitting their offer.
Tenderer must upload following documents along with their offer
Note for B :- The original Bank Guarantee should be delivered in person to the official
nominated as indicated in the tender document within the deadline of submission of bids.
ii) Tenderer may have to produce the original Documents in physical form at short notice
whenever asked by RLDA at any stage of tender evaluation process or even after
finalization of tender.
iii) In E-tender, all submissions of documents are to be uploaded on web-site. There may be
last minute hic-cups and delay in uploading the Documents and payment of Bid Security
etc. Tenderer’s/Prospective bidders are advised to upload their offer well in time. RLDA
will not be responsible for any delay/non submission of offer due to any reason
whatsoever
16
(C) CHECK LIST OF DOCUMENTS ATTACHED WITH THE OFFER
(For guidance to Tenderer)
17
partners/members. Any Concealment / wrong
information in regard to above shall make the bid
ineligible or the contract shall be determined
under Clause 62 of the Standard General
Conditions of Contract.
18
Note: Authorisation given in POA only will be
considered irrespective of any authorization
that may have given in Partnership Deed. In
case of non-submission of POA or invalid
POA, offer is liable to be rejected.
19
liability against the company (Standard Performa
as per Annexure XXIV).
20
5 In case of a (i) A copy of Certificate of Registration
“Registered (ii) A copy of Memorandum of Association of
Society & Society/Trust Deed
(iii) A copy of Rules & Regulations of the Society
Registered
(iv) A copy of Power of Attorney in favour of the
Trust” individual to sign the tender documents and
create liability against the Society/Trust.
(Standard Performa as per Annexure-XXXII)
6 In case of LLP (i) A copy of LLP Agreement,
(ii) A copy of Certificate of Incorporation; and
(iii) A copy of Power of Attorney/Authorization
issued by the LLP in favour of the individual to
sign the tender on behalf of the LLP and create
liability against the LLP (Standard proforma as
per Annexure XXVII & XXVIII).
(iv) An undertaking by all partners of the LLP that
they are not blacklisted or debarred by
Railways or any other Ministry / Department of
the Govt. of India from participation in tenders
/ contracts as on the date of submission of bids,
either in their individual capacity or in any
firm/LLP or JV in which they were / are
partners/members. Concealment / wrong
information in regard to above shall make the
contract liable for determination under Clause
62 of the Standard General Conditions of
Contract.
6 (A) In case of HUF A copy of notarized affidavit on Stamp Paper
declaring that he who is submitting the tender on
behalf of HUF is in the position of ‘Karta’ of
Hindu Undivided Family (HUF) and he has the
authority, power and consent given by other
members to act on behalf of HUF (Standard
proforma as per Annexure XXXI).
21
10 Annexure-VIB Maximum value of construction works executed and
payment received in any one of the previous three
financial years or the current financial year (up to date
of inviting tender) for calculating A on prescribed
proforma as per Annexure VIB duly verified by
Chartered Accountant. (Mandatorily for tender value
more than Rs. 20 crore)
22
(D) PRECAUTIONS TO BE TAKEN FOR PREPARING LEGAL DOCUMENTS
(For guidance to Tenderer):
(ii) Should be purchased from the Place/State where the document is being executed.
(iii) Values of the non judicial stamp paper (NJSP) should be as mentioned in Tender conditions, where
value of NJSP is not mentioned in the tender conditions, value of NJSP should as per the law of the state
in which the document is being executed.
(iv) Date of purchase of Non Judicial stamp paper should be prior from the date of execution of document.
(i) The document should be signed on each page and also at the appropriate place meant for signature of
executants/deponent.
(ii) Signatory/executants should ensure that on the date of signing the document he/she has valid
authority/attorney in his/her favour for signing.
(iii) In affidavit declaration clause as well as verification clause both should be signed by
deponent/executants.
(iv) Where the document requires witnessing, it should be duly signed by witnesses alongwith their names
and addresses.
(v) On Power of Attorney, signatures of the Attorney holder should also be got done and attested by
executants.
(i) Where the format has been prescribed by the RLDA, the document should be executed in that format.
(ii) Date and place of execution should always be mentioned on the document.
4. Notarization of document
(i) The document should be duly attested (signed and stamped) by notary public on each page.
(ii) The seal of the notary public should contain his name, area of practice and Registration number.
(iii) Notarial stamps of appropriate value wherever required should be affixed on the document
23
PART I
1.0 Applicability: These instructions and conditions of contract shall be applicable for the
subject tender and contract of RLDA for execution of ‘Works’ as defined in Clause 1.1.5 of
SECTION-I of RFP.
v. RLDA General Conditions of Contract updated with correction slips issued up to date of
inviting tender or as otherwise specified in the tender documents.
vi. CPWD Specifications 2019 Vol I & II updated with correction slips issued up to date of
inviting tender or as otherwise specified in the tender documents, if applicable in the
contract.
vii. Indian Railways Unified Standard Specification (IRUSS-2019) updated with correction
slips issued up to date of inviting tender or as otherwise specified in the tender documents,
if applicable in the contract.
viii. Indian Railways Unified Standard Specifications (Works and Material) 2010 updated with
correction slips issued up to date of inviting tender or as otherwise specified in the tender
documents, if applicable in the contract.
ix. Drawings
xi. Relevant B.I.S. Codes updated with correction slips issued up to date of inviting tender or
as otherwise specified in the tender documents.
24
1.1 Interpretation: These Instructions to Tenderers shall be read in conjunction with the
Standard General Conditions of Contract which are referred to herein and shall be subject to
modifications, additions or suppression by Special Conditions of Contract and/or Special
Specifications, if any, annexed to the Tender Forms.
1.2 Definition: In these Instructions to Tenderers, the following terms shall have the meanings
assigned hereunder except where the context otherwise requires:
(a) “Railways” shall mean the President of the Republic of India or the administrative officers
of Railways or Successor Railways authorized to deal with any matter, which these
presents are concerned on his behalf.
(b) “RLDA” shall mean a Statutory Authority under the Ministry of Railways represented by
the Vice Chairman or the administrative officers of RLDA or Successor RLDA authorized
to deal with any matter, which these presents are concerned on his behalf.
(c) “Vice Chairman” shall mean the Officer-in-Charge of the general superintendence and
control of the Unit and shall also include Members and shall mean and include their
successors of the Successor RLDA.
“Authority” shall mean RLDA and the Officer-in-Charge of the general superintendence
and control of the Unit and shall also include Members and shall mean and include their
successors of the Successor RLDA.
(d) “General Manager/Chief Project Manager” shall mean the Officer-in-Charge of the
RLDA and shall mean and include their successors of the successors of RLDA.
(e) “Engineer” shall mean the executive in-charge of the works and shall include the superior
officers, and shall mean & include the Engineers of the Successor of RLDA.
(g) “Limited Tenders” shall mean tenders invited from all or some contractors on the approved
or select list of contractors with RLDA.
(h) “Open Tenders” shall mean the tenders invited in open and public manner and with
adequate notice.
(i) “Works” shall mean the works contemplated in the drawings and Bill(s) of Quantities set
forth in the tender forms and required to be executed according to the specifications.
25
(j) “Specifications” shall mean the CPWD Specifications Vol-I and Vol.-II 2019 as
amended/corrected upto latest correction slips and Specifications for Materials and Works
of Railways as specified under the authority of the Ministry of Railways or Chief Engineer
or as amplified, added to or superseded by special specifications if any, appended to the
Tender Forms.
(k) Standard Schedule of Rates (SSOR) shall mean the schedule of Rates adopted by RLDA,
which includes-
1. “Delhi Schedule Of Rates (DSR)” i.e. the Standard Schedule of Rates published by
Director General/ Central Public Works Department, Government of India, New Delhi,
updated with correction slips issued up to date of inviting tender or as otherwise specified
in the tender documents.
2. “Unified Standard Schedule of Rates of Railways (USSOR)” i.e. the Standard Schedule
of Rates of Railways issued under the authority of the Chief Engineer from time to time,
updated with correction slips issued up to date of inviting tender or as otherwise specified
in the tender documents;
(k) “Drawings” shall mean the maps, drawings, plans and tracings, or prints thereof annexed
to the Tender Forms.
(l) “Contractor’s authorized Engineer” shall mean a graduate engineer or equivalent, having
more than 3 years’ experience in the relevant field of construction work involved in the
contract, duly approved by the Engineer.
(m) Date of inviting tender shall be the date of publishing tender notice on Tender wizard
website if tender is published on website or the date of publication in newspaper in case
tender is not published on website.
(n) “Bill of Quantities” shall mean Schedule of Item(s) included in the tender document along
with respective quantities.
1.3 Words importing the singular number shall also include the plural and vice versa where the
context requires.
2.1 Works of construction and of supply of material shall be entrusted for execution to
contractors whose capabilities and financial status have been investigated and approved to
the satisfaction of RLDA. A list of approved contractors may also be maintained by RLDA.
The said list be revised periodically once in a year or so by giving wide publicity through
advertisements etc. For registration, the contractor including a contractor who is already on
the approved list shall apply to the concerned General Manager (Construction) / Chief
26
Administrative Officer (Construction) / Principal Chief Engineer / Principal Chief Signal &
Telecommunication Engineer / Principal Chief Mechanical Engineer / Principal Chief
Electrical Engineer/ Divisional RLDA Manager, furnishing particulars regarding:
(b) his capacity to undertake and carry out works satisfactorily as vouched for by a
responsible official or firm; details about the transport equipment, construction tools
and plants etc. required for the work, maintained by him;
(c) his previous experience of works similar to that to be contracted for, in proof of
which original certificates or testimonials may be called for and their genuineness
verified, if needs be, by reference to the signatories thereof;
(d) his knowledge from actual personal investigation of the resources of the area/zone
or zones in which he offers to work;
(e) his ability to supervise the work personally or by competent and duly authorized
agent;
2.2 An applicant shall clearly state the categories of works and the
area/zone/division(s)/district(s) in which he desires registration in the list of approved
contractors.
2.3 The selection of contractors for enlistment in the approved list would be done by a committee
for different value of slabs as notified by RLDA.
2.4 An annual fee as prescribed by RLDA from time to time would be charged from such
approved contractors to cover the cost of sending notices to them and clerkage for tenders
etc. Notices shall be sent to them on registered e-mail address and registered postal address.
3. Tender Form: Tender Forms shall embody the contents of the contract documents either directly
or by reference and shall be as per specimen form, Annexure-I. e-Tender Forms shall be issued
free of cost to all tenderers.
27
4. Omissions & Discrepancies: Should a tenderer find discrepancies in or omissions from the
drawings or any of the Tender Forms or should he be in doubt as to their meaning, he should at
once notify the authority inviting tenders. The tender inviting authority may, if deemed necessary,
clarify the same to all tenderers. It shall be understood that every endeavor has been made to avoid
any error which can materially affect the basis of tender and successful tenderer shall take upon
himself and provide for the risk of any error which may subsequently be discovered and shall make
no subsequent claim on account thereof.
5. Bid Security:
(1) (a) The tenderer shall be required to submit the Bid Security with the tender for the due
performance with the stipulation to keep the offer open till such date as specified in the
tender, under the conditions of tender. The Bid Security shall be as under:
For works estimated to cost ₹ 2 lakh plus ½% (half percent) of the excess of
more than ₹ 1 crore the estimated cost of work beyond ₹ 1 crore
subject to a maximum of ₹ 1 crore
Note:
(i) The Bid Security shall be rounded off to the nearest ₹100. This Bid Security shall be
applicable for all modes of tendering.
(ii) Any firm recognized by the Department of Industrial Policy and Promotion (DIPP) as
‘Start ups’ shall be exempted from payment of Bid Security detailed above.
(iii) Labour Cooperative Societies shall submit only 50% of above Bid Security detailed
above.
(b) It shall be understood that the tender documents have been issued to the tenderer and the
tenderer is permitted to tender in consideration of stipulation on his part, that after
submitting his tender he will not resile from his offer or modify the terms and conditions
thereof in a manner not acceptable to the Engineer. Should the tenderer fail to observe or
comply with the said stipulation, the aforesaid amount shall be liable to be forfeited to
RLDA.
(c) If his tender is accepted, this Bid Security mentioned in sub para (a) above will be retained
as part security for the due and faithful fulfillment of the contract in terms of Clause 16 of
the Standard General Conditions of Contract. The Bid Security of other Tenderers shall,
save as herein before provided, be returned to them, but RLDA shall not be responsible for
28
any loss or depreciation that may happen thereto while in their possession, nor be liable to
pay interest thereon.
(2) The Bid Security shall be deposited through e-payment gateway OR in form of Bank Guarantee
as per the format at Appendix VIA. The Bank Guarantee bond shall be as per Annexure-VIA
and shall be valid for a period of 60 days beyond the bid validity period.
(3) In case, submission of Bid Security in the form of Bank Guarantee, following shall be
ensured:
ii. The original Bank Guarantee should be delivered in person to the official nominated as
indicated in the tender document within the deadline of submission of bids.
iii. Non submission of scanned/Xerox copy of Bank Guarantee with the bid submitted
physically in sealed Envelope on e-tendering portal (tenderwizard) and/or non-submission
of original Bank Guarantee within the specified period shall lead to summary rejection of
bid.
iv. The Tender Security shall remain valid for a period of 90 days beyond the validity period
for the Tender.
v. The details of the BG, physically submitted should match with the details available in the
scanned copy and the data entered during bid submission time, failing which the bid will
be rejected
vi. The Bank Guarantee shall be placed in an envelope, which shall be sealed. The envelope
shall clearly bear the identification “Bid for the Bijwasan, New Delhi Project (Balance
Work)” and shall clearly indicate the name and address of the Bidder. In addition, the Bid
Due Date should be indicated on the right-hand top corner of the envelope.
vii. The envelope shall be addressed to the officer and address as mentioned in the tender
document.
viii. If the envelope is not sealed and marked as instructed above, the Authority assumes no
responsibility for the misplacement or premature opening of the contents of the Bid
submitted and consequent losses, if any, suffered by the Bidder.
6. Care in Submission of Tenders:
(a) (i) Before submitting a tender, the tenderer will be deemed to have satisfied himself by
actual inspection of the site and locality of the works, that all conditions liable to be
encountered during the execution of the works are taken into account and that the
29
rates he enters in the tender forms are adequate and all-inclusive to accord with the
provisions in Clause-37 of the Standard General Conditions of Contract for the
completion of works to the entire satisfaction of the Engineer.
(a)(ii) Tenderers will examine the various provisions of The Central Goods and Services
Tax Act, 2017(CGST)/Integrated Goods and Services Tax Act, 2017(IGST)/ Union
Territory Goods and Services Tax Act, 2017(UTGST)/ respective state’s State
Goods and Services Tax Act (SGST) also, as notified by Central/State Govt.& as
amended from time to time and applicable taxes before bidding. Tenderers will
ensure that full benefit of Input Tax Credit (ITC) likely to be availed by them is
duly considered while quoting rates.
(b) When work is tendered for by a firm or company, the tender shall be signed by the
individual legally authorized to enter into commitments on their behalf.
(c) RLDA will not be bound by any power of attorney granted by the tenderer or by
changes in the composition of the firm made subsequent to the execution of the
contract. It may, however, recognize such power of attorney and changes after
obtaining proper legal advice, the cost of which will be chargeable to the Contractor.
6.1 The tenderers shall submit a copy of certificate stating that all their statements/documents
submitted along with bid are true and factual. Standard format of certificate to be submitted
by the bidder is enclosed as Annexure-V. Non submission of above certificate by the bidder
shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon
the tenderer to identify, state and submit the supporting documents duly self-attested/digitally
signed by which they/he is qualifying the Qualifying Criteria mentioned in the Tender
Document.
30
a) The complete, Bid Document can be viewed/downloaded (for view purpose only and not
for bidding) on free view tab of the e-tendering portal i.e. www.tenderwizard.in/RLDA free
of cost or link on Tender section of RLDA website.
b) A Vendor’s Manual containing the detailed guidelines for e-tendering system is also
available on e-tendering portal (i.e. Tenderwizard).
c) It is mandatory for all the bidders to have class-III Digital Signature Certificate from any
of the licensed Certifying Agency (Bidders can see the list of licensed Certifying Agencies
from the link www.cca.gov.in) to participate in e-tendering of RLDA.
6.3 REGISTRATION
a) It is mandatory for the bidders to get their firm/company etc. registered with e-tendering
portal of RLDA, i.e. www.tenderwizard.in/RLDA to have user ID & password by
submitting a non-refundable annual Registration charges of Rs. 2500/- (Rupees Two
Thousand Five Hundred Only) plus applicable taxes to be paid online using the e-
payment gateway to ITI Limited through the portal address mentioned above.
b) Above charges can be paid online using the e-payment gateway to ITI Limited. The
registration so obtained by the prospective bidder shall be valid for one year from the date
of its issue and shall be subsequently renewable on payment of charges applicable at that
time.
c) Participant shall safely keep their User ID and password, which will be issued by the
service provider i.e. ITI Ltd. upon registration, and which is necessary for e-bidding.
d) Bidders are advised to change the password immediately on receipt of activation mail in
their own interest.
e) Bidders shall not disclose their User ID as well as password and other material
information relating to the e-bidding to any one and safeguard its secrecy.
31
them. This shall be the responsibility of the prospective registered bidders to check the
web site for any such corrigendum/addendum till the time of closing of Bid and ensure
that bid submitted by them is in accordance with all the corrigendum(s)/ addendums.
b) The documents available under Free View Section on the website may be downloaded for
the purpose of viewing only. Bidders may please note that bid documents downloaded
from tender view shall be used for bid submission.
c) Bidders cannot download & submit the bid after the due date and time of e-bid
downloading/submission mentioned in the NIT. Time being displayed on e-tendering
portal of RLDA (“Standard Time”) shall be final and binding on the bidder. E-Bids are
required to be submitted by bidders, only as per the Indian Standard Time (IST) and not
the time as per their location/country.
32
key is subjected to asymmetric encryption using buyers/bid openers public keys.
h) The uploaded tender documents become readable only after the tender opening by the
authorized bid openers.
i) Upon the successful and timely submission of bids (i.e. after clicking “Freeze Bid
Submission” in the portal), the portal will give a successful bid submission message& a
bid ID to the bid. A bid summary will be displayed with the bid ID and the date& time of
submission of the bid with all other relevant details.
j) The bid summary has to be printed and kept as an acknowledgement of thesubmission of
the bid. The acknowledgement may be used as an entry pass for anybid opening meetings.
Mob:
9599653865
b) It is mandatory for all bidders to have Class-III Digital Signature Certificate (DSC) in the name
of the person along with name of Company who will digitally sign the bid from any of licensed
Certifying Agency (CA).
c) Bidder shall ensure use of registered Digital Signature Certificate (DSC) only and safety of the
same.
d) In case the Digital Signature Certificate (DSC) holder who is digitally signing the bid and the
person having Authority to Sign as per Clause 6.11 are different, even then all the terms and
conditions of the tender document will be binding upon the bidder.
Note:
1. Bid Security fee payment instruments has to be made online only on e-bidding portal using
the e-payment gateway to ITI Limited as per e-bidding process schedule.
33
2. The Bidder /Authorized representative shall submit E-bids online with his digital signature
and the same person who has digitally signed e-bids shall sign above mentioned requisite Bid
Forms.
3. The complete application shall be digitally signed by the Authorized Signatory of the bidder
& submitted “online” and Bid Sheets should be filled and submitted “online” only. Scanned
copies of various documents can be prepared in PDF file format only. Bidders can upload a
single file of size 15 MB only but they can upload multiple files.
34
6.10 PREPARATION AND SUBMISSION OF BIDS
(a) Tender document may be downloaded from website www.tenderwizard.in/RLDA under the
link ‘Tender’ well before the deadline for submission of bids. Document specified in this
tender document are required to be uploaded.
(b) After downloading/getting the tender document/schedules from
www.tenderwizard.in/RLDA the Bidder should go through them carefully and then submit
the documents as asked, otherwise bid will be rejected. It is construed that the bidder has
read all the terms and conditions before submitting their offer. Bidders are advised that prior
to bid submission they should read the bidsubmission manual available on e-
tendering portal of RLDA.
(c) Bidders may ensure that all the pages of the documents mentioned in the tender document
must be signed & stamped by authorized signatory and serially numbered. In case,it is found
that bidder has not complied with the same, the documents shall be deemed to be signed and
stamped as this is a digitally signed e-tender.
(d) The bids shall be submitted online following the instructions appearing on the screen.
Bidders may insert their e-Token/Smart Card in their computer and Log onto the portal
www.tenderwizard.in/RLDA using the User-Id and Password chosen during registration.
Then they may enter the password of the e-Token/SmartCard to access the DSC.
(e) Prior to bid submission, bidder should get ready with the documents to be uploadedas part of
the bid as indicated in the tender document/schedule. They can be in PDF formats. No other
format is accepted. If there is more than one PDF document, then they can be clubbed
together in a single PDF file for uploading. There is no limit for uploading file. Bids shall
be submitted online onlyat portal www.tenderwizard.in/RLDA.
Tenderer/Contractor are advised to follow the instructions provided in the ‘Instructions to
the Contractors/Tenderer for the e-submission of the bids online.
Bid documents may be scanned with 100 dpi with black and white option which helps in
reducing size of the scanned document.
Intending tenderers are advised to visit the online portal www.tenderwizard.in/RLDA till the
closing date of submission of tender to check if there is any extension of deadline of
submission of tender.
(f) Cost of Tender Document & Earnest Money Deposit (EMD)
During bid submission the bidder has to select the payment option as online payment through
E-Procurement Portal to pay the EMD and enter details of the instruments. In case of
exemption from payment of cost of tender document and EMD as a matter of Govt. Policy,
the scanned copy of document in support of exemption will have to be uploaded by the bidder
during bid submission. In case the bidder is registered as a vendor under the category of
Micro, Small and Medium Enterprises (MSME), he must state his Udyog Aadhar
Memorandum (UAM) number as registered on CPPP. The onus of proving that the bidder is
35
exempted from payment of cost of tender document and/or EMD lies on the bidder. In this
connection, it should be noted that mere opening of bid does not mean that the bid has to be
considered by RLDA as a valid bid. If later, it is discovered from the uploaded documents
that bidder is not exempted from payment of EMD, his bid shall be treated as non-responsive.
It may be noted that the benefits under Public Procurement Policy for Micro and Small
Enterprises (MSEs) Order, 2012 are applicable to only Supply and Service Contracts.
i. Earnest Money Deposit (EMD) – The bids shall be accompanied by total Earnest Money
Deposit (EMD) of Rs. 1 Crore (Rupees One Crore only) to be submitted online on e-
procurement portal or in the form of Bank Guarantee (format specified in annexure VIA).
Bidders are required to submit the documents that are uploaded on the portal in
“ORIGINAL” in a sealed envelope within a week from the date of opening to: DGM/Tender,
Rail Land Development Authority, 7th Floor, Tower-I, Konnectus Building, Bhavbhutti
Marg, New Delhi – 110002.
Failing which the bid shall be rejected. The envelope should bear the tender details (Tender
No., Tender Name etc.).
(g) The bid should be submitted online in the prescribed format. No other mode of submission
is accepted.
(h) Bid shall be digitally signed by a representative of the bidder and submitted “on- line”. No
hard copy of the documents (except those specifically asked for in the tender document) are
required to be submitted.
(i) The bidders will have to accept unconditionally the online user portal agreement which
contains the Terms and Conditions of NIT including General and Special Terms &
Conditions and other conditions, if any, along with on-line undertaking in support of the
authenticity regarding the facts, figures, information and documentsfurnished by the bidder
on-line in order to become an eligible bidder.
(j) The bidder has to digitally sign and upload the required bid documents one by one as
indicated. Bidders to note that the very act of using DSC for downloading the bids and
uploading their offers shall be deemed to be a confirmation that they have read all sections
and pages of the tender/bid document including terms and conditions without any exception
and have understood the entire document and areclear about tender requirements which will
be binding upon the bidder.
(k) The bidders are requested to submit the bids through online e-tendering system before the
deadline for submission of bids (as per Server System Clock displayed on the portal). RLDA will
not be held responsible for any sort of delay or the difficulties faced during online submission of
bids by the bidders at the eleventh hour.
(l) The bidder may seek clarification online only within the specified period. The identity of bidder
36
will not be disclosed by the system. RLDA will clarify the relevant queries of bidders as far as
possible. The clarifications given will be visibleto all the bidders intending to participate in that
tender. The clarifications may be asked from the day of “Pre Bid Query Receipt Start Date and
Time” till “Pre Bid Query Receipt End Date and Time”.
CONSIDERATION OF TENDERS
37
7. Right of RLDA to Deal with Tenders: RLDA reserves the right of not to invite tenders for any of
RLDA work or works or to invite open or limited tenders and when tenders are called to accept a
tender in whole or in part or reject any tender or all tenders without assigning reasons for any such
action. In case if tender is accepted in part by RLDA administration, Letter of Acceptance shall be
issued as counter offer to the Tenderer, which shall be subject to acceptance by the Tenderer.
With a view to assess the tenders technically without being influenced by the financial bids, 'Two
Packets System of tendering' shall be adopted wherein tender documents provide for the same.
7B. Pre Bid Conference: In tenders having advertised value more than Rs 50 Crore or as mentioned in
the tender document, RLDA shall conduct Pre Bid Conference(s) with the prospective bidders.
7C. Make in India Policy: Provisions of Make in India Policy 2017 issued by Govt. of India, as
amended from time to time, shall be followed for consideration of tenders.
7D. Permission to Bid for a bidder from a country which shares Land boundary with India:
Any bidder from the countries sharing a land border with India will be eligible to bid in any
procurement of works (including turnkey projects) only if the bidder is registered with the
Competent Authority. The Competent Authority for registration will be the Registration Committee
constituted by the Department for Promotion of Industry and Internal Trade (DPIIT), Government
of India. For interpretation of this para, Department of Expenditure, Ministry of Finance,
Government of India letter F.No.6/18/2019-PPD dated 23/07/2020 shall be referred.
7E. Clarification of Bids: To assist in the examination, evaluation & comparison and pre-qualification
of the Tender, RLDA may, at its discretion, ask any Bidder for a clarification of its Bid. Any
clarification submitted by a Bidder that is not in response to a request by RLDA shall not be
entertained or considered. RLDA request for clarification and the response of the bidder in this
regard shall be in writing.
However, if a Bidder does not provide clarification of its bid by the date and time communicated
in RLDA request for clarification, the bid shall be evaluated as per the documents submitted along
with the bid.
8. Execution of Contract Document: The Tenderer whose tender is accepted shall be required to
appear in person at the office of General Manager/Chief Project Manager or concerned Engineer, as
the case may be, or if tenderer is a firm or corporation, a duly authorized representative shall appear
(there would be no need for appear in person if agreement is signed digitally) and execute the
contract agreement within seven days of notice from RLDA that the Contract Agreement is ready.
Failure to do so shall constitute a breach of the agreement affected by the acceptance of the tender.
The Contract Agreement shall be entered into by RLDA only after submission of valid Performance
Guarantee by the Contractor. In such cases RLDA may determine that such tenderer has abandoned
the contract and there upon his tender and acceptance thereof shall be treated as cancelled and RLDA
38
shall be entitled to forfeit the full amount of the Bid Security and other dues payable to the Contractor
under this contract. The failed Contractor shall be debarred from participating in the re-tender for
that work.
9. Form of Contract Document: Every contract shall be complete in respect of the document it shall
so constitute. Not less than 2 copies of the contract document shall be signed by the competent
authority and the Contractor and one copy given to the Contractor (there would be no need of
signing two copies if agreement is signed digitally).
(a) For RLDA Contracts, awarded on the basis of the percentage above or below the total cost
estimate based on CPWD DSR 2021 Rates duly modified with applicable Cost Index and
increase in GST/chapter(s) of Standard Schedule of Rates (SSOR) for the whole or part of
financial year, the contract agreement required to be executed by the tenderer whose tender is
accepted shall be as per specimen form, Annexure-II. During the currency of the RLDA
Contract, work orders as per specimen form Annexures-III, for works not exceeding ₹ 5,00,000
each, shall be issued by the Divisional Raliway Manager / Executive Engineer under the
agreement for Zone Contract.
(b) For contracts for specific works, the contract document required to be executed by the tenderer
whose tender is accepted shall be an agreement as per specimen form Annexure- IV.
39
ANNEXURE - I
RLDA
TENDER FORM (First Sheet)
Tender No. ____________________
Name of Work: Development of Bijwasan Railway Station at Bijwasan, New Delhi (Balance Work).
To
The Vice Chairman
Rail Land Development Authority
New Delhi.
I/We ____________________ have read the various conditions to tender attached hereto and agree to
abide by the said conditions. I/We also agree to keep this offer open for acceptance for a period of ________
days from the date fixed for closing of the tender and in default thereof, I/We will be liable for forfeiture of
my/our “Bid Security”. I/We offer to do the work for RLDA, at the rates quoted in the attached bill(s) of
quantities and hereby bind myself/ourselves to complete the work in all respects within fifteen (15) months
from the date of issue of letter of acceptance of the tender.
2. I/We also hereby agree to abide by the General Conditions of Contract, with all correction slips up-to-
date and to carry out the work according to the Special Conditions of Contract and Specifications of
materials and works as laid down by RLDA in the annexed Special Conditions/Specifications, CPWD
Specifications 2019 Vol.-I and Vol.-II, CPWD DSR 2021/Standard Schedule of Rates (SSOR) with all
correction slips up-to-date for the present contract.
3. A Bid Security of ₹ 1.0 Crore has already been deposited online through e-procurement portal OR in
form of Bank Guarantee as per the format at Appendix VIA. Full value of the Bid Security shall stand
forfeited without prejudice to any other right or remedies in case my/our Tender is accepted and if:
(a) I/We do not submit the Performance Guarantee within the time specified in the Tender
document;
(b) I/We do not execute the contract documents within seven days after receipt of notice issued by
RLDA that such documents are ready; and
(c) I/We do not commence the work within fifteen days after receipt of orders to that effect.
4. I/We am/are a Startup firm registered by …………………… Department of Industrial Policy and
Promotion (DIPP) and my registration number is ……………. valid upto …………………. (Copy
enclosed) and hence exempted from submission of Bid Security.
40
5. We are a Labour Cooperative Society and our Registration No. is ……………….. with
…………………..and hence required to deposit only 50% of Bid Security.
6. Until a formal agreement is prepared and executed, acceptance of this tender shall constitute a binding
contract between us subject to modifications, as may be mutually agreed to between us and indicated in
the letter of acceptance of my/our offer for this work.
_____________________________
41
ANNEXURE - I (Contd. …)
(e) CPWD Specifications Vol-I and Vol.-II 2019 as amended/corrected upto latest correction slips
available at CPWD website
(
and Standard Specifications (Works and Materials) of Indian Railways
as amended/corrected upto
2 latest correction slips available at Indian Railway website
(f) )
CPWD DSR 2021 as amended/corrected upto latest correction slips including CPWD AOR as
_
amended/corrected upto latest correction slips available on the CPWD website.
_
(g) Standard Schedule of Rates _ (SSOR) as amended/corrected upto latest correction slips, available on
_
the Indian Railway website
_
(h) All general and detailed_drawings pertaining to this work will be issued by the Engineer or his
_ to time) with all changes and modifications.
representatives (from time
_
2. Drawings for the Work: The Drawing for the works have been attached with the Tender Document and
_
can be referred as only for the_ guidance of Tenderer(s). Detailed working drawings (if required) based
generally on the drawing mentioned
_ above, will be given by the Engineer or his representative from time
_ is attached at Annexure-B for reference and can be viewed in the
to time. The list of the drawings
office of JGM/Projects/RLDA _ from 11:00 Hours to 16:00 Hrs.
_
3. The Tenderer(s) shall quote his
_ / their rates as a percentage above or below the rate/amount prepared
based on CPWD DSR 2021 _Rates duly modified with applicable Cost Index and increase in GST/
_
Standard Schedule of Rates (SSOR) of Indian Railway as applicable except where he/they are required
to quote item rates and must _tender for all the items shown in the Bill(s) of Quantities attached. The
_ Bill(s) of Quantities are given as a guide and are approximate only and
quantities shown in the attached
are subject to variation according to the needs of RLDA. RLDA does not guarantee work under each item
of the Bill(s) of Quantities. The tenderer(s) shall quote rates / rebates only at specified place in Tender
Form supplied by RLDA. Any revision of rates / rebates submitted (quoted) through a separate letter
whether enclosed with the bid (Tender Form) or submitted separately or mentioned elsewhere in the
document other than specified place shall be summarily ignored and will not be considered.
42
4. Tenders containing erasures and / or alterations of tender documents are liable to be rejected. Any
correction made by tender(s) in his/their entries must be attested by him / them.
5. The works are required to be completed within a period of 15 months from the date of issue of acceptance
letter.
6. Bid Security:
(a) Subject to exemptions provided under para 5(1) (a) of Part-1 (ITT) of this document, the tender
must be accompanied by a Bid Security as mentioned in tender documents, failing which the tender
shall be summarily rejected.
(b) The Tenderer(s) shall keep the offer open for a minimum period of 60 days (in case of two packet
system of tendering 90 days) from the date of closing of the Tender. It is understood that the tender
documents have been issued to the Tenderer(s) and the Tenderer(s), is / are permitted to tender in
consideration of the stipulation on his / their part that after submitting his / their tender subject to
the period being extended further, if required by mutual agreement from time to time, he will not
resile from his offer or modify the terms and conditions thereof in a manner not acceptable to
RLDA. Should the tenderer fail to observe or comply with the foregoing stipulation, the amount
deposited or Bank guarantee bond submitted as Bid Security for the due performance of the above
stipulation, shall be forfeited to RLDA.
(c) If his tender is accepted,
(i) the Bid Security mentioned in sub para(a) above deposited through online payment on e-
procurement portal OR in form of Bank Guarantee as per the format at Appendix VIA will be
retained as part security for the due and faithful fulfillment of the contract in terms of Clause 16
of the Standard General Conditions of Contract;
(ii) the Bid Security mentioned in sub para(a) above submitted as Bank guarantee bond, will be
encashed as part security for the due and faithful fulfillment of the contract in terms of Clause
16 of the Standard General Conditions of Contract.
The Bid Security of other Tenderers shall, save as herein before provided, be returned to them, but
RLDA shall not be responsible for any loss or depreciation to the Bid Security that may happen
thereto while in their possession, nor be liable to pay interest thereon.
(d) In case Contractor submits the Term Deposit Receipt/Bank Guarantee Bond towards either the Full
Security Depositor the Part Security Deposit equal to or more than Bid Security, RLDA shall return
the Bid Security so retained as per sub para(c) above, to the Contractor.
7. Rights of the RLDA to deal with Tender: The authority for the acceptance of the tender will rest with
RLDA. It shall not be obligatory on the said authority to accept the lowest tender or any other tender,
and tenderer(s) shall neither demand any explanation for the cause of rejection of his/ their tender nor
RLDA to assign reasons for declining to consider or reject any particular tender or tenders.
43
8. If the tenderer(s) deliberately gives/give wrong information in his / their tender or creates/create
circumstances for the acceptance of his / their tender, RLDA reserves the right to reject such tender at
any stage.
9. If any partner(s) of a partnership firm expires after the submission of its tender or after the acceptance
of its tender, RLDA shall deem such tender as cancelled/contract as terminated under clause 61 of the
Standard General Conditions of Contract, unless the firm retains its character as per partnership
agreement. If a sole proprietor expires after the submission of tender or after the acceptance of tender,
RLDA shall deem such tender as cancelled / contract as terminated under clause 61 of the Standard
General Conditions of Contract.
10. Eligibility Criteria:
10.1 Technical Capacity-
For demonstrating Technical Capacity and experience (the “Technical Capacity”), the Bidder shall
have:
(A) satisfactorily completed the works as mentioned below during the last seven years ending one
month prior to the Bid Due Date.
(i) Three similar works each costing not less than 40% of the estimated cost of this work.
OR
Two similar works each costing not less than 60% of the estimated cost of this work.
OR
One similar work costing not less than 80% of the estimated cost of this work.
(i) Passenger terminals having a minimum passenger handling capacity of 5000 persons /day
in railway stations, metro stations, airport terminals (with or without related airport
infrastructure works), ports, integrated check posts, and bus terminals; or
(ii) Social and Commercial infrastructure: Commercial real estate project (such as
educational institution, hospital, hotel, convention centre, mall/shopping complex, sports
complex, office complex) at a single site with a minimum built up area of 15,000 (Fifteen
thousand) square metres;
The value of executed works shall be brought to current costing level by enhancing the actual
value of work at a simple rate of 7% per annum, calculated from the date of completion to
one month prior to the Bid Due Date.
44
AND
(B) Minimum one ongoing building work (not necessarily Similar work) of contract value not
less than Rs. 230 crore secured during the last Five years ending one month prior to the Bid
Due Date.
The value of executed works shall be brought to current costing level by enhancing the actual
value of work at a simple rate of 7% per annum. calculated from the date of award to one
month prior to the Bid Due Date.
Notes :
(a) The work under category (ii) above may be the same or different from the work under category (i)
above.
(b) For this purpose, the work should have been directly awarded to the Bidder by a Govt. Department;
or by a company having average annual turnover of Rs 500 crore and above in last 3 financial years
excluding the current financial year. The company should have been incorporated at least five years
back as on 31.03.2022. However, works awarded on nomination basis or subletted on back to back
basis shall not be considered.
(c) For this purpose, cost of work shall mean gross value of the completed work including the cost of
materials supplied by the Government or owner, but excluding those supplied free of cost. This
should be certified by an officer not below the rank of Project Manager/Executive Engineer or
equivalent.
(d) For the purpose of evaluation, the works where the Bidder has received payments for not less than
75 (seventy-five) per cent value of awarded project cost of such project as per the original agreement,
shall also be considered as completed works.
(e) Work of specialized E&M services, etc. if executed under separate contracts shall be considered for
the purpose of assessing the technical competency only without adding its monetary value for
determining the eligibility criteria.
10.2 Financial Capacity: For demonstrating Financial Capacity (the “Financial Capacity”), the Bidder
shall have:
(A) had average annual financial turn over (gross) of 50% of the advertised value of this work on
civil and/or electrical construction works during the immediate last three consecutive financial years
ending on 31st March 2022. This should be duly audited by a Chartered Accountant. For financial
year 2021-22, it may be certified by CA, if not audited. Year in which no turnover is shown would
also be considered for working out the average.
(B) achieved average monthly financial progress of at least Rs. 20 crore per month in any single
construction work costing not less than 40% of the advertised value of this work (not necessarily
similar work), during the last 7 (seven) years ending on 31.03.2022. The value of average monthly
financial progress shall be worked out on the basis of completion cost of work divided by actual
45
duration of completion of work. The value of average monthly financial progress shall be brought
to current costing level by enhancing the actual value of monthly turnover of single work at simple
rate of 7% per annum; calculated from the date of completion of the work to 31.03.2022.
(C) Should not have incurred any loss (profit after tax should be positive) in more than two years during
the last five consecutive financial years ending on 31st March 2022 duly audited by the Chartered
Accountant. For financial year 2021-22, it may be certified by CA, if not audited.
(D) have a minimum net worth of Rs. 70 crore certified by Chartered Accountant at the close of the
preceding Financial Year.
46
amount already paid including the PVC amount (if paid) shall be considered as the completion cost
of work.
In case of substantially completed work, the total gross amount already paid including the PVC
amount (if paid), as mentioned in the certificate, shall be considered as the cost of substantially
completed work.
5. If a bidder has successfully completed a work as subcontractor and the work experience certificate
has been issued for such work to the subcontractor by a Govt. Organization or public listed company
as defined in Note for Item 10.1 Para 10 of the Tender Form (Second Sheet), the same shall be
considered for the purpose of fulfillment of credentials.
6. In case a work is considered similar in nature for fulfillment of technical credentials, the overall cost
including the PVC amount (if paid) of that completed work or substantially completed work, shall be
considered and no separate evaluation for each component of that work shall be made to decide
eligibility.
7. In case of newly formed partnership firm, the credentials of individual partners from previous
propriety firm(s) or dissolved previous partnership firm(s) or split previous partnership firm(s), shall
be considered only to the extent of their share in previous entity on the date of dissolution / split and
their share in newly formed partnership firm. For example, a partner A had 30% share in previous
entity and his share in present partnership firm is 20%. In the present tender under consideration, the
credentials of partner A will be considered to the extent of 0.3*0.2*value of the work done in the
previous entity. For this purpose, the tenderer shall submit along with his bid all the relevant
documents which include copy of previous partnership deed(s), dissolution deed(s) and proof of
surrender of PAN No.(s) in case of dissolution of partnership firm(s) etc.
8. In case of existing partnership firm, if any one or more partners quit the partnership firm, the
credentials of remaining partnership firm shall be re-worked out i.e., the quitting partner(s) shall take
away his credentials to the extent of his share on the date of quitting the partnership firm(e.g. in a
partnership firm of partners A, B & C having share 30%, 30% & 40% respectively and credentials
of Rs 10 crore; in case partner C quits the firm, the credentials of this partnership firm shall remain
as Rs 6 crore). For this purpose, the tenderer shall submit along with his bid all the relevant
documents which include copy of previous partnership deed(s), dissolution deed(s) and proof of
surrender of PAN No.(s) in case of dissolution of partnership firm(s) etc.
9. In case of existing partnership firm if any new partner(s) joins the firm without any modification in
the name and PAN/TAN no. of the firm, the credentials of partnership firm shall get enhanced to the
extent of credentials of newly added partner(s) on the same principles as mentioned in item 6 above.
For this purpose, the tenderer shall submit along with his bid all the relevant documents which include
copy of previous partnership deeds, dissolution/splitting deeds and proof of surrender of PAN No.(s)
in case of dissolution of partnership firm etc.
10. Any partner in a partnership firm cannot use or claim his credentials in any other firm without leaving
the partnership firm i.e., In a partnership firm of A&B partners, A or B partner cannot use credentials
of partnership firm of A&B partners in any other partnership firm or propriety firm without leaving
partnership firm of A&B partners.
11. In case a partner in a partnership firm is replaced due to succession as per succession law, the
proportion of credentials of the previous partner will be passed on to the successor.
47
12. If the percentage share among partners of a partnership firm is changed, but the partners remain the
same, the credentials of the firm before such modification in the share will continue to be considered
for the firm as it is without any change in their value. Further, in case a partner of partnership firm
retires without taking away any credentials from the firm, the credentials of partnership firm shall
remain the same as it is without any change in their value.
13. In a partnership firm “AB” of A&B partners, in case A also works as propriety firm “P” or partner
in some other partnership firm “AX”, credentials of A in propriety firm “P” or in other partnership
firm “AX” earned after the date of becoming a partner of the firm AB shall not be added in partnership
firm AB.
14. In case a tenderer is LLP, the credentials of tenderer shall be worked out on above lines similar to a
partnership firm.
15. In case company A is merged with company B, then company B would get the credentials of company
A also.]
Documents testifying tenderer previous experience and financial status should be produced along with
the tender.
Tenderer(s) who is / are not borne on the approved list of the Contractors of RLDA shall submit
along with his / their tender:
(i) Certificates and testimonials regarding contracting experience for the type of job for which tender is
invited with list of works carried out in the past.
(ii) Audited Balance Sheet duly certified by the Chartered Accountant regarding contractual payments
received in the past.
(iii) The list of personnel / organization on hand and proposed to be engaged for the tendered work.
Similarly list of Plant & Machinery available on hand and proposed to be inducted and hired for the
tendered work.
(iv) A copy of certificate stating that they are not liable to be disqualified and all their
statements/documents submitted along with bid are true and factual. Standard format of the certificate
to be submitted by the bidder is enclosed as Annexure-V. Non submission of a copy of certificate by
the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon
the tenderer to identify, state and submit the supporting documents duly self attested / digitally signed
by which they/he are/is qualifying the Qualifying Criteria mentioned in the Tender Document.
(v) RLDA reserves the right to verify all statements, information and documents submitted by the bidder
in his tender offer, and the bidder shall, when so required by RLDA, make available all such
information, evidence and documents as may be necessary for such verification. Any such
verification or lack of such verification, by RLDA shall not relieve the bidder of its obligations or
liabilities hereunder nor will it affect any rights of RLDA there under.
48
(vi) (a) In case of any information submitted by tenderer is found to be false, forged or incorrect at any
time during process for evaluation of tenders, it shall lead to forfeiture of the tender Bid Security
besides banning of business for a period of upto five years.
(b) In case of any information submitted by tenderer is found to be false, forged or incorrect after the
award of contract, the contract shall be terminated. Bid Security, Performance Guarantee and
Security Deposit available with RLDA shall be forfeited. In addition, other dues of the contractor,
if any, under this contract shall be forfeited and agency shall be banned for doing business for a
period of upto five years.
12. Non-compliance with any of the conditions set forth therein above is liable to result in the tender
being rejected.
13. Execution of Contract Documents: The successful Tenderer(s) shall be required to execute an
agreement with the President of India acting through the Vice Chairman, RLDA for carrying out the
work according to the Standard General Conditions of Contract, Special Conditions / Specifications
annexed to the tender and CPWD Specifications Vol-I and Vol.-II 2019 as amended/corrected upto
latest correction slips and Standard Specifications (Works and Materials) of Railway as
amended/corrected upto latest correction slips, mentioned in tender form (First Sheet).
14. Documents to be Submitted Along with Tender
(i) The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or
on behalf of a Partnership Firm / Company / Joint Venture (JV) / Registered Society / Registered
Trust / Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc. The tenderer(s)
shall enclose the attested copies of the constitution of their concern, and copy of PAN Card along
with their tender. Tender Documents in such cases are to be signed by such persons as may be legally
competent to sign them on behalf of the firm, company, association, trust or society, as the case may
be.
(b) HUF:
(i) A copy of notarized affidavit on Stamp Paper declaring that he who is submitting the tender on
behalf of HUF is in the position of ‘Karta’ of Hindu Undivided Family (HUF) and he has the
authority, power and consent given by other members to act on behalf of HUF.
(ii) All other documents in terms of Para 10 of the Tender Form (Second Sheet) above.
49
(d) Joint Venture (JV): All documents as mentioned in para 17 of the Tender Form (Second Sheet). –
NOT APPLICABLE
(i) The copies of MOA (Memorandum of Association) / AOA (Articles of Association) of the
company
(ii) A copy of Certificate of Incorporation
(iii) A copy of Authorization/Power of Attorney issued by the Company (backed by the resolution
of Board of Directors) in favour of the individual to sign the tender on behalf of the company
and create liability against the company.
(iv) All other documents in terms Para 10 of the Tender Form (Second Sheet) above.
(iii) If it is NOT mentioned in the submitted tender that tender is being submitted on behalf of a Sole
Proprietorship firm / Partnership firm / Joint Venture / Registered Company etc., then the tender shall
be treated as having been submitted by the individual who has signed the tender.
(iv) After opening of the tender, any document pertaining to the constitution of Sole Proprietorship Firm
/ Partnership Firm / Registered Company/ Registered Trust / Registered Society / HUF/LLP etc. shall
be neither asked nor considered, if submitted. Further, no suo moto cognizance of any document
available in public domain (i.e., on internet etc.) or in RLDA record/office files etc. will be taken for
consideration of the tender, if no such mention is available in tender offer submitted.
(v) A tender from JV shall be considered only where permissible as per the tender conditions.
50
(vi) RLDA will not be bound by any change of power of attorney or in the composition of the firm made
subsequent to the submission of tender. RLDA may, however, recognize such power of attorney and
changes after obtaining proper legal advice, the cost of which will be chargeable to the Contractor.
15. The tenderer whether sole proprietor / a company or a partnership firm / joint venture (JV) / registered
society / registered trust / HUF / LLP etc if they want to act through agent or individual partner(s),
should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a
Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm
or any other person, specifically authorizing him/them to sign the tender, submit the tender and further
to deal with the Tender/ Contract up to the stage of signing the agreement except in case where such
specific person is authorized for above purposes through a provision made in the partnership deed /
Memorandum of Understanding / Article of Association /Board resolution, failing which tender shall
be summarily rejected.
A separate power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in
favour of the specific person whether he/they be partner(s) of the firm or any other person, shall be
submitted after award of work, specifically authorizing him/them to deal with all other contractual
activities subsequent to signing of agreement, if required.
Note: A Power of Attorney executed and issued overseas, the document will also have to be legalized
by the Indian Embassy and notarized in the jurisdiction where the Power of Attorney is being issued.
However, the Power of Attorney provided by Bidders from countries that have signed the Hague
Legislation Convention 1961 are not required to be legalized by the Indian Embassy if it carries a
conforming Appostille certificate.
51
the tenderer will give full information as to the date of retirement of such Engineer or gazetted officer
from the said service and as to whether permission for taking such contract, or if the Contractor be a
partnership firm or an incorporated company, to become a partner or director as the case may be, has
been obtained by the tenderer or the Engineer or officer, as the case may be from RLDA or any officer,
duly authorized by him in this behalf, shall be clearly stated in writing at the time of submitting the
tender.
b) In case, upon successful award of contract, should a tenderer depute for execution of the works under
or to deal matters related with this contract, any retired Engineer of gazette rank or retired gazetted
officer working before his retirement in the Engineering or any other department of any of
Railway/RLDA owned and administered by Railway/RLDA for the time being, and now in his
employment, then the tenderer will ensure that retired Engineer or retired gazetted officer had retired
from government service at least 1 year prior to the date of his employment with tenderer and in case
he had retired from service within a year then he possesses the requisite permission from RLDA or
any officer, duly authorized by him in this behalf, to get associated with the tenderer.
c) Should a tenderer or Contractor being an individual, have member(s) of his family or in the case of
partnership firm/ company / joint venture (JV) / registered society / registered trust etc. one or more of
his partner(s)/shareholder(s) or member(s) of the family of partner(s)/shareholder(s) having share of
more than 1%in the tendering entity employed in gazetted capacity in the Engineering or any other
department of Railway/RLDA, then the tenderer at the time of submission of tender, will inform the
authority inviting tenders the details of such persons.
Note: -If information as required as per 16.a), b), c) above has not been furnished, contract is liable to be
dealt in accordance with provision of clause 62 of the Standard General Condition of contract.
17. Participation of Joint Venture (JV) in Works Tender: This para shall be applicable for works tenders
wherein tender documents provide for the same.
17.2 Number of members in a JV shall not be more than three, if the work involves only one department
(say Civil or S&T or Electrical or Mechanical) and shall not be more than five, if the work involves
more than one Department. One of the members of the JV shall be its Lead Member who shall have
a majority (at least 51%) share of interest in the JV. The other members shall have a share of not less
than 20% each in case of JV with upto three members and not less than 10% each in case of JV with
more than three members. In case of JV with foreign member(s), the Lead Member has to be an
Indian firm/company with a minimum share of 51%.
17.3 A member of JV shall not be permitted to participate either in individual capacity or as a member of
52
another JV in the same tender.
17.4 The tender form shall be purchased and submitted only in the name of the JV and not in the name of
any constituent member. The tender form can however be submitted by JV or any of its constituent
member or any person authorized by JV through Power of Attorney to submit tender.
17.5 Bid Security shall be submitted by JV or authorized person of JV either as :
(i) Cash through e-payment gateway or as mentioned in tender document, or
(ii) Bank Guarantee bond either in the name of JV, or in the name of all members of JV as per MOU
irrespective of their share in the JV if the JV has not been constituted legally till the date of
submission of tender.
17.6 A copy of Memorandum of Understanding (MoU) duly executed by the JV members on a stamp
paper, shall be submitted by the JV alongwith the tender. The complete details of the members of the
JV, their share and responsibility in the JV etc. particularly with reference to financial, technical and
other obligations shall be furnished in the MoU.
17.7 Once the tender is submitted, the MoU shall not normally be modified / altered / terminated during
the validity of the tender. In case the tenderer fails to observe/comply with this stipulation, the full
Bid Security shall be liable to be forfeited.
17.8 Approval for change of constitution of JV shall be at the sole discretion of RLDA. The constitution
of the JV shall not normally be allowed to be modified after submission of the bid by the JV, except
when modification becomes inevitable due to succession laws etc., provided further that there is no
change in qualification of minimum eligibility criteria by JV after change of composition. However,
the Lead Member shall continue to be the Lead Member of the JV. Failure to observe this requirement
would render the offer invalid.
17.9 Similarly, after the contract is awarded, the constitution of JV shall not be normally allowed to be
altered during the currency of contract except when modification become inevitable due to succession
laws etc. and minimum eligibility criteria should not get vitiated. Failure to observe this stipulation
shall be deemed to be breach of contract with all consequential penal action as per contract
conditions.
17.10 On award of contract to a JV, a single Performance Guarantee shall be submitted by the JV as per
tender conditions. All the Guarantees like Performance Guarantee, Bank Guarantee for Mobilization
Advance, Machinery Advance etc. shall be accepted only in the name of the JV and no splitting of
guarantees amongst the members of the JV shall be permitted.
17.11 On issue of LOA (Letter of Acceptance), the JV entity to whom the work has been awarded, with
the same shareholding pattern as was declared in the MOU/JV Agreement submitted alongwith the
tender, shall be got registered before the Registrar of the Companies under 'The Companies Act -
2013' (in case JV entity is to be registered as Company) or before the Registrar/Sub-Registrar under
53
the 'The Indian Partnership Act, 1932' (in case JV entity is to be registered as Partnership Firm) or
under 'The LLP Act 2008' (in case JV entity is to be registered as LLP). A separate PAN shall be
obtained for this entity. The documents pertaining to this entity including its PAN shall be furnished
to RLDAs before signing the contract agreement for the work. In case the tenderer fails to
observe/comply with this stipulation within 60 days of issue of LOA, contract is liable to be
terminated. In case contract is terminated RLDA shall be entitled to forfeit the full amount of the Bid
Security and other dues payable to the Contractor under this contract. The entity so registered, in the
registered documents, shall have, inter-alia, following Clauses:
17.11.1 Joint and Several Liability - Members of the entity to which the contract is awarded, shall be
jointly and severally liable to RLDA for execution of the project in accordance with General and
Special Conditions of Contract. The members of the entity shall also be liable jointly and severally
for the loss, damages caused to RLDAs during the course of execution of the contract or due to
non-execution of the contract or part thereof.
17.11.2 Duration of the Registered Entity - It shall be valid during the entire currency of the contract
including the period of extension, if any and the maintenance period after the work is completed.
17.11.3 Governing Laws - The Registered Entity shall in all respect be governed by and interpreted in
accordance with Indian Laws.
17.12 Authorized Member - Joint Venture members in the JV MoU shall authorize Lead member on
behalf of the Joint Venture to deal with the tender, sign the agreement or enter into contract in
respect of the said tender, to receive payment, to witness joint measurement of work done, to sign
measurement books and similar such action in respect of the said tender/contract. All
notices/correspondences with respect to the contract would be sent only to this authorized member
of the JV.
17.13 No member of the Joint Venture shall have the right to assign or transfer the interest right or liability
in the contract without the written consent of the other members and that of RLDA in respect of the
said tender/contract.
54
tenders / contracts as on the date of submission of bids, either in their individual capacity or in
any firm/LLP in which they were / are partners/members. Any Concealment / wrong
information in regard to above shall make the bid ineligible or the contract shall be determined
under Clause 62 of the Standard General Conditions of Contract.
17.14.2 In case one or more members is/are Proprietary Firm or HUF, the following documents shall be
enclosed:
(i) A copy of notarized affidavit on Stamp Paper declaring that his Concern is a proprietary Concern
and he is sole proprietor of the Concern OR he who is signing the affidavit on behalf of HUF is
in the position of ‘Karta’ of Hindu Undivided Family (HUF) and he has the authority, power and
consent given by other members to act on behalf of HUF.
17.14.3 In case one or more members of the JV is/are companies, the following documents shall be
submitted:
(i) A copy of resolutions of the Directors of the Company, permitting the company to enter into a
JV agreement,
(ii) The copies of MOA (Memorandum of Association) / AOA (Articles of Association) of the
company
(iii) A copy of Certificate of Incorporation
(iv) A copy of Authorization/copy of Power of Attorney issued by the Company (backed by the
resolution of Board of Directors) in favour of the individual, to sign the tender, sign MOU/JV
Agreement on behalf of the company and create liability against the company
17.14.4 In case one or more members of the JV is/are LLP firm/s, the following documents shall be
submitted:
(i) A copy of LLP Agreement
(ii) A copy of Certificate of Incorporation of LLP
(iii) A copy of resolution passed by partners of LLP firm, permitting the Firm to enter into a JV
agreement
(iv) A copy of Authorization /copy of Power of Attorney issued by the LLP firm (backed by
resolution passed by the Partners) in favour of the individual, to sign the tender and/or sign the
MOU/ JV agreement on behalf of the LLP and create liability against the LLP.
(v) An undertaking by all partners of the LLP that they are not blacklisted or debarred by RLDAs
or any other Ministry / Department of the Govt. of India from participation in tenders /
contracts as on the date of submission of bids, either in their individual capacity or in any
firm/LLP or JV in which they were / are partners/members. Any Concealment / wrong
information in regard to above shall make the contract liable for determination under Clause
62 of the Standard General Conditions of Contract.
17.14.5 In case one or more members of the JV is/are Society/s or Trust/s, the following documents shall
be submitted:
(i) A copy of Certificate of Registration
(ii) A copy of Memorandum of Association of Society/Trust Deed
(iii) A copy of Rules & Regulations of the Society
55
(iv) A copy of Power of Attorney, in favour of the individual to sign the tender documents and create
liability against the Society/Trust.
17.14.6 All other documents in terms of Para 10 of the Tender Form (Second Sheet) above.
17.15 Credentials & Qualifying Criteria: Technical, financial eligibility and Bid capacity of the JV shall be
adjudged based on satisfactory fulfillment of the following criteria:
17.15.1 Technical Eligibility Criteria (‘a’ or ‘b’ mentioned hereunder):
(a) For Works without composite components
The technical eligibility for the work as per para 10.1 above, shall be satisfied by either the ‘JV
in its own name & style’ or ‘Lead member of the JV’.
Each other (non-lead) member(s) of JV, who is/ are not satisfying the technical eligibility for
the work as per para 10.1 above, shall have technical capacity of minimum 10% of the cost of
work i.e., each non-lead member of JV member must have satisfactorily completed or
substantially completed during the last 07 (seven) years, ending last day of month previous to
the one in which tender is invited, one similar single work for a minimum of 10% of advertised
value of the tender.
(b) For works with composite components
The technical eligibility for major component of work as per para 10.1 above, shall be satisfied
by either the ‘JV in its own name & style’ or ‘Lead member of the JV’ and technical eligibility
for other component(s) of work as per para 10.1 above, shall be satisfied by either the ‘JV in
its own name & style’ or ‘any member of the JV’.
Each other (non-lead)member(s) of JV, who is/ are not satisfying the technical eligibility for
any component of the work as per para 10.1 above, shall have technical capacity of minimum
10% of the cost of any component of work mentioned in technical eligibility criteria. i.e., each
other (non-lead) member of must have satisfactorily completed or substantially completed
during the last 07 (seven) years, ending last day of month previous to the one in which tender
is invited, one similar single work for a minimum of 10% of cost of any component of work
mentioned in technical eligibility criteria.
Note for Para 17.15.1:
a) The Major component of the work for this purpose shall be the component of work having highest
value. In cases where value of two or more component of work is same, any one work can be
classified as Major component of work.
b) Value of a completed work done by a Member in an earlier JV shall be reckoned only to the extent
of the concerned member's share in that JV for the purpose of satisfying his/her compliance to the
above mentioned technical eligibility criteria in the tender under consideration.
56
17.15.2 Financial Eligibility Criteria
The JV shall satisfy the requirement of “Financial Eligibility” mentioned at para 10.2 above. The
“financial capacity” of the lead member of JV shall not be less than 51% of the financial eligibility
criteria mentioned at para 10.2 above.
The arithmetic sum of individual “financial capacity” of all the members shall be taken as JV’s
“financial capacity” to satisfy this requirement.
Note: Contractual payment received by a Member in an earlier JV shall be reckoned only to the
extent of the concerned member’s share in that JV for the purpose of satisfying compliance of the
above mentioned financial eligibility criteria in the tender under consideration.
17.15.3 Bid Capacity
The JV shall satisfy the requirement of “Bid Capacity” requirement mentioned at para 10.3 above.
The arithmetic sum of individual “Bid capacity” of all the members shall be taken as JV’s “Bid
capacity” to satisfy this requirement.
18. Participation of Partnership Firms in works tenders:
18.1 The Partnership Firms participating in the tender should be legally valid under the provisions of
the Indian Partnership Act.
18.2 The partnership firm should have been in existence or should have been formed prior to
submission of tender. Partnership firm should have either been registered with the Registrar or
the partnership deed should have been notarized as per the Indian Partnership Act, prior to
submission of tender.
18.3 Separate identity / name should be given to the partnership firm. The partnership firm should
have PAN / TAN number in its own name and PAN / TAN number in the name of any of the
constituent partners shall not be considered. The valid constituents of the firm shall be called
partners.
18.4 Once the tender has been submitted, the constitution of the firm shall not normally be allowed
to be modified / altered / terminated during the validity of the tender as well as the currency of
the contract except when modification becomes inevitable due to succession laws etc., in which
case prior permission should be taken from RLDA and in any case the minimum eligibility
criteria should not get vitiated. The re-constitution of firm in such cases should be followed by
a notary certified Supplementary Deed. The approval for change of constitution of the firm, in
any case, shall be at the sole discretion of RLDA and the tenderer shall have no claims what-so-
ever. Any change in the constitution of Partnership firm after submission of tender shall be with
the consent of all partners and with the signatures of all partners as that in the Partnership Deed.
Failure to observe this requirement shall render the offer invalid and full Bid Security shall be
forfeited.
57
If any Partner/s withdraws from the firm after submission of the tender and before the award of
the contract, the offer shall be rejected and Bid Security of the tenderer will be forfeited. If any
new partner joins the firm after submission of tender but prior to award of contract, his / her
credentials shall not qualify for consideration towards eligibility criteria either individually or in
proportion to his share in the previous firm. In case the tenderer fails to inform RLDA
beforehand about any such changes / modification in the constitution which is inevitable due to
succession laws etc. and the contract is awarded to such firm, then it will be considered a breach
of the contract conditions liable for determination of the contract under Clause 62 of the
Standard General Conditions of Contract.
18.5 A partner of the firm shall not be permitted to participate either in his individual capacity or as
a partner of any other firm in the same tender.
18.6 The tender form shall be submitted only in the name of partnership firm. The Bid Security shall
be submitted by partnership firm. The Bid Security submitted in the name of any individual
partner or in the name of authorized partner (s) shall not be considered.
18.7 On issue of Letter of Acceptance (LOA) to the partnership firm, all the guarantees like
Performance Guarantee, Guarantee for various Advances to the Contractor shall be submitted
only in the name of the partnership firm and no splitting of guarantees among the partners shall
be acceptable.
18.8 On issue of Letter of Acceptance (LOA), contract agreement with partnership firm shall be
executed in the name of the firm only and not in the name of any individual partner.
18.9 In case the Letter of Acceptance (LOA) is issued to a partnership firm, the following
undertakings shall be furnished by all the partners through a notarized affidavit, before signing
of contract agreement.
The partners of the firm to which the Letter of Acceptance (LOA) is issued, shall be jointly and severally
liable to RLDA for execution of the contract in accordance with General and Special Conditions of the
Contract. The partners shall also be liable jointly and severally for the loss, damages caused to RLDA
during the course of execution of the contract or due to non-execution of the contract or part thereof.
The partnership deed/partnership firm agreement shall normally not be modified/altered/ terminated
during the currency of contract and the maintenance period after the work is completed as contemplated
in the conditions of the contract. Any change carried out by partners in the constitution of the firm
without permission of RLDA, shall constitute a breach of the contract, liable for determination of the
contract under Clause 62 of the Standard General Conditions of Contract.
58
(c) Governing laws: The partnership firm agreement shall in all respect be governed by and interpreted in
accordance with the Indian laws.
(d) No partner of the firm shall have the right to assign or transfer the interest right or liability in the contract
without the written consent of the other partner/s and that of RLDA.
18.10 The tenderer shall clearly specify that the tender is submitted on behalf of a partnership firm. The
following documents shall be submitted by the partnership firm, with the tender:
(i) A notarized copy of the Partnership Deed or a copy of the Partnership deed registered with the
Registrar.
(ii) A notarized or registered copy of Power of Attorney in favour of the individual to tender for the
work, sign the agreement etc. and create liability against the firm.
(iii) An undertaking by all partners of the partnership firm that they are not blacklisted or debarred
by RLDAs or any other Ministry / Department of the Govt. of India from participation in tenders
/ contracts as on the date of submission of bids, either in their individual capacity or in any
firm/LLP in which they were / are partners/members. Any Concealment / wrong information in
regard to above shall make the bid ineligible or the contract shall be determined under Clause 62
of the Standard General Conditions of Contract.
(iv) All other documents in terms of Para 10 of the Tender Form (Second Sheet) above.
(Signature)
(Designation)
Signature of Tenderer(s) _________ RLDA Date
_____________ Date _____________
59
ANNEXURE-A
60
“As per the Technical specification published by the Manufacturer and as per best Industry practice
for the related works”.
5.0 APPLICABLE CODES AND STANDARDS
61
2.1 Indian Roads Congress Standards (IRC) and Indian Standards (BIS)
IRC 5 Standard Specifications and Code of Practice for Road Bridges,
Section I – General Features of Design
IRC 6 Standard Specifications and Code of Practice for Road Bridges,
Section II – Loads and Stresses
IRC 11 Recommended Practices for the Design of Layout of Cycle Tracks
IRC 19 Standard Specifications and Code of Practice for Water Bound Macadam
IRC 112 Standard Specifications and Code of Practice for Road Bridges
Section III–Cement Concrete (Plain and Reinforced)
IRC 22 Standard Specifications and Code of Practice for Road Bridges,
Section VI – Composite Construction
IRC 24 Standard Specifications and Code of Practice for Road Bridges,
Section V – Steel Road Bridges
IRC 37 Guidelines for the Design of Flexible Pavement
IRC 45 Recommendations for Estimating the Resistance of Soil below the
maximum Scour Level in the Design of Well Foundations of Bridges
IRC 48 Tentative Specifications for Bituminous Surface Dressing Using Pre-
coated Aggregates
IRC 78 Standard Specifications and Code of Practice for Road Bridges,
Section VII Parts 1 and 2, Foundations and Substructure
IRC 87 Guidelines for the Design and Erection of False Work for Road Bridges
IRC:SP 11 Handbook of Quality Control for Construction of Roads and Runways
IS 456 Plain and Reinforced Concrete – Code of Practice
IS 800 General Construction In Steel – Code of Practice
62
BS 4872 Approval testing of welders when welding procedure approval is not
required
BS 5075 Concrete admixtures
BS 5135 Process of arc welding of carbon and carbon manganese steels
BS 5212 Part 2 Cold poured joint sealants for concrete pavements
BS 5328 Methods for specifying concrete, including ready mixed concrete
BS 5400 Steel, concrete and composite bridges
BS 5400 Part 4 Code of practice for design of concrete bridges
BS 5400 Part 6 Specification for materials and workmanship, steel
BS 5606 Accuracy in building
BS 5896 High tensile steel wire and stand for the pre-stressing of concrete.
BS 5930: Code of Practice for Site Investigations.
BS 5950 Part 2 Specification for materials, fabrication and erection: hot rolled sections
BS 6031 Code of Practice for Earthworks.
BS 6105 Corrosion-resistant stainless steel fasteners
BS 6164 Safety in tunnelling in the construction industry.
BS 6349 Code of Practice for Dredging and Land Reclamation.
BS 6443 Penetrant flaw detection
BS 6681 Specification for malleable cast iron
BS 7079 Preparation of Steel substrates before application of paints and related
products
BS 7385 Part 2 Evaluation and measurement for Vibrations in Buildings – E to Damage
levels from Ground-Borne Vibrations
BS 7542 method of test for curing compound for concreter
BS 8000 Part 4 Code of Practice for Waterproofing.
BS 8000 Part 5 Code of Practice for Below Ground Drainage.
BS 8002 Code of Practice for Earth Retaining Structures.
BS 8004 Code of Practice for Foundations.
BS 8007 Design of Concrete Structures for Retaining Aqueous Liquids
BS 8081 Code of Practice for Ground Anchorages
BS 8110 Structural use of concrete
BS 8301 Section 5 Code of practice for building drainage
BS 8550 Concrete – Specification of Materials
BS EN 1997 Eurocode 7: Geotechnical design
BS EN 1998 Eurocode 8: Design of structure for earthquake resistance
CIRIA Report 44 Medical Code of Practice for working in compressed air.
CIRIA Report 80 A review of instruments for gas and dust monitoring
CIRIA Report 81 Underground Tunnel water proofing
CIRIA Report C515 Groundwater Control – Design and Practice
CIRIA Report C580 Embedded Retaining Walls – Guidance for Economic
CIRIA Report C660 Design Early Age Thermal CrackControlin Concrete
63
2.3 ASTM Standards
ASTM C-1202 Test methods for Electrical indication of concrete’s ability to resist chloride
ion penetration.
ASTM C-1240 Micro Silica/Silica fume in concrete
ASTM D-297 Methods for Rubber Products-Chemical Analysis
ASTM D-395 Compression set of vulcanized rubber
ASTM D-412 Tension testing of vulcanized rubber
ASTM D-429 Adhesion of vulcanized rubber to metal
ASTM D-573 Accelerated aging of vulcanized rubber by the oven method
ASTM D-624 Tear resistance of vulcanized rubber
ASTM D-797 Young’s modulus in flexure of elastomer at normal and subnormal
temperature
ASTM D-1075 Effect of water on cohesion of compacted bituminous mixtures
ASTM D-1143 Test method for piles under static axial comp. test
ASTM D-1149 Accelerated ozone cracking of vulcanized rubber
ASTM D-1556 In-situ density by sand replacement
ASTM D-1559 Test for resistance to plastic flow of bituminous mixtures using Marshall
apparatus
ASTM D-2172 Extraction, quantitative, of bitumen from bituminous paving mixtures
ASTM D-2240 Indentation hardness of rubber and plastic by means of a Durometer
ASTM D-3689 Testing method of testing individual piles under static axial tensile load
ASTM D-4945 Test method for high strain dynamic testing of piles
ASTM E-11 Specification for wire cloth sieve for testing purpose
ASTM: Section 4: Construction, Volume 04.08: Soil and Rock I, and Volume 04.09: Soil and
RockII,
64
AASHTO M213-81 Preformed ` joint fillers for concrete paving and structural
construction
AASHTO M 282-80 Joints sealants, hot poured, elastomeric-type, for port- land cement concrete
pavements
AASHTO M 294-70 Fine aggregate for bituminous paving mixtures
AASHTO T22-82 Compressive strength of cylindrical concrete specimens
AASHTO T23-80 Making and curing concrete compressive and flexural strength test specimens
in the field
AASHTO T26-79 Quality of water to be used in concrete
AASHTO T96-77 Resistance to abrasion of small size coarse aggregate by use of the Los
Angeles machine
AASHTO T99-81 The moisture-density relations of soils using a 5.5-lb (2.5kg) rammer and a
12-in (305mm) Drop
ASHTO 104-77 Soundness of aggregate by use of sodium sulphate or magnesium sulphate
AASHTO T176-73 Plastic fines in graded aggregates and soil by use of the sand equivalent test
AASHTO T180-74 The moisture density relations of soils using a 10-lb (4.54kg) rammer and an
18-in (457mm) Drop
AASHTO T182-82 Coating and stripping of bitumen-aggregate mixtures
AASHTO T191-61 Density of soil In-place by the sand-cone method
1) EXTERNAL PAINT
Providing and applying surface texture with natural ceramic chips & granite stone textured
'finish (SUZUKA – Ceramic/stoney/magic or equivalent make of the similar specification
of materials) of approved shade comprising of water-borne, penetrating, water repellent
Exterior Masking Primer (EMP) with water based Fluorocarbon 'resin & emp; silicon resin
clear dirt & emp; dust resistant protection coat of FSI clear coat or equivalent in 'two coats,
which shall be highly water repellant, anti-algae & emp; anti-fungal in nature to external
'wall surfaces. The coating shall also cover hairline cracks with following application
method which includes one coat of External Masking Primer, one coat of natural granite &
emp; Ceramic 'chips texture, all in approved natural shade and texture with a final two coats
coat of 'fluorocarbon –silicon resin clear coat. It shall also include preparation of surface,
appropriate primer coat etc. applied as per manufacturer's instruction as well as per direction
of Engineer in charge. The finish shall be in natural color and non-pigmented, water
repellant, resistant to ultra violet, alkali and condensate formation, nothing extra shall be
paid on account of scaffolding etc. and complete work is to be done as per the instruction
and direction of Engineer-in-charge. The measurement of the work shall be done for the
finished portion only.
2) Waterproofing for Horizontal and Vertical Surfaces- Waterproofing system shall be installed
by experienced authorized applicator of manufacturer.
65
2.1) For Horizontal Surface: -
a) Substrate preparation: Cleaning the plain cement concrete surface to make it aggregate,
dust and sludge free, removing any extended portions by grinding using suitable
equipment. Any voids and depressions more than 10 mm shall be treated with Sika latex
SBR.
b) Providing and applying a 1.5 mm thick double sided, modified bitumen waterproofing
membrane with cross laminated PE film for wet application on Podium The membrane
shall be applied after making concrete wall in saturated surface dry condition and applying
a bonding slurry (2-3 kg /sqm). The membrane is then unrolled and pressed into the fresh
slurry after removal of the release liner. Both long and short edges of the membrane are
overlapped by min. 80 mm and firmly pressed together using a roller with staggered
overlaps. The membrane shall have tensile strength 4 N/mm or as acceptable and submitted
by manufacturer according to ASTM; elongation 200 % or as acceptable and submitted by
manufacturer according to ASTM; resistance to tear 23 N or as acceptable and submitted
by manufacturer according to ASTM D624; joint peel resistance 700 N/m or as acceptable
and submitted by manufacturer according to ASTM D1876 at 23 °C; joint shear resistance
220 N or as acceptable and submitted by manufacturer according to ASTM E154; low
temperature flexibility of -15 °Cover crack tested for 100 cycles or as acceptable and
submitted by manufacturer according to ASTM C836; resistance to lateral water migration
70 m according to ASTM D5385 mod.
c) Providing and applying a two‐part, crack bridging, elastic, ultra-fast curing polyurethane
waterproofing membrane system spray applied at an average thickness of 1.5 mm- 2mm
including compatible primer and all and the waterproofing membrane having the following
key performance properties and conforming to standards and approvals as mentioned
herein; Key Performance Properties:
66
• Tensile strength >10 N/mm2 [28d/+23ºC] or as acceptable and submitted by manufacturer
• Elongation at break (%) > 510% after 28d/+23ºC or as acceptable and submitted by
manufacturer
• Thermal resistance – The elastic properties are maintained at temperatures as low as ‐20°C.
or as acceptable and submitted by manufacturer
• Curing speed/rate – Cup Gel Test: Gel time (25°C) starts after ~ 20 seconds.
Standards/Approvals or as acceptable and submitted by manufacturer: The waterproofing
membrane must conform to applicable international and IS code System: Primer shall be
lightly broadcast with quartz sand 0.3‐0.8 mm) Waterproofing compound :@ 1.8kg/Sqm
Providing & applying the pre-applied plain finish HDPE membrane should be having
minimum thickness of 1.2mm. Fully bonded membrane shall comprise of HDPE layer of
not less than 0.8mm, strong adhesive and protective layer. Fully bonded membrane shall
have following minimum properties - Composite Thickness (ASTM D 3767)-1.2 mm,
Tensile Strength of Film (ASTM D 412) >27 MPa, Elongation (ASTM D 412) > 400%,
Low Temperature Flexibility @ -25oC (ASTM D 1970)- Pass, Resistance to Hydrostatic
Head (ASTM D 5385) > 60 Meter, Crack Cycling (ASTM D 836/ASTM C 1305) -Pass,
Peel Adhesion to Concrete (ASTM D 903) ->880 N/m, Dimension stability (ASTM 1204)
< 2%, Puncture Resistance (ASTM E 154) > 1000 N or as acceptable and submitted by the
manufacturer. Membrane system shall be installed by experienced authorized applicator of
manufacturer.
5) STEEL DOOR
a) Providing and fixing multipurpose hollow metal doors shall be galvanised steel
conforming to IS 277, made out of minimum 1.2 (18 SWG) for both frame and shutter,
G.I. sheet (zinc coating 120 gsm/sqm). Frame shall be 125 x 55 grooved profile with built
in rebate for grooved seal. Frame shall be mitered and field assembled. grove seal to be
provided along with frame as standard. Door shutter shall be double skin of 46mm thick
with or without vision panel. The infill material shall be resin bonded honeycomb core.
All door set shall be factory prepped for receiving appropriate hardware and provided
with necessary reinforcement for hinges, locks and door closers. The door stiles should
be interlocked, for pairs of doors integral astragals has to be provided on the meeting stile
for both active and inactive leaf. Vision lite, minimum 5mm clear toughened, fixing with
clip-on arrangement. All frame and door shutter shall be finished polyester powder coated
67
to minimum 50microns, of approved colour as per the direction of the engineer incharge.
Cost of double leaf door set shall include following hardware and accessories as a
complete assembly. SS ball bearing hinges of SS304 grade of size 100x75x3mm, 1no
mortise dead lock, 55mm BS, 20mm sq. fore end, including escutcheon, sss as per EN
12209 with both side key cylinder on active leaf and 2nos flush bolt on the inactive leaf
in case of double leaf door, 1no of dust proof socket, 1pairs Pull handle D type, 22dia,
CTC 300mm, back-to-back per leaf, with spindle, SS 304, SSS finish. 1no of Door closer
with spring size of EN 2-4, as per EN1154 and CE marked per leaf. Suitable anchor
fasteners for fixing on different type of wall construction as per manufacturer
recommendation. Once frames are installed it shall be filled with PUF.
b) Door frame shall be step rebate grooved profile of size 125 x 75mm made out of 1.20mm
(18gauge) minimum thick galvanized steel sheet. Frames shall be mitered and field
assembled with self tabs. Frames to have inbuild grooved sealing system for taking fire
rated seals. All provision should be mortised, drilled and tapped for receiving appropriate
hardware. Frames should be provided with back plate bracket and anchor fasteners for
installation on a finished plastered masonry wall opening. Frames shall be filled with fire
rated puff (paid extra).
c) Door leaf shall be 60mm thick fully flush double skin step design door, insulated with or
without vision lite. Door leaf shall be manufactured from 1.2mm (18guage) minimum
thick galvanised steel sheet. The internal construction of the door should be rigid
reinforcement pads for receiving appropriate hardware. The infill material shall be 120kg
high density mineral wool insulation material. Intumescent seals 15 x 1.5mm to be
provided. All doors shall be factory prepped for receiving appropriate hardware and
provided with necessary reinforcement for hinges, locks, and door closers. The edges
should be interlocked with a bending radius of 1.4mm. For pair of doors integrated
astragals has to be provided on the meeting stile for both active and inactive leaf. Vision
lite wherever applicable shall be maximum 200 x 300mm (or max 0.06sq.mt) with clear
borosilicate fire rated glass of 6mm. Glass shall be fixed with suitable gasket and with
clip-on arrangement.
d) Door and frames shall be finished Pure Polyester Powder coated and shall have passed
minimum 500 hours of salt spray test.
e) Rate shall include supply and installation of frame, shutter as a complete assembly
including all hardware, smoke seals & glass with tape.
The SS work may have to be fabricated out of SS sheets of 1.2 mm thickness, SS hollow
sections, SS pipes, etc. and may involve any or combination of two or more of these in
sizes, quantity and quality as specified in the drawings or as directed by the Engineer-in-
68
Charge. The Contractor shall design, prepare drawings, furnish all the materials, skilled
staff and labour, transportation, equipment, tools, tackles, temporary work, hoisting,
erection and all other things that may be required for carrying out the work described
above as per drawings, specifications and the instructions of the Engineer-in-Charge.
69
3. Horizontal Steps – Four
4. Inclination – 30 Degree
5. Speed – 0.50 M/s
6. Gear Box – Helical – Work Gear
7. Motor Protecting Rate – IP55
8. Frequency – 50 Hz
9. Lighting Voltage – 240v
10. Start – VVVF (Inverter)
11. Power Voltage – 415v
12. Arrangement – According to Layout
13. Motor Power – 2*11 KW
14. Truss – Hot Dip Galvanized
15. Delivery In – Four Pieces
16. Intermediate Support – One
17. Standard Installation – No – 800mm extension on top
18. Handrail Color – Black
19. Ballustrade Panel – Hairline Stainless Steel
20. Ballustrade Profile - Hairline Stainless Steel
21. Ballustrade – Inclined at a height of 1000mm
22. Skirting - Hairline Stainless Steel
a) 25 mm thick Flamed finish granite stone slab Jet Black, Cherry Red, Elite Brown, Cat
Eye or equivalent.
b) Extra for Grooves in Tread of Steps @3 Nos. (6mm width & 6mm depth) along the
length of tread complete under direction of Engineer-In-Charge.
70
halters. Aluminium halters to be fixed purlins with SS 304 screws. The profiled roof
panel should have ribs for extra strength including required accessories, fasteners etc.
Sheets are to be laid to meet the requirements of the building geometry and fixed on
Aluminium Halters. The Roofing system provider shall provide the testing done for
Water leakage (Static & Dynamic) and Air Infiltration test as per ASTM and other
relevant standards. All installation is to be carried out by approved trained roofing
installer and applicators.
ii) Halter – Aluminium Halters of grade 6082(T6) of suitable height with thermal barrier
pads 6mm to be fixed to the sub purlins with SS 304 screws only.
iii) Insulation shall be 100 mm thick with vapour barrier i.e. Rockwool with minimum
density 60 kg/m3 as approved by Engineer-In-Charge.
iv) Vapour control barrier – Polyethylene film or Aluminium foil of 0.20mm thick, heavy-
duty type.
v) Liner – It shall be of sheet manufactured from 0.45mm to 0.47mm base metal thickness.
The panel shall be manufactured out of Hi tensile pre-painted Zincalume/Galvalume
steel-AZ150 having minimum yield strength of 550 MPa with Super durable Polyester
/SMP or approved equivalent quality paint coat as per AS/NZS 2728 Class 3.
The entire Double skin system is installed over the structure purlin. The contractor shall
prepare the shop drawings based on the drawings supplied by the Engineer-in-charge
for approval.
vi) Aluminium Flashing 0.9mm thick: Flashings manufactured from aluminium alloy AA
3004(AlMn1Mg1) as specified in BS EN 1396: 2007 thickness of 0.9 mm and
Fluorocarbon PVDF finish on the exposed surface. The material shall be other same
color. Girth – 575mm-600 mm.
vii) Providing and fixing of 2.0 mm thick Aluminium gutter with double side vulcanised
rubber Expansion joints at every 12m length or as per the requirement. Necessary down
take spout with diameter upto 150 mm at required intervals & other accessories like
Cover plate, end caps and welding at joints. The Girth of gutter would be upto 1200mm.
viii) Supply and Fixing of Deck Strip Flashing around the structural/Roofing openings as per
drawing, specification and instruction of Engineer-In-charge.
12) POLYCARBONATE SHEET
Providing and fixing of minimum 22 mm thick 5 cells and 6 walls UV protected Multicell
Polycarbonate Panel System over structural steel / MS purlin as per approved colour/shade
and as per drawing, Specification and instruction of Engineer-In-charge.
71
PREFERRED MAKE LISTS APPROVED MAKES/ BRANDS
i) The sanitary fitting shall be of premium quality of approved brand make and manufacture as
per approval of Engineer-in-Charge. All the urinals, taps shall be sensor based if not mentioned
in the specific item of work.
ii) Specification/brands names of materials to be used as per the scope of work are listed here. The
efforts should be made by the agency to use indigenous products. The agency should also
consider the availability of spares parts/components for maintenance purposes while proposing
any brand/manufacturer. The alternate brand can be used only after the approval of Authority.
iii) Samples of all materials, fittings etc. to be incorporated in the work shall be submitted by the
Contractor and got it approved from the Authority before supply in bulk at site of work. Wherever
particular make or its equivalent is mentioned in this schedule, the decision of Authority in
selection of the particular make or its equivalent shall be final and binding on the Contractor.
The approved samples will be kept in custody of Authority till completion of the work.
Materials not conforming strictly to the approved samples will be rejected.
72
Admixtures, Other construction CICO Sika BASF
chemicals MAPEI MYK Arment
10 BASF Sika TIKIDAN
Waterproofing Compound(Crystalline) Fosroc MYK Arment Sunanda
Chemicals
Pidilite M.C.
Bauchemie
GRACE Fosroc Pidilite
11 Waterproofing Self Adhesive MYK Arment Technolicol TIKIDAN
SIKA Mapei Asian Paints
(HDPE) membrane M.C. Sunanda
Bauchemie
Pidilite STP Polygomma
12 EPDM Waterproofing Membrane Fire Stone DBS Sunanda
PU Elastomeric Membrane BASF Fosroc Sika
13 (spray applied for Deck STP Pidilite MYK Arment
Waterproofing) Sunanda
Fosroc, Sika BASF
14 Concrete Curing Compound Pidilite Mapei MYK Arment
TIKIDAN M.C.
Bauchemie
UP Twiga Poly Glass Ownscorning
15 Rockwool India USG Kanauff
Glass wool Insulation
16 Rock Wool Insulation Lloyds Roxul
Rockwool
Pidilite Fosroc BASF
17 Swellable Bar Hayakawa
DPI Gallina Lexan
18 Daylighting
Polycarbonate Sheet Tuflite Polygal Danpal
19 Expanded Poly Styrene Sheet (EPS) Penguin Kiwi E-Pack
Frayssin
20 Soil anchor for diaphragm wall Tata Usha Martin et India,
Dynami
c
21 Decking Steel Sheet TATA Steel RINL JSW
22 Rebaring Chemical Hilti Fischer ICFS
73
28 Ferrouscrete Ultratech JK
AAC Mortar
29 Expansion Filler Board- Supreme STP-
Premoulded compressible(Non (Capcell Shalitex-
Bituminous) HD100), (SEJ-R-NB)
30 Saint Gobain Gyproc USG KANAUF
Moisture Resistant Board
Greenlam Duro Merino
Century TIKIDAN
31 Merino Duro Greenlam
Veneered Particle Board
Kitply Archid Century
32 Saint Gobain, , Shakti Horman Navair,
Fire rated Glazed door
33 Shakti Horman, Pacific, IHMS,
Metal Fire rated Doors
Navair, Sukriti ASES
34 Promat, , Ardor Navair,
Wooden Fire rated Doors
Kenwood ASES Secrurity
35 Becker Fire Assa Abloy
Fire Rated Hardware& System solutions (Yale),
36 3 M, Hilti, Dorma,
Fire Seal, Fire smoke Seal
Sealz, Lorient, Kelargo,
37 Vetrotech Pyroguard, AGC/AIS
Fire rated Glass Saint- Gobain
Schott-Pyran Pyroswiss
38 Shakti Hormann Gandhi Avian,
Fire rated rolling shutter Automation
39 Orient Stobich Pacific
Fire curtain
New Green Kent Neco
40 Schuco, Aluk, Technal,
Façade and window wall system
Façade 1, SAPA, Lilli,
41 Wacker Dow corning, GE momentive
Silicone Sealant
Mapei, MC- bauchemie Pidilite
42 Hilti 3M, STI,
Fire stop in curtainwalls system Fischer
43 Merino Greenlam Century
Laminated Particle Board / Laminates
Archid Duro
44 Century Green Merino
74
Archid Duro Tata Pravesh
Flush door / Laminated Flush Doors
45 Exterior Grade- MDF Century Green, Action Tesa
46 System for motorized curtain Somfy, Forest Hunter Doulgas,
motorized
systems,
Toso company
limited
47 Toilet Cubicles Merino Greenlam T Line
Dorma STYLAM
48 Hardware for Fire Check Door Dorma AssaAbloy Hafale
Horman Becker
49 LG 3M, Garware,
Frosted film
50 Merino Greenlam Century
Plywood/ Veneer/Laminate
Archid Duro
51 CS Group Herculus Z-Tech
Expansion Joint -Modular
Vexcolt MIGUA
52 Aluminium glass partition system Dormakaba Lindner, Vetro Partizone
Kubik, Bottom line, Otic,
53 Aluminium openable louver Technal, Domal, Yogi Glaze
54 Air transfer grill Ruski, System Air, Trox
55 BMU/Façade cleaning System SECO JKB, MT and T
(Madrash tools
&
tackles)
56 Fosroc Pidilite Sika
Poly-Sulphide Sealant
CICO Mapei Myk Arment
M.C.
Bauchemie
57 Birla Wall Care JK White Saint Gobain
Wall Putty
Ferrouscrete Berger Asian Paints
58 Fosroc Sika Cico
Curing Compound
STP Pidilite BASF
59 Asian Paints Akzonobel
Oil Bound Washable Distemper Dulux
ICI Nerolac Ultratech
75
60 Nerolac Asian Dulux
Acrylic Distemper
61 Dulux Nerolac Asian Paints
Premium Acrylic Emulsion paints
62 BP White Decoprime WT Akzonobel
Cement Primer (Berger) (Asian) (Dulux)
Nerolac
63 Berger Nerolac
Snowcem Plus (DurocemExtra (Nerocem
Cement Paint With Titanium)
)
Asian Ultratech
64 Akzonobel
(Dulux) Nerolac Asian Paints
Steel / Wood Primer
Berger Jenson
&
Nicholson
65 Akzonobel Asian (Apex Nerolac Kansai
Textured Exterior Paint (Dulux) Ultima) (Excel)
Spectrum
66 Akzonobel Asian Kansai
Synthetic Enamel Paint (Dulux) (Apcolite) Nerolac
(Synthetic
Enamel)
76
73 Stone sealer Ardex Endura MYK Killick
Latricrete Guar
d Speciality
Products Limited
74 Kerakoll. Akemi, Pidilite
75 Water & Stain repellant coating for Killick Guard Dowcornin Pidilite
Speciality g,
stone cladding and stone flooring
Products
Limited,
76 OZONE Hafale Geze
Stainless Steel Hardware
KICH
77 Automatic Sliding Door Dorma Ozone
78 Metal roofing system (Aluminum ). Kalzip Kingspan Tiger
Hindalco
2. FALSE CEILING
Hunter Douglas
4
Gyproc Durlum SAINT GOBIN
False Ceiling
Grid System Gridline Armstrong USG KNAUF
5 Hunter Douglas Durlum SAS
77
7 Cement Fiber Everest, Shera Board,
NCL Industries
Board/ Cement
(Bison Panel),
Bonded particle
board Visakalndu Century (Zykron),
Stries (V-
next),
3. FLOORINGS
78
10
NITCO Unitile Ultra
Paver Block & Unistone Terra Ferma
Dalal
Kerb Stone Tiles
Industrie
s
11 Tile / Stone Pidilite Ferrous Crete MYK Laticrete
Adhesive Fosroc BASF Kerakoll
/Tile / Epoxy Grout M.C. Bauchemie
12 Dash / Anchoring
Hilti Fisher Bosch
Fasteners
13 Floor Hardener
Ironite Fosroc Hardonite
14 Ashford M.C. Bauchemie
Sikka
15
Laminated Floor Action Tessa Greenlam Pergo
Century
16 Composite
Marble / Granite NITCO Johnson Kalinga
/ Engineered
Stone
17 Water Asian Paint Pidilite ICI Dulux
Based
Melamine
Polish
18 Clamp System Hilti Fischer Bosch
For Dry
Stone Cladding
19 Calcium Everest NCL Aerolite
Silicate False
20 Ceiling Gyproc USG KNAUF Armstrong
Calcium Silicate
Ceiling
Tile / Board
4. GLAZINGS
79
Hardware (Heavy
Duty)
2 Aluminum Jindal Nalco Hindalco
Structural
Members –
Windows, Glazing
and Partitions
3 Glazing Structural / Saint Gobain Gujrat Guardian Asahi
Suspended /
Skylight Modi
4
Saint Gobain AIS Guardian
Clear / Float /
Frosted Glass MODI Guard Atul
5
Glass Spider Fittings Dorma Hafale Ozone
6
Stainless Steel Modular Rinox Ozone D-line
Railing, Accessories etc. in KICH
Grade SS 304 & 316 Dorma Koncept
7
Hermitically Saint Gobain Modiguard Guardian
Sealed
performance
glass
Toughened Glass
8
Fire Rated Guardian Schott Ferilite
Vision Panels Saint Gobain Glaverbel
9
Ceramic panel Cladding Hunter Douglas Neolith Terreal
10
Aluminum Louvers Hunter Douglas Armstrong Colt
11 Aludecor Alucobond Alpolic
Aluminium
Composite Panels
12
Fenesta Windowmagi Kommerling
UPVC Doors c
& Windows
Prominance
5. HARDWARE
80
S. Material Approved Makes / Brands
No.
1 GKW Atul Hilti
Nuts / Bolts / Fastners / Screws
Rawlplug
2 Godrej Everite Doorset
Door/Window Fittings
Hardwyn
3 Dorma Godrej Hettich
Door Closer Everite Hardwyn Ozone
4 Dorma Geze AssaAbloy
Die Cast Patch Fittings
Hettich Ozone
5 Iclean Shakti Hormann Promat
Fire Rated Doors
Navair
6
Dorma Geze Hettich
Floor Springs Ozone
Dorset
7 SS Mortise lock with
one dead bolt and pair of Dorma Godrej Hafele
SS handles steel Ozone Hettich
Dorset
grade SS 304
8 SS Mortise latch &lock with Dorma Godrej Hafele
six levers and pair of SS Ozone Hettich
handles steel grade SS304 Dorset
9
SS Tower bolt Dorma Godrej Hafele
10 SS Butt hinges with ball Dorma Godrej Ingersoll Rand
bearing grade SS 304
Hettich
11 Stainless Steel Sliding Ingersoll Rand Hafele Godrej
Door bolts
12 Pull handle back-to-back of
length 150mm of Steel Godrej Geze Ozone
Grade SS 304
Hettich
81
15 Dorma Hafele Godrej
Lever handle in SS 304finish Hettich
16
Magic Eye Dorma, Rand Godrej, Ingersoll
17
Brass Hardware Magnum EPPW Paladium
82
M.S. PIPE (GREATER THAN PRAKAS
OR EQUAL TO 300 MM DIA – JINDAL STAR H
SPIRAL & SURYA
WELDED
ADVANCE L&T DANFOSS
9 BUTTERFLY VALVES
VTM AXIM CASTLE
BELIMO DANFOSS SIEMENS
10 MOTORIZED
OVENTROP HONEYWELL
BUTTERFLYVALVE
PRESSURE BELIMO DANFOSS SIEMENS
11
INDEPENDE OVENTROP FLOWCON
NT CONTROL VALVE (PICV)
12 CHECK VALVES ADVANCE L&T DANFOSS
VTM AXIM CASTLE
ZOLOTO ADVANCE KITZ
13 BALL VALVE
VTM AXIM CASTLE
SIEMENS ADVANCE CASTLE
HONEYW
14 BALANCING VALVES VTM AXIM EL L
DANFOSS
2-WAY MODULATING BELIMO HONEYWELL SIEMENS
15
VALVES WITH DANFOSS FLOWCON
THERMOSTAT
2-WAY ON OFF VALVE
16 WITH THERMOSTAT BELIMO HONEYWELL SIEMENS
FOR FCU
RESISTOFLEX EASYFLEX AREAFLEX
17 EXPANSION BELLOWS
DUNLOP AXIM FLOWCON
SANDHU RAPID COOL EMARLD
18 POT/Y-STRAINERS
AXIN
ANERGY ARMSTRONG EMERALD
19 SUCTION GUIDE
AXIN
WITHSTRAINER
HONEYW
BELIMO SIEMENS EL LL
20 BTU METER
SHENITECH CASTLE FLAMCO
BELIMO HONEYWELL SIEMENS
21 RH SENSOR
OMNICRON
HONEYW
DANFOSS BELIMO EL L
22 THERMOSTAT
SIEMENS OMNICRON
83
PRESSURE GUAGE FEIBIG H. GURU EMERALD
23
(INDUSTRIAL TYPE) & AXIN WAREE BAUMER
TEMPERATURE GAUGE
RAPID
SIEMENS CONTR ANERGY
24 DIFFERENTIAL PESSURE
O
SWITCH
SANT
FEIBIG H. GURU H. GURU
25 THERMOMETERS
EMERALD AXIN
BELL &
ANERGY GOSSET SANDHU
26 CLOSED EXPANSION TANK
EMERALD
ANERGY EMERALD SANDHU
27 AIR SEPARATOR
CASTLE FLAMCO
28 AUTO AIR VENT ANERGY RAPID COOL OVENTROP
29 PLUG VALVE ANERGY RAPID COOL
30 G.I. SHEETS SAIL TATA JINDAL
31 MS. SHEETS HINDALCO BALCO NALCO
RUSKI
SYSTEMAIR CARYAIRE N
32 FIRE DAMPERS
TITUS
GREENHECK AIRMASTER
33 DAMPER ACTUATOR BELIMO SINIDER
RUSKI
SYSTEMAIR CARYAIRE N
34 GRILLS/DIFFUSERS
TITUS
TROX AIRMASTER
SYSTEMAIR CARYAIRE TITUS
35 FRESH AIR LOUVERS
TROX
OWENS
RESIN BONDED GLASS UP TWIGA CORNIN KIMMCO
36
WOOL INSULATION G
K-FLEX
PIDILITE
PROTECTIVE COATING (WEATHER FOSTER 30-36 IDENDAN
PROTECT
37 OVER COAT)
INSULATION (LAG COATING) CISBOND/CISC STARBO
HE M MAGIK 30-36 ND 30-36
OWENS
RESINBONDED GLASS UP TWIGA CORNIN KIMMCO
38
WOOL G
ACOUSTIC INSULATION K-FLEX
84
PIDILITE FOSTER CISBOND
39 INSULATION ADHESIVE
HENKEL
ROLASTAR DUCTOFAB ZECO
40 FACTORY MADE DUCTING
TECHNOFAB ECODUCT
FILTERS (IN AIR- THERMODYNE PUROLATOR ANFILCO
41
CONDITIONING SYSTEM) MACKMARK
VENTILATION FANS:
GREENH
42 TUBE/VANE AXIAL KRUGER SYSTEM AIR EC K
KRUGER SYSTEM AIR CARYAIRE
43 INLINE (CENTRIFUGAL)
OSTBERG
KRUGER CROMPTON WOLTER
44 PROPELLER FANS
NICOTRA DYNAIR
EDGETECH ZECO SYSTEM
45 AIR WASHER / SCRUBBER AIR
VTS CRYSTAL
AIR
46 FAN KRUGER NIKOTRA COMFERI
47 PUMP KIRLOSKAR BEACON WILO
48 FILTERS AS PER MANUFACTURER’S STANDARD
FLAKTW
DRI ENVENTUS OO DS
49 HEAT RECOVERY WHEEL
UNITS OSTBERG EDGETECH ZECO
50 HEAT PIPE HPT SPC VTS
51 VIBRATION ISOLATOR EASYFLEX RESISTOFLE DUNLOP
X
HILTI FISCHER GRIPPLE
52 ANCHOR/FASTENER POWER
RAWLPLUG FASTEN WUERTH
ER
EASYFL
GPL GRIPPLE EX ZIP-
CLIP
53 DUCT SUPPORT HIRA
HI-TECH WALRAV HILTI
EN
Fischer
54 PUF SADDLES FOR PIPE LLOYDS BEARDSELL MALANPU
SUPPORT R
TECHNONICOL SEVEN STAR
55 FCU LINK ATS (CSI) OVENTROP CIM
85
RUSKIN TITUS SYSTEMAIR TROX
56 SOUND ATTENUATOR
AIRMASTER CARYAIRE
57 CO SENSOR SIEMENS OMICRON JOHNSON
DANFOSS ABB SIEMENS
58 VFD
FUJI
59 CO2 SENSOR SIEMENS OMICRON JOHNSON
60 ONLINE SCALE PREVENTER SCALE GUARD RISTELLO SUPREMO
UNIVERSAL
61 UVCI U UVTRONIX SUPCO
V SOLUTIONS
62 AHU / FCU MOTOR ABB CROMPTION SIEMENS
FINOLEX KISSAN PRINCE
63 HIGH DENSITY PVC PIPE
SUPREME
64 PACS STULUZ EMERSON BLUE BOX
ALUMINIUM SHEET /
65 PERFORATED ALUMINIUM NALCO HINDALCO BALCO
SHEET
HONEYWELL TRION TRANE
66 ELECTRONIC AIR
JOHNSO
FILTRATION N RUSKIN MAGNETO
SYSTEM CONTRO TITUS
LS
DAIKIN TOSHIBA CARRIER
67 VRF/VRV SYATEM
MITSUBISHI VOLTAS HITACHI
CAMIPRO RAJCO MANDEV
68 COPPER REFRIGERANT
MEXFLOW
PIPE
69 CHILLED WATER HI- MIDEA CARYAIRE EDGETECH
WALL & CASSETTE
UNITS
UP TWIGA CARYAIRE ATCO
70 FLEXIBLE DUCT
RUSKIN TITUS SEVEN STAR
86
a)
Grohe
Geberit Kohler Roca
Concealed cistern
jaguar
WC connector Geberit Kohler Viega
Auto Urinal Flush Duravit Kohler Roca
System Jaquar Kohler
87
16 Centrifugally Cast (Spun)
Ductile Iron Pipes Electro Steel Jindal (Hissar) Kalinga
&Fittings
RCC manhole Covers &
17
Frames KK manhole Grating Co. Pvt Ltd
D.I. Manhole Covers Neco, Raj Iron Foundry Kartar
& Frames Agra
18 Kartar Castle Zoloto
Gun Metal Valves, Globes
NRV - Ball type - Danfoss Zoloto Audco
Sewage application
Bellow Type, CIM Danfoss Honeywell
19 Pressure Reducing
Valve
20 Floor Taps Jayana Chilly Nirali
88
30 Insulation for hot Lloyd
water pipes
Insulation for Kaiflex Armaflex Careflex
31
external/ exposed hot
water pipe Lloyd
Pipe protection for
32
external water Pypkote Armaflex Makpolykote
supply
pipes
33 GI/MS Pipe IWL - Pypkote Rustech - Coatek
Protection Wrapping
& Coating
34 Kaff Carysil Futura
Stainless Steel Sink
Cera Anupam Neelkanth
89
48 Venus Bajaj Spherhot Photon
Water Heater (Geyser)
Racold Havells
49
Hand Drier Euronics Duravit Grohe Kohler
52 Anti-Vibration
Resistoflex Dunlop Flexionics
Mounting &
Flexible connections
53 Electronic Flow Meter Blue Star Usha Voltas
90
64 Balancing Valve Advance Utam& VTM L&T
91
First Aid Hose Reel
Drum Safe Fire
89 Tyco Viking HD
Sprinkler & Rosette
Plates Spray Safe
92
97 Flexible Duct Mapro nwall Resistoflex
Connector Industri
al corporation
98 Stainless Steel Safex Padmini GETech
Branch Pipe
Fireman Axe /
99
Installation Control
Valve Safex Padmini GETech
103 Kanwal
Rubber Bellow Industri Resistroflex AIP Valves
al Corporation
104 Deluge Valve Safex Tyco HD
Flexible Drop
105 (UL Approved) Safex HD Kofulso
93
114 CT AE Kappa Nutech
Electrical
115 MCCB / Siemens Schneider Legrand
MPCB /
ABB Havells
MCB/RCCB
Contractors / Times,
116
Overload Relays/
Starter L&T Siemens Schneider
117 PCD Agni Tricolite
Annunciation panels
Adlec
Single phase
118 preventor Minilac L&T Siemens
Anti Vibration Kanwal Industrial Resistoflex Ewren
119
Mounting Corporation
120 Starter L&T Siemens Crompton
GE ABB BCH
Current
121 Transformer (Cast AE L& T Kappa
Resin)
122 Nuts / bolts Lakshmi Unbrako
9. INSULATION
94
Submersible
2 Draina
ge KSB Grundfoss Crompton
Pumps
3 Ball Valves ARCO SANT Zoloto
8
Float Switch
Nolta Danfoss Honey Well
Liquid Level
11
Controllers/
Liquid Level Advance Honey Well Danfoss
Indicator
12 Ion Exchange Renaissance Aqua Pentair
Filter / Softener
Watcon
95
17 Mechanical Seal Burgmann Sealol
Submersible Sump
9
Pumps for collection
chamber,
equalization tank,
Plant room KSB Grundfoss Crompton
drainage, Filter
backwash sump
96
Domestic Hydro
10 pneumatic Willo - Mather
transfer Grundfos DP-Holland
pump
Pressure Transmitters
11 Johnson Control
/Hydrostatic
Level Indicators WIKA Siemens
Pressure Gauges
12 Fiebig H. Guru WIKA
13 Dosing System ASIA LMI Milton Roy Grundfoss
Pump Vibration
14
Pads &Suction &
Delivery Flexible
Connectors Easyflex Resistoflex Dunlop
15 Pressure Sand M.S.
& Activated Prefabricated BRISANZA FONTUS
carbon filter
16
Air Blowers
Everest Beta ABL
17 Ultra Violet Alpha UV Sukrut Neotec
Disinfection for
Treated Effluent
18 Air Diffusors BOBKAY MM Aqua REHAU
21 Sludge Pumps
(Centrifugal) Kirloskar Grundfoss ITT Industries
97
29 DO Meter Hach Toshniwal Oakton
30
TDS Meter
Hach Toshniwal Oakton
31 Ultra Violet Alfa UV Mumbai Eureka Forbes
Water Purifier Pentair
(WTP / STP)
Syphonic Roof
32 Drainage System Geberit Saint Gobain
33 Ozonisation System Oraipl Ozonics Voltas
34 Geared Motor Bonfiglioli Grease Cotton otova rio
98
4 MCCB ABB - Tmax L&T- D’Sine
99
FINOLEX HAVELL’S POLYCAB
FRLS PVC
14 KEI RR KABLES RAVIN
INSULATED COPPER
WIRE/STRANDED GEMSCAB
FLEIBLE WIRES
XLPE INSULATED
PVC SHEATHED HAVELLS POLYCAB BATRAHENLAY
AL/COPPER
15 CONDUCTOR RAVIN FINOLEX KEI
ARMOURED
/ UNARMOURED 1.1
KV
(1100 V) GRADE
POWER CABLE
33KV AND 11 KV H.T. GEMSCAB DUCAB APAR
16 CABLE (XLPE, FRLS) RAVIN CABLE KEI
DOWELLS COMET BRACO
17 LUGS / GLAND
3M CABSEAL COSMOS
PVC CONDUIT & AKG BEC PRECISION
18 ACCESSORIES
POLYPACK
(IS
IMARKED)
MS CONDUIT BEC AKG NIC
19
(ISI MARKED) JPC
LIGHTING
PROTECTI DEHN OBO ABB
20
ON SYSTEM AS PER
IEC-62305
21 DLP TRUNKING MK HONEYWELL OBO LEGRAND
BETTERMAN
FLOOR
TRUNKING / MK HONEYWELL OBO LEGRAND
22
RACEWAY BETTERMAN
CABLE TRAY SLOTCO MEM BEC
23 (LADDER TYPE /
MK OBO
PERFORATED/
(HONEYWELL)
WIRE MESH
CABLE TRAY SLOTCO MEM BEC
24
SUPPORT SYSTEM MK OBO
(HONEYWELL)
CABLE SLOTCO MEM BEC
MANAGEMENT
SYSTEM
25 (WIR MK OBO LEGRAND
E TRUNKING)
100
RACEWAY [UNDER (HONEYWELL)
FLOOR AND
SURFACE]
STREET LIGHT /
26 SOLAR STREET PHILIPS BAJAJ WIPRO
LIGHT FITTING
WITH POLE
CEILING ORIENT HAVELLS USHA
27
FAN / BAJAJ
EXHAUSTF
AN
OCTAGONAL STEEL
28 POLE AND HIGH BAJAJ PHILIPS CROMPTON
MAST
PHILIPS HAVELLS BAJAJ
29 INTERNAL LIGHTING
WIPRO CROMPTON SCHNEIDER
LED
PHILIPS HAVELLS BAJAJ
30 OUTDOOR LIGHTING
WIPRO CROMPTON SCHNEIDER
PHILIPS HAVELLS SCHNEIDER
31 SMART LIGHTING
BAJAJ CROMPTON
LANDSCAPE CROMPTON BAJAJ PHILIPS (SIGNIFY)
32
LIGHTING HAVELLS
FIXTURES
PHILIPS HAVELLS BAJAJ
33 SMART POLE
SCHNEIDER CROMPTON
UPS REILLO PCI NUMERIC DELTA
34
(PARALLEL EATON FUJI
REDUNDANT
)
VALVE PANASONIC HBL AMAR RAJA
35 REGULATED
ROCKET EXIDE
LEAD ACID
(VRLA) BATTERY
MPCB, L&T SIEMENS LEGRAND
36
CONTACTOR SCHNEIDER ABB
ISOLATORS
CONNECTORS
37 (COLOURS AS PER WAGO PHOENIX CONNECTWEL
PHASE & NEUTRAL)
CONTACT
DISTRIBUTION ABB LEGRAND L&T
38 BOARDS WITH MCB /
SCHNEIDER SIEMENS
RCBO / RCCB
101
/ RCBO / ELCB
39 INDUSTRIAL SOCKET SIEMENS SCHNEIDER MK
102
8 MAINTENANCE FREE ECOSAFE
EARTHING
ATS (AUTOMATIC ASCO CATERPILLAR GE
9
TRANSFORMER SWITCH) VITZROTECH
ABB SCHNEIDER SIEMENS
10 PROTECTION RELAYS
L&T
CURRENT TRANSFORMER
(CAST RESIN EPOXY GILBERT &
11 AE MAXWELL KAPPA
COATED) / POTENTIAL
TRANSFORMER
MULTIFUNCTION AND
DIGITAL ELECTRONIC SCHNEIDER
12 (CONSERV) L&T SIEMENS
METER WITH LCD
DISPLAY
ABB SCHNEIDER SIEMENS
13 HRC FUSE AND FUSE FITTING
L&T
DOWELL’S
COMET (BILLER INDIA) JAINSON
14 CABLE LUGS
3D RAYCHEM
SUDHIR
KOTSON POWER LTD ESSENNAR
15 DRY TYPE TRANSFORMER
DTPL TELWAANE
ABB SIEMENS SUDHIR
16 COMPACT SUBSTATION (CSS) POWER
C&S AMBIT
ABB ALSTOM KAPPA
17 CT & PT (33KV & 11KV)
CGL
KAPPA PRAGATI
18 CT & PT (415V)
L&T ADVANCE
SCHNEIDER L&T DEHN
19 SPD (SURGE ARRESTER)
ABB PHONEIX
L&T SIEMENS ABB
20 INDICATING LAMPS
SCHNEIDER
103
1 DIESEL ENGINE PERKINS VOLVO PENTA
CROMPT
LEROYSOMERS ON STAMFORD
2 ALTERNATOR
GREAVES
KEC
3 BATTERIES PANASONIC EXIDE AMARON
MAX POWER STATCON AMAR RAJA
4 BATTERIES
AE HBL
CHARGER
5 PLC SCHNEIDER ALLEN BRADLE SIEMENS
PIONEER
NIS/NGR RESITECH ESSEN ELECTRICA
6 NEUTR LS
AL GROUNDING LACHHMA
N CUTLER NATIONAL
RESISTANCE
ELECTRONI HAMMER
CS
7 AMF AS PER OEM STANDARDS
104
8 CO-AXIAL FEEDER CABLE TELECO
M
CELLCOMM
9 TRUNK MOBILE RADIO MOTOROLA SAMSUNG
CAME NICE BENINCA
10 BOOM BARRIER
GODREJ
L&T HAVELLS POLYCAB
11 CO-AXIAL TV CABLE
FINOLEX SKYTONE
12 PASSIVE NETWORKING IT SIEMON RITTAL NIKON
RACKS
13 FIRE CABLE NETAPP NETGEAR EMD
HP DELL IBM
14 NETWORK ATTACHED
STORAGE
PELCO BOSCH NETAPP
15 DESKTOP PC HP DELL LENOVO
16 PROFESSIONAL DISPLAY HP DELL LENOVO
PANEL
NEC AVAYA ALACATEL
17 EPABX
SIEMENS PANASONIC
18 HOT LINE PHONES AVAYA NEC MATRIX
19. VMS PELCO BOSCH MILESTONE
QOGNIFY MIRASYS AVIGILON
20. VIDEO WALL with Controller BARCO PLANAR SAMSUNG
Christy NEC Delta
105
PROGRAMMABLE & JOHNSO
HONEYWELL SIEMENS N
2 APPLICATION CONTR
SPECI OLS
FIC CONTROLLER(DDC) SCHNEIDER
ELECTRIC
JOHNSO
HONEYWELL SIEMENS N
3 WEB BASED BMS CONTR
ENTERPRISE OLS
SOFTWARE WITH SCHNEIDER
UNLIMITED USER ELECTRIC
LICENSE
JOHNSON
HONEYWELL SIEMENS CONTROLS
4 WEB SERVER ENGINES /
NETWORK SCHNEIDER
AREACONTROLLERS ELECTRIC
JOHNSO
HONEYWELL SIEMENS N
5 POWER & CONTR
ENERGY OLS
MANAGEMENTSOFTW SCHNEIDER
ARE. ELECTRIC
JOHNSO
HONEYWELL SIEMENS N
6 DUCT TEMPERATURE CONTR
SENSOR OLS
SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
JOHNSO
HONEYWELL SIEMENS N
IMMERSION TYPE CONTR
7 OLS
TEMPERATURE
SENSOR SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
BELIMO ALERTON
JOHNSON
HONEYWELL SIEMENS CONTROLS
8 ROOM TEMPERATURE SCHNEIDER GREYSTONE OMICRON
SENSOR ELECTRIC ENERGY
BELIMO ALERTON
106
No. AL
JOHNSO
HONEYWELL SIEMENS N
CONTR
9 DUCT HUMIDITY SENSOR OLS
SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
DWYER
JOHNSO
HONEYWELL SIEMENS N
CONTR
10 ROOM HUMIDITY SENSOR OLS
SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
DWYER
SCHENITECH HONEYWELL KAMPSTR
11 FLOW METER UP
OMICRON
JOHNSO
HONEYWELL SIEMENS N
CONTR
12 DUCT STATIC PRESSURE OLS
SENSOR SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
BELIMO DANFOSS
VEKESELER FILPRO SIEMENS
JOHNSON
13 WATER LEVEL SWITCH OMICRON HONEYWELL CONTROLS
SONTAY
JOHNSON
HONEYWELL SIEMENS CONTROLS
14 DP SWITCH – WATER
SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
JOHNSO
HONEYWELL SIEMENS N
CONTR
15 DP SWITCH – AIR OLS
SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
BELIMO SONTAY
JOHNSO
HONEYWELL SIEMENS N
CO2 SENSOR / CONTR
16 INDOOR AIR QUAILITY(IAQ) OLS
SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
107
BELIMO
JOHNSO
HONEYWELL SIEMENS N
CONTR
17 WATER FLOW SWITCH OLS
SCHNEIDER GREYSTONE OMICRON
ELECTRIC ENERGY
LANDIS & GYR SCHENITECH BELIMO
JOHNSON
HONEYWELL SIEMENS CONTROLS
18 PRESSURE TRANSMITTER – SCHNEIDER GREYSTONE OMICRON
WATER ELECTRIC ENERGY
DANFOSS
VERIS SETO MAMAC
19 CURRENT RELAY
OMRON ABB OMICRON
VOLTAGE / CURRENT / SCHNEIDER ABB L&T
20 ELECTRIC
POWER FACTOR
TRANSDUCER HONEYWELL JOHNSON OMICRON
CONTROLS
FLAME PROOF LEVEL VEKSLER FILPRO SONTAY
21
SWITCH / LEVEL KELE OMICRON HONEYWE
TRANSMITTER LL
PH / CHLORINE ANALYZER HONEYWELL HACH GREISINGE
22 R
TDS / CONDUCTIVITY
METER SONTAY OMICRON
108
AVAYA/PA
28 LAN CABLES FOR BMS BELDEN DIGI-LINK ND
NETWORK UIT
BEC AKG PRECISION
29
MS / GI / PVC CONDUITS NIC STEELKRAFT
30 NETWORK SWITCHES HP CISCO
31 CENTRAL CONTROL HP DELL
STATION
JOHNSON SIEMENS HONEYWE
32 THERMOSTAT CONTROLS LL
SAUTER GREYSTONE ALC
JOHNSON SIEMENS HONEYWE
33 DAMPER ACTUATOR CONTROLS LL
DWYER GE
JOHNSON SIEMENS HONEYWE
34 CO SENSOR CONTROLS LL
GREYSTONE
OMRON ENERCON L&T
35 CURRENT RELAY
SITU MAMAC
JOHNSON SIEMENS HONEYWE
36 NETWORK TEMP, RH & PIR CONTROLS LL
SENSOR
BELIMO GREYSTONE
LANDIS & GYR KELE SONTAY
37 WATER FLOW METERS
HONEYWELL JOHNSON BELIMO
KAMSTRUP LANDIS & GYR HONEYWE
38 ULTRASONIC BTU METERS LL
BELIMO ENDREES+HAUSER DANFOSS
ABB TRITON HONEYWE
39 HARDNESS ANALYSER LL
POLYMETRON
HONEYWELL ABB BELIMO
40 ULTRASONIC /
ELECTROMAGNETIC WATER GREYSTONE
FLOW METERS
JOHNSON SIEMENS HONEYWE
41 3-WAY MOTORIZED VALVES CONTROLS LL
BELIMO
SCHNEIDER HONEYWELL INVENSYS
OUTSIDE AIR
SIEMENS JOHNSON GREYSTON
109
42 TEMPERATURE / RH SENSOR CONTROLS E
BELIMO
43 SAFETY THERMOSTAT FOR ANERGY RAPID CONTROL HONEYWE
HEATER LL
110
Rallison Polycab Bonton
2 Fire Survival Cable
Batra Henlay No Burn
APC Emerson Schneider
3 UPS System
Mitsubishi Siemens
Public Address & Honeywell Bosch Bose
4
Back Ground Heinrich Vonamic BiAmp
Music System
Dorma HID Geze
Access Control Bosch Link Siemens
5
UTC Honeywell
6 Emergency Break Glass Unit Honeywell GE Bosch
111
2
Optical Turnstiles Boon Edam Gunnebo kaba
Central
3 Vac Sistemair Sachvac Schonbach
uum System
4 Multi-Purpose Poles Keselec Heper Wipro
Everlast
Composites Private
Limited
13 Tactile warning Eminent overseas Jindal (JSW) JB Enterprise
studs/ strips
Prarthana Canon Kich,
Technical Services (Sundaram
Pvt. Ltd, Group),
14 Ornate Pots
Smart Exteriors Yuccabe Raunaq Sales
(Removable Planters)
112
17 Kids Play Equipment Koochie Kompam
113
17 Cables for Conferencing Bosch Televic Brahler
. System
Conference systems
18 Control software for Bosch Televic Brahler
Meetings, Database
. Management,
Identification / Access
Software
Automated camera Bosch Televic Brahler
19. tracking system and
video display software. RANE or ANY OTHER APPROVED BY Conference System
OEM
Customized GUI Bosch Televic Brahler
20.
Interface for Multimedia RANE or ANY OTHER APPROVED BY Conference System
Screen OEM
Conference Audio Bosch Televic Brahler
21.
Recording software RANE or ANY OTHER APPROVED BY Conference System
OEM
Conference Microphone Bosch Televic Brahler
22. management and Synoptic
control software RANE or ANY OTHER APPROVED BY Conference System
OEM
23. PC for different software Dell, HP, Lenovo
24. Audio Distribution Box ANY REPUTED MAKE APPROVED BY CONFERENCE
SYSTEM OEM
114
35. In wall Speakers JBL TANNOY BOSE
36. Audio Amplifiers CROWN LABGRUPPEN BOSE
37. Audio Digital Signal BSS Bose Biamp
Processor
38. Ceiling Microphone Tiles Shure Sennheiser Clearone
Samsung Barco Christie
39. Video Walls
Planner Delta
40. Fied Video Display Artherholm Element One Soltec
Samsung NEC Christie
41. Professional Display
Panasonic Sony Planner
42. Encoder Type 1 Crestron AMX Lightware
43. Encoder Type 2 Crestron AMX Lightware
44. Decoder Type 1 Crestron AMX Lightware
45. Decoder Type 2 Crestron AMX Lightware
46. Video Conferencing Unit Cisco Polycom
47. Wireless Presentation Crestron AMX Barco
System
48. Table Cable Manager Type1 Crestron AMX Barco
49. Table Cable Manager Type2 AVC Logic Equivalent Indian
OEM
50. Table Cable Manager Type3 AVC Logic Equivalent Indian
OEM
51. PTZ Camera Type1 Panasonic Sony Canon
52. PTZ Camera Type2 Panasonic Sony Canon
53. Camera Controller Panasonic Sony Canon
54. Camera & Controller Power Panasonic Sony Canon
Unit
55. Video Wall Mount for Video Vogal, B Tech, Chief Vogal, B
wall
56. Display Wall Mount Type1 Vogal, B Tech, Chief Vogal, B
57. Display Wall Mount Type 2 AVC Logic Equivalent Indian
OEM
58. Display Wall Mount Type3 AVC Logic Equivalent Indian
OEM
59. Interactive touch screen Wacom, PEN Wacom, Elotouch, XP
Elotouch, XP
60. Room Controller Crestron AMX Extron
61. Network Switch Cisco JUNIPER Extreme
Centralized Management
62. and control software to
Crestron AMX Extron
control all networked AV
devices, on- premises
installation
63. Touch Screen for control Crestron AMX Extron
115
GUI
Corning Commscope Penduit
64. CAT6A cable Belden
Corning Commscope Penduit
65. Optical Fibre Cable Belden
Corning Commscope Penduit
66. Audio Cable Belden
Kramer Crestron Extron
67. Speaker Cable
Belden Krystal
Kramer Crestron Extron
68. HDMI cable Belden Krystal
All required Corning Commscope Penduit
69.
accessories for Belden
Optical fiber
connectivity
70. All required connectors Commscope Nutrik Penduit
71. Equipment Rack Middleatlantic Netrack Tripp Lite
72. Conduits As per Electrical Installation make list
73. Cable compartment As per Electrical Installation make list
74. Raceway As per Electrical Installation make list
22. LAN, IP BASED EPABX
Sr. ITEM APPROVED MAKES / BRANDS
No.
UTP CAT6A Cable and its components BELDEN COMMSCOPE SIEMON
1. such as IO, Patch Panels, Face Plates PANDUIT-
and all their accessories PANNET
Single Mode Fiber & Multi Mode optic
cables of various core capacities and PANDUIT-
COMMSCOP SIEMON PANNET
2. their accessories –wall mounted or rack
mounted LIUs, patch cords and pigtails E
and other accessories
3. Networking enclosures, racks ofvarious APW-VERO RITTAL PANDUIT-
sizes –15U up to 42U PRESIDENT PANNET
Networking Switches - Access
Switches, Distribution Switches, Core
Switches, Server Farm Switches and
4. CISCO EXTREME HPE (ARUBA)
their components such as 1G SFP, 10G
NETWORKS
SFP+ and 40G QSFP+
transceivers and modules and other
accessories such as power supplies,
fans, stacking cables.
116
5. Wireless Controllers, Wireless Access CISCO EXTREME HPE (ARUBA)
Points and their accessories NETWORKS
6. Internet Router and its accessories CISCO EXTREME HPE (ARUBA)
NETWORKS
7. Network Management System CISCO EXTREME HPE (ARUBA)
NETWORK
S
8. Firewall & its accessories CHECKPOINT CISCO PALOALTO
9. AAA - Authentication Solution and its CISCO HP ARUBA FORSCOUT
accessories
10. Network Traffic Analytics Solution CISCO DARKTRA IBM
and its accessories CE
11. Secure Internet Gateway Solution and AKAMAI CISCO INFOBLOX
its accessories
IP based PBX Communication
12. Solution, IP Phones, Softphones, Voice AVAYA CISCO MITEL
Gateway, Communications Software
and Mobility Client, Desktop Client
Software
DELL HP LENOVO
Industry Standard Intel Platform
13. OR AS PER IP-PBX COMMUNICATION SYSTEM
Server Hardware
PLATFORM OEM
14. 0.5 mm dia FRLS PVC insulated DELTON
annealed copper conductor cable - 4
pairs
117
SPECIAL CONDITIONS
1.0 GENERAL OBLIGATIONS OF THE CONTRACTOR
a) The Contractor shall, subject to the provisions of the Contract and with due care and
diligence, execute and maintain the Works and provide all labour, including the
supervision thereof, materials, constructional plant and all other things, whether of a
temporary or permanent nature, required in and for such execution and maintenance,
so far as the necessity for providing the same is specified in or is reasonably to be
inferred from the Contract.
b) The Contractor shall take full responsibility for the adequacy, stability and safety of
all site operations and methods of construction, provided that the Contractor shall
not be responsible, except as may be expressly provided in the Contract, for the design
or specification of the permanent works, or for the design or specification of any
temporary works prepared by the Authority.
c) The Contractor shall carry out all the works strictly in accordance with the drawings,
details and instructions of the Engineer-in-Charge. In the opinion of the Engineer-in-
Charge if any changes are to be made, the same shall be intimated in writing to the
Contractor and the Contractor shall carry out the same. The Engineer-in-Charge's
decision in this regard shall be final and not open to arbitration.
d) The permission of felling of trees which cause a material adverse effect on the
construction of the project are identified, the Contractor shall facilitate the Authority in
seeking such permission including but not limited to conducting tree survey, numbering,
transplantation and compensatory tree plantation plans, chasing the application with
forest Department etc. No claims towards damages shall be admissible on this account.
e) Since Delhi area is a pollution sensitive region, there are few periods in a year during
which restrictions are imposed on construction activity by the concerned statutory
authorities. No claims towards damages on this account shall be admissible.
This Contract shall, in all respects, be construed and operated as an Indian Contract
and shall be subject to Indian laws in force from time to time. The Contractor should
conform to all laws of the land and the regulations and bye-laws of any local authority
and of any water or lighting companies with whose systems the structure isproposed
to be connected. The Contractor shall give all notices required by the said acts,
regulations or bye-laws and pay all fees in connection therewith. The Contractor
118
shall protect and indemnify the Authority against all claims or liabilities arising from
his actions in violation of such laws, ordinances, regulations and bye- laws by him.
The Engineer will repay or allow to the Contractor all such sums as the Engineer-
in-Charge shall certify to have been properly payable by the Authority and paid by
the Contractor in respect of such fees.
The contract price shall be adjusted to take account of any increase or decrease in cost
resulting from a change in the applicable laws in India (including the introduction of
newlaws and the repeal or modification of existing laws) or in the judicial or official
governmental interpretation of such laws, made after the last date of submission of
tender, which affect the contract price and the performance of obligations under the
contract.
1.4 Opportunities for other Contractors
The Contractor shall, in accordance with the requirements of the Engineer, afford
all reasonable opportunities for carrying out their work to any other Contractors
employed by the Authority and their workmen and to the workmen of the Authority
and of any other duly constituted authorities, who may be employed in the execution
on or near the site of any work not included in the Contract or of any Contract which
the Authority may enter into in connection with or ancillary to the Works.
1.5 Interference with Traffic and adjoining properties
All operations necessary for the execution of the Works shall, so far as compliance
with the requirements of the Contract permits, be carried on so as not to interfere
unnecessarily or improperly with the convenience of the public, or the accessto use
and occupation of public or private roads and footpaths to or of properties whether in
the possession of the Authority or of any other person. The Contractor shall save
harmless and indemnify the Authority in respect of all claims, proceedings, damages,
costs, charges and expenses whatsoever arising out of, or in relation to, any such matters
in so far as the Contractor is responsible therefore.
1.6 Watching and Lighting
The Contractor shall in connection with the Works, provide and maintain at his own
cost all lights, guards, fencing and watching when and where necessary or as required
119
by the Engineer or by any duly constituted authority, for the protection of the Works,
or for the safety and convenience of the public or others.
1.7 Way leaves etc.
The Contractor shall bear all costs and charges for special or temporary way leaves
required by him in connection with access to the Site. The Contractor shall also provide
at his own cost any additional accommodation outside the Site required by him for the
purposes of the Works.
120
1.8 Site Office for the Authority
The Contractor shall provide Site Accommodation (total area approx. 95 m2) for the Engineer Staff
according to the following schedule of offices:
(a) Offices shall be accessible only from a corridor within the building. The corridor and
reception area entrances shall be provided with an external double door.
(b) Materials for the construction shall be robust and durable. The building shall be
weatherproof, vermin proof, well insulated thermally and acoustically. Internal walls shall
be soundproofed. Electrical power and lighting, including all fixtures and fittings, power,
telecoms and internet sockets with LAN/wifi internet availability, shall be provided to each
room, including air conditioning to maintain the internal temperature within the range of
20 to 24 degrees Celsius at all times. A standby generator shall also be provided and
installed with an automatic switchover if load shedding or power outages are a regular
phenomenon at the Site Accommodation.
(c) Internal doors shall be flush, fitted with door closers, mortise locks with keys and lever
handles.
121
(d) External doors shall be a pair of solid core doors, external quality, hung on heavy duty
hinges, one leaf fitted with barrel bolts top and bottom and the other leaf fitted with a mortice
or similar lock.
(e) Windows, of area not less than 10% of the floor area, shall be provided to all rooms,
securely barred, fitted with blinds and having opening sections fitted with locks and
mosquito screens.
(f) The building shall be provided with a continuous water supply and drainage to Kitchen,
Washroom and Toilets. The Toilets shall be equipped with low level suites and be
adequately ventilated through the ceiling.
(g) The Kitchen shall be fitted out with a 2 drainer stainless steel double sink unit, hot water
heater, worktop with cupboards under, tiling above the sink and worktop and wall mounted
cupboards.
(h) Fire and Safety regulations shall be complied with and fire- fighting equipment shall be
provided in accordance with the recommendations of the Delhi Fire Services.
(i) The Contractor shall provide, erect and maintain appropriate name boards as specified, for
each of the offices. The wording shall be agreed with the Engineer.
(j) The Contractor shall provide protective clothing and safety equipment for 12 persons,
comprising, as a minimum – Safety Helmets, Safety Harness, Steel-toed construction
shoes/boots (sizes to be notified), Day-Glo waistcoat, Industrial safety goggles, Industrial
gloves, Breathing Masks and Filters, Ear protectors, Heavy weight suits (sizes to be
notified), Lamps (with batteries), etc as required by the Engineer.
(k) The Contractor shall provide an adjacent shaded hard standing parking area for 5 cars.
(l) The Contractor shall arrange for upkeep, service and security of the offices and compound.
These to be thoroughly cleaned and rubbish and waste to be removed at least once per
day.
(m) The Contractor shall submit a detailed office layout plan showing all relevant details of
these site offices, not limited to that described above, which will require a notice from the
Engineer.
(n) The Contractor shall provide and maintain furniture, communication equipment including but
not limited to four (4) sets of computers (desktop or laptop as per the specific instruction of
Engineer) with operating system Windows-10 or any updated version, software MS Office,
and any other software required for viewing the drawings, designs and/or other BIM outputs,
1 one A4 & A3 colour printer with scanner for Project Manager, one high speed A4 printer
and A0 size plotter (Both of which can be common for Contractor as well as Engineer’s
offices) along with their repair, maintenance and consumables. All the office equipment will
be property of the contractor after satisfactory completion of the work.
(o) The contractor shall complete the site office setup in all respects within one month of issue
of LOA failing which damages @ Rs 50000 per week shall be imposed till the completion
of the setup as above.
122
2.0 INSURANCES TO BE TAKEN BY THE CONTRACTOR & AUTHORITY
TO BEINDEMNIFIED
b) All plants and equipments and other things brought to the site by the Contractor
shall be insured for a sufficient amount not less than Rs.5 lacs or 1% of the
Tendered Value, whichever is more.
c) Authority's building rented to the Contractor if the building or part thereof is
used by the Contractor for the purpose of storing or using materials of
combustible nature, on which the decision of the Engineer-in-Charge shall be
final and binding.
2.1.2 The insurance shall be against all losses or damages from whatever causes, other
than excepted risks, for which the Contractor is responsible under the Contract. The
insurance cover shall be for the period of Contract and also for the period of
maintenance, for loss or damage arising from a cause prior to commencement of the
period of maintenance, and for any loss or damage, occasioned by the Contractor in
the course of any operations carried out for the purpose of complying with his
obligations during Maintenance Period.
2.1.3 Such insurance shall be effected with an insurer and with terms approved by the
Authority. The Contractor shall, whenever required, produce the policy or policies
and the receipts for payment of the current premiums.
2.2 Third Party Insurance
2.2.1 Before commencing the execution of the Works from the date specified in Clause
17A of GCC, the Contractor shall insure against the liability for any material or
physical damage, loss injury or death which may occur to any property or life
including that of the Authority or to any person, including any employee of the
Authority, by or arising out of the execution of the Works or in the carrying out of
the Contract. The sum insured will be for Rs.250000.00 limited to 10 Occurrences
per year. After each occurrence, Contractor shall pay additional premium necessary
to make insurance valid for ten occurrences always. The Insurance Policy should
cover this amount at all times till issue of Completion Certificate by the Engineer-
in-Charge.
123
2.2.2 Such insurance shall be effected with an insurer and its terms approved by the
Authority. The Contractor shall, whenever required, produce before Engineer the
policy or policies of insurance and the receipts of payment of the current premiums.
The Authority shall not be liable for any payment in respect of any damages or
compensation payable according to law in respect or in consequence of any accident
or injury or loss of life to any workman or other person in the employment of the
Contractor or any sub-Contractor, except an accident or injury resulting from any
actor default of the Authority, his agents or servants. The Contractor shall insure
against such liability with an insurer approved by the Authority for a sum as per
established norms during the entire period.
Without prejudice to the other rights of the Authority against the Contractor in
respect of such default, the Authority shall be entitled to deduct from any sums
payable to the Contractor the amount of any damages, compensation costs, charges
and other expenses paid by the Authority and which are payable by the Contractor
under this clause.
In all cases where the Contractor has taken any insurances, he shall not be entitled
to reimbursement by the Authority of any shortfall or deficiency in the amount
payable by the Contractor towards settlement of claims and that paid by the insurer
in settlement of same claim.
Without prejudice to his liability under this clause the Contractor shall also
cause all Sub-Contractors to effect, for their respective portions of the works,
similar policies of insurance in accordance with the provisions of this clause and
shall produce or cause to produce to the Authority such policies. The
Contractor shall not permit a Sub- Contractor to commence work at the site
unless the said insurance Policies are submitted. In the event of failure of the Sub-
Contractor to take out such a policy of Insurance before commencing the works at
the site, the Contractor shall be responsible for any claim or damage attributable to
the said Sub- Contractor.
124
2.7 Period of Policies
All the insurance covers mentioned above shall be kept alive during the period
of the Contract from the date specified for start of the work until the Contractor
obtains successfully completes the Maintenance Period/Defect Liability Period.
b) The right of the Authority to execute the works or any part thereof on, over, under,
in or through any land.
c) Injuries or damage to persons or property caused by Excepted risks or resulting from
any act or neglect of the Authority, his agents, servants or other Contractors, not being
employed by the Contractor or for or in respect of any claims, proceedings,
damages, costs, charges and expenses in respect thereof or in relation thereto.
Where the injury or damage was contributed to by the Contractor, his
servants or agents, such part of the compensation as may be just and equitable having
regard to the extent of the responsibility of the Authority, his servant or agent or other
Contractors, for the damage or injury.
125
3.0 SAFETY AND SECURITY
3.2.3 Details of all critical industrial injuries shall be reported promptly to the Engineer.
3.2.4 Report shall cover type, nature, cause, physician's report and action for prevention
of those types again.
3.3.1 Smoking within plant, restricted areas, closed areas, near storage place of lubricant
oil and fuel etc. is strictly prohibited.
3.3.2 The Contractor shall erect and maintain barricades required in connection with his
operation to guard or protect
126
(a) Excavation
(b) Hoisting/lifting
(c) Slab openings
(iii) All power distribution shall be carried out with coated, adequately insulated
and of appropriate current/load rating cables. It shall be securely routed for this
purpose. No loose, naked, hanging wires shall be permitted.
(iv) Over load protection devices shall be installed whenever and wherever heavy
current/load consuming construction plant or machinery susceptible to hazard
is in use and as directed by the Engineer-in-charge.
127
(v) Metallic plugs and sockets shall be used in field work. Switch board shall
bein close proximity so as to have quick control over the supply.
(vi) Proper and adequate earthing connection should be provided for all
installations, plant and machinery and distribution system.
(vii) Hand lamps and inspection lamps shall be adequately insulated and guarded
with wire mesh and should have proper plugs for use.
(viii) Security and illuminatory light shall be secured firmly and protected to
withstand all weather conditions.
All scaffolds, ladders and other safety devices mentioned or described herein shall
be maintained in a safe condition and no scaffold, ladder or equipment shall be
altered or removed while it is in use. Adequate washing and maintenance
facilities shall be provided at or near places at work.
c) Those engaged in handling any materials which are injurious to eyes shall be
provided with protective goggles.
128
3.8 Storing Fuel, Oil and Lubricant
The Contractor shall take approval from the Safety Officer of the Authority for
storing the lubricants, oil and fuel at site for running the machinery required
for the construction.
The Contractor shall, within twenty four (24) hours of the occurrence of any accident
on, or about the Site, or in connection with the execution of the Works, report such
accident to the Engineer and to the appropriate authority wherever such report is
required by law. The Contractor will indemnify the Authority from all accident
cases.
129
3.15 Security Measures
The Contractor shall be responsible at his cost for security of Works for the
duration of the Contract and shall provide and maintain continuously adequate
security personnel to fulfill these obligations. The requirements of security measures
shall include, but not limited to, maintenance of Law and order at site,
provision of all lighting, guard, flagmen, and other measures necessary for
protection of Works within the camps and elsewhere at site, for all materials
delivered to the site and all persons employed in connection with the Works
continuously throughout working and non-working periods including nights,
Sundays, holidays, for the duration of the Contract. At work sites in close
proximity of traffic corridors where public are likely to come close to the work
area, suitable fencing as directed by the Engineer should be provided.
i) Q.A. Plan for Basic Construction Materials indicating the details of tests to be
undergone before use in works.
ii) Q.A. Plan for site activities indicating the details of tests to be conducted at the
various stages of construction for various activities.
iii) In house/on site testing facilities to be developed for materials, site activities and
calibration of equipments.
iv) Site documents to be maintained including records of results of tests for materials
and workmanship, inventory record on availability of vital materials and their
consumption vis-à-vis design requirements, site inspection records, quality audit
record, safety audit record, site progress record, etc.
v) Check lists for source approval of materials etc., check lists for site activities and
proforma for recording results of tests.
130
4.2 Guidance in preparation
For guidance in the preparation of the Manual, the following printed Publications
may be referred to :
i) Quality Assurance Manual for Construction of Concrete Structures (Bridgs
& Flyovers) by C.P.W.D.
ii) Compilation of Quality Assurance Circulars of C.P.W.D.
(b) All trees and shrubbery, which are not specifically required to be cleared or
removed for construction purposes, shall be preserved and shall be protected from
any damage that may be caused by Contractor's construction operations and
equipment or by their Employees/Workers. The removal of trees or shrubs will be
permitted only after prior approval of the Engineer. Special care shall be exercised
where trees or shrubs are exposed to injuries by construction equipment,
blasting, excavating, dumping, chemical damage or other operation and the
Contractor shall adequately protect such trees by use of protective barriers or other
methods approved by the Engineer. Trees shall not be used for anchorage. The
Contractor shall be responsible for injuries to trees and shrubs caused by his
operations and Employees/Workers. The terms "injury" shall include, without
limitation, bruising, scarring, tearing and breaking of roots, trunks or branches. All
injured trees and shrubs shall be restored as nearly practicable, without delay, to
their original condition at Contractor's expense.
131
(c) Where trees have to be necessarily cut for progressing temporary or permanent
works, the Contractor shall arrange for compensatory afforestation as may be
required by Environmental Rules and Regulations.
(e) Excessive emission of dust into the atmosphere will not be permitted during
manufacture, handling and storage of concrete aggregates/fly ash/
earth/building materials and the Contractor shall use such methods and
equipment as are necessary for collection and disposal or prevention of dust
during these operations. The Contractor's method of storing and handling
cement shall also include means of eliminating atmospheric discharge of dust.
Equipment and vehicles that give objectionable emission of exhaust gases shall
not be operated. Burning of materials resulting from cleaning of trees branches,
combustible construction materials and rubbish may be permitted only when
atmospheric conditions for burning are considered favourable.
(f) Special care must be exercised in ensuring that the labour housed in labour
camp within the work site area do not indulge in any activity like drinking
alcohol, taking drugs etc and other activities that may affect the ecological
balance such as cutting of shrubs for fuel, creating open air nuisance etc.
6.1 Mobilisation
Period of Mobilisation shall be 15 days counting from the stipulated date of start of
work as mentioned in Letter of Acceptance by the Engineer-in-Charge. The
Contractor shall carry out following activities within this period stated. He shall
submit to the Engineer within 4 days of stipulated date of start, the proposed layout
of locating offices, stores, godowns, yards, water, electric network etc. for approval
of the Engineer.
ii. Line out including establishing of grid line levels and its approval
from the Engineer.
132
iii. Submitting list of proposed specialized sub-Contractors as may be
requiredfor approval of the Engineer.
viii. Obtaining approval of local authorities and complying with any statutory
requirements prior to actual start of work.
If, at any time during the execution of the Works, the Engineer shall require the
Contractor to make boreholes or to carry out exploratory excavation, such
requirement shall be ordered in writing and shall be deemed to be an Extra item for
which payment shall be made by the Engineer in terms of Clause 12 of Contract.
133
6.4.1 The Contractor is entirely responsible for the design, construction, maintenance and
removal of all temporary works employed in carrying out the Contract. Within a
reasonable time (and in any case not less than fifteen days) before he intends to
commence construction of any temporary works, the Contractor shall submit full
particulars including drawings of the same, for the approval of the Engineer.
The Engineer's approval will in no way relieve the Contractor of his responsibility
for the safety of the Works, operators, adjoining property, structures or services
and compliance with appropriate regulations and codes of practice. Documents for
Temporary works supporting adjoining buildings, property and public utilities and
roads shall also be submitted to the appropriate authority for their approval if
requested/required.
6.4.2 The temporary works shall be designed and constructed in such a manner as to
enable the permanent structures to be built around them without detriment
to their effectiveness and due allowance will be deemed to have been made for all
necessary adjustments thereto to enable the Works to proceed.
6.4.3 Timber shoring, boards, struts or similar items shall not be left in position upon
completion of the Works without the written consent of the Engineer.
6.4.4 All services or utilities on or adjoining the site which are required to be maintained
operational shall be protected from movement, subsidence or damage from any
cause whatsoever by adequate temporary props, struts, shores and protective screens
to the approval of the Engineer and the agent of the service or utility.
6.4.5 The Contractor shall make safe and reinstate all areas affected by temporary works.
6.4.6 The Contractor shall use properly designed and manufactured steel staging platforms
for carrying out work above 3.0m height. All required staging for supporting,
centering, shuttering of beams, slab, masonry work, etc. shall be carried out strictly
as per the Supplier’s instructions or approved arrangement. It is to be noted that
designing of such work shall be carried out by the Contractor and shall be submitted
for approval of the Engineer. No work above 3.0 m shall be permitted without
compliance of this condition.
134
permanent and Site access roads free of spillage and shall not interfere with the flow
of traffic. Also same shall apply to terraces and other developed areas.
6.7 Name Board at Site
The Contractor shall prepare and display name board at site as per design approved by the
Engineer. It shall have
i. Name of Project
ii. Name of Authority
iii. Name of Consulting Architect (if any)
iv. Name of Project Management Consultant (if any)
v. Name of Contractor
6.8 Site Drainage/Cleaning/Nuisance
6.8.1 All water which may accumulate on the Site during the progress of the works or in
trenches and excavation, shall be removed from the site to the satisfaction of the
Engineer at the Contractor's cost.
6.8.2 The Site shall be maintained free from rubbish. Proper stacking of scaffolding
materials, shuttering material, bricks/brick bats, steel pieces, etc. needed for work
on day to day basis shall be organized, Heaps in unplanned manner and disorderly
fashion shall not be permitted. The Engineer's decision in this matter shall be final.
6.8.3 The Contractor shall not, at any time, cause or permit any nuisance on the site or do
anything which shall cause unnecessary disturbance or inconvenience to the
Authority, tenants or occupants of other properties near the site and to the public in
general.
135
6.9 Disposal of Rubbish
(i) The Contractor shall cart away from site and deposit where directed by the Engineer
all refuse, etc. arising from the Works both as it accumulates and at completion of
the Works at the direction of the Engineer.
(ii) It is the responsibility of the Contractor to obtain a certificate from the local
authorities concerned to the effect that all rubbish arising out of Contractor's
activities at the construction site or any other offsite activities borrow pits and/or
disposal area (s) has been properly disposed off.
6.10 Shift Working
The Contractor shall be allowed to work in three shifts with prior approval of the
Engineer.
6.11 Urgent Repairs
If, by reason of any accident or failure, or other event occurring to, in, or in
connection with the Works or any part thereof, either during the execution of the
Works or during the period of Maintenance, any remedial or other Work or repair
shall, in the opinion of the Engineer, be urgently necessary for the safety of the
Works and the Contractor is unable or unwilling at once to do such work or repair,
the Authority may employ and pay other persons to carry out such work or
repairs the Engineer may consider necessary. If the Work or repair so done by the
Authority is work which, in the opinion of the Engineer, the Contractor was liable
to do at his own expense under the Contract, all expenses properly incurred by the
Authority in so doing shall be recoverable from the Contractor by the Authority or
may be deducted by the Authority from any moneys due or which may become due
to the Contractor. Provided always that the Engineer, shall, as soon after the
occurrence of any such emergency as may be reasonably practicable, notify the
Contractor thereof in writing.
The Contractor shall, if required by the Engineer in writing, search under the
directions of the Engineer for the cause of any defect, imperfection or fault
appearing during the progress of the Works or within the Period of Maintenance
(Defect Liability period). If such defect, imperfection or fault shall be one for which
the Contractor is liable, the cost of the work carried out in searching as aforesaid
shall be borne by the Contractor and he shall in such case repair, rectify and make
good such defect, imperfection or fault at his own expense in accordance with the
provisions of Contract.
136
7.0 PROGRAMME AND PERFORMANCE
If at any time it should appear to the Engineer that the actual progress of work
doesnot conform to the approved programme the Contractor shall produce at the
requestof the Engineer, a revised programme showing modifications to the approved
programme, necessary to ensure completion of the work within the time for
completion stipulated in the Contract. The submission to and approval by the
Engineer-in-Charge of such programme or the furnishing of such particulars shall
not relieve the Contractor of any of his duties or responsibilities or obligations under
the Contract. The Engineer-in- Charge shall have full power and authority during
progress of work, to issue such instructions as may be necessary for the
proper and adequate execution and maintenance of the Work. The Contractor
shall carry out and be bound by the same.
137
7.5 Site Order Book
A site order book shall be kept at the site of the work. As far as possible,
all orders regarding the works are to be entered in this book. All entries
therein shall be signed by the Engineer or his representative and the
Contractor or his representative. In important cases, the Engineer-in-charge
will countersign the entries, which have been made. The site order book shall
not be removed from the work site except with written permission of the
Engineer and the Contractor or his representative shall be bound to take
note of all instructions and directions meant for the Contractor as entered
in the site order book without having to be called on separately to note them.
The Contractor shall ensure compliance of the noting in site order book
within three days of the noting. In case of failure to do so, the corresponding
work shall be stopped and work already done shall not be accepted.
7.6 Progress Photographs and Video recording
During the Construction stage the Contractor shall install IP based CCTV
Camera in sufficient numbers to capture the real time video and photo for the
complete in totality the under progress work at each stage and share the
details with the Authority for complete access of the system.
Further, during the Construction Period, the Contractor shall provide to the
Authority for every calendar quarter, a video recording, which will be
compiled into a 3(three) hour digital video disc or any substitute thereof,
covering the status and progress of Works in that quarter. The video
recording shall be provided to the Authority no later than 15 (fifteen) days
after the close of each quarter after the date of commencement of work. The
video recording must contain shooting through drone and/or other available
digital best quality medium, with still high resolution coloured photos being
taken from few vantage locations during drone and/or other available digital
best quality medium flight. These still photos shall be later used to create a
time lapse video of the Project prepared by the professional agency and
submitted to the Authority.
138
8.1.2 The Engineer and any person authorized by him shall at all times have access
to the Works and to all workshops and places where work is being prepared
or from where materials, manufactured articles or machinery are being
obtained for the Works and the Contractor shall afford every facility for and
every assistance in or in obtaining the right to such access.
10.0 Minimum Qualifications & Experience required and Discipline to which should
belong
139
Deputy B.Tech/BE or 10 Years Civil & electrical 2 (one Civil and
Technical Equivalent 1 Electrical)
Representative
B.Tech/BE or 5 Years (7 Years for Civil & electrical 3 ( 2 Civil and
Engineers/ Billing
Diploma Diploma) One Electrical)
Engineer
B.Tech/BE or 5 Years Civil 1(One)
Quality Engineer
Equivalent
B.Tech/BE or 5 Years Civil 1(One)
Planning
Equivalent
Engineer
Diploma with 2 Years Any Engineering 1(One)
Safety Engineer
experience in Stream
safety code
(i) Safety and Defect Liability of works: As mentioned in the Notice Inviting Tender
(Section-1), scope of the subject work is execution of balance works. The already
completed works, which are largely the structural works, conforms to the drawings
and specifications. The balance works are to be constructed on/ ‘in sync” with the
existing incomplete works, in order to complete the building and utilities etc. While
the Contractor will be required to execute the balance work, he/she will have the
responsibility of the structural safety/soundness of the entire building/utilities
during execution and on completion of the works. On completion, the contractor
will be responsible for Defect Liability of the entire works, including those already
executed by the previous contractor.
(ii) Use of available material in works:- Certain material mainly reinforcement steel
which were procured & are in position and paid under the previous contract are to
be incorporated in the balance works. Joint measurement with Authority of such
works shall be carried out before commencing the balance work.
140
(iii) The Contractor shall engage an architect of repute for Landscaping and Signages
work of the Bijwasan Railway Station Project and cost will be borne by the
Contractor
(iv) The Contractor shall arrange for the application and obtain the permission from the
Electricity Authority (BSES/TATA etc.) for the electrical connection of the
Bijwasan Railway Station Project. All the statutory expenses and the work to be
carried out by the department for the electrical connection will be borne by RLDA.
(v) The Contractor shall arrange for the application and obtain the permission from
Delhi Jal Board for the Water Supply and Sewage connection Bijwasan Railway
Station Project. All the statutory expenses and the work to be carried out by the
department for the water supply and the sewage connection will be borne by RLDA.
(vi) The Contractor shall obtain the statutory approval from the Fire Authority for the
work carried out at the Bijwasan Railway Station Project.
(vii) The Contractor shall obtain the permission from the concerned Govt. Authority for
operation and running of installed Lifts and Escalators in the Bijwasan Railway
Station Project.
(viii) It may be noted that the overlaps, spacers, chairs of the reinforcement used in the
reinforced concrete work will not be measured for payment in the respective items
of work under Bill of quantities. The reinforcement steel shall be paid as per the
issued “Good for Construction” Drawing. The Contractor shall quote the rate
accordingly by taking into account the above mentioned instruction.
(ix) All the structural steel work shall be sand or grit blasted for surface preparation
before application of painting system as mentioned in the contract. If there is any
damage to the paint during handling, erection and placement of the members, the
same shall be made good to the satisfaction of Engineer-in-charge.
(x) All the exterior grade paint and finishes shall be having a warranty of not less than
7 (seven) years and interior grade paint and finishes shall be having a warranty of
not less than 5 (five) years.
(xi) Charges for outside laboratory testing of any materials/works as per the requirement
of CPWD specification/IS Codes/ British Standards/American Standards/ any other
relevant code considered suitable by the Engineer-in-charge will be borne by the
Contractor and nothing extra will be payable on this account. Additional tests, if
any, over and above the stipulated frequency of tests requested by the Authority,
the charges for such tests shall be borne by the Authority. In case the test report of
such additional tests is not satisfactory, then the testing charges shall be borne by
the Contractor. Sample for the additional tests shall also be provided by the
contractor and nothing extra will be paid on this account.
141
(xii) In case of any ambiguity regarding description of item, rate etc. for scheduled items,
the detail description of such items as mentioned in DSR 2021 and/or as amended
by CPWD will prevail.
(xiii) The contractor will comply with all applicable statutory regulations and guidelines
of Central Pollution Control Board, National Green Tribunal and Delhi Pollution
Control Committee applicable during the contract period and keep the Authority
indemnified.
(xiv) Contractor may appoint specialized agencies for execution of specialized works
i.e. Plumbing, STP, Fire Fighting, LIFT & Escalators, HVAC, etc. with prior
approval of all such agencies from RLDA.
(xv) All the material to be used in the work shall be from the list of approved make
provided in the tender document and contractor shall obtain prior approval from
RLDA of the make and material to be used in the items of work before the
procurement.
142
➢ Avoid materials that contain ozone-depleting chemicals (e.g. CFCs or
HCFCs).
➢ Avoid materials that emit potentially harmful volatile organic chemicals
(VOCs).
➢ Employ construction practices that minimize dust production and
combustible by-products.
➢ Avoid materials that can leach harmful chemicals into ground water; do
not allow potentially harmful chemicals to enter sewers or storm drains.
➢ Protect soil against erosion by wind or storm-water and topsoil depletion.
➢ Minimize noise generation during construction; screen mechanical
equipment to block noise.
➢ Protect natural habitats, restore natural habitats where feasible within scope
of Project.
1) The Site Laboratory shall be approximately 150m2 in area. It shall consist of the
following accommodation:
2) The remainder of the 150m2 shall consist of storage area for concrete cube curing tanks.
The laboratory, office, etc., shall be in one building; the curing tank and storage
building may be in a separate building, but if so it shall be adjacent to the laboratory
building and connected to it by a level, weatherproof passageway. In addition, an
area of covered hard standing of 50m2 for motor vehicles shall be provided adjacent
to the laboratory.
3) The laboratory shall be constructed to the best Engineering practice and the
Engineer shall issue a notice of no objection. Two independent telephone lines with two
extensions each shall be provided for the laboratory. Telephones shall be located in
areas as agreed with the Engineer.
4) A covered water tank with minimum capacity of 2000 litres shall be installed, as a source
of constant water pressure (15 kPa minimum) for each laboratory.
5) In the case of sinks used for washing samples, adequate trapping and/or separating
devices shall be provided to ensure the proper functioning of the facility
143
13.4.1The laboratory equipment, as listed below, shall be issued a notice from the Engineer.
The Contractor shall submit for the Engineer's notice within 2 weeks of the
Commencement Date the name of the supplier he intends to use for each piece of
apparatus together with the relevant catalogue and catalogue number.
13.4.2The layout of the equipment in the testing laboratory shall require a notice of no
objection from the Engineer. The equipment shall be maintained to accuracy appropriate
to the required testing methods with routine calibration by an accredited organisation
as recommended by the appropriate Authority. The Equipment shall also be calibrated
after maintenance or relocation.
13.4.3The Contractor’s site laboratory shall be equipped with the following material testing
equipment as a minimum. The nature and quantity of equipment required for testing
may be varied by the Engineer depending on the detail of the Contractor's Design and
Construction methods or for any other reason which he deems to be valid and
necessary for the proper control of quality, all at the Contractor’s cost:
144
Chisel 25mm x 150mm 2 Nos.
Hammer 2 Nos.
One-gallon field cans 24 Nos.
Sampling spoon 2 Nos.
Soft hair brush 2 Nos.
Moisture cans 250 ml. 48 Nos.
Sieve Analysis
Sieve shaker (portable) 1 unit
Coarse sieves In Sizes from 100mm to 10mm 1 set
Fine Sieves (#4, #8, #16, #30, #40, #50, #100, #200 each) 1 set
As
Pans & Covers
required
Specific Gravity and Absorption of Coarse Aggregate
Wire basket, 200mm dia. 5 No
Heavy duty suspension balance, 20 kg x 1 gm. with accessories for weight in water 1 set
Suitable water container 1 No
Unit Weight of Aggregate
Balance, 100 kg. Capacity with 10 gm precision 1 No.
Tamping rod 16mm diameter x 600mm long 1 No.
Measuring containers (3, 10, 15, 30 litres) 1 each
Flakiness and Elongation
Flakiness gauge, elongation index 1 set
Soundness Test
Sodium sulphate 25 kgs
Soaking tank 1 No.
Balance, Capacity 3 kg., Sensitivity 0.1 gm. 1 set
Sieves :Coarse 1 set
Fine 1 set
Concrete
Buckets for concrete sampling 12 Nos.
Slump cone 12 Nos.
Tamping rod 12 Nos
Base plate 12 Nos.
Mixing pan for concrete 2 Nos.
Scoop for general purpose 2 Nos.
Concrete thermometer 1 No.
Concrete cylinder mould, 150mm * 300mm; 100mm * 300mm 10 each
Concrete cube mould, 100mm cube & 150mm cube 10 each
Adjustable spanners for dismantling cube moulds 6 No.
Capping set 2 Nos.
As
Capping compound
required
Concrete curing tank with capacity for 270 cubes, temperature controlled, with
5 Nos.
circulation system drain and lockable cover
Schmidt test hammer 1 No.
Compression testing machine (simple hand operated) 1 No.
As
Mould oil
required
Temperature chart recorder 1 No.
Miscellaneous
Vernier callipers to measure up to 200mm, with elongated jaws 5 Nos.
Steel rule, 300mm long graduated 2 Nos.
Rubber gloves 10 pr.
Cotton working gloves 20 pr.
First aid kit 1 set
145
Wire brush 6 No.
Steel tape, 3m, 5m, 30m 3 each
Ballpein hammer, 1 kg 2 Nos.
Paint scraper. Approx. 100mm wide 8 Nos.
Float, steel Approx. 280mm x 120mm 8 Nos.
Sack barrow 1 No.
Shovel: Square Mouthed 2 Nos.
: Round Mouthed 2 Nos.
24-wheel trolley, heavy duty, approx. 0.7m x 1.0m with long pneumatic tyred type 1 No.
Wheelbarrow, rubber tyred 1 No.
Comprehensive tool kit. To include screwdrivers, pliers, claw hammer, multi-grips,
1 No.
spanners (adjustable)
Type NR Schmidt Hammer and tester with recording device 1 No. Testing Anvil for
1 No.
Schmidt Hammer test (SHT)
Chart recording paper for SHT 10 Pkts
Cover meter for detecting metal objects to depth of 100mm below the surface of non-
3 No.
magnetic objects
Noise meter 1 No.
RCPT testing Machine for Concrete 1No.
Permeability testing Machine for Concrete 1No.
146
ANNEXURE - I (Contd. …)
TENDER FORM (Third Sheet) – (NOT APPLICABLE)
Name of Work: Development of Bijwasan Railway Station at Bijwasan, New Delhi (Balance Work)
BILL OF QUANTITIES
1. Cost estimate based on CPWD DSR 2021 Item rates duly modified with applicable Cost Index and
enhanced GST Rate /Standard Schedule of Rates (SSOR):
S.N Item No. Description Approximate Unit Rates in Figures and Amount
. of Item of Quantity Words to be filled by
(₹)
Work tenderer
(₹)
1 2 3 4 5 6 7
1 2 3 4 5 6 7
The quantities shown in above Bill of Quantities are approximate and are as a guide to give the
tenderer(s) an idea of the quantum of work involved. RLDA reserves the right to increase/ decrease
and/or delete or include any of the quantities given above and no extra rate will be allowed on this
account.
I/We undertake to do the work at __________ % above/below the rate/amount based on CPWD DSR
2021 Item Rates duly modified with applicable Cost Index and enhanced GST Rate/Standard Schedule
of Rates (SSOR) of the Indian Railways or at the rates quoted above for each item.
Dated ______________
Note: Columns 1 to 7 shall be filled by the office of the Authority inviting tender. Columns 6 & 7
shall be filled by the Tenderer(s) only when percentage tenders are not invited.
147
ANNEXURE – II
148
ANNEXURE - III
WORK ORDER UNDER RLDA CONTRACT – (NOT APPLICABLE)
WORK ORDER NO._________, DATED ________ UNDER CONTRACT AGREEMENT
NO. RLDA/RFP/CD-84/SRD-18 of 2022 dated 15.12.2022.
Name of Work: Development of Bijwasan Railway Station at Bijwasan, New Delhi (Balance Work)
Schedule of Drawings ____________________________________________________________
Authority__________________________________ Allocation _________________________
The Contractor(s) ____________________________ is / are hereby ordered to carry out the following
works at ________% above/below the CPWD DSR 2021 duly modified with applicable Cost Index
and increased GST Rate/Standard Schedule of Rates (SSOR) of Indian Railways, updated with
correction slips issued up to date of inviting tender or as otherwise specified in the tender documents
under RLDA Contract Agreement here-in-before referred to:
The works herein mentioned are required to be completed on or before ________ (Date). The quantities
provided herein are approximate and subject to variation under Clause 42 of the Standard General
Conditions of Contract updated with correction slips issued up to date of inviting tender or as otherwise
specified in the tender documents.
__________________
RLDA
Date ___________
I agree to complete the works herein set forth on or before the date specified under the RLDA
Contract Agreement herein before referred to in conformity with the drawings hereto annexed and in
accordance with the General and Special (if any) Conditions of Contract updated with correction slips
issued up to date of inviting tender or as otherwise specified in the tender documents and the CPWD
Specifications Vol-I and Vol.-II 2019 as amended/corrected upto latest correction slips and Standard
Specifications of Indian Railways updated with correction slips issued up to date of inviting tender or
as otherwise specified in the tender documents .
I also agree to maintain such works for the period specified below from the date of completion:
149
(a) Repair and maintenance work including white/color washing: three calendar months from
date of completion.
(b) All new works except earth work: Six/Twelve calendar months from date of completion.
Contractor _______________ (Signature) RLDA: Designation _____________
Address __________________________
(Acting For and on behalf of RLDA)
Date _____________ Date _____________
150
ANNEXURE - IV
RLDA
CONTRACT AGREEMENT OF WORKS
CONTRACT AGREEMENT NO. RLDA/RFP/CD-84/SRD-18 of 2022 DATED 15.12.2022
ARTICLES OF AGREEMENT made this _________ day of _________ 20______ between
RAIL LAND DEVELOPMENT AUTHORITY a Statutory Authority under Ministry of Railways
hereafter called the "RLDA" of the one part and ___________________________herein after called
the "Contractor" of other part.
WHEREAS the Contractor has agreed with RLDA for performance of the works
_____________________ set forth in the Bill(s) of Quantities hereto annexed upon the Standard
General Conditions of Contract, the CPWD Specifications Vol.-I and Vol.-II 2019 updated with
correction slips issued up to date of inviting tender or as otherwise specified in the tender documents
and the applicable CPWD Delhi Schedule of Rate(DSR) 2021 updated with correction slips issued up
to date of inviting tender or as otherwise specified in the tender documents and Specifications of Indian
Railways updated with correction slips issued up to date of inviting tender or as otherwise specified in
the tender documents and the applicable Standard Schedule of Rates (SSOR) of Indian Railways
updated with correction slips issued up to date of inviting tender or as otherwise specified in the tender
documents and the Special Conditions and Special Specifications, if any and in conformity with the
drawings here-into annexed AND WHEREAS the performance of the said works is an act in which
the public are interested.
NOW THIS INDENTURE WITNESSETH that in consideration to the payments to be made
by RLDAs, the Contractors will duly perform the said works in the said Bill(s) of Quantities set forth
and shall execute the same with great promptness, care and accuracy in a workman like manner to the
satisfaction of RLDA and will complete the same in accordance with the said specifications and said
drawings and said conditions of contract on or before the ______ day of ___________ 20___ and will
maintain the said works for a period of ________Calendar months from the certified date of their
completion and will observe, fulfill and keep all the conditions therein mentioned (which shall be
deemed and taken to be part of this contract, as if the same have been fully set forth herein), AND
RLDA, both hereby agree that if the Contractor shall duly perform the said works in the manner
aforesaid and observe and keep the said terms and conditions, RLDA will pay or cause to be paid to
the Contractor for the said works on the final completion thereof the amount due in respect thereof at
the rates specified in the Bill(s) of Quantities hereto annexed.
Contractor _______________ (Signature) RLDA: Designation ___________
Address _________________________ (For Rail Land Development Authority)
Date _____________ Date _____________
151
ANNEXURE-V
M/s_____________________________ (hereinafter called the tenderer) for the purpose of the Tender
documents for the work of Development of Bijwasan Railway Station at Bijwasan, New Delhi
(Balance Work) as per the tender No. RLDA/RFP/CD-84/SRD-18 of 2022 dated 15.12.2022 of
(RLDA)**, do hereby solemnly affirm and state on the behalf of the tenderer including its constituents
as under:
1. I/we the tenderer (s) am/are signing this document after carefully reading the contents.
2. I/We the tenderer(s) also accept all the conditions of the tender and have signed all the pages
in confirmation thereof.
3. I/we hereby declare that I/we have obtained the tender documents from RLDA downloaded
the tender documents from RLDA website www.tenderwizard.com/RLDA. I/we have verified
the content of the document from the website and there is no addition, no deletion or no
alteration to the content of the tender document. In case of any discrepancy noticed at any
stage i.e. evaluation of tenders, execution of work or final payment of the contract, the master
copy available with RLDA shall be final and binding upon me/us.
4. I/we declare and certify that I/we have not made any misleading or false representation in the
forms, statements and attachments in proof of the qualification requirements.
5. I/We also understand that my/our offer will be evaluated based on the
documents/credentials submitted along with the offer and same shall be binding upon
me/us.
6. I/We declare that the information and documents submitted along with the tender by
me/us are correct and I/we are fully responsible for the correctness of the information
and documents, submitted by us.
7. I/we certify that I/we the tenderer(s) is/are not blacklisted or debarred by RLDA/Railways or
any other Ministry / Department of Govt. of India from participation in tender on the date of
submission of bids, either in individual capacity or as a HUF/ member of the partnership
firm/LLP/JV/Society/Trust.
8. I/we understand that if the contents of the certificate submitted by us are found to be
forged/false or incorrect at any time during process for evaluation of tenders, it shall lead to
forfeiture of the Bid Security besides banning of business for a period of upto five year.
Further, I/we (insert name of the tenderer) **_____________and all my/our constituents
understand that my/our offer shall be summarily rejected.
152
9. I/we also understand that if the contents of the certificate submitted by us are found to be
false/forged or incorrect at any time after the award of the contract, it will lead to termination
of the contract, along with forfeiture of Bid Security/Security Deposit and Performance
guarantee besides any other action provided in the contract including banning of business for
a period of upto five year.
10. I/We have read the clause regarding restriction on procurement from a bidder of a country
which shares a land border with India and certify that I am/We are not from such a country or,
if from such a country, have been registered with the competent Authority. I/We hereby certify
that I/we fulfil all the requirements in this regard and am/are eligible to be considered
(evidence of valid registration by the competent authority is enclosed)
**The contents in Italics are only for guidance purpose. Details as appropriate are to be filled in
suitably by tenderer.
This affidavit is to be given by each member of JV.
153
ANNEXURE – VI
Reference -Para 10.3 & 17.15.3 of Tender Form (Second Sheet) of Annexure I of ITT
Where,
A = Maximum value of construction works executed and payment received in any one of the previous
three financial years or the current financial year (up to date of inviting tender), taking into account
the completed as well as works in progress.
N= Number of years prescribed for completion of work for which bids has been invited.
B = Existing commitments and balance amount of ongoing works with the tenderer as per the
prescribed performa of Railway for statement of all works in progress and also the works which are
awarded to Tenderers but yet not started upto the date of inviting of Tender.
Note:
(a) The Tenderer(s) shall furnish the details of -
(i) Maximum value of construction works executed and payment received in any one of
the previous three financial years or the current financial year (up to date of inviting
tender) for calculating A, and
(ii) Existing commitments and balance amount of ongoing works with tenderer as per the
prescribed proforma of RLDA for statement of all works in progress and also the
works which are awarded to tenderer but yet not started upto the date of inviting of
tender for calculating B. In case of no works in hand, a ‘NIL’ statement should be
furnished.
The submitted details for (i) and (ii) above should be duly verified by Chartered
Accountant.
(b) In case if a bidder is JV, the tenderer(s) must furnish the details of
(i) Maximum value of construction works executed and payment received in any one of
the previous three financial years or the current financial year (up to date of inviting
tender) by each member of JV for calculating A, and
(ii) Existing commitments and balance amount of ongoing works with each member of
JV either in individual capacity or as a member of other JV as per the prescribed
proforma of RLDA for statement of all works in progress and also the works which
are awarded to each member of JV either in individual capacity or as a member of
other JV but yet not started upto the date of inviting of tender for calculating B. In
case of no works in hand, a ‘NIL’ statement should be furnished.
The submitted details for (i) and (ii) above should be duly verified by Chartered
Accountant.
154
(c) Value of a completed work/work in progress/work awarded but yet not started for a Member
in an earlier JV shall be reckoned only to the extent of the concerned member's share in that JV
for the purpose of satisfying his/her compliance to the above mentioned bid capacity in the
tender under consideration.
(d) The arithmetic sum of individual “bid capacity” of all the members shall be taken as JV’s “bid
capacity”.
(e) In case, the tenderer/s failed to submit the above statement along with offer, their/his offer shall
be considered as incomplete and will be rejected summarily.
(f) The available bid capacity of tenderer shall be assessed based on the details submitted by the
tenderer. In case, the available bid capacity is lesser than estimated cost of work put to tender,
his offer shall not be considered even if he has been found eligible in other eligibility
criteria/tender requirement.
155
Annexure –VIA
Para 5 of ITT and Clause 16.(4) of Standard GCC
(Bid Security/Performance Security)
Bank Guarantee from any scheduled commercial bank of India
(On non-judicial stamp paper, which should be in the name of the Executing Bank).
WHEREAS:
B. The Agreement requires the Contractor to furnish a Performance Security for due and faithful
performance of its obligations, under and in accordance with the Agreement, during the
{Construction Period/ Defects Liability Period} (as defined in the Agreement) in a sum of
Rs….. Lakhs. (Rupees ………..….. Lakhs) (the “Guarantee Amount”).
NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and
affirms as follows:
1. The Bank hereby unconditionally and irrevocably guarantees the due and faithful
performance of the Contractor’s obligations during the {Construction Period/Defects
Liability Period} under and in accordance with the Agreement, and agrees and undertakes
to pay to the [mention Finance of Authority], upon its mere first written demand, and without
any demur, reservation, recourse, contest or protest, and without any reference to the
Contractor, such sum or sums up to an aggregate sum of the Guarantee Amount as the
Authority shall claim, without the Authority being required to prove or to show grounds or
reasons for its demand and/or for the sum specified therein.
2. A letter from the Authority, under the hand of an officer not below the rank of Deputy
General Manager in the Rail Land Development Authority, that the Contractor has
committed default in the due and faithful performance of all or any of its obligations under
and in accordance with the Agreement shall be conclusive, final and binding on the Bank.
156
The Bank further agrees that the Authority shall be the sole judge as to whether the
Contractor is in default in due and faithful performance of its obligations during and under
the Agreement and its decision that the Contractor is in default shall be final and binding on
the Bank, notwithstanding any differences between the Authority and the Contractor, or any
dispute between them pending before any court, tribunal, arbitrators or any other authority
or body, or by the discharge of the Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act as if the Bank
were the principal debtor and any change in the constitution of the Contractor and/or the
Bank, whether by their absorption with any other body or corporation or otherwise, shall not
in any way or manner affect the liability or obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the Authority to
proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the liability of the
Bank under this Guarantee, to vary at any time, the terms and conditions of the Agreement
or to extend the time or period for the compliance with, fulfilment and/ or performance of
all or any of the obligations of the Contractor contained in the Agreement or to postpone for
any time, and from time to time, any of the rights and powers exercisable by the Authority
against the Contractor, and either to enforce or forbear from enforcing any of the terms and
conditions contained in the Agreement and/or the securities available to the Authority, and
the Bank shall not be released from its liability and obligation under these presents by any
exercise by the Authority of the liberty with reference to the matters aforesaid or by reason
of time being given to the Contractor or any other forbearance, indulgence, act or omission
on the part of the Authority or of any other matter or thing whatsoever which under any law
relating to sureties and guarantors would but for this provision have the effect of releasing
the Bank from its liability and obligation under this Guarantee and the Bank hereby waives
all of its rights under any such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or security
now or which may hereafter be held by the Authority in respect of or relating to the
Agreement or for the fulfilment, compliance and/or performance of all or any of the
obligations of the Contractor under the Agreement.
7. Notwithstanding anything contained hereinbefore, the liability of the Bank under this
Guarantee is restricted to the Guarantee Amount and this Guarantee will remain in force for
the period specified in paragraph 8 below and unless a demand or claim in writing is made
157
by the Authority on the Bank under this Guarantee all rights of the Authority under this
Guarantee shall be forfeited and the Bank shall be relieved from its liabilities hereunder.
8. The Guarantee shall cease to be in force and effect on 6 (six) months of the expiry of
Maintenance Period. Unless a demand or claim under this Guarantee is made in writing
before expiry of the Guarantee, the Bank shall be discharged from its liabilities hereunder.
9. The Bank undertakes not to revoke this Guarantee during its currency, except with the
previous express consent of the Authority in writing, and declares and warrants that it has
the power to issue this Guarantee and the undersigned has full powers to do so on behalf of
the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by post
addressed to the Bank at its above referred branch, which shall be deemed to have been
duly authorised to receive such notice and to effect payment thereof forthwith, and if sent
by post it shall be deemed to have been given at the time when it ought to have been
delivered in due course of post and in proving such notice, when given by post, it shall be
sufficient to prove that the envelope containing the notice was posted and a certificate
signed by an officer of the Authority that the envelope was so posted shall be conclusive.
11. The Bank hereby confirms that it is on the SFMS (Structured Financial Messaging System)
and shall invariably send the advice of this Bank Guarantee to the following bank details –
158
(Signature)
(Name)
(Designation)
(Code Number)
(Address)
NOTES:
(i) The bank guarantee should contain the name, designation and code number of the officer(s)
signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as well as
of issuing branch should be mentioned on the covering letter of issuing branch.
159
Annexure –VIB
Reference -Para 10.2 & 17.15.2 of Tender Form (Second Sheet) of Annexure I of ITT
1. The average annual contractual turnover shall be calculated as an average of “total contractual
payments” in the previous three financial years. However, in case balance sheet of the previous
year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be
considered for calculating average annual contractual turnover.
2. The information supplied shall be substantiated by data in the audited balance sheets and profit
and loss accounts for the relevant years in respect of the bidder or all members constituting the
bidder.
3. Contents of this form should be certified by a Chartered Accountant duly supported by Audited
Balance Sheet duly certified by the Chartered Accountant.
Certified that all figures and facts submitted in this form have been furnished after full consideration
of all observations/notes in Auditor’s reports._____________________
(Signature of Chartered Accountant)
Name of CA:______________
Registration No: ______________
(Seal)
160
Part II
STANDARD GENERAL CONDITIONS OF CONTRACT
1. (1) Definitions: In these Standard General Conditions of Contract, the following terms shall have
the meaning assigned hereunder except where the context otherwise requires:
(a) "Railways" shall mean the President of the Republic of India or the Administrative Officers of
Railway or of the Successor Railway authorized to deal with any matters which these presents
are concerned on his behalf.
(b) “RLDA” shall mean a Statutory Authority under the Ministry of Railways shall mean the Vice
Chairman or the administrative officers of RLDA or Successor RLDA authorized to deal with
any matter, which these presents are concerned on his behalf.
(c) “Vice Chairman” shall mean the Officer-in-Charge of the general superintendence and control
of the Unit and shall also include Members and shall mean and include their successors of the
Successor RLDA.
“Authority” shall mean RLDA and the Officer-in-Charge of the general superintendence and
control of the Unit and shall also include Members and shall mean and include their successors
of the Successor RLDA
(d) "Executive Director/General Manager/Chief Project Manager" shall mean the Officer in-charge
of the Engineering Department of RLDA for General Superintendence and Control and shall
mean & include their successors, of the Successor RLDA.
(e) “Engineer” shall mean the executive in-charge of the works and shall include the superior
officers and shall mean & include the Engineers of the Successor of RLDA.
(f) "Engineer's Representative" shall mean the Nodal Officer, and shall mean and include the
Engineer's Representative of the Successor RLDA.
(h) "Contract" shall mean and include the Agreement, the Work Order, the accepted Bill(s) of
Quantities or Chapter(s) of CPWD Delhi Schedule of Rates (DSR) 2021 duly modified by the
tender percentage for items of works quantified, or not quantified, or Chapters of Standard
Schedule of Rates (SSOR) of Railway modified by the tender percentage for items of works
quantified, or not quantified, the Standard General Conditions of Contract, the Special
Conditions of Contracts, if any; the Drawing, the Specifications, the Special Specifications, if
any and Tender Forms, if any.
(i) "Works" shall mean the works to be executed in accordance with the contract.
(j) "Specifications" shall mean the CPWD Specifications Vol.-I and Vol.-II 2019 published by
CPWD with latest amendment/corrections and/or Standard Specifications for Materials &
161
Works of Railways as specified by Railways under the authority of the Chief Engineer or as
amplified, added to or superseded by Special Specifications, if any.
(k) Standard Schedule of Rates (SSOR) shall mean the schedule of Rates adopted by RLDA, which
includes-
1. “Delhi Schedule Of Rates (DSR)” i.e. the Standard Schedule of Rates published by Director
General/ Central Public Works Department, Government of India, New Delhi, updated with
correction slips issued up to date of inviting tender or as otherwise specified in the tender
documents.
2. “Unified Standard Schedule of Rates of Railway (USSOR)” i.e. the Standard Schedule of
Rates of Railway issued under the authority of the Chief Engineer from time to time, updated
with correction slips issued up to date of inviting tender or as otherwise specified in the
tender documents;
(l) "Drawing" shall mean the maps, drawings, plans and tracings or prints there of annexed to the
contract and shall include any modifications of such drawings and further drawings as may be
issued by the Engineer from time to time.
(m) "Constructional Plant" shall mean all appliances or things of whatsoever nature required for
the execution, completion or maintenance of the works or temporary works (as hereinafter
defined) but does not include materials or other things intended to form or forming part of the
permanent work.
(n) "Temporary Works" shall mean all temporary works of every kind required for the execution
completion and/or maintenance of the works.
(o) "Site" shall mean the lands and other places on, under, in or through which the works are to be
carried out and any other lands or places provided by RLDA for the purpose of the contract.
(p) "Period of Maintenance" shall mean the specified period of maintenance from the date of
completion of the works, as certified by the Engineer.
(q) ‘Contractor’s authorized Engineer’ shall mean a graduate Engineer or equivalent, having more
than 3 years’ experience in the relevant field of construction work involved in the contract,
duly approved by Engineer.
(r) Date of inviting tender shall be the date of publishing tender notice on IREPS website if tender
is published on website or the date of publication in newspaper in case tender is not published
on website.
(s) “Bill of Quantities” shall mean Schedule of Item(s) included in the tender document along with
respective quantities and rates and or quoted percentage above/below, accepted by RLDA.
1. (2) Singular and Plural: Words importing the singular number shall also include the plural and
vice versa where the context requires.
1. (3) Headings and Marginal Headings: The headings and marginal headings in these Standard
General Conditions are solely for the purpose of facilitating reference and shall not be deemed
162
to be part thereof or be taken into consideration in the interpretation or construction thereof the
contract.
GENERAL OBLIGATIONS
2. (1) Execution Co-Relation and Intent of Contract Documents: The contract documents shall be
signed in triplicate by RLDA and the Contractor. The contract documents are complementary
and what is called for by anyone shall be as binding as if called for by all, the intention of the
documents is to include all labour and materials, equipments and transportation necessary for
proper execution of work. Materials or works not covered by or properly inferable from any
heading or class of the specifications shall not be supplied by RLDA to the Contractors unless
distinctly specified in the contract documents. Materials or works described in words which so
applied have a well-known technical or trade meaning, shall be held to refer to such recognized
standards.
2.(2) If a work is transferred from the jurisdiction of one RLDA office to another RLDA office or to
a Project authority or vice versa while contract is in subsistence, the contract shall be binding on
the Contractor and the Successor RLDA/Project in the same manner & take effect in all respects
as if the Contractor and the Successor RLDA/Project were parties thereto from the inception and
the corresponding officer or the Competent Authority in the Successor RLDA/Project will
exercise the same powers and enjoy the same authority as conferred to the Predecessor
RLDA/Project under the original contract/agreement entered into.
2. (3) If for administrative or other reasons the contract is transferred to the Successor RLDA, the
contract shall, notwithstanding any things contained herein contrary there to, be binding on the
Contractor and the Successor RLDA in the same manner and take effect in all respects as if the
Contractor and the Successor RLDA had been parties thereto from the date of this contract.
3. (1) Law Governing the Contract: The contract shall be governed by the law for the time being in
force in the Republic of India.
3.(2) Compliance to Regulations and Bye-Laws: The Contractor shall conform to the provision of
any statute relating to the works and regulations and bye-laws of any local authority and of any
water and lighting companies or undertakings, with whose system the work is proposed to be
connected and shall before making any variation from the drawings or the specifications that
may be necessitated by so confirming give to the Engineer notice specifying the variation
proposed to be made and the reason for making the variation and shall not carry out such
variation until he has received instructions from the Engineer in respect thereof. The Contractor
shall be bound to give all notices required by statute, regulations or bye-laws as aforesaid and to
pay all fees and taxes payable to any authority in respect thereof.
163
the Contractor shall be entitled to Extension of Time for the period of such delay in accordance
with the provisions of Clause-17A(ii).
4. Communications to be in Writing: All notices, communications, reference and complaints
made by RLDA or the Engineer or the Engineer's Representative or the Contractor inter-se
concerning the works shall be in writing or e-mail on registered e-mail IDs i.e. the e mail id
provided for correspondence in the contract agreement, otherwise email id registered with IREPS
and no notice, communication, reference or complaint not in writing or through e-mail, shall be
recognized.
5. Service of Notices on Contractors: The Contractor shall furnish to the Engineer the name,
designation and address of his authorized agent and all complaints, notices, communications and
references shall be deemed to have been duly given to the Contractor, if delivered to the
Contractor or his authorized agent or left at or posted to the address so given and shall be deemed
to have been so given in the case of posting on day on which they would have reached such
address in the ordinary course of post/ e-mail or on the day on which they were so delivered or
left. In the case of contract by partners, any change in the constitution of the firm shall be
forthwith notified by the Contractor to the Engineer.
6. Occupation and Use of Land: No land belonging to or in the possession of RLDA shall be
occupied by the Contractor without the permission of RLDA. The Contractor shall not use, or
allow to be used the site for any purposes other than that of executing the works. Whenever
non-RLDA bodies/persons are permitted to use RLDA premises with competent authority’s
approval, conservancy charges as applicable from time to time may be levied.
7. Assignment or Subletting of Contract: The Contractor shall not assign or sublet the contract
or any part thereof or allow any person to become interested therein in any manner whatsoever
without the special permission in writing of the General Manager/Chief Project Manager/Chief
Engineer, save as provided below. Any breach of this condition shall entitle RLDA to rescind
the contract under Clause 62 of these Conditions and also render the Contractor liable for
payment to RLDA in respect of any loss or damage arising or ensuing from such cancellation;
provided always that execution of the details of the work by petty Contractor under the direct
and personal supervision of the Contractor or his agent shall not be deemed to be sub-letting
under this clause.
In case Contractor intends to subcontract part of work, he shall submit a proposal in writing
seeking permission of General Manager/Chief Project Manager/Chief Engineer for the same.
While submitting the proposal to RLDA, Contractor shall ensure the following:
(a) (i) Total value of work to be assigned to sub-contractor(s) shall not be more than 50% of total
contract value.
(ii) The subcontractor shall have successfully completed at least one work similar to work
proposed for subcontract in last 5 years, ending date of submission of proposal by Contractor
to RLDA, costing not less than 35% value of work to be subletted, through a works contract.
For fulfilment of above, Work Experience Certificate issued by a Govt.
Department/Organisation shall be considered. Further, Work Experience Certificate issued by
a Public listed company shall be considered provided the company is having average annual
turnover of Rs 500 crore and above in last 3 financial years excluding the current financial
164
year, listed on National Stock Exchange or Bombay Stock Exchange, registered at least
5 years back from the date of submission of proposal by Contractor to RLDA and work
experience certificate issued by a person authorised by the Public Listed Company to issue
such certificates.
Note: for subletting of work costing up to Rs 50 lakh no previous work experience shall be
asked for by RLDA.
In case contractor submits subcontractor’s work experience certificate issued by public listed
company, the contractor shall also submit along with work experience certificate, the relevant
copy of work order, bill of quantities, bill wise details of payment received duly certified by
Chartered Accountant, TDS certificates for all payments received and copy of final/last bill
paid by company in support of above work experience certificate.
(iii) There is no banning of business with the sub-contractor in force over RLDA/Indian Railway.
(b) The Contractor shall provide to the Engineer a copy of the agreement to be entered into by
Contractor with subcontractor. No subcontractor shall be permitted without a formal agreement
between Contractor and subcontractor. This agreement shall clearly define the scope of work to
be carried out by subcontractor and the terms of payment in clear & unambiguous manner.
(d) The Contractor shall intimate to the Engineer not less than 7 days in advance, the intended date
of commencement of subcontractor’s work.
(e) Once having entered into above arrangement, Contractor shall discontinue such arrangement, if
he intends to do so at his own or on the instructions of RLDA, with prior intimation to General
Manager/Chief Project Manager/Chief Engineer.
(f) The Contractor shall indemnify RLDA against any claim of subcontractor.
(g) The Contractor shall release payment to the Sub-contractor(s) promptly and shall endeavour to
resolve all issues amicably and speedily with the Sub-contractor(s), so that the execution of work
is not affected in any manner whatsoever.
(h) In addition to issuance of work experience certificate to Contractor, the Engineer, when, based
on documents, is satisfied that subcontracted work has been carried out by subcontractor, shall
issue work experience certificate to the subcontractor also for the portion of work subcontracted
and successfully completed by the sub-contractor.
Note: Work Experience Certificate to the subcontractor shall be issued only when the
contractor’s work is complete and contractor is entitled for the issuance of Work Experience
Certificate. However, in the same contract, when the General Manager/Chief Project Manager,
based on documents, is satisfied that the subcontractor has successfully carried out subletted
work; without issuance of work experience certificate to subcontractor at this stage, the General
Manager/Chief Project Manager can, only once, consider the successfully completed subletted
work for the fulfilment of eligibility for further subletting of work to the subcontractor in the
same contract. When the contractor’s work is complete and contractor is entitled for the issuance
165
of work experience certificate, the subcontractor shall be issued one Work Experience
Certificate for the total scope of work executed by the subcontractor in the contract.
(i) The responsibility of successful completion of work by subcontractor shall lie with Contractor.
Subcontracting will in no way relieve the Contractor to execute the work as per terms of the
Contract.
(j) Further, in case Engineer is of the view that subcontractor’s performance is not satisfactory, he
may instruct the Contractor to remove the subcontractor from the work and Contractor has to
comply with the above instructions with due promptness. Contractor shall intimate the actual
date of discontinuation of subcontract to Engineer. No claim of Contractor whatsoever on this
account shall be entertained by RLDA and this shall be deemed as ‘excepted matter’ (matter not
arbitrable).
(k) The permitted subcontracting of work by the Contractor shall not establish any contractual
relationship between the sub-contractor and RLDA and shall not relieve the Contractor of any
responsibility under the Contract.
8. Assistance by RLDA for the Stores to be obtained by the Contractor: Owing to difficulty in
obtaining certain materials (including Tools & Plant) in the market, RLDA may have agreed without
any liability therefore to endeavour to obtain or assist the Contractor in obtaining the required
quantities of such materials as may be specified in the Tender. In the event of delay or failure in
obtaining the required quantities of the aforesaid material, the Contractor shall not be deemed
absolved of his own responsibility and shall keep in touch with the day to day position regarding
their availability and accordingly adjust progress of works including employment of labour and
RLDA shall not in any way be liable for the supply of materials or for the non-supply thereof for
any reasons whatsoever nor for any loss or damage arising in consequence of such delay or non-
supply.
9. Railway Passes: No free Railway passes shall be issued by Railway to the Contractor or any of
his employee/worker.
10. Carriage of Materials: No forwarding orders shall be issued by RLDA for the conveyance of
Contractor's materials, tools and plant by train which may be required for use in the works and the
Contractor shall pay full freight charges at public tariff rates therefor.
11. Use of Ballast Trains: Railway may agree to allow the Contractor use of the ballast or material
trains under such conditions as shall be specially prescribed, provided that the Contractor shall
pay for the use thereof charges calculated at public tariff rates on the marked carrying capacity of
each vehicle subject to specified minimum charge per day or part of day and provided further that
the Contractor shall indemnify RLDA against any claims or damages arising out of the use or
misuse thereof and against any liabilities under the Workmen's Compensation Act, 1923 or any
statutory amendments thereto.
12. Representation on Works: The Contractor shall, when he is not personally present on the site of
the works place, keep a responsible agent at the works during working hours who shall on
receiving reasonable notice, present himself to the Engineer and orders given by the Engineer or
the Engineer's representative to the agent shall be deemed to have the same force as if they had
166
been given to the Contractor. Before absenting himself, the Contractor shall furnish the name and
address of his agent for the purpose of this clause and failure on the part of the Contractor to
comply with this provision at any time will entitle RLDA to rescind the contract under Clause 62
of these Conditions.
13. Relics and Treasures: All gold, silver, oil, other minerals of any description, all precious stones,
coins, treasures relics antiquities and other similar things which shall be found in or upon the site
shall be the property of RLDA and the Contractor shall duly preserve the same to the satisfaction
of RLDA and shall from time to time deliver the same to such person or persons as RLDA may
appoint to receive the same.
14. Excavated Material: The Contractor shall not sell or otherwise dispose of or remove except for
the purpose of this contract, the sand, stone, clay ballast, earth, trees, rock or other substances or
materials which may be obtained from any excavation made for the purpose of the works or any
building or produced upon the site at the time of delivery of the possession thereof but all the
substances, materials, buildings and produce shall be the property of RLDA provided that the
Contractor may, with the permission of the Engineer, use the same for the purpose of the works
either free of cost or pay the cost of the same at such rates as may be determined by the Engineer.
15. Indemnity by Contractors: The Contractor shall indemnify and save harmless RLDA from and
against all actions, suit, proceedings, losses, costs, damages, charges, claims and demands of every
nature and description brought or recovered against RLDAs by reason of any act or omission of
the Contractor, his agents or employees, in the execution of the works or in his guarding of the
same. All sums payable by way of compensation under any of these conditions shall be considered
as reasonable compensation to be applied to the actual loss or damage sustained, and whether or
not any damage shall have been sustained.
16.(1) Security Deposit: The Security Deposit shall be 5% of the contract value. The Bid Security
submitted by the Contractor with his tender will be retained/encashed by RLDA as part of security
for the due and faithful fulfillment of the contract by the Contractor. Provided further that, if
Contractor submits through e-payment gateway or Term Deposit Receipt issued from a Scheduled
commercial bank of India or irrevocable Bank Guarantee Bond from a Scheduled commercial
bank of India, either towards the Full Security Deposit or the Part Security Deposit equal to or
more than Bid Security, RLDA shall return the Bid Security, to the Contractor.
Balance of Security Deposit may be deposited by the Contractor through e-payment gateway or
Term Deposit Receipt issued from Scheduled commercial bank of India or irrevocable Bank
Guarantee bond issued from Scheduled commercial bank of India, or may be recovered at the rate
of 6% of the bill amount till the full Security Deposit is recovered. Provided also that in case of
defaulting Contractor, RLDA may retain any amount due for payment to the Contractor on the
pending "on account bills" so that the amounts so retained (including amount guaranteed through
Performance Guarantee) may not exceed 10% of the total value of the contract.
The Irrevocable Bank Guarantee submitted towards Security deposit shall be initially valid up to
the stipulated date of Maintenance period plus 60 days and shall be extended from time to time,
depending upon extension of contract granted in terms of Clause 17A and 17B of the Standard
General Conditions of Contract.
167
Note: Security Deposit deposited through e-payment gateway or DD/PO by the Contractor or
recovered from the running bills of a Contractor or submitted by contractor as Term Deposit
Receipt(s) can be refunded/returned to the contractor, in lieu of irrevocable Bank Guarantee bond
issued from scheduled commercial bank of India, to be submitted by him, for an amount equal to
or more than the already available Security Deposit, provided however that, in a contract of value
less than Rs. 50 Crore, such refund/ return of the already available Security Deposit is permitted
up to two times and in a contract of value equal to or more than Rs. 50 Crore, such refund / return
of the already available Security Deposit is permitted up to three times.
16.(2) (i) Refund of Security Deposit: Security Deposit mentioned in sub clause (1) above shall be
returned to the Contractor along with or after, the following:
16. (2) (ii) Forfeiture of Security Deposit: Whenever the contract is rescinded as a whole under clause
62 (1) of these conditions, the Security Deposit already with RLDAs under the contract shall be
forfeited. However, in case the contract is rescinded in part or parts under clause 62 (1) of these
conditions, the Security Deposit shall not be forfeited.
16.(3) No interest shall be payable upon the Bid Security, Performance Guarantee and Security
Deposit or amounts payable to the Contractor under the Contract, but Government Securities
deposited in terms of Sub-Clause 16.(4)(b) of this clause will be payable with interest accrued
thereon.
168
(i) A deposit of Cash;
(ii) Irrevocable Bank Guarantee;
(iii) Government Securities including State Loan Bonds at 5% below the market value;
(iv) Pay Orders and Demand Drafts tendered by any Scheduled Commercial Bank of India;
(v) Guarantee Bonds executed or Deposits Receipts tendered by any Scheduled Commercial
Bank of India;
(vi) Deposit in the Post Office Saving Bank;
(vii) Deposit in the National Savings Certificates;
(viii) Twelve years National Defence Certificates;
(ix) Ten years Defence Deposits;
(x) National Defence Bonds and
(xi) Unit Trust Certificates at 5% below market value or at the face value whichever is less.
Also, FDR in favour of FA&CAO (free from any encumbrance) may be accepted.
(c) The Performance Guarantee shall be submitted by the successful bidder after the Letter of
Acceptance (LOA) has been issued, but before signing of the contract agreement. This P.G.
shall be initially valid upto the stipulated date of completion plus 60 days beyond that. In case,
the time for completion of work gets extended, the Contractor shall get the validity of P.G.
extended to cover such extended time for completion of work plus 60 days.
(d) The value of PG to be submitted by the Contractor is based on original contract value and shall
not change due to subsequent variation(s) in the original contract value.
(e) The Performance Guarantee (PG) shall be released after physical completion of the work based
on 'Completion Certificate' issued by the competent authority stating that the Contractor has
completed the work in all respects satisfactorily.
(f) Whenever the contract is rescinded, the Performance Guarantee already submitted for the
contract shall be encashed.
(g) The Engineer shall not make a claim under the Performance Guarantee except for amounts to
which RLDA is entitled under the contract (not withstanding and/or without prejudice to any
other provisions in the contract agreement) in the event of:
(i) Failure by the Contractor to extend the validity of the Performance Guarantee as described
herein above, in which event the Engineer may claim the full amount of the Performance
Guarantee.
(ii) Failure by the Contractor to pay President of India any amount due, either as agreed by the
Contractor or determined under any of the Clauses/Conditions of the Agreement, within 30
days of the service of notice to this effect by Engineer.
(iii) The Contract being determined or rescinded under clause 62 of these conditions.
17. Force Majeure Clause: If at any time, during the continuance of this contract, the performance
in whole or in part by either party of any obligation under this contract shall be prevented or
delayed by reason of any war, hostility, acts of public enemy, civil commotion, sabotage, serious
loss or damage by fire, explosions, epidemics/pandemics, strikes, lockouts or acts of God
(hereinafter, referred to events) provided, notice of the happening of any such event is given by
either party to the other within 30 days from the date of occurrence thereof, neither party shall by
reason of such event, be entitled to terminate this contract nor shall either party have any claim
for damages against the other in respect of such non-performance or delay in performance, and
169
works under the contract shall be resumed as soon as practicable after such event has come to an
end or ceased to exist, and the decision of the Engineer as to whether the works have been so
resumed or not shall be final and conclusive, PROVIDED FURTHER that if the performance in
whole or in part of any obligation under this contract is prevented or delayed by reason of any
such event for a period exceeding 120 days, either party may at its option terminate the contract
by giving notice to the other party.
17A Extension of Time in Contracts: Subject to any requirement in the contract as to completion of
any portion or portions of the works before completion of the whole, the Contractor shall fully and
finally complete the whole of the works comprised in the contract (with such modifications as may
be directed under conditions of this contract) by the date entered in the contract or extended date
in terms of the following clauses:
(i) Extension due to Modification: If any modifications have been ordered which in the opinion
of the Engineer have materially increased the magnitude of the work, then such extension of the
contracted date of completion may be granted as shall appear to the Engineer to be reasonable in
the circumstances, provided moreover that the Contractor shall be responsible for requesting
such extension of the date as may be considered necessary as soon as the cause thereof shall
arise.
(ii) Extension for Delay not due to RLDA or Contractor: If in the opinion of the Engineer, the
progress of work has any time been delayed by any act or neglect of RLDA employees or by
other Contractor employed by RLDA under Sub-Clause (4) of Clause 20 of these Conditions or
in executing the work not forming part of the contract but on which Contractor's performance
necessarily depends or by reason of proceeding taken or threatened by or dispute with adjoining
or to neighbouring owners or public authority arising otherwise through the Contractor's own
default etc. or by the delay authorized by the Engineer pending arbitration or in consequences of
the Contractor not having received in due time necessary instructions from RLDA for which he
shall have specially applied in writing to the Engineer or his authorized representative then upon
happening of any such event causing delay, the Contractor shall immediately give notice thereof
in writing to the Engineer within 15 days of such happening, but shall nevertheless make
constantly his best endeavours to bring down or make good the delay and shall do all that may
be reasonably required of him to the satisfaction of the Engineer to proceed with the works. The
Contractor may also indicate the period for which the work is likely to be delayed and shall be
bound to ask for necessary extension of time.
(iii) Extension for Delay due to RLDA: In the event of any failure or delay by RLDA to hand over
the Contractor possession of the lands necessary for the execution of the works or to give the
necessary notice to commence the works or to provide the necessary drawings or instructions or
any other delay caused by RLDA due to any other cause whatsoever, then such failure or delay
shall in no way affect or vitiate the contract or alter the character thereof or entitle the Contractor
to damages or compensation therefor, but in any such case, RLDA may grant such extension or
extensions of the completion date as may be considered reasonable.
The Contractor shall indicate the period for which the work is likely to be delayed and shall seek
extension of time as may be considered necessary under clause 17A(i) or/and 17A(ii) or/ and
17A(iii) above, as soon as the cause thereof shall arise and, in any case, not less than 15 days
before the expiry of the date fixed for completion of the works. The Engineer shall consider the
same and shall grant and communicate such extension of time as in his opinion is reasonable
having regard to the nature and period of delay and the type and quantum of work affected thereby.
No other compensation shall be payable for works so carried forward to the extended period of
time; the same rates, terms and conditions of contract being applicable, as if such extended period
of time was originally provided in the original contract itself.
170
The non-submission of request for extension or submission of request within less than 15 days
before the expiry of the date fixed for completion of the works, shall make him ineligible for
extension under these sub clauses, subject to final decision of Engineer.
17B Extension of Time with Liquidated Damages (LD) for delay due to Contractor: The time for
the execution of the work or part of the works specified in the contract documents shall be
deemed to be the essence of the contract and the works must be completed not later than the
date(s) as specified in the contract. If the Contractor fails to complete the works within the time
as specified in the contract for the reasons other than the reasons specified in Clause 17 and 17A,
RLDA may, if satisfied that the works can be completed by the Contractor within reasonable
short time thereafter, allow the Contractor for further extension of time (Proforma at Annexure-
VII) as the Engineer may decide. On such extension RLDA will be entitled without prejudice to
any other right and remedy available on that behalf, to recover from the Contractor as agreed
damages and not by way of penalty for each week or part of the week, a sum calculated at the
rate of Liquidated Damages as decided by Engineer, between zero point zero five percent to
zero point three percent of contract value of the works for each week or part of the week.
For the purpose of this Clause, the contract value of the works shall be taken as value of work as
per contract agreement including any supplementary work order/contract agreement issued.
Provided also, that the total amount of liquidated damages under this condition shall not exceed
5% of the contract value or of the total value of the item or groups of items of work for which a
separate distinct completion period is specified in the contract.
(ii) Above Twenty Five percent but upto Fifty 0.10 % of contract value for each
percent of original period of completion weekor part of the week
including period of extension of time
granted under Section 17A(i)
(iii) Above Fifty percent of original period of 0.30 % of contract value for each
completion including period of extension weekor part of the week
of timegranted under Section 17A(i)
Provided further, that if RLDA is not satisfied that the works can be completed by the
Contractor and in the event of failure on the part of the contractor to complete the work within further
extension of time allowed as aforesaid, RLDA shall be entitled without prejudice to any other right or
171
remedy available in that behalf, to appropriate the contractor’s Security Deposit and rescind the
contract under Clause 62 of these Conditions, whether or not actual damage is caused by such default.
NOTE:
In a contract, where extension(s) of time have been allowed once under clause 17B, further request(s)
for extension of time under clause 17A can also be considered under exceptional circumstances. Such
extension(s) of time under clause 17A shall be without any Liquidated damages, but the Liquidated
damages already recovered during extension(s) of time granted previously under clause 17B shall not
be waived. However, Price variation during such extension(s) shall be dealt as applicable for
extension(s) of time under clause 17B.
17C Bonus for Early Completion of Work: In open tenders having advertised value more than
Rs.50 crore and original period of completion 12 months or more, when there is no reduction in
original scope of work by more than 10%, and no extension granted on either RLDA or Contractor’s
account, Contractor shall be entitled for a bonus of 1% for each 30 days early completion of work. The
period of less than 30 days shall be ignored while working out bonus. The maximum bonus shall be
limited to 5% of original contract value. The completion date shall be reckoned as the date of issuance
of completion certificate by Engineer.
18.(1) Illegal Gratification: Any bribe, commission, gift or advantage given, promised or offered
by or on behalf of the Contractor or his partner or agent or servant or anyone on his behalf, to any
officer or employee of RLDA or to any person on his behalf in relation to obtaining or execution of
this or any other contract with RLDA shall, in addition to any criminal liability which he may incur,
subject Contractor to the rescission of the contract and all other contracts with RLDA and to the
payment of any loss or damage resulting from such decision and RLDA shall be entitled to deduct the
amounts so payable from the Contractor’s bills/Security Deposit or any other dues of Contractor with
the Government of India.
18.(2) The Contractor shall not lend or borrow from or have or enter into any monitory dealings or
transactions either directly or indirectly with any employee of RLDA and if he shall do so, RLDA shall
be entitled forthwith to rescind the contract and all other contracts with RLDA. Any question or dispute
as to the commission of any such offence or compensation payable to RLDA under this Clause shall
be settled by the General Manager of RLDA, in such a manner as he shall consider fit & sufficient and
his decision shall be final & conclusive. In the event of rescission of the contract under this Clause,
the Contractor will not be paid any compensation whatsoever except payments for the work done upto
the date of rescission.
EXECUTION OF WORKS
19.(1) Contractor's understanding: It is understood and agreed that the Contractor has, by careful
examination, satisfied himself as to the nature and location of the work, the conformation of the
ground, the character, quality and quantity of the materials to be encountered, the character of
equipment and facilities needed preliminary to and during the progress of the works, the general and
local conditions, the labour conditions prevailing therein and all other matters which can in any way
affect the works under the contract.
172
19.(2) Commencement of Works: The Contractor shall commence the works within 15 days after
the receipt by him of an order in writing to this effect from the Engineer and shall proceed with the
same with due expedition and without delay
19.(3) Accepted Programme of Work: The Contractor who has been awarded the work shall as
soon as possible but not later than 30 days after the date of receipt of the acceptance letter in respect
of contracts with initial completion period of two years or less or not later than 90 days for other
contracts have to submit the detailed programme of work indicating the time schedule of various items
of works in the form of Bar Chart/PERT/CPM. He shall also submit the details of organisation (in
terms of labour and supervisors), plant and machinery that he intends to utilize (from time to time) for
execution of the work within stipulated date of completion. The programme of work amended as
necessary by discussions with the Engineer, shall be treated as the agreed programme of the work for
the purpose of this contract and the Contractor shall endeavor to fulfill this programme of work. The
progress of work will be watched accordingly and the liquidated damages will be with reference to the
overall completion date. Nothing stated herein shall preclude the Contractor in achieving earlier
completion of item or whole of the works than indicated in the programme.
The order in which the Contractor intends to carry out the Works, including the anticipated timing
of each stage, Contractor’s Documents, procurement, manufacture of Plant, delivery to Site,
construction, erection and testing, each of these stages for work by each Subcontractor, if any, the
sequence and timing of inspections and tests specified in the Contract, and a supporting report
which includes:
a general description of the methods which the Contractor intends to adopt, and of the major
stages, in the execution of the Works, and
details showing the Contractor’s reasonable estimate for the number of each class of Contractor’s
Personnel &Equipment, required on the Site for each major stage.
Unless the Engineer, within 21 days after receiving a programme, gives notice to the Contractor stating
the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance
with the programme, subject to his other obligations under the Contract. The Engineer shall be entitled
to rely upon the programme when planning their activities.
If, at any time, the Engineer gives notice to the Contractor that a programme fails (to the extent stated)
to comply with the Contract or to be consistent with actual progress and the Contractor’s stated
173
intentions, the Contractor shall submit a revised programme to the Engineer within 15 days in
accordance with this Sub-Clause.
19.(4) Setting out of Works: The Contractor shall be responsible for the correct setting out of all
works in relation to original points, lines and levels of reference at his cost. The Contractor shall
execute the work true to alignment, grade, levels and dimensions as shown in the drawing and as
directed by the Engineer's representative and check these at frequent intervals. The Contractor shall
provide all facilities like labour and instruments and shall co-operate with the Engineer's representative
for checking of all alignment, grades, levels and dimensions. If, at any time, during the progress of the
works any error appear or arise in any part of the work, the Contractor, on being required so to do by
the Engineer's representative shall, at his own cost rectify such errors, to the satisfaction of the
Engineer's representative.
Such checking shall not absolve the Contractor of his own responsibility of maintaining accuracy in
the work. The Contractor shall carefully protect and preserve all bench marks, sight rails, pegs and
other things used in setting out the work.
20.(1) Compliance to Engineer’s Instructions: The Engineer shall direct the sequence in which
the several parts of the works shall be executed and the Contractor shall execute without delay all
orders given by the Engineer from time to time; but the Contractor shall not be relieved thereby from
responsibility for the due performance of the works in all respects.
20.(3) Extra Works: Should works over and above those included in the contract require to be
executed at the site, the Contractor shall have no right to be entrusted with the execution of such works
which may be carried out by another Contractor or Contractors or by other means at the option of
RLDA.
20.(4) Separate Contracts in Connection with Works: RLDA shall have the right to let other
contracts in connection with the works. The Contractor shall afford other Contractors reasonable
opportunity for the storage of their materials and the execution of their works and shall properly
connect and coordinate his work with theirs. If any part of the Contractor’s work depends upon proper
execution or result upon the work of another Contractor(s), the Contractor shall inspect and promptly
report to the Engineer any defects in such works that render it unsuitable for such proper execution
and results. The Contractor's failure so-to inspect and report shall constitute an acceptance of the other
Contractor's work as fit and proper for the reception of his work, except as to defects which may
develop in the other Contractor's work after the execution of his work.
(a) Failure of the Engineer's representative to disapprove any work or materials shall not prejudice
the power of the Engineer thereafter to disapprove such work or material and to order the
removal or breaking up thereof.
174
(b) If the Contractor shall be dissatisfied by reason of any decision of the Engineer's representative,
he shall be entitled to refer the matter to the Engineer who shall there upon confirm or vary such
decision.
22.(1) Adherence to Specifications and Drawings: The site and the detailed drawings shall be
made available to the contractor commensurate with the accepted programme of work submitted under
clause 19(3). The whole of the works shall be executed in perfect conformity with the specifications
and drawings of the contract. If Contractor performs any works in a manner contrary to the
specifications or drawings or any of them and without such reference to the Engineer, he shall bear all
the costs arising or ensuing therefrom and shall be responsible for all loss to RLDA.
22.(2) Drawings and Specifications of the Works: The Contractor shall keep one copy of
Drawings and Specifications at the site, in good order, and such contract documents as may be
necessary, available to the Engineer or the Engineer's Representative.
22.(3) Ownership of Drawings and Specifications: All Drawings and Specifications and copies
thereof furnished by RLDA to the Contractor are deemed to be the property of RLDA. They shall not
be used on other works and with the exception of the signed contract set, shall be returned by the
Contractor to RLDA on completion of the work or termination of the Contract.
22.(4) Compliance with Contractor's Request for Details: The Engineer shall furnish with
reasonable promptness, after receipt by him of the Contractor's request, additional instructions by
means of drawings or otherwise, necessary for the proper execution of the works or any part thereof.
All such drawings and instructions shall be consistent with the Contract Documents and reasonably
inferable there from.
22.(5) Meaning and Intent of Specification and Drawings: If any ambiguity arises as to the
meaning and intent of any portion of the Specifications and Drawings or as to execution or quality of
any work or material, or as to the measurements of the works the decision of the Engineer thereon
shall be final subject to the appeal (within 7 days of such decision being intimated to the Contractor)
to the General Manager/Chief Project Manager/Chief Engineer who shall have the power to correct
any errors, omissions, or discrepancies in aforementioned items and whose decision in the matter in
dispute or doubt shall be final and conclusive.
23. Working during Night: The Contractor shall not carry out any work between sun-set and
sun-rise without the previous permission of the Engineer. However, if the Engineer is satisfied that
the work is not likely to be completed in time except by resorting to night work, he may order the
same without confirming any right on the Contractor for claiming any extra payment for the same.
24. Damage to RLDA Property or Private Life and Property: The Contractor shall be
responsible for all risk to the work and for trespass and shall make good at his own expense all loss or
damage whether to the works themselves or to any other property of RLDA or the lives, persons or
property of others from whatsoever cause in connection with the works until they are taken over by
RLDA, although all reasonable and proper precautions may have been taken by the Contractor. In case
RLDA shall be called upon to make good any costs, loss or damages, or to pay any compensation,
including that payable under the provisions of the Workmen's Compensation Act or any statutory
amendments thereof to any person or persons sustaining damages as aforesaid by reason of any act, or
175
any negligence or omissions on the part of the Contractor; the amount of any costs or charges including
costs and charges in connection with legal proceedings, which RLDA may incur in reference thereto,
shall be charged to the Contractor. RLDA shall have the power and right to pay or to defend or
compromise any claim of threatened legal proceedings or in anticipation of legal proceedings being
instituted consequent on the action or default of the Contractor, to take such steps as may be considered
necessary or desirable to ward off or mitigate the effect of such proceedings, charging to Contractor,
as aforesaid; any sum or sums of money which may be paid and any expenses whether for
reinstatement or otherwise which may be incurred and the propriety of any such payment, defence or
compromise, and the incurring of any such expenses shall not be called in question by the Contractor.
25. Sheds, Storehouses and Yards: The Contractor shall at his own expense provide himself
with sheds, storehouses and yards in such situations and in such numbers as in the opinion of the
Engineer is requisite for carrying on the works and the Contractor shall keep at each such sheds,
storehouses and yards a sufficient quantity of materials and plant in stock as not to delay the carrying
out of the works with due expedition and the Engineer and the Engineer's representative shall have
free access to the said sheds, store houses and yards at any time for the purpose of inspecting the stock
of materials or plant so kept in hand, and any materials or plant which the Engineer may object to shall
not be brought upon or used in the works, but shall be forthwith removed from the sheds, storehouses
or yards by the Contractor. The Contractor shall at his own expenses provide and maintain suitable
mortar mills, soaking vats or any other equipments necessary for the execution of the works.
26. Provision of Efficient and Competent Staff at Work Sites by the Contractor:
26.1 The Contractor shall place and keep on the works at all times efficient and competent staff to
give the necessary directions to his workmen and to see that they execute their work in sound & proper
manner and shall employ only such supervisors, workmen & labourers in or about the execution of
any of these works as are careful and skilled in the various trades.
26.2 The Contractor shall at once remove from the works any agents, permitted sub-contractor,
supervisor, workman or labourer who shall be objected to by the Engineer and if and whenever
required by the Engineer, he shall submit a correct return showing the names of all staff and workmen
employed by him.
26.3 In the event of the Engineer being of the opinion that the Contractor is not employing on the
works a sufficient number of staff and workmen as is necessary for proper completion of the works
within the time prescribed, the Contractor shall forthwith on receiving intimation to this effect deploy
the additional number of staff and labour as specified by the Engineer within seven days of being so
required and failure on the part of the Contractor to comply with such instructions will entitle RLDA
to rescind the contract under Clause 62 of these conditions.
176
27.(1) Workmanship and Testing: The whole of the works and/or supply of materials specified
and provided in the contract or that may be necessary to be done in order to form and complete any
part thereof shall be executed in the best and most substantial workman like manner with materials of
the best and most approved quality of their respective kinds, agreeable to the particulars contained in
or implied by the specifications and as referred to in and represented by the drawings or in such other
additional particulars, instructions and drawings given during the carrying on of the works and to the
entire satisfaction of the Engineer according to the instructions and directions which the Contractors
may from time to time receive from the Engineer. The materials may be subjected to tests at the NABL
approved external laboratory of repute by means of such machines, instruments and appliances as the
Engineer may direct and wholly at the expense of the Contractor.
27.(2) Removal of Improper Work and Materials: The Engineer or the Engineer's Representative
shall be entitled to order from time to time:
(a) The removal from the site, within the time specified in the order, of any materials which in his
opinion are not in accordance with the specifications or drawings.
(c) the removal and proper re-execution, notwithstanding any previous tests thereof or on account
payments therefor, of any work which in respect of materials or workmanship is not in his opinion in
accordance with the specifications and in case of default on the part of the Contractor in carrying out
such order, RLDA shall be entitled to rescind the contract under Clause 62 of these conditions.
(d) The provision of Construction and Demolition Waste Management Rule 2016 issued by Ministry
of Environment Forest and Climate Change dated 29.03.2016 and published in the Gazette of India,
Part – II, Section -3, Sub-section (ii) are binding upon the Contractor. Contractor shall implement these
provisions at worksites, for which no extra payment will be payable.
28. Facilities for Inspection: The Contractor shall afford the Engineer and the Engineer's
Representative every facility for entering in and upon every portion of the work at all hours for the
purpose of inspection or otherwise and shall provide all labour, materials, planks, ladders, pumps,
appliances and things of every kind required for the purpose and the Engineer and the Engineer's
Representative shall at all times have free access to every part of the works and to all places at which
materials for the works are stored or being prepared.
29. Examination of Work before Covering Up: The Contractor shall give 7 days’ notice to the
Engineer or the Engineer's Representative whenever any work or materials are intended to be covered
up in the earth, in bodies or walls or otherwise to be placed beyond the reach of measurements in order
that the work may be inspected or that correct dimensions may be taken before being so covered,
placed beyond the reach of measurement in default whereof, the same shall at the option of the
Engineer or the Engineer's Representative be uncovered and measured at the Contractor's expense or
no allowance shall be made for such work or materials.
30. Temporary Works: All temporary works necessary for the proper execution of the works shall
be provided and maintained by the Contractor and subject to the consent of the Engineer shall be
removed by him at his expenses when they are no longer required and in such manner as the Engineer
177
shall direct. In the event of failure on the part of the Contractor to remove the temporary works, the
Engineer will cause them to be removed and cost as increased by supervision and other incidental
charges shall be recovered from the Contractor. If temporary huts are provided by the Contractor on
RLDA land for labour engaged by him for the execution of works, the Contractor shall arrange for
handing over vacant possession of the said land after the work is completed; if the Contractor's labour
refuse to vacate, and have to be evicted by RLDA, necessary expenses incurred by RLDA in
connection therewith shall be borne by the Contractor.
31.(1) Contractor to Supply Water for Works: Unless otherwise provided in the Contract, the
Contractor shall be responsible for the arrangements to obtain supply of water necessary for the works.
31.(2) Water Supply from Railway System: Railway may supply to the Contractor part or whole
of the quantity of the water required for the execution of works from Railway existing water supply
system at or near the site of works on specified terms and conditions and at such charges as shall be
determined by Railway and payable by the Contractor, provided that the Contractor shall arrange, at
his own expense, to effect the connections and lay additional pipelines and accessories on the site and
that the Contractor shall not be entitled to any compensation for interruption of failure of the water
supply.
31.(3) Water Supply by Railway Transport: In the event of RLDA arranging supply of water to the
Contractor at or near the site of works by travelling water tanks or other means, the freight and other
charges incurred thereby, including demurrage charges that may be levied, shall be paid by the
Contractor in addition to the charges referred to in Sub-Clause (2) of the Clause provided that the
Contractor shall not be entitled to any compensation for interruption or failure of the water supply.
31.(4)(a) Contractor to Arrange Supply of Electric Power for Works: Unless otherwise
provided in the contract, the Contractor shall be responsible for arrangements to obtain supply of
Electric Power for the works.
Railway may supply to the Contractor part or whole of the electric power wherever available and
possible, required for execution of works from RLDA's existing electric supply systems at or near the
site of works on specified terms and conditions and such charges as shall be determined by Railway
and payable by the Contractor provided the cost of arranging necessary connections to Railway’s
Electric Supply systems and laying of underground/overhead conductor, circuit protection, electric
power meters, transmission structure, shall be borne by the Contractor and that the Contractor shall
not be entitled to any compensation for interruption or failure of the Electric supply system.
32. Property in Materials and Plant: The materials and plant brought by the Contractor upon the
site or on the land occupied by the Contractor in connection with the works and intended to be used
for the execution thereof shall immediately be deemed to be the property of RLDA. Such of them as
during the progress of the works are rejected by the Engineer under Clause 25 of these conditions or
are declared by him not to be needed for the execution of the works or such as on the grant of the
certificate of completion remain unused shall immediately on such rejection, declaration or grant cease
to be deemed the property of RLDA and the Contractor may then (but not before) remove them from
the site or the said land. This clause shall not in any way diminish the liability of the Contractor nor
shall RLDA be in any way answerable for any loss or damage which may happen to or in respect of
178
any such materials or plant either by the same being lost, stolen, injured or destroyed by fire, tempest
or otherwise.
The Contractor shall take all reasonable care of all tools, plant and materials or other property whether
of a like description or not belonging to RLDA and committed to his charge for the purpose of the
works and shall be responsible for all damage or loss caused by him, his agents, permitted sub-
contractor, or his workmen or others while they are in his charge. The Contractors shall sign
accountable receipts for tools, plants and materials made over to him by the Engineer and on
completion of the works shall hand over the unused balance of the same to the Engineer in good order
and repair, fair wear and tear excepted, and shall be responsible for any failure to account for the same
or any damage done thereto.
RLDA may hire to the Contractor such plant as concrete mixers, compressors and portable engines for
use during execution of the works on such terms as may be specified in the special conditions or in a
separate agreement for Hire of Plant.
34.(1) Precaution During Progress of Works: During the execution of works, unless otherwise
specified, the Contractor shall at his own cost provide the materials for and execute all shoring,
timbering and strutting works as is necessary for the stability and safety of all structures, excavations
and works and shall ensure that no damage, injury or loss is caused or likely to be caused to any person
or property.
34.(2) Roads and Water Courses: Existing roads or water courses shall not be blocked cut through,
altered, diverted or obstructed in any way by the Contractor, except with the permission of the
Engineer. All compensations claimed for any unauthorized closure, cutting through, alteration,
diversion or obstruction to such roads or water courses by the Contractor or his agent or his staff shall
be recoverable from the Contractor’s bills/Security Deposit or any other dues of Contractor with the
Government of India.
34.(3) Provision of Access to Premises: During progress of work in any street or thoroughfare, the
Contractor shall make adequate provision for the passage of traffic, for securing safe access to all
premises approached from such street or thoroughfare and for any drainage, water supply or means of
lighting which may be interrupted by reasons of the execution of the works and shall react and maintain
at his own cost barriers, lights and other safeguards as prescribed by the Engineer, for the regulation
of the traffic, and provide watchmen necessary to prevent accidents. The works shall in such cases be
executed night and day, if so ordered by the Engineer and with such vigour so that the traffic way be
impeded for as short a time as possible.
34.(4) Safety of Public: The Contractor shall be responsible to take all precautions to ensure the
safety of the public whether on public or RLDA property and shall post such look out men as may, in
the opinion of the Engineer, be required to comply with regulations appertaining to the work.
Contractor shall ensure placement of barricading / partitions at the place of work to ensure safety of
habitants of adjacent area, failing which Engineer may advise stoppage of work as per his discretion.
179
34.(5) Display Board: The Contractor shall be responsible for displaying the details of works i.e. name
of work, approximate cost, expected date of completion, name and address of the Contractor and
address of Engineer on a proper steel Board of size not less than 1m x 1m.
35. Use of Explosives: Explosives shall not be used on the works or on the site by the Contractor
without the permission of the Engineer and then also only in the manner and to the extent to which
such permission is given. Where explosives are required for the works, they shall be stored in a special
magazine to be provided by and at the cost of the Contractor in accordance with the Explosive Rules.
The Contractor shall obtain the necessary license for the storage and the use of explosives. All
operations in which or for which explosives are employed shall be at the sole risk and responsibility
of the Contractor and the Contractor shall indemnify RLDA in respect thereof.
36.(1) Suspension of Works: The Contractor shall on the order of the Engineer, suspend the
progress of the works or any part thereof for such time or times and in such manner as the Engineer
may consider necessary and shall during such suspension properly protect and secure the work so far
as is necessary in the opinion of the Engineer. If such suspension is:
36.(3) Suspension Lasting More than 3 Months: If the progress of the works or any part thereof
is suspended on the order of the Engineer for more than three months at a time, the Contractor may
serve a written notice on the Engineer requiring permission within 15 days from the receipt thereof to
proceed with the works or that part thereof in regard to which progress is suspended and if such
permission is not granted within that time the Contractor by further written notice so served may, but
is not bound to, elect to treat the suspension where it affects part only of the works as an omission of
such part or where it affects the whole of the works, as an abandonment of the contract by RLDA.
180
(i) The rates, entered in the accepted Bill(s) of Quantities of the Contract are intended to provide
for works duly and properly completed in accordance with the General and Special (if any)
Conditions of the Contract and the Specifications and drawings together with such
enlargements, extensions, diminutions, reductions, alterations or additions as may be ordered in
terms of Clause 42 of these conditions and without prejudice to the generality thereof and shall
be deemed to include and cover superintendence and labour, supply, including full freight of
materials, stores, patterns, profiles, moulds, fittings, centerings, scaffolding, shoring props,
timber, machinery, barracks, tackle, roads, pegs, posts, tools and all apparatus and plant required
on the works, except such tools, plant or materials as may be specified in the contract to be
supplied to the Contractor by RLDA, the erection, maintenance and removal of all temporary
works and buildings, all watching, lighting, bailing, pumping and draining, all prevention of or
compensation for trespass, all barriers and arrangements for the safety of the public or of
employees during the execution of works, all sanitary and medical arrangements for labour
camps as may be prescribed by RLDA, the setting of all work and of the construction, repair
and upkeep of all center lines, bench marks and level pegs thereon, site clearance, all fees duties,
royalties, rent and compensation to owners for surface damage or taxes and impositions payable
to local authorities in respect of land, structures and all material supplied for the work or other
duties or expenses for which the Contractor may become liable or may be put to under any
provision of law for the purpose of or in connection with the execution of the contract and all
such other incidental charges or contingencies as may have been specially provided for in the
Specifications.
However, if rates of existing GST or cess on GST for Works Contract is increased or any new
tax /cess on Works Contract is imposed by Statute after the date of opening of tender but within
the original date of completion/date of completion extended under clause 17 & 17A and the
Contractor thereupon properly pays such taxes/cess, the Contractor shall be reimbursed the
amount so paid.
Further, if rates of existing GST or cess on GST for Works Contract is decreased or any
tax/cess on Works Contract is decreased / removed by Statute after the date of opening of
tender, the reduction in tax amount shall be recovered from Contractor’s bills/Security Deposit
or any other dues of Contractor with the Government of India.
38. Demurrage and Wharfage Dues: Demurrage charges calculated in accordance with the scale
in force for the time being on RLDA and incurred by the Contractor failing to load or unload
any goods or materials within the time allowed by RLDA for loading as also wharfage charges,
of materials not removed in time, as also charges due on consignments booked by or to him
shall be paid by the Contractor, failing which such charges shall be debited to the Contractor's
account in the hands of RLDA and shall be deducted from any sums which may become due
to him in terms of the contracts.
181
of Rates (SSOR)" modified by the tender percentage as accepted in the contract for that
chapter of Standard Schedule of Rates (SSOR). However, the cumulative value of all such
extra item(s) together (modified by the respective tender percentage) shall not exceed 10 % of
the original contract value.
For item(s) not covered in this sub clause, the rate shall be decided as agreed upon between
the Engineer and the Contractor before the execution of such items of work as per sub clause
(b).
(b) Other Items: For any item of work to be carried out by the Contractor but not included in the
accepted Bill(s) of Quantities and also not covered under sub clause (a) above, the Contractor
shall be bound to notify the Engineer at least seven days before the necessity arises for the
execution of such items of works that the accepted Bill(s) of Quantities does not include rate
or rates for such extra work involved. The rates payable for such items shall be decided at the
meeting to be held between the Engineer and Contractor, in as short a period as possible after
the need for the special item has come to the notice. In case the Contractor fails to attend the
meeting after being notified to do so or in the event of no settlement being arrived at, RLDA
shall be entitled to execute the extra works by other means and the Contractor shall have no
claim for loss or damage that may result from such procedure.
The assessment of rates for extra item(s) shall be arrived at based on the prevailing market rates
of labour, machinery & materials and by taking guidance from the following documents in
order of priority:
i. Analysis of Rates for “Delhi Schedule of Rates issued by CPWD (DSR)”
ii. Analysis of Rates for “Unified Standard Schedule of Rates of Indian Railways (USSOR)”
iii. Market Analysis
39.(2) Provided that if the Contractor commences work or incurs any expenditure in regard thereto
before the rates as determined and agreed upon as lastly here unto fore-mentioned, then and in
such a case the Contractor shall only be entitled to be paid in respect of the work carried out or
expenditure incurred by him prior to the date of determination of the rates as aforesaid
according to the rates as shall be fixed by the Engineer. However, if the Contractor is not
satisfied with the decision of the Engineer in this respect, he may appeal to the General
Manager/Chief Project Manager/Chief Engineer within 30 days of getting the decision of the
Engineer, supported by analysis of the rates claimed. The General Manager/Chief Project
Manager/Chief Engineer decision after hearing both the parties in the matter would be final
and binding on the Contractor and RLDA.
40.(1) Handing over of Works: The Contractor shall be bound to hand over the works executed
under the contract to RLDA complete in all respects to the satisfaction of the Engineer. The
Engineer shall determine the date on which the work is considered to have been completed, in
support of which his certificate shall be regarded as sufficient evidence for all purposes. The
Engineer shall determine from time to time, the date on which any particular section of the
work shall have been completed, and the Contractor shall be bound to observe any such
determination of the Engineer.
40.(2) Clearance of Site on Completion: On completion of the works, the Contractor shall clear
away and remove from the site all constructional plant, surplus materials, rubbish and
182
temporary works of every kind and leave the whole of the site and works clean and in a
workman like condition to the satisfaction of the Engineer. No final payment in settlement of
the accounts for the works shall be paid, held to be due or shall be made to the, Contractor till,
in addition to any other condition necessary for final payment, site clearance shall have been
affected by him, and such clearance may be made by the Engineer at the expense of the
Contractor in the event of his failure to comply with this provision within 7 days after
receiving notice to that effect. Should it become necessary for the Engineer to have the site
cleared at the expenses of the Contractor, RLDA shall not be held liable for any loss or damage
to such of the Contractor's property as may be on the site and due to such removal there from
which removal may be affected by means of public sales of such materials and property or in
such a way as deemed fit and convenient to the Engineer.
40A Offloading of Part(s) of Work: At the final stage of completion/ commissioning of work, in
case the contractor fails to complete the final part(s) of the work and the value of such part(s)
of the work is limited to 5% of the original contract value, the Engineer may allow/decide for
offloading of such part(s) of works, either after the Contractor’s request in writing to do so or
after serving a 14 (Fourteen) days suo-moto notice (as per annexure- VIIA), if the Engineer is
of the opinion that :-
(i) Such Offloading of works (up to 5% of original contract value) would enable successful
completion of contract/work,
(ii) Termination/ Part termination of the contract at this stage is not be in the interest of
RLDA/work;, and
(iii) The anticipated additional cost for execution of such works through other mode would not
be substantial and can be recovered from the pending dues of the contractor;
The Contractor shall be informed, in due course, by the Engineer of the mode and cost of execution
of such offloaded work through other agency(ies) (as per annexure- VIIB). The extra expenditure
so incurred in execution of the offloaded work, shall be recovered from subsequent Bill(s) or any
other dues of the Contractor, but not exceeding the value of Performance Guarantee available in the
contract. There shall be no other repercussion of such offloading on execution of the balance
contract. The Contractor shall have no claim on account of above mentioned offloading of works.
41. Modification to Contract to be in Writing: In the event of any of the provisions of the contract
required to be modified after the contract documents have been signed, the modifications shall
be made in writing and signed by RLDA and the Contractor and no work shall proceed under
such modifications until this has been done. Any verbal or written arrangement abandoning,
modifying, extending, reducing or supplementing the contract or any of the terms thereof shall
be deemed conditional and shall not be binding on RLDA unless and until the same is
incorporated in a formal instrument and signed by RLDA and the Contractor, and till then RLDA
shall have the right to repudiate such arrangements.
42.(1) Powers of Modification to Contract: The Engineer on behalf of RLDA shall be entitled by
order in writing to enlarge or extend, diminish or reduce the works or make any alterations in
183
their design, character position, site, quantities, dimensions or in the method of their execution
or in the combination and use of materials for the execution thereof or to order any additional
work to be done or any works not to be done and the Contractor will not be entitled, to any
compensation for any increase/reduction in the quantities of work but will be paid only for the
actual amount of work done and for approved materials supplied against a specific order.
42.(2) (i) Unless otherwise specified in the special conditions of the contract, the accepted variation
in quantity of each individual item of the contract would be upto 25% of the quantity
originally contracted, except in case of foundation work (in which no variation limit shall
apply). However, the rates for the increased quantities shall be as per sub- para (iii) below.
(ii) The Contractor shall be bound to carry out the work at the agreed rates and shall not be
entitled to any claim or any compensation whatsoever upto the limit of 25% variation in
quantity of individual item of works.
(iii) In case an increase in quantity of an individual item by more than 25% of the agreement
quantity is considered unavoidable, then same shall be executed at following rates
a. Quantities operated in excess of 125% but upto 140% of the agreement quantity of the
concerned item, shall be paid at 98% of the rate awarded for that item in that particular
tender;
b. Quantities operated in excess of 140% but upto 150% of the agreement quantity of the
concerned item shall be paid at 96% of the rate awarded for that item in that particular
tender;
c. Variation in quantities of individual items beyond 150% will be avoided and would be
permitted only in exceptional unavoidable circumstances and shall be paid at 96% of the
rate awarded for that item in that particular tender.
d. Variation to quantities of Minor Value Item:
The limit for varying quantities for minor value items shall be 100% (as against 25%
prescribed for other items). A minor value item for this purpose is defined as an item whose
original agreement value is less than 1 % of the total original contract value.
d.(i) Quantities operated upto and including 100% of the agreement quantity of the concerned
minor value item, shall be paid at the rate awarded for that item in that particular tender;
d.(ii) Quantities operated in excess of 100% but upto 200% of the agreement quantity of the
concerned minor value item, shall be paid at 98% of the rate awarded for that item in
that particular tender;
d.(iii) Variation in quantities of individual minor value item beyond 200% will be avoided and
would be permitted only in exceptional unavoidable circumstances and shall be paid at
96% of the rate awarded for that item in that particular tender.
(iv) In case of earthwork items, the variation limit of 25% shall apply to the gross quantity of
earthwork items and variation in the quantities of individual classifications of soil shall not be
subject to this limit.
(v) As far as DSR of CPWD/Standard Schedule of Rates (SSOR) items are concerned, the
variation limit of 25% would apply to the value of SSOR schedule(s) as a whole and not on
individual DSR/SSOR items. However, in case of Non Standard Schedule of Rates (SSOR)
items, the limit of 25% would apply on the individual items irrespective of the manner of
quoting the rate (single percentage rate or individual item rate).
184
42.(3) Valuation of Variations: The enlargements, extensions, diminution, reduction, alterations or
additions referred to in Sub-Clause (2) of this Clause shall in no degree affect the validity of the
contract; but shall be performed by the Contractor as provided therein and be subject to the same
conditions, stipulations and obligations as if they had been originally and expressively included
and provided for in the Specifications and Drawings and the amounts to be paid therefor shall be
calculated in accordance with the accepted Bill(s) of Quantities. Any extra item(s)/quantities of
work falling outside the purview of the provisions of Sub-Clause (2) above shall be paid for at the
rates determined under Clause-39 of these Conditions.
CLAIMS
43.(1) Quarterly Statement of Claims: The Contractor shall prepare and furnish to the Engineer
once in every quarter commencing from the month following the month of issue of Letter of
Acceptance, an account giving full and detailed particulars of all claims for any additional expenses to
which the Contractor may consider himself entitled to and of all extra or additional works ordered by
the Engineer which he has executed during the preceding quarter and no claim for payment for such
work will be considered which has not been included in such particulars.
43.(2) Signing of "No Claim" Certificate : The Contractor shall not be entitled to make any claim
whatsoever against RLDA under or by virtue of or arising out of this contract, nor shall RLDA entertain
or consider any such claim, if made by the Contractor, after he shall have signed a "No Claim"
Certificate in favour of RLDA in such form as shall be required by RLDA after the works are finally
measured up. The Contactor shall be debarred from disputing the correctness of the items covered by
"No Claim" Certificate or demanding a clearance to arbitration in respect thereof.
185
(a) It shall be open to the Contractor to take specific objection to any recorded measurements or
Classification on any ground within seven days of the date of such measurements. Any re-measurement
taken by the Engineer or the Engineer's representative in the presence of the Contractor or in his
absence after due notice has been given to him in consequence of objection made by the Contractor
shall be final and binding on the Contractor and no claim whatsoever shall thereafter be entertained
regarding the accuracy and Classification of the measurements.
(b) If an objection raised by the Contractor is found by the Engineer to be incorrect the Contractor
shall be liable to pay the actual expenses incurred in measurements.
45(ii). Measurement of Works by Contractor’s Authorized Representative (in case the contract
provides for the same):
(a) The Contractor shall be paid for the works at the rates in the accepted Bill(s) of Quantities and for
extra works at rates determined under Clause 39 of these Conditions on the measurements taken by
the Contractor’s authorized Engineer in accordance with the rules prescribed for the purpose by
RLDA. The quantities for items the unit of which in the accepted Bill(s) of Quantities is 100 or
1000 shall be calculated to the nearest whole number, any fraction below half being dropped and
half and above being taken as one; for items the unit of which in the accepted Bill(s) of Quantities
is single, the quantities shall be calculated to two places of decimals. Such measurements will be
taken of the work in progress from time to time. The date and time on which ‘on account’ or ‘final’
measurements are to be made shall be communicated to the Engineer.
The date and time of test checks shall be communicated to the Contractor who shall be present at
the site and shall witness the test checks, failing the Contractor’s attendance the test checks may be
conducted in his absence and such test checks shall not withstanding such absence be binding upon
Contractor provided always that any objection made by Contractor to test check shall be duly
investigated and considered in the manner set out below:
(i) It shall be open to the Contractor to take specific objection to test checks of any recorded
measurement within 7 days of date of such test checks. Any re-test check done by the concerned
RLDA’s authority in the presence of the Contractor or in his absence after due notice given to
him in consequent of objection made by the Contractor shall be final and binding on the
Contractor and no claim whatsoever shall thereafter be entertained regarding the accuracy and
classification of the measurements.
(ii) If an objection raised by the Contractor is found by the Engineer to be incorrect the Contractor
shall be liable to pay the actual expenses incurred in measurements.
(b) Incorrect measurement, actions to be taken: If in case during test check or otherwise, it is
detected by the Engineer that agency has claimed any exaggerated measurement or has claimed
any false measurement for the works which have not been executed; amounting to variation of 5%
or more of claimed gross bill amount, action shall be taken as following:
(i) On first occasion of noticing exaggerated/ false measurement, Engineer shall recover liquidated
damages equal to 10% of claimed gross bill value.
(ii) On any next occasion of noticing any exaggerated/false measurement, RLDA shall recover
liquidated damages equal to 15% of claimed gross bill value. In addition, the facility of
recording of measurements by Contractor as well as release of provisional payment shall be
withdrawn. Once withdrawn, measurements shall be done by RLDA as per clause 45(i) above.
186
46.(1) "On-Account " Payments: The Contractor shall be entitled to be paid from time to time by
way of "On-Account" payment only for such works as in the opinion of the Engineer he has executed
in terms of the contract but not less than Rs.10.0 Cr. as the gross value of completed work of each
running account bill. All payments due on the Engineer’s/Engineer's Representative's certificates of
measurements or Engineer’s certified “Contractor’s authorized Engineer’s measurements” shall be
subject to any deductions which may be made under these presents and shall further be subject to,
unless otherwise required by Clause 16 of these Conditions, a retention of 6% (six percent) by way of
Security Deposits, until the amount of Security Deposit by way of such retentions shall amount to 5%
of the total value of the contract provided always that the Engineer may by any certificate make any
correction or modification in any previous certificate which shall have been issued by him and that the
Engineer may withhold any certificate, if the works or any part thereof are not being carried out to his
satisfaction.
46.(2) Rounding off Amounts: The total amount due on each certificate shall be rounded off to the
nearest rupee, i.e. sum less than 50 paise shall be omitted and sums of 50 paise and more upto ₹1 will
be reckoned as ₹ 1.
46.(3) On Account Payments not Prejudicial to Final Settlement: "On-Account" payments made
to the Contractor shall be without prejudice to the final making up of the accounts (except where
measurements are specifically noted in the Measurement Book as "Final Measurements" and as such
have been signed by the Contractor and Engineer/Engineer's Representative) and shall in no respect
be considered or used as evidence of any facts stated in or to be inferred from such accounts nor of
any particular quantity of work having been executed nor of the manner of its execution being
satisfactory.
46.(4) If payment(s) of Advances are applicable in the contract, as mentioned in the Tender
Documents, RLDA shall make payment(s) of Interest bearing advances, on the request of contractor.
The payment and recovery of such Advances shall be made as under:
(a): Mobilisation Advance –
This shall be limited to 10% of the Contract value and shall be paid in 2 stages :
Stage 1– 5% of Contract Value on signing of the contract agreement.
Stage 2 – 5% on mobilization of site-establishment, setting up offices, bringing in equipment
and actual commencement of work.
The stage 1 of advance shall be payable immediately after signing of contract agreement.
The stage 2 of advance shall be payable at the time of mobilisation, only after submission of an
utilization certificate by the contractor that the Stage 1 advance has been properly utilized in the
contract.
These Advances shall be payable against irrevocable guarantee (Bank Guarantee, FDRs) from a
scheduled commercial bank of India of at least 110% of the value of the sanctioned advance
amount (covering principal plus interest).
(b): Advance Against Machinery and Equipment –
This advance shall be limited to a maximum of 10% of the contract value against new Machinery
& Equipment, involving substantial outlay, brought to site and essentially required for the work.
187
This advance shall not exceed 75% of the purchase price of such Equipment and shall be payable
when Equipment is hypothecated to RLDA by a suitable bond or alternatively covered by an
irrevocable Bank Guarantee from a scheduled commercial bank of India for full cost of the Plant &
Equipment in a form acceptable to RLDAs. The Plant & Equipment shall be insured for the full
value and for the entire period, they are required for the work. This Plant & Equipment shall not
be removed from the site of work without prior written permission of the Engineer. No advance
should be given against old Plant & Machinery.
The advances under sub clause (a) and (b) above, are subject to the following conditions -
(i) The full amount of Advances shall be recovered from contractor dues. The recovery shall
commence when the value of contract executed reaches 15% of original contract value and shall
be completed when the value of work executed reaches 85% of the original contract value. The
instalments on each "on account bill" will be on pro-rata basis.
Interest shall be recovered on the advance outstanding for the period commencing from the
date of payment of advance till date of particular on-account bill (through which recovery of
principal is effected) and adjusted fully against on-account bill along with pro-rata principal
recovery. In the event of any short-fall, the same shall be carried forward to the next on-account
bill and shall attract interest.
(ii) The advances shall be used by the Contractor for the purpose of the Contract, and for the
purpose for which they are paid. Under no circumstances, shall the advances be diverted for other
purposes. Any such diversion shall be construed as a breach of the Contract and the Contractor
shall be asked to return the advance at once and pay interest at 15% per annum till the advance is
recovered back from him. The Contractor shall return the advance and pay the interest in one go
without demur. The Contractor, if required by the Engineer shall provide the details of utilisation
of Mobilisation advance.
(iii) If the Contractor is found to have contravened the provision, it will constitute a breach of
contract and RLDA shall be entitled to terminate the contract and forfeit his Performance
Guarantee as well as Security Deposit.
(iv) In cases, where the Contract is rescinded as per clause 62 of the contract or short closed under
any other condition(s) of the contract, without making full recovery of advances and accrued
interest thereon, by RLDA, such balance of advances and accrued interest thereon shall
immediately become due and payable by the Contractor to RLDA. The same shall be recovered
from any due of Contractor with the Government of India.
46.(5) Manner of Payment: Unless otherwise specified payments to the Contractor will be
transferred electronically to his bank account. The Bank Account details is to be submitted by the
Bidder for electronic Transfer of the specified due payments.
188
46A.1 Applicability: Price Variation Clause (PVC) shall be applicable only in tender having
advertised value above Rs. 2 Crores. Provided further that, in a contract where PVC is applicable,
following shall be outside the purview of price adjustments (i.e. shall be excluded from the gross value
of the work for the purpose of price variation) :
46A.2 Base Month: The Base Month for ‘Price Variation Clause’ shall be taken as the one month
prior to closing of tender, unless otherwise stated elsewhere. The quarter for applicability of PVC shall
commence from the month following the Base month. The Price Variation shall be based on the
average Price Index of the quarter under consideration.
46A.3 Validity:
Rates accepted by RLDA Administration shall hold good till completion of work and no additional
individual claim shall be admissible except:
46A.4 Components of various items in a contract on which variation in prices be admissible, shall be
steel, cement, ferrous material, non-ferrous material, insulators, zinc and other materials, labour, plant
& machinery, fuel, explosives, detonators etc. Adjustment for variation in prices of these items shall
be determined in the manner prescribed.
46A.6 The percentages of various components in various type of works shall be as specified for all
item (s)/ Bill(s) of Quantities in tender document and the same shall be fixed as per table &
classifications given below:
1B, 1C,
Classification 3D, 3E,
3B, 3C,
4D, 4E,
1A, 4B, 4C,
S 5D, 5E,
5B, 5C,
2& 4A 5A 6A 7 8A 9A 6D, 6E,
N 6B 6C,
3A 8D 8E
8B 8C
& &
Components & &
9D 9E
9B 9C
1 Fixed * 15 15 15 15 15 15 15 15 15 15 15
2 Labour Lc 20 25 30 20 50 20 20 0 0 10 25
3 Steel Sc 0 0 0 0 0 0 0 85 0 50 0
4 Cement Cc 0 0 15 0 0 0 0 0 85 0 0
189
5 Plant
Machinery PMc 30 15 5 20 15 20 30 0 0 10 30
& Spares
6 Fuel &
Fc 25 15 5 15 15 20 15 0 0 10 20
Lubricants
7 Other
Mc 10 15 30 30 5 25 20 0 0 5 10
materials
8 Detonators
& Ec 0 15 0 0 0 0 0 0 0 0 0
Explosive
Total 100 100 100 100 100 100 100 100 100 100 100
* It shall not be considered for any price variation.
The classification mentioned in the table above represents following type of item(s) in the work(s) –
1 Earthwork in Formation
1A All Item(s) excluding 1B or/and 1C
1B Item(s) for supply of Steel
1C Item(s) for supply of Cement
2 Ballast Supply Works
3 Tunnelling Works (Without Explosives)
3A All Item(s) excluding 3B or/and 3C or/and 3D or/and 3E
3B Item(s) for supply of Steel
3C Item(s) for supply of Cement or/and Grout
3D Item(s) for Fabrication & Erection of Structures including supply of Steel
3E Item(s) for Fabrication & Erection of Structures excluding supply of Steel.
4 Tunnelling Works (With explosives)
4A All Item(s) excluding 4B or/and 4C or/and 4D or/and 4E
4B Item(s) for supply of Steel
4C Item(s) for supply of Cement or/and Grout
4D Item(s) for Fabrication & Erection of Structures including supply of Steel
4E Item(s) for Fabrication & Erection of Structures excluding supply of Steel.
5 Building Works
5A All Item(s) excluding 5B or/and 5C or/and 5D or/and 5E
5B Item(s) for supply of Steel
5C Item(s) for supply of Cement
5D Item(s) for Fabrication & Erection of Structures including supply of Steel
5E Item(s) for Fabrication & Erection of Structures excluding supply of Steel.
6 Bridges & Protection work
6A All Item(s) excluding 6B or/and 6C or/and 6D or/and 6E
6B Item(s) for supply of Steel
6C Item(s) for supply of Cement
6D Item(s) for Fabrication, Assembly, Erection& Launching of Girders including supply of
Steel
6E Item(s) for Fabrication, Assembly, Erection &Launching of Girders excluding supply of
Steel
190
7 Permanent Way linking
8 Platform, Passenger Amenities
8A All Item(s) excluding 8B or/and 8C or/and 8D or/and 8E
8B Item(s) for supply of Steel item/fittings
8C Item(s) for supply of Cement Item
8D Item(s) for Fabrication & Erection of Structures including supply of Steel
8E Item(s) for Fabrication & Erection of Structures excluding supply of Steel
9 Any Other Works not covered in Classification 1 to 8
9A All Item(s) excluding 9B or/and 9C or/and 9D or/and 9E
9B Item(s) for supply of Steel
9C Item(s) for supply of Cement or/and Grout
9D Item(s) for Fabrication & Erection of Structures including supply of Steel
9E Item(s) for Fabrication & Erection of Structures excluding supply of Steel
46A.7 Formulae: The Amount of variation in prices in various components (labour, material etc.)
shall be worked out by the following formulae:
(i) L = (W or WSF or WF or WSFL or WFL) x (LQ – LB) x LC
LB x 100
191
Where,
L Amount of price variation in Labour
M Amount of price variation in Materials
F Amount of price variation in Fuel
E Amount of price variation in Explosives
PM Amount of price variation in Plant, Machinery and Spares
S Amount of price variation in Steel Supply Item
C Amount of price variation in Cement Supply Item
T Percentage variation payable on the gross value of bill of Concreting (Bill(s) of
Quantities for concrete items)
R Percentage variation payable on the gross value of bill of Ferrous Items (Bill(s) of
Quantities for ferrous items)
N Percentage variation payable on the gross value of bill of Non-Ferrous Items (Bill(s)
of Quantities for non-ferrous items)
I Percentage variation payable on the gross value of bill of Insulator (Bill(s) of
Quantities for Insulator items)
G Percentage variation payable on the gross value of bill of General Works (Bill(s) of
Quantities for General items)
Er Percentage variation payable on the gross value of erection (Bill(s) of Quantities for
Erection Item)
LC % of Labour Component in the item(s)
MC % of Material Component in the item(s)
FC % of Fuel Component in the item(s)
EC % of Explosive Component in the item(s)
PMC % of Plant, Machinery and Spares Component in the item(s)
SC % of Steel Supply item Component in the item(s)
CC % of Cement Supply item Component in the item(s)
W Gross value of work done by Contractor as per on-account bill(s) excluding the
Gross value of work under WS or/and WC or/and WSF or/and WF or/and WSFL or/and
WFL and cost of materials supplied by RLDA either free or at fixed rate,
WS Gross value of work done by Contractor for item(s) of supply of steel.
WC Gross value of work done by Contractor for item(s) of supply of cement and /or
supply of grout material.
WSF Gross value of work done by Contractor for item(s) of Fabrication & Erection of
Structures including supply of Steel.
WF Gross value of work done by Contractor for Fabrication & Erection of Structures
excluding supply of Steel.
192
WSFL Gross value of work done by Contractor for item(s) of Fabrication, Assembly,
Erection / Launching of Girders including supply of Steel.
WFL Gross value of work done by Contractor for item(s) of Fabrication, Assembly,
Erection / Launching of Girders excluding supply of Steel.
LB Consumer Price Index for Industrial Workers - All India: Published in R.B.I.
Bulletin for the base period
LQ Consumer Price Index for Industrial Workers - All India: Published in R.B.I.
Bulletin for the average price index of the 3 months of the quarter under
consideration
MB Wholesale Price Index: All commodities – as published in the R.B.I. Bulletin for the
base period
MQ Wholesale Price Index: All commodities – as published in the R.B.I. Bulletin for the
average price index of the 3 months of the quarter under consideration
FB The average of official prices of Diesel available on the official website of
‘Petroleum Planning and Analysis cell’ under Ministry of Petroleum and Natural
Gas for Delhi, Kolkata, Mumbai &Chennai, for the base period
FQ The average of official prices of Diesel available on the official website of
‘Petroleum Planning and Analysis cell’ under Ministry of Petroleum and Natural
Gas for Delhi, Kolkata, Mumbai &Chennai, for the 3 months of the quarter under
consideration
EB Index number of Monthly Whole Sale Price Index for the category ‘Explosive’ of
(g). Manufacture of other chemical products under (J) MANUFACTURE OF
CHEMICALS AND CHEMICAL PRODUCTS, published by Office of Economic
Adviser, Govt. of India, Ministry of Commerce & Industry, Department of Industrial
Policy & Promotion (DIPP), for the base period.
EQ Index number of Monthly Whole Sale Price Index for the category ‘Explosive’ of
(g). Manufacture of other chemical products under (J) MANUFACTURE OF
CHEMICALS AND CHEMICAL PRODUCTS, published by Office of Economic
Adviser, Govt. of India, Govt. of India, Ministry of Commerce & Industry,
Department of Industrial Policy & Promotion (DIPP), for the average price index of
3 months of the quarter under consideration.
PMB Index Number of Wholesale Prices in India by Groups and Sub Groups (Averages)
for ‘Manufacture of machinery for mining, quarrying and construction’– published
in RBI (Reserve Bank of India) Bulletin, for the base period.
PMQ Index Number of Wholesale Prices in India by Groups and Sub Groups (Averages)
for ‘Manufacture of machinery for mining, quarrying and construction’– published
in RBI (Reserve Bank of India) Bulletin, for the average price index of 3 months of
the quarter under consideration.
SB The average rate provided by the Joint Plant Committee for the relevant category of
steel item as mentioned in Clause 46A.9; for the base period.
SQ The average rate provided by the Joint Plant Committee for the relevant category of
steel item as mentioned in Clause 46A.9; for the 3 months of the quarter under
consideration.
CB Index No. of Wholesale Price Index of sub-group Cement, Lime & Plaster as
published in RBI Bulletin for the base period
193
CQ No. of Wholesale Price Index of sub-group Cement, Lime & Plaster as published in
RBI Bulletin for the average price index of the 3 months of the quarter under
consideration
RT IEEMA price index for Steel Blooms (size 150mmx150mm) for the month which is
two months prior to date of inspection of material.
RO IEEMA price index for Steel Blooms (size 150mmx150mm)for the month which is
one month prior to date of opening of tender.
PT IEEMA price index for Copper wire rods for the month which is two months prior
to date of inspection of material.
PO IEEMA price index for Copper wire rods for the month which is one month prior to
date of opening of tender.
ZT IEEMA price index for Zinc for the month which is two months prior to date of
inspection of material
ZO IEEMA price index for Zinc for the month which is one month prior to date of
opening of tender
IT RBI wholesale price index for the sub-group “Insulators” for the month which is two
months prior to date of inspection of material
IO RBI wholesale price index for the sub-group “Insulators” for the month which is one
month prior to date of opening of tender
SIGWK = Value of signalling works for a stage payment of the item signalling works;
INVSIG = Value of inventory for signalling works for a stage payment of the item inventory
for signalling works;
INTGTESTSIG = Value of integrated testing and commission for signalling works of RLDA
Project;
COMWK= Value of telecommunication works for a stage payment of the item
telecommunication works;
INVCOM = Value of inventory for telecommunication works for a stage payment of the item
inventory for telecommunication works; and
INTGTESTCOM = Value of integrated testing and commission for telecommunication works
of RLDA Project.
(b) Price adjustment for changes in cost of signalling works and telecommunication works shall
be paid in accordance with the following formula:
(i) VSIGWK = 0.85 SIGWK x [PELEX x (ELEXi – ELEXo)/ ELEXo + POFC x (OFCi
– OFCo)/OFCo + PLB x (LBi – LBo)/LBo + POTH x (OTHi - OTHo)/OTHo + S30C
x (P30Ci – P30Co)/ P30Co + S24C x (P24Ci – P24Co)/ P24Co + S19C x (P19Ci –
P19Co)/ P19Co + S12C x (P12Ci – P12Co)/ P120Co + S9C x (P9Ci – P9Co)/ P9Co +
S6C x (P6Ci – P6Co)/ P6Co + S4C x (P4Ci – P4Co)/ P4Co + S2C x (P2Ci – P2Co)/ P2Co
194
+ S12C2.5 x (P12C2.5i – P12C2.5o)/ P12C2.5o + S2C2.5 x (P2C2.5i – P2C2.5o)/
P2C2.5o + S2C25 x (P2C25i – P2C25o)/ P2C25o + QC x (PQCi – PQCo)/ PQCo;
(ii) VINVSIG = 0.85 SIGWK x [PELEX x (ELEXi – ELEXo)/ ELEXo + POTH x (OTHi
- OTHo)/OTHo];
(iii) VINTGTESTSIG = 0.85 INTGTESTSIG x [PLB x (LBi – LBo)/LBo + POTH x
(OTHi- OTHo)/OTHo];
(iv) VCOMWK = 0.85 COMWK x [PELEX x (ELEXi – ELEXo)/ ELEXo + POFC x
(OFCi – OFCo)/OFCo + PLB x (LBi – LBo)/LBo + POTH x (OTHi - OTHo)/OTHo +
S30C x (P30Ci – P30Co)/ P30Co + S24C x (P24Ci – P24Co)/ P24Co + S19C x (P19Ci –
P19Co)/ P19Co + S12C x (P12Ci – P12Co)/ P120Co + S9C x (P9Ci – P9Co)/ P9Co +
S6C x (P6Ci – P6Co)/ P6Co + S4C x (P4Ci – P4Co)/ P4Co + S2C x (P2Ci – P2Co)/
P2Co+ S12C2.5 x (P12C2.5i – P12C2.5o)/ P12C2.5o + S2C2.5 x (P2C2.5i – P2C2.5o)/
P2C2.5o + S2C25 x (P2C25i – P2C25o)/ P2C25o + QC x (PQCi – PQCo)/ PQCo+
PCEQP x (CEQPi – CEQPo)/CEQPo];
(v) VINVCOM = 0.85 SIGWK x [PELEX x (ELEXi – ELEXo)/ ELEXo + PCEQP x
(CEQPi – CEQPo)/CEQPo + POTH x (OTHi - OTHo)/OTHo]; and
(vi) VINTGTESTCOM = 0.85 INTGTESTCOM x [PLB x (LBi – LBo)/LBo + POTH x
(OTHi - OTHo)/OTHo].
Where
VSIGWK = Increase or decrease in the cost of signalling works during the period under
consideration due to changes in the rates for relevant components as specified in sub-paragraph
(h);
VINVSIG = Increase or decrease in the cost of inventory for signalling during the period under
consideration due to changes in the rates for relevant components as specified in sub-paragraph
(h);
VINTGTESTSIG = Increase or decrease in the cost of integrated testing and commissioning
of signalling works of RLDA Project during the period under consideration due to changes in
the rates for relevant components as specified in sub-paragraph (h);
VCOMWK = Increase or decrease in the cost of communication works during the period under
consideration due to changes in the rates for relevant components as specified in sub-paragraph
(h);
VINVCOM = Increase or decrease in the cost of inventory for telecommunications works
during the period under consideration due to changes in the rates for relevant components as
specified in sub-paragraph (h);
VINTGTESTCOM = Increase or decrease in the cost of integrated testing and commissioning
of telecommunication works of RLDA Project during the period under consideration due to
changes in the rates for relevant components as specified in sub-paragraph (h);
PCEQP, PELEX, PIC, PLB, POFC, and POTH are the percentages of communication
equipment, electronics, PVC insulated cables, labour, optical fibre cables, and other materials
respectively;
195
CEQPo = The wholesale price index as published by the Ministry of Commerce and Industry,
Government of India (hereinafter called “WPI”) for communication equipment for the month
of the Base Month;
CEQPi = The WPI for communication equipment for the average price index of the 3 months
of the quarter under consideration;
ELEXo = The WPI for electronics for the month of the Base Month;
ELEXi = The WPI for electronics for the average price index of the 3 months of the quarter
under consideration;
P30Ci = Price payable per Km as adjusted in accordance with price variation Clause for size
30C x 1.5 sq mm signalling cable
P30Co = Price per Km of cable as per purchase order/ Contract agreement.
S30C = Percentage of size 30C x 1.5 sq mm signalling cable shall govern the price adjustment
of the contract price for signalling and telecommunication works.
P24Ci = Price payable per Km as adjusted in accordance with price variation Clause for size
24C x 1.5 sq mm signalling cable
P24Co = Price per Km of cable as per purchase order/ Contract agreement.
S24C = Percentage of size 24C x 1.5 sq mm signalling cable shall govern the price adjustment
of the contract price for signalling and telecommunication works.
P19Ci = Price payable per Km as adjusted in accordance with price variation Clause for size
19C x 1.5 sq mm signalling cable
P19Co = Price per Km of cable as per purchase order/ Contract agreement.
S19C = Percentage of size 19C x 1.5 sq mm signalling cable shall govern the price adjustment
of the contract price for signalling and telecommunication works.
P12Ci = Price payable per Km as adjusted in accordance with price variation Clause for size
12C x 1.5 sq mm signalling cable
P12Co = Price per Km of cable as per purchase order/ Contract agreement.
S12C = Percentage of size 12C x 1.5 sq mm signalling cable shall govern the price adjustment
of the contract price for signalling and telecommunication works.
P9Ci = Price payable per Km as adjusted in accordance with price variation Clause for size 9C
x 1.5 sq mm signalling cable
P9Co = Price per Km of cable as per purchase order/ Contract agreement.
S9C = Percentage of size 9C x 1.5 sq mm signalling cable shall govern the price adjustment of
the contract price for signalling and telecommunication works.
P6Ci = Price payable per Km as adjusted in accordance with price variation Clause for size 6C
x 1.5 sq mm signalling cable
P6Co = Price per Km of cable as per purchase order/ Contract agreement.
S6C = Percentage of size 6C x 1.5 sq mm signalling cable shall govern the price adjustment of
the contract price for signalling and telecommunication works.
196
P4Ci = Price payable per Km as adjusted in accordance with price variation Clause for size 4C
x 1.5 sq mm signalling cable
P4Co = Price per Km of cable as per purchase order/ Contract agreement.
S4C = Percentage of size 4C x 1.5 sq mm signalling cable shall govern the price adjustment of
the contract price for signalling and telecommunication works.
P2Ci = Price payable per Km as adjusted in accordance with price variation Clause for size 2C
x 1.5 sq mm signalling cable
P2Co = Price per Km of cable as per purchase order/ Contract agreement.
S2C = Percentage of size 2C x 1.5 sq mm signalling cable shall govern the price adjustment of
the contract price for signalling and telecommunication works.
P12C2.5i = Price payable per Km as adjusted in accordance with price variation Clause for size
12C x 2.5 sq mm signalling cable
P12C2.5o = Price per Km of cable as per purchase order/ Contract agreement.
S12C2.5 = Percentage of size 12C x 2.5 sq mm signalling cable shall govern the price
adjustment of the contract price for signalling and telecommunication works.
P2C2.5i = Price payable per Km as adjusted in accordance with price variation Clause for size
2C x 2.5 sq mm signalling cable
P2C2.5o = Price per Km of cable as per purchase order/ Contract agreement.
S2C2.5 = Percentage of size 2C x 2.5 sq mm signalling cable shall govern the price adjustment
of the contract price for signalling and telecommunication works.
P2C25i = Price payable per Km as adjusted in accordance with price variation Clause for size
2C x 25 sq mm signalling cable
P2C25o = Price per Km of cable as per purchase order/ Contract agreement.
S2C25 = Percentage of size 2C x 25 sq mm signalling cable shall govern the price adjustment
of the contract price for signalling and telecommunication works.
PQCi = Price payable per Km as adjusted in accordance with price variation Clause for size
0.9mm dia, 6 Quad cable.
PQCo= Price per Km of cable as per purchase order/ Contract agreement.
QC = Percentage of size 0.9mm dia, 6 Quad cable shall govern the price.
LBo = The consumer price index for industrial workers – All India, published by Labour
Bureau, Ministry of Labour, Government of India, (hereinafter called “CPI”) for the month of
the Base Month;
LBi = The CPI for industrial workers – All India for the average price index of the 3 months
of the quarter under consideration;
OFCo = The WPI for fibre cables for the month of the Base Month;
OFCi = The WPI for fibre cables for the average price index of the 3 months of the quarter
under consideration;
197
OTHo = The WPI for all commodities for the month of the Base Month; and
OTHi = The WPI for all commodities for the average price index of the 3 months of the quarter
under consideration.
(c) The following percentages shall govern the price adjustment of the Contract Price for
signalling and telecommunication works:
Signalling Telecommunication
Works
Integ
Integr
Telec rated
ated
Signal Signa ommu Telec testin
testin
ling lling nicati omm g and
g and
Work invent on invent Com
Component Com
s ory Work ory missi
missi
s oning
oning
198
0.9 mm dia, 6Quad cable (QC) ***% _ _ ***% _ _
***
Labour (PLB) ***% _ ***% ***% ***%
%
***
Other materials ***% ***% ***% ***% ***%
%
100
Total
100% 100% 100% 100% 100% %
199
Cu= Price of Copper Rod in Rs. Per MT.
CC= Price of PVC Compound in Rs. Per MT.
Fe= Price of Steel for Armouring (Flat strip 4mm x 0.8 mm/ Round 1.4mm dia) in Rs. Per
MT.
Al = Price of EC grade LME Aluminium rods (Properzi rods) in Rs. Per MT.
(Prices per MT for Cu, CC, Fe, Al as prevailing on 1stworking day of the calendar
month covering the date One month prior to the date of inspection call letter will be
applicable for the calculation of updated price. The above prices and indices are as
published by IEEMA vide circular reference no. IEEMA (PVC) /CABLE --/--/-- one
month prior to the date of inspection.)
The value of variation factors for copper, steel and PVC Compound are different for
different sizes of signalling cables. Accordingly, the PVC formula for some of the types
of signalling cable is as given under:-
Underground RLDA Signalling Cable unscreened and armoured copper conductor
(i) Size 30 C x 1.5 sq.mm.
P30Ci=P30Co+0.391(Cu-Cuo) +0.557(CC-CCo) +0.425(Fe-Feo)
For armouring, price of steel flat strip of size 4mmx0.8mm is to be taken into
consideration.
(ii) Size 24C x 1.5 sq.mm
P24Ci= P24Co+0.313(Cu-Cuo) + 0.481 (CC-CCo) +0.398(Fe-Feo)
For armouring, value of steel flat strip of size 4mmx0.8mm is to be taken into
consideration.
(iii) Size 19C x 1.5 sq.mm
P19Ci= P19Co+0.248(Cu-Cuo) + 0.395(CC-CCo) +0.343(Fe-Feo)
For armouring, value of steel flat strip of size 4mmx0.8mm is to be taken into
consideration.
(iv) Size 12C x 1.5 sq.mm
P12Ci=P12Co+0.157(Cu-Cuo) + 0.277(CC-CCu) +0.289(Fe-Feo)
For armouring, value of steel wire size 1.4mm dia is to be taken into consideration.
(v) Size 9C x 1.5 sq.mm
P9Ci= P9Co+0.117(Cu-Cuo) +0.241(CC-CCu) +0.383(Fe-Feo)
For armouring, value of steel wire size 1.4mm dia is to be taken into consideration.
(vi) Size 6Cx 1.5 sq.mm
P6Ci= P6Co+0.078(Cu-Cuo) +0.199(CC-CCu) +0.329(Fe-Feo)
For armouring, value of steel wire size 1.4mm dia is to be taken into consideration.
(vii) Size 4Cx1.5 sq.mm
200
P4Ci=P4Co+0.052(Cu-Cuo) +0.152(CC-CCo) +0.277(Fe-Feo)
For armouring, value of steel wire size 1.4mm dia is to be taken into consideration.
(viii) Size 2C x 4 sq.mm(multistrand)
P2Ci= P2Co+0.073(Cu-Cuo) +0.156(CC-CCo) +0.3(Fe-Feo)
For armouring, value of steel wire size 1.4mm dia is to be taken into consideration.
(ix) Size 12C x 2.5 sq.mm
P12C2.5i= P12C2.5o+0.282 (Cu-Cuo) +0.371 (CC-CCo) +0.342 (Fe-Feo)
For armouring, value of steel flat strip of size 4mmx0.8mm is to be taken into
consideration.
(x) Size 2C x 2.5 sq.mm
P2C2.5i= P2C2.5o+0.047 (Cu-Cuo) +0.139 (CC-CCo) +0.277 (Fe-Feo)
For armouring, value of steel wire size 1.4mm dia is to be taken into consideration.
(xi) Size 2C x 25 sq.mm PVC insulated, armoured, Aluminium power cable
P2C25i= P2C25o+0.146 (Al-Alo) +0.303 (CC-CCo) +0.306 (Fe-Feo)
For armouring, value of steel flat strip of size 4mmx0.8mm is to be taken into
consideration.
(xii) For Jelly filled, 0.9mm dia, 6 quad cable
PQCi = PQCo + 0.135 (Al-Alo) + 0.139 (Cu-Cuo) + 0.515 (CC-Cco) + 0.693 (Fe-Feo).
For PVC Compound Grade CW-22, is to be taken into consideration.
46A.8 The demands for escalation of cost shall be allowed on the basis of provisional indices as
mentioned above in Clause 46A.7. Any adjustment needed to be done based on the finally published
indices shall be made as and when they become available.
46A.9: (1) Relevant categories of steel for the purpose of operating Price Variation formula as
mentioned in this Clause shall be as under:
SL Classification Rates to be used for calculating SQ or SB
1. Reinforcement bars and other Average of per tonne rates of 10mm dia TMT & 25mm
rounds dia TMT; confirming IS1786; Fe 500
2. All types and sizes of angles, Average of per tonne rates of ‘Angle 75x75x6mm, Mild
channels and joists Steel Plate 10mm thickness and Channel 150x75mm;
confirming IS2062, E250 Gr “A”
3. All types and sizes of plates Average of per tonne rates of ‘MS Plates 10mm
thickness and 25mm thickness; confirming IS2062,
E250 Gr “A”
4. Any other section of steel not Average of price for the 3 categories covered under SL
covered in the above categories 1, 2 & 3 in this table.
201
(2). Relevant city for referring “JPC (Joint Plant Committee)”rates of steel items (SQ /SB) in different
Zonal Railway/RLDAs shall be as under :
SL City Railway/RLDA
1. Delhi Northern , North Central, North Eastern, North Western
2. Kolkata Eastern, East Central, East Coast, Northeast Frontier, South Eastern,
Southeast Central
3. Mumbai Central, Western, West Central
4. Chennai Southern, South Central&South Western
The price adjustment as worked out above, i.e. either increase or decrease shall be applicable upto the
stipulated date of completion of work including the extended period of completion where such
extension has been granted under Clause 17A of the Standard General Conditions of Contract.
However, where extension of time has been granted due to Contractor’s failure under Clause 17B of
the Standard General Conditions of Contract, price adjustment shall be done as follows:
a. In case the indices increase above the indices applicable to the last month of original
completion period or the extended period under Clause 17A, the price adjustment for the period
of extension granted under Clause 17B shall be limited to the amount payable as per the Indices
applicable to the last month of the original completion period or the extended period under
Clause 17A of the Standard General Conditions of Contract; as the case may be.
b. In case the indices fall below the indices applicable to the last month of original/ extended
period of completion under Clause 17A, as the case may be; then the lower indices shall be
adopted for the price adjustment for the period of extension under Clause 17B of the Standard
General Conditions of Contract.
47. Maintenance of Works: The Contractor shall at all times during the progress and continuance
of the works and also for the period of maintenance specified in the Tender Form after the date of issue
of the certificate of completion by the Engineer or any other earlier date subsequent to the completion
of the works that may be fixed by the Engineer, be responsible for and effectively maintain and uphold
in good substantial, sound and perfect condition all and every part of the works and shall make good
from time to time and at all times as often as the Engineer shall require, any damage or defect that may
during the above period arise in or be discovered or be in any way connected with the works, provided
that such damage or defect is not directly caused by errors in the contract documents, act of providence
or insurrection or civil riot, and the Contractor shall be liable for and shall pay and make good to
RLDA or other persons legally entitled thereto whenever required by the Engineer so to do, all losses,
damages, costs and expenses they or any of them may incur or be put or be liable to by reasons or in
consequence of the operations of the Contractor or of his failure in any respect. The Maintenance
period shall be as per provisions of the contract and as per detail mentioned in Annexure-III but not
less than 12 months from the date of completion.
48.(1) Certificate of Completion of Works: As soon as in the opinion of the Engineer, the work has
been completed and has satisfactorily passed any final test or tests that may be prescribed, the Engineer
shall issue a certificate of completion duly indicating the date of completion in respect of the work and
the period of maintenance of the work shall commence from the date of completion mentioned in such
202
certificate. The certificate, inter alia, should mention that the work has been completed in all respects
and that all the contractual obligations have been fulfilled by the Contractor and that there is no due
from the Contractor to RLDAs against the contract concerned.
The Engineer may also issue such a certificate indicating date of completion with respect to any part
of the work (before the completion of the whole of work), which has been both completed to the
satisfaction of the Engineer and occupied or used by RLDA. When any such certificate is given in
respect of part of a work, such part shall be considered as completed and the period of maintenance of
such part shall commence from the date of completion mentioned in the completion certificate issued
for that part of the work.
48(3) Final Supplementary Agreement: After the work is completed or otherwise concluded by the
parties with mutual consent, and taken over by RLDA as per terms and conditions of the contract
agreement, and there is unequivocal no claim on either side under the Contract other than as mentioned
in item 4 of Annexure XIV, the parties shall execute the Final Supplementary Agreement as per
Annexure XIV.
49. Approval only by Maintenance Certificate: No certificate other than Maintenance Certificate, if
applicable, referred to in Clause 50 of the Conditions shall be deemed to constitute approval of any
work or other matter in respect of which it is issued or shall be taken as an admission of the due
performance of the contract or any part thereof.
50.(1) Maintenance Certificate: The Contract shall not be considered as completed until a
Maintenance Certificate, if applicable, shall have been signed by the Engineer stating that the works
have been completed and maintained to his satisfaction. The Maintenance Certificate shall be given
by the Engineer upon the expiration of the period of maintenance or as soon thereafter as any works
ordered during such period pursuant to Sub Clause (2) to Clause 48 of these Conditions shall have
been completed to the satisfaction of the Engineer, and full effect shall be given to this Clause
notwithstanding the taking possession of or using the works or any part thereof by RLDA.
The Competent Authority to issue above Maintenance Certificate shall normally be the authority who
is competent to sign the contract. If this Competent Authority is of the rank lower than JA Grade, then
a JA Grade Officer (concerned with the work) should issue the Certificate. The Certificate, inter alia,
should mention that the work has been completed in all respects and that all the contractual obligations
203
have been fulfilled by the Contractor and that there is no due from the Contractor to RLDA against the
contract concerned
50.(2) Cessation of RLDA’s Liability: RLDA shall not be liable to the Contractor for any matter
arising out of or in connection with the contract for execution of the works unless the Contractor has
made a claim in writing in respect thereof before the issue of the Maintenance Certificate under this
clause.
50.(3) Unfulfilled Obligations: Notwithstanding the issue of the Maintenance Certificate the
Contractor and (subject to Sub-Clause (2) of this Clause) RLDA shall remain liable for the fulfillment
of any obligation incurred under the provision of the contract prior to the issue of the Maintenance
Certificate which remains unperformed at the time such Certificate is issued and for the purposes of
determining the nature and extent of any such obligations, the contract shall be deemed to remain in
force between the parties thereto.
51.(1)Final Payment: On the Engineer's certificate of completion in respect of the works, adjustment
shall be made and the balance of account based on the Engineer or the Engineer's representative's
certified measurements or Engineer’s certified “contractor’s authorized engineer’s measurements” of
the total quantity of work executed by the Contractor upto the date of completion and on the rates
accepted in Bill(s) of Quantities and for extra works on rates determined under Clause 39 of these
Conditions shall be paid to the Contractor subject always to any deduction which may be made under
these presents and further subject to the Contractor having signed delivered to the Engineer enclosing
either a full account in detail of all claims he may have on RLDA in respect of the works or having
delivered No Claim Certificate and the Engineer having after the receipt of such account given a
certificate in writing that such claims are not covered under excepted matter i.e. Clauses 7(j), 8, 18,
22(5), 39.1, 39.2, 40A, 43(2), 45(i)(a), 55, 55-A(5), 57, 57A, 61(1), 61(2) and 62(1), 63(iv) and 63.2.11
of the Standard General Conditions of Contract or in any Clause (stated as excepted matter) of the
Special Conditions of the Contract, that the whole of the works to be done under the provisions of the
Contracts have been completed, that they have been inspected by him since their completion and found
to be in good and substantial order, that all properties, works and things, removed, disturbed or injured
in consequence of the works have been properly replaced and made good and all expenses and demands
incurred by or made upon RLDA for or in the respect of damage or loss by from or in consequence of
the works, have been satisfied agreeably and in conformity with the contract.
51.(2) Post Payment Audit: It is an agreed term of contract that RLDA reserves to itself the right
to carry out a post-payment audit and/ or technical examination of the works and the Final Bill
including all supporting vouchers, abstracts etc. and to make a claim on the Contractor for the refund
of any excess amount paid to him till the release of security deposit or settlement of claims, whichever
is later, if as a result of such examination any over-payment to him is discovered to have been made
in respect of any works done or alleged to have been done by him under the contract.
(i) For a contract of more than one crore of rupees, the Contractor shall, whenever required, produce
or cause to be produced for examination by the Engineer any quotation, invoice, cost or other
account, book of accounts, voucher, receipt, letter, memorandum, paper of writing or any copy
of or extract from any such document and also furnish information and returns verified in such
manner as may be required in any way relating to the execution of this contract or relevant for
204
verifying or ascertaining cost of execution of this contract (the decision of the Engineer on the
question of relevancy of any documents, information or return being final and binding in the
parties). The Contractor shall similarly produce vouchers etc., if required to prove to the
Engineer, that materials supplied by him, are in accordance with the specifications laid down in
the contract.
(ii) If any portion of the work in a contract of value more than one crore of rupees be carried out by
a sub-contractor or any subsidiary or allied firm or company (as per Clause 7 of the Standard
General Conditions of Contract), the Engineer shall have power to secure the books of such sub-
contract or any subsidiary or allied firm or company, through the Contractor, and such books
shall be open to his inspection.
(iii) The obligations imposed by Sub Clause (i) & (ii) above is without prejudice to the obligations
of the Contractor under any statute rules or orders binding on the Contractor.
52. Withholding and Lien in Respect of Sums Claimed: Whenever any claim or claims for
payment of a sum of money arises out of or under the contract against the Contractor, RLDA shall be
entitled to withhold and also have a lien to retain such sum or sums in whole or in part from the
security, if any, deposited by the Contractor and for the purpose aforesaid, RLDA shall be entitled to
withhold the said cash Security Deposit or the Security if any, furnished as the case may be and also
have a lien over the same pending finalization or adjudication of any such claim. In the event of the
security being insufficient to cover the claimed amount or amounts or if no security has been taken
from the Contractor, RLDA shall be entitled to withhold and have a lien to the extent of the such
claimed amount or amounts referred to supra, from any sum or sums found payable or which at any
time thereafter may become payable to the Contractor under the same contract or any other contract
with this or any other RLDA or any Department of the Central Government pending finalization or
adjudication of any such claim.
It is an agreed term of the contract that the sum of money or moneys so withheld or retained under the
lien referred to above, by RLDA will be kept withheld or retained as such by RLDAs till the claim
arising out of or under the contract is determined by the arbitrator (if the contract governed by the
Arbitration Clause) or by the competent court as the case may be and that the Contractor will have no
claim for interest or damages whatsoever on any account in respect of such withholding or retention
under the lien referred to supra and duly notified as such to the Contractor. For the purpose of this
clause, where the Contractor is a partnership firm or a company, RLDA shall be entitled to withhold
and also have a lien to retain towards such claimed amount or amounts in whole or in part from any
sum found payable to any partner / company, as the case may be whether in his individual capacity or
otherwise.
(i) Any sum of money due and payable to the Contractor (including the Security Deposit returnable
to him) under the contract may be withheld or retained by way of lien by RLDA, against any
claim of this or any other RLDA or any other Department of the Central Government in respect
of payment of a sum of money arising out of or under any other contract made by the Contractor
with this or any other Department of the Central Government.
(ii) However, recovery of claims of RLDA in regard to terminated contracts may be made from the
Final Bill, Security Deposits and Performance Guarantees of other contract or contracts,
205
executed by the Contractor. The Performance Guarantees submitted by the Contractor against
other contracts, if required, may be withheld and encashed. In addition, 10% of each subsequent
‘on-account bill’ may be withheld, if required, for recovery of RLDA’s dues against the
terminated contract.
(iii) It is an agreed term of the contract that the sum of money so withheld or retained under this
Clause by RLDA will be kept withheld or retained as such by RLDA till the claim arising out of
or under any other contract is either mutually settled or determined by arbitration, if the other
contract is governed by Arbitration Clause or by the competent court as the case may be and
Contractor shall have no claim for interest or damages whatsoever on this account or on any
other ground in respect of any sum of money withheld or retained under this Clause and duly
notified as such to the Contractor.
53. Signature on Receipts for Amounts: Every receipt for money which may become payable or
for any security which may become transferable to the Contractors under these presents, shall, if signed
in the partnership name by anyone of the partners of a Contractor's firm be a good and sufficient
discharge to RLDA in respect of the moneys or security purported to be acknowledged thereby and in
the event of death of any of the Contractor, partners during the pendency of the contract, it is hereby
expressly agreed that every receipt by anyone of the surviving Contractor partners shall if so signed as
aforesaid be good and sufficient discharge as aforesaid provided that nothing in this Clause contained
shall be deemed to prejudice or effect any claim which RLDA may hereafter have against the legal
representative of any Contractor partner so dying for or in respect to any breach of any of the conditions
of the contract, provided also that nothing in this clause contained shall be deemed to prejudice or
effect the respective rights or obligations of the Contractor partners and of the legal representatives of
any deceased Contractor partners interse.
LABOUR
54. Wages to Labour: The Contractor shall be responsible to ensure compliance with the provision
of the Minimum Wages Act, 1948 (hereinafter referred to as the “said Act”) and the Rules made
thereunder in respect of any employees directly or through petty Contractors or sub-contractors
employed by him for the purpose of carrying out this contract.
If, in compliance with the terms of the contract, the Contractor supplied any labour to be used
wholly or partly under the direct orders and control of RLDAs whether in connection with any work
being executed by the Contractor or otherwise for the purpose of RLDA such labour shall, for the
purpose of this Clause, still be deemed to be persons employed by the Contractor.
If any moneys shall, as a result of any claim or application made under the said Act be
directed to be paid by RLDA, such money shall be deemed to be moneys payable to RLDA by the
Contractor and on failure by the Contractor to repay RLDA any moneys paid by it as aforesaid within
seven days after the same shall have been demanded, RLDA shall be entitled to recover the same from
Contractor’s bills/Security Deposit or any other dues of Contractor with the Government of India.
54-A. Apprentices Act: The Contractor shall be responsible to ensure compliance with the
provisions of the Apprentices Act, 1961 and the Rules and Orders issued thereunder from time to time
in respect of apprentices directly or through petty Contractors or sub-contractors employed by him for
the purpose of carrying out the Contract.
206
If the Contractor directly or through petty Contractors or sub-contractors fails to do so, his
failure will be a breach of the contract and RLDA may, in its discretion, rescind the contract. The
Contractor shall also be liable for any pecuniary liability arising on account of any violation of the
provisions of the Act.
55. Provisions of Payments of Wages Act: The Contractor shall comply with the provisions of
the Payment of Wages Act, 1936 and the rules made thereunder in respect of all employees employed
by him either directly or through petty Contractors or sub-contractors in the works. If in compliance
with the terms of the contract, the Contractor directly or through petty Contractors or sub-contractors
shall supply any labour to be used wholly or partly under the direct orders and control of the Engineer
whether in connection with the works to be executed hereunder or otherwise for the purpose of the
Engineer, such labour shall nevertheless be deemed to comprise persons employed by the Contractor
and any moneys which may be ordered to be paid by the Engineer shall be deemed to be moneys
payable by the Engineer on behalf of the Contractor and the Engineer may on failure of the Contractor
to repay such money to RLDA deduct the same from any moneys due to the Contractor in terms of the
contract. RLDA shall be entitled to recover the same from Contractor’s bills/Security Deposit or any
other dues of Contractor with the Government of India all moneys paid or payable by RLDA by way
of compensation of aforesaid or for costs of expenses in connection with any claim thereto and the
decision of the Engineer upon any question arising out of the effect or force of this Clause shall be
final and binding upon the Contractor.
55-A.(1) The Contractor shall comply with the provision of the contract labour (Regulation and
Abolition) Act, 1970 and the Contract labour (Regulation and Abolition) Central Rules 1971 as
modified from time to time, wherever applicable and shall also indemnify RLDA from and against any
claims under the aforesaid Act and the Rules.
55-A.(2) The Contractor shall obtain a valid license under the aforesaid Act as modified from time
to time before the commencement of the work and continue to have a valid license until the completion
of the work. Any failure to fulfill the requirement shall attract the penal provision of the Act.
55-A.(3) The Contractor shall pay to the labour employed by him directly or through sub-
contractors the wages as per provision of the aforesaid Act and the Rules wherever applicable. The
Contractor shall notwithstanding the provisions of the contract to the contrary, cause to be paid the
wages to labour, indirectly engaged on the works including any engaged by sub-contractors in
connection with the said work, as if the labour had been immediately employed by him.
55-A.(4) In respect of all labour directly or indirectly employed in the work for performance of the
Contractor's part of the contract, the Contractor shall comply with or cause to be complied with the
provisions of the aforesaid Act and Rules wherever applicable.
55-A.(5) In every case in which, by virtue of the provisions of the aforesaid Act or the rules, RLDA
is obliged to pay any amount of wages to a workman employed by the Contractor or his sub-contractor
in execution of the work or to incur any expenditure on account of the contingent, liability of RLDA
due to the Contractor's failure to fulfill his statutory obligations under the aforesaid Act or the rules,
RLDA will recover from the Contractor, the amount of wages so paid or the amount of expenditure so
incurred and without prejudice to the rights of RLDA under the Section 20, Sub-Section (2) and
207
Section 2, Sub-Section (4) of the aforesaid Act, RLDA shall be at liberty to recover such amount or
part thereof from Contractor’s bills/Security Deposit or any other dues of Contractor with the
Government of India. RLDA shall not be bound to contest any claim made against it under Sub-Section
(1) of Section 20 and Sub-Section (4) of Section 21 of the aforesaid Act except on the written request
of the Contractor and upon his giving to RLDA full security for all costs for which RLDA might
become liable in contesting such claim. The decision of the General Manager/Chief Project
Manager/Chief Engineer regarding the amount actually recoverable from the Contractor as stated
above shall be final and binding on the Contractor.
55-C (i) Contractor is to abide by the provisions of various labour laws in terms of above clause 54,
55, 55-A and 55-B of the Standard General Conditions of Contract. In order to ensure the same, an
application has been developed and hosted on website ‘www.shramikkalyan.indianrailawys.gov.in’.
Contractor shall register his firm/company etc. and upload requisite details of labour and their payment
in this portal. These details shall be available in public domain. The registration/ updation in Portal
shall be done as under:
(a) Contractor shall apply for onetime registration of his company/firm etc. in the Shramikkalyan
portal with requisite details subsequent to issue of Letter of Acceptance. Engineer shall
approve the contractor’s registration in the portal within 7 days of receipt of such request.
(b) Contractor once approved by any Engineer, can create password with login ID (PAN No.) for
subsequent use of portal for all Letter of Acceptances (LoAs) issued in his favour.
(c) The contractor once registered on the portal, shall provide details of his Letter of Acceptances
(LoAs) / Contract Agreements on shramikkalyan portal within 15 days of issue of any LoA
for approval of concerned Engineer. Engineer shall update (if required) and approve the
details of LoA filled by contractor within 7 days of receipt of such request.
(d) After approval of LoA by Engineer, contractor shall fill the salient details of contract labours
engaged in the contract and ensure updating of each wage payment to them on shramikkalyan
portal on monthly basis.
(e) It shall be mandatory upon the contractor to ensure correct and prompt uploading of all salient
details of engaged contractual labour & payments made thereof after each wage period.
(ii) While processing payment of any ‘On Account Bill’ or ‘Final Bill’ or release of ‘Advances’ or
‘Performance Guarantee / Security Deposit’, contractor shall submit a certificate to the Engineer or
Engineer’s representatives that “I have uploaded the correct details of contract labours engaged in
208
connection with this contract and payments made to them during the wage period in RLDA’s
Shramikkalyan portal at ‘www.shramikkalyan.indianRLDAs.gov.in’ till ____Month, ____Year.”
55-D. Provisions of “The Building and Other Construction Workers (Regulation of Employment
and Conditions of Service) Act, 1996” and “The Building and Other Construction Workers’
Welfare Cess Act, 1996”:
The tenderers, for carrying out any construction work, shall get themselves registered with the
Registering Officer under Section-7 of the Building and Other Construction Workers Act, 1996 and
Rules made thereto by the concerned State Govt., and submit Certificate of Registration issued by
Registering Officer of the concerned State Govt. (Labour Dept.). The Cess shall be deducted from
contractor’s bills as per provisions of the Act.
56. Reporting of Accidents: The Contractor shall be responsible for the safety of all employees
directly or through petty Contractors or sub-contractor employed by him on the works and shall report
serious accidents to any of them however and wherever occurring on the works to the Engineer or the
Engineers Representative and shall make every arrangement to render all possible assistance.
57. Provision of Workmen’s Compensation Act: In every case in which by virtue of the
provisions of Section 12 Sub-Section (1) of the Workmen's Compensation Act 1923, RLDA is obliged
to pay compensation to a workman directly or through petty Contractor or sub-contractor employed
by the Contractor in executing the work, RLDA will recover from the Contractor the amount of the
compensation so paid, and, without prejudice to the rights of RLDA under Section 12 Sub-section (2)
of the said Act, RLDA shall be at liberty to recover such amount or any part thereof from Contractor’s
bills/Security Deposit or any other dues of Contractor with the Government of India. RLDA shall not
be bound to contest any claim made against it under Section 12 Sub-Section (1) of the said Act except
on the written request of the Contractor and upon his giving to RLDA full security for all costs for
which RLDA might become liable in consequence of contesting such claim.
57-A. Provision of Mines Act: The Contractor shall observe and perform all the provisions of the
Mines Act, 1952 or any statutory modifications or re-enactment thereof for the time being in force and
any rules and regulations made thereunder in respect of all the persons directly or through the petty
Contractors or sub-contractors employed by him under this contract and shall indemnify RLDA from
and against any claims under the Mines Act, or the rules and regulations framed thereunder, by or on
behalf of any persons employed by him or otherwise.
58. RLDA not to Provide Quarters for Contractors: No quarters shall normally be provided
by RLDA for the accommodation of the Contractor or any of his staff employed on the work. In
exceptional cases where accommodation is provided to the Contractor at RLDA's discretion, recoveries
shall be made at such rates as may be fixed by RLDA for the full rent of the buildings and equipments
therein as well as charges for electric current, water supply and conservancy.
59.(1) Labour Camps: The Contractor shall at his own expense make adequate arrangements for
the housing, supply of drinking water and provision of latrines and urinals for his staff and workmen,
directly or through the petty Contractors or sub-contractors and for temporary creche (Bal-Mandir)
where 50 or more women are employed at a time. Suitable sites on RLDA land, if available, may be
209
allotted to the Contractor for the erection of labour camps, either free of charge or on such terms and
conditions that may be prescribed by RLDA. All camp sites shall be maintained in clean and sanitary
conditions by the Contractor at his own cost.
59.(2) Compliance to Rules for Employment of Labour: The Contractor(s) shall conform to all
laws, bye-laws rules and regulations for the time being in force pertaining to the employment of local
or imported labour and shall take all necessary precautions to ensure and preserve the health and safety
of all staff employed directly or through petty contractors or sub-contractors on the works.
59.(3) Preservation of Peace: The Contractor shall take requisite precautions and use his best
endeavours to;
(i) Prevent any riotous or unlawful behaviour by or amongst his workmen and other employed directly
or through the petty Contractors or sub-contractors on the works and for the preservation of peace and
protection of the inhabitants and
(ii) Security of property in the neighbourhood of the works. In the event of RLDA requiring the
maintenance of a Special Police Force at or in the vicinity of the site during the tenure of works, the
expenses thereof shall be borne by the Contractor and if paid by RLDA shall be recoverable from the
Contractor.
59.(4) Sanitary Arrangements: The Contractor shall obey all sanitary rules and carry out all
sanitary measures that may from time to time be prescribed by RLDA Medical Authority and permit
inspection of all sanitary arrangements at all times by the Engineer, the Engineer's Representative or
the Medical Staff of RLDA. Should the Contractor fail to make the adequate sanitary arrangements,
these will be provided by RLDA and the cost thereof recovered from the Contractor.
59.(5) Outbreak of Infectious Disease: The Contractor shall remove from his camp such labour
and their families as refuse protective inoculation and vaccination when called upon to do so by the
Engineer or the Engineer's Representative on the advice of RLDA Medical Authority. Should cholera,
plague, or other infectious disease break out, the Contractor shall burn the huts, beddings, clothes and
other belongings of or used by the infected parties and promptly erect new huts on healthy sites as
required by the Engineer, failing which within the time specified in the Engineer's requisition, the work
may be done by RLDA and the cost thereof recovered from the Contractor.
59.(6) Treatment of Contractor's Staff in Railways Hospitals: The Contractor and his staff, other
than labourers and their families requiring medical aid from RLDA hospital and dispensaries will be
treated as private patients and charged accordingly. The Contractors' labourers and their Families will
be granted free treatment in Railways hospitals and dispensaries where no other hospitals or
dispensaries are available provided the Contractor pays the cost of medicines, dressing and diet money
according to the normal scale and additional charges for special examinations such as pathological and
bacteriological examination, X-Ray, etc. and for surgical operation.
59. (7) Medical Facilities at Site: The Contractor shall provide medical facilities at the site as may
be prescribed by the Engineer/RLDA in relation to the strength of the Contractor's resident staff and
workmen.
210
59. (8) Use of Intoxicants: The sale of ardent spirits or other intoxicating beverages upon the work
or in any of the buildings, encampments or tenements owned, occupied by or within the control of the
Contractor or any of his employees shall be forbidden and the Contractor shall exercise his influence
and authority to the utmost extent to secure strict compliance with this condition.
59.(9) Restrictions on the Employment of Retired Engineers of Railways Services Within One
Year of their Retirement: The Contractor shall not, if he is a retired Government Engineer of
Gazetted rank, himself engage in or employ or associate a retired Government Engineer of Gazetted
rank, who has not completed one year from the date of retirement, in connection with this contract in
any manner whatsoever without obtaining prior permission of the President and if the Contractor is
found to have contravened this provision it will constitute a breach of contract and administration will
be entitled to terminate the contract and forfeit his Performance Guarantee as well as Security Deposit.
60.(1) Non-Employment of Labourers below the age of 15: The Contractor shall not employ
children below the age of 15 as labourers directly or through petty Contractors or sub-contractors for
the execution of work.
60.(2) Medical Certificate of Fitness for Labour: It is agreed that the Contractor shall not employ
a person above 15 and below 19 years of age for the purpose of execution of work under the contract
unless a medical certificate of fitness in the prescribed form (Proforma at Annexure-VIII) granted to
him by a certifying surgeon certifying that he is fit to work as an adult, is obtained and kept in the
custody of the Contractor or a person nominated by him in this behalf and the person carries with him,
while at work; a token giving a reference to such certificate. It is further agreed that the responsibility
for having the adolescent examined medically at the time of appointment or periodically till he attains
the age of 19 years shall devolve entirely on the Contractor and all the expenses to be incurred on this
account shall be borne by him and no fee shall be charged from the adolescent or his parent for such
medical examination.
60.(4) Medical Re-Examination of Labourer: Where any official appointed in this behalf by the
Ministry of Labour is of the opinion that any person employed in connection with the execution of any
work under this contract in the age group 15 to 19 years is without a certificate of fitness or is having
a certificate of fitness but no longer fit to work in the capacity stated in the certificate, he may serve
on the Contractor, or on the person nominated by him in this regard, a notice requiring that such persons
shall be examined by a certifying surgeon and such person shall not if the concerned official so directs,
be employed or permitted to do any work under this contract unless he has been medically examined
and certified that he is fit to work in the capacity stated in the certificate.
EXPLANATIONS:
(1) Only Qualified Medical Practitioners can be appointed as "Certifying Surgeons" and the term
"Qualified Medical Practitioners" means a person holding a qualification granted by an authority
211
specified in the Schedule to the Indian Medical Degrees Act, 1916 (VII to 1916) or in the
Schedule to the Indian Medical Council Act, 1933 (XXVII) of 1933.
(2) The Certifying surgeon may be a medical officer in the service of State or Municipal
Corporation.
DETERMINATION OF CONTRACT
61.(1) Right of RLDA to Determine the Contract: RLDA shall be entitled to determine and
terminate the contract at any time should, in RLDA's opinion, the cessation of work becomes necessary
owing to paucity of funds or from any other cause whatever, in which case the value of approved
materials at site and of work done to date by the Contractor will be paid for in full at the rate specified
in the contract. Notice in writing from RLDA of such determination and the reasons therefor shall be
conclusive evidence thereof.
61.(2) Payment on Determination of Contract: Should the contract be determined under sub
clause (1) of this clause and the Contractor claims payment for expenditure incurred by him in the
expectation of completing the whole of the work, RLDAs shall admit and consider such claims as are
deemed reasonable and are supported by vouchers to the satisfaction of the Engineer. RLDA's decision
on the necessity and propriety of such expenditure shall be final and conclusive.
61.(3) The Contractor shall have no claim to any payment of compensation or otherwise, howsoever
on account of any profit or advantage which he might have derived from the execution of the work in
full but which he did not derive in consequence of determination of contract.
212
(xi) Fail to remove materials from the site or to pull down and replace work after receiving from the
Engineer notice to the effect that the said materials or works have been condemned or rejected
under Clause 25 and 27 of these Conditions, or
(xii) Fail to take steps to employ competent or additional staff and labour as required under Clause
26 of these Conditions, or
(xiii) Fail to afford the Engineer or Engineer's representative proper facilities for inspecting the works
or any part thereof as required under Clause 28 of these Conditions, or
(xiv) Promise, offer or give any bribe, commission, gift or advantage either himself or through his
partner, agent or servant to any officer or employee of RLDA or to any person on his or on their
behalf in relation to the execution of this or any other contract with this RLDA.
(xv) Fail to adhere to the provisions of Para 16 of Tender Form (Second Sheet) of Annexure I of the
Instructions to Tenderers, or provision Clause 59(9) of these Conditions.
(xvi)Submits copy of fake documents / certificates in support of credentials, submitted by the tenderer
Then and in any of the said Clause, the Engineer on behalf of RLDA may serve the Contractor with a
notice (Proforma at Annexure-IX) in writing to that effect and if the Contractor does not within seven
days after the delivery to him of such notice proceed to make good his default in so far as the same is
capable of being made good and carry on the work or comply with such directions as aforesaid of the
entire satisfaction of the Engineer, RLDA shall be entitled after giving 48 hours’ notice (Proforma at
Annexure-X or XII, as the case may be) in writing under the hand of the Engineer to rescind the
contract as a whole or in part or parts (as may be specified in such notice) and after expiry of 48 hours’
notice, a final termination notice (Proforma at Annexure-XI or XIII, as the case may be) should be
issued.
Note: Engineer at his discretion may resort to the part termination of contract with notices (Proforma
at Annexure- IX, XII and XIII), only in cases where progress of work is more than or equal to 80% of
the original scope of work.
62.(2) Right of RLDA after Rescission of Contract owing to Default of Contractor: In the event
of any or several of the courses, referred to in Sub-Clause (1) of this Clause, being adopted:
(a) The Contractor shall have no claim to compensation for any loss sustained by him by reason of his
having purchased or procured any materials or entered into any commitments or made any advances
on account of or with a view to the execution of the works or the performance of the contract and
Contractor shall not be entitled to recover or be paid any sum for any work thereto for actually
performed under the contract unless and until the Engineer shall have certified the performance of such
work and the value payable in respect thereof and the Contractor shall only be entitled to be paid the
value so certified.
(b) In the contract which has been rescinded as a whole, the Security Deposit already with Railways
under the contract shall be encashed/ forfeited and the Performance Guarantee already submitted for
the contract shall be encashed. The balance work shall be got done independently without risk & cost
of the failed Contractor. The failed Contractor shall be debarred from participating in the tender for
executing the balance work. If the failed Contractor is a JV or a Partnership firm, then every
member/partner of such a firm shall be debarred from participating in the tender for the balance work
in his/her individual capacity or as a partner of any other JV /partnership firm.
213
Further the authorized representative of failed Contractor cannot be accepted as authorized
representative in new contract.
(i) The full Performance Guarantee available for the contract shall be recovered. No additional
Performance Guarantee shall be required for balance of work being executed through the part
terminated contract. The contract value of part terminated contract stands reduced to the balance value
of work under the contract.
(ii) The Security Deposit of part terminated contract shall be dealt as per clause 16(2) of these
Conditions.
(iii) The defaulting Contractor shall not be issued any completion certificate for the contract.
(iv) The balance work shall be got done independently without risk & cost of the failed Contractor.
The failed Contractor shall be debarred from participating in the tender for executing the balance work.
If the failed Contractor is a JV or a Partnership firm, then every member/partner of such a firm shall
be debarred from participating in the tender for the balance work in his/her individual capacity or as a
partner of any other JV /partnership firm.
(v) Further the authorized representative of failed Contractor will not be accepted as authorized
representative in new contract.
(d) The Engineer or the Engineer's Representative shall be entitled to take possession of any materials,
tools, implements, machinery and buildings on the works or on the property on which these are being
or ought to have been executed, and to retain and employ the same in the further execution of the works
or any part thereof until the completion of the works without the Contractor being entitled to any
compensation for the use and employment thereof or for wear and tear or destruction thereof.
(e) The Engineer shall as soon as may be practicable after removal of the Contractor fix and determine
ex-parte or by or after reference to the parties or after such investigation or enquiries as he may
consider fit to make or institute and shall certify what amount (if any) had at the time of rescission of
the contract been reasonably earned by or would reasonably accrue to the Contractor in respect of the
work then actually done by him under the contract and what was the value of any unused, or partially
used materials, any constructional plant and any temporary works upon the site. The legitimate amount
due to the Contractor after making necessary deductions and certified by the Engineer should be
released expeditiously.
(i) This clause is applicable in the tender having advertised value less than or equal to Rs 50 Crore.
(ii) All disputes and differences of any kind whatsoever arising out of or in connection with the
contract, whether during the progress of the work or after its completion and whether before or
after the determination of the contract, shall be referred by the Contractor to the "General
Manager/Chief Project Manager" through “Notice of Dispute” provided that no such notice
shall be served later than 30 days after the date of issue of Completion Certificate by the
214
Engineer. General Manager/Chief Project Manager shall, within 30 days after receipt of the
Contractor’s “Notice of Dispute”, notify the name of conciliator(s) to the Contractor. Vice
Chairman/RLDA will nominate the Conciliator(s) who shall be a Gazetted Officer of
Railways/RLDA not below Junior Administrative Grade.
(iii)The Conciliator(s) shall assist the parties to reach an amicable settlement in an independent and
impartial manner within the terms of contract.
(iv) If the parties reach agreement on a settlement of the dispute, they shall draw up and sign a
written settlement agreement duly signed by Engineer In-charge, Contractor and conciliator(s).
When the parties sign the settlement agreement, it shall be final and binding on the parties.
(v) The parties shall not initiate, during the conciliation proceedings, any arbitral or judicial
proceedings in respect of a dispute that is the subject matter of the conciliation proceedings.
(vi) The conciliation proceedings shall be terminated as per Section 76 of ‘The Arbitration and
Conciliation Act, 1996.
63.1 Matters Finally Determined by RLDA: All disputes and differences of any kind whatsoever
arising out of or in connection with the contract, whether during the progress of the work or after its
completion and whether before or after the determination of the contract, shall be referred by the
Contractor to the General Manager/Chief Project Manager and the General Manager/Chief Project
Manager shall, within 120 days after receipt of the Contractor’s representation, make and notify
decisions on all matters referred to by the Contractor in writing provided that matters for which
provision has been made in Clauses 7(j), 8, 18, 22(5),39.1, 39.2, 40A,43(2), 45(i)(a), 55, 55-A(5), 57,
57A,61(1), 61(2),62(1), 63(iv) and 63.2.11of the Standard General Conditions of Contract or in any
Clause (stated as excepted matter) of the Special Conditions of the Contract, shall be deemed as
‘excepted matters’ (matters not arbitrable) and decisions of RLDA authority, thereon shall be final and
binding on the Contractor; provided further that ‘excepted matters’ shall stand specifically excluded
from the purview of the Dispute Adjudication Board (DAB) and Arbitration.
63.2 Dispute Adjudication Board (DAB): This clause is applicable in the tender having advertised
value more than Rs.50 Crore.
63.2.1 Any dispute/s if not settled with the Engineer, shall be referred to DAB.
The DAB shall consist of a panel of three Retired RLDA/Railway Officers, retired not below senior
administrative grade (SAG). The DAB shall be formed within 90 days of signing of Contract
Agreement. For this purpose, a panel of DAB members shall be maintained in the General Manager’s
office. The complete panel, which shall not be less than five members, shall be sent by Chief Engineer
to the Contractor to nominate one member of the DAB from the panel as Contractor’s nominee within
two weeks of receipt of the panel. On receipt of Contractor’s nominee, the Chief Engineer shall
nominate one member from the same panel as RLDA nominee for the DAB. Both above nominees
shall jointly select presiding member of the DAB from the same panel.
63.2.2 The appointment of DAB shall be effectuated by way of a tri-partite agreement among RLDA,
Contractor and the respective DAB members. The terms of the remuneration of each member shall be
215
as fixed by Ministry of RLDAs from time to time. Each party shall be responsible for paying one-half
of this remuneration.
63.2.3 If one or more of the members appointed refuses to act as DAB member, or is unable or
unwilling to perform his functions as DAB member for any reason whatsoever or dies or in the opinion
of the Chief Engineer fails to act without undue delay, the parties shall terminate the mandate of such
DAB member and thereupon new DAB member shall be appointed in the same manner, as the outgoing
DAB member had been appointed.
63.2.4 The appointment of any member may be terminated by mutual agreement of both Parties, but
not by RLDA or the Contractor acting alone. Unless otherwise agreed by both the Parties, the
appointment of the DAB (including each member) shall expire upon expiry of this Contract
Agreement.
63.2.5 Before start of DAB proceedings, each DAB member shall give the following certificate to
RLDA and the Contractor:
“I have no any past or present relationship in relation to the subject matter in dispute, whether
financial, business, professional or other kind. Further, I have no any past or present relationship with
or interest in any of the parties whether financial, business, professional or other kind, which is likely
to give rise to justifiable doubts as to my independence or impartiality.”
63.2.6 DAB proceedings shall be conducted as decided by the DAB. The DAB shall give its decision
within 90 days of a Dispute referred to it by any of the Parties, duly recording the reasons before
arriving at the decision. The DAB shall decide the issue within terms and conditions of the contract.
This time limit shall be extendable subject to the Parties mutual agreement.
63.2.7 The DAB decision shall not be binding on both the Parties. In case any party is not satisfied
by the decision of DAB, then the aggrieved party may approach Arbitral Tribunal for arbitration
proceedings.
63.2.8 No dispute shall be referred to Arbitral Tribunal unless the same has been referred to DAB for
adjudication. However, in case DAB is not formed due to any reason, the disputes can be directly
referred to Arbitral Tribunal to adjudicate the dispute.
63.2.9 In the specific cases of any misconduct by any of the members of the DAB, the parties shall
have the right to specifically bring it to the notice of the DAB such conduct, through a statement filed
with necessary documents in proof of such misconduct and the DAB, after taking NOTICE of such
conduct initiate the replacement of the member concerned, in the same manner the member to be
replaced was appointed.
63.2.10 Once the decision is given by DAB, DAB cannot review the decision at its own or on the
request of one party, unless both parties agree for review of decision by DAB.
63.2.11 In case DAB decision is not challenged by either party within 180 days of receipt of decision
of DAB, the decision shall be considered as final and parties would be barred for referring the same to
Arbitral Tribunal for adjudication.
216
63.2.12 The obligation of RLDA and the Contactor shall not be altered by reasons of issue being or
under reference to DAB.
63.2.13 The DAB shall conduct the proceedings at any convenient venue which shall be decided by
DAB in consultations with parties.
63.2.14 It is a term of this contract that the Parties shall not approach any Court of Law for settlement
of such disputes or differences unless an attempt has first been made by the parties to settle such
disputes or differences through DAB and Arbitral Tribunal.
64.(1)(i): In the event of any dispute or difference between the parties hereto as to the construction or
operation of this contract, or the respective rights and liabilities of the parties on any matter in question,
dispute or difference on any account or as to the withholding by RLDA of any certificate to which the
Contractor may claim to be entitled to, or if RLDA fails to make a decision within 120 days, then and
in any such case, but except in any of the “excepted matters” referred to in Clause 63.1 of these
Conditions, the Contractor, after 120 days but within 180 days of his presenting his final claim on
disputed matters shall demand in writing that the dispute or difference be referred to arbitration.
64.(1)(ii)(a): The demand for arbitration shall specify the matters which are in question, or subject of
the dispute or difference as also the amount of claim item-wise. Only such dispute or difference, in
respect of which the demand has been made, together with counter claims or set off, given by RLDA,
shall be referred to arbitration and other matters shall not be included in the reference.
64.(1)(ii)(b): The parties may waive off the applicability of Sub-Section 12(5) of Arbitration and
Conciliation (Amendment) Act 2015, if they agree for such waiver in writing, after dispute having
arisen between them, in the format given under Annexure XV of these conditions.
64.(1)(iii)(a): The Arbitration proceedings shall be assumed to have commenced from the day, a written
and valid demand for arbitration is received by RLDA.
64.(1)(iii)(b): The claimant shall submit his claims stating the facts supporting the claims alongwith all
the relevant documents and the relief or remedy sought against each claim within a period of 30 days
from the date of appointment of the Arbitral Tribunal.
64.(1)(iii)(c): RLDA shall submit its defence statement and counter claim(s), if any, within a period of
60 days of receipt of copy of claims from Tribunal, unless otherwise extension has been granted by
Tribunal.
64.(1)(iii)(d): Place of Arbitration: The place of arbitration would be within the geographical limits of
the Division of RLDA where the cause of action arose or the Headquarters of the concerned RLDA or
any other place with the written consent of both the parties.
64.(1)(iv): No new claim shall be added during proceedings by either party. However, a party may
amend or supplement the original claim or defense thereof during the course of arbitration proceedings
subject to acceptance by Tribunal having due regard to the delay in making it.
217
64.(1)(v): If the Contractor(s) does/do not prefer his/their specific and final claims in writing, within a
period of 90 days of receiving the intimation from RLDAs that the final bill is ready for payment,
he/they will be deemed to have waived his/their claim(s) and RLDA shall be discharged and released
of all liabilities under the contract in respect of these claims.
64.(2): Obligation During Pendency of Arbitration: Work under the contract shall, unless otherwise
directed by the Engineer, continue during the arbitration proceedings, and no payment due or payable
by RLDA shall be withheld on account of such proceedings, provided, however, it shall be open for
Arbitral Tribunal to consider and decide whether or not such work should continue during arbitration
proceedings.
64.(3)(a)(i): In cases where the total value of all claims in question added together does not exceed ₹
1,00,00,000/- (Rupees One Crore), the Arbitral Tribunal shall consist of a Sole Arbitrator who shall be
a Gazetted Officer of Railways/RLDA not below Junior Administrative Grade, nominated by the Vice
Chairman/RLDA. The sole arbitrator shall be appointed within 60 days from the day when a written
and valid demand for arbitration is received by Vice Chairman/RLDA.
64.(3)(a)(ii): In cases not covered by the Clause 64(3)(a)(i), the Arbitral Tribunal shall consist of a
panel of three Gazetted Railway/RLDA Officers not below Junior Administrative Grade or 2 RLDA
Gazetted Officers not below Junior Administrative Grade and a retired Railway/RLDA Officer, retired
not below the rank of Senior Administrative Grade Officer, as the arbitrators. For this purpose, RLDA
will send a panel of at least four (4) names of Gazetted Railway/RLDA Officers of one or more
departments of Railway/RLDA which may also include the name(s) of retired Railway/RLDA
Officer(s) empanelled to work as Railway/RLDA Arbitrator to the Contractor within 60 days from the
day when a written and valid demand for arbitration is received by the Vice Chairman/RLDA.
Contractor will be asked to suggest to Vice Chairman/RLDA at least 2 names out of the panel for
appointment as Contractor’s nominee within 30 days from the date of dispatch of the request by RLDA.
The Vice Chairman/RLDA shall appoint at least one out of them as the Contractor’s nominee and will,
also simultaneously appoint the balance number of arbitrators either from the panel or from outside
the panel, duly indicating the ‘presiding arbitrator’ from amongst the 3 arbitrators so appointed. Vice
Chairman/RLDA shall complete this exercise of appointing the Arbitral Tribunal within 30 days from
the receipt of the names of Contractor’s nominees. While nominating the arbitrators, it will be
necessary to ensure that one of them is from the Accounts Department. An officer of Selection Grade
of the Accounts Department shall be considered of equal status to the officers in Senior Administrative
Grade of other departments of Railway/RLDA for the purpose of appointment of arbitrator.
64.3.(a).iii: The serving Railway/RLDA officer working in arbitral tribunal in the ongoing arbitration
cases as per clause 64.(3)(a)(i) and clause 64.(3)(a)(ii) above, can continue as arbitrator in the tribunal
even after his retirement.
218
(i) In cases where the total value of all claims in question added together does not exceed ₹ 50,00,000/-
(Rupees Fifty Lakh), the Arbitral Tribunal shall consist of a Retired Railway/RLDA Officer, retired not
below the rank of Senior Administrative Grade Officer, as the arbitrator. For this purpose, RLDA will
send a panel of at least four (4) names of retired Railway/RLDA Officer(s) empanelled to work as
Railway/RLDA Arbitrator duly indicating their retirement dates to the Contractor within 60 days from
the day when a written and valid demand for arbitration is received by the Vice Chairman/RLDA.
Contractor will be asked to suggest to General Manager at least 2 names out of the panel for
appointment as arbitrator within 30 days from the date of dispatch of the request by RLDA. The Vice
Chairman shall appoint at least one out of them as the arbitrator within 30 days from the receipt of the
names of Contractor’s nominees.
(ii) In cases where the total value of all claims in question added together exceed ₹ 50,00,000/- (Rupees
Fifty Lakh), the Arbitral Tribunal shall consist of a Panel of three (3) retired Railway/RLDA Officer,
retired not below the rank of Senior Administrative Grade Officer, as the arbitrators. For this purpose,
RLDA will send a panel of at least four (4) names of retired Railway/RLDA Officer(s) empanelled to
work as Railway/RLDA Arbitrator duly indicating their retirement date to the Contractor within 60
days from the day when a written and valid demand for arbitration is received by the Vice
Chairman/RLDA.
Contractor will be asked to suggest to Vice Chairman/RLDA at least 2 names out of the panel for
appointment as Contractor’s nominee within 30 days from the date of dispatch of the request by RLDA.
The Vice Chairman/RLDA shall appoint at least one out of them as the Contractor’s nominee and will,
also simultaneously appoint the balance number of arbitrators either from the panel or from outside the
panel, duly indicating the ‘Presiding Arbitrator’ from amongst the 3 arbitrators so appointed. Vice
Chairman/RLDA shall complete this exercise of appointing the Arbitral Tribunal within 30 days from
the receipt of the names of Contractor’s nominees. While nominating the arbitrators, it will be necessary
to ensure that one of them has served in the Accounts Department.
64.(3)(c)(i): If one or more of the arbitrators appointed as above refuses to act as arbitrator, withdraws
from his office as arbitrator, or vacates his/their office/offices or is/are unable or unwilling to perform
his functions as arbitrator for any reason whatsoever or dies or in the opinion of the General Manager
fails to act without undue delay, the Vice Chairman/RLDA shall appoint new arbitrator/arbitrators to
act in his/their place in the same manner in which the earlier arbitrator/arbitrators had been appointed.
Such re-constituted Tribunal may, at its discretion, proceed with the reference from the stage at which
it was left by the previous arbitrator (s).
64.(3) (c) (ii): (a) The Arbitral Tribunal shall have power to call for such evidence by way of affidavits
or otherwise as the Arbitral Tribunal shall think proper, and it shall be the duty of the parties hereto to
do or cause to be done all such things as may be necessary to enable the Arbitral Tribunal to make the
award without any delay. The proceedings shall normally be conducted on the basis of documents and
written statements.
(b) Before proceeding into the merits of any dispute, the Arbitral Tribunal shall first decide and pass
its orders over any plea submitted/objections raised by any party, if any, regarding appointment of
Arbitral Tribunal, validity of arbitration agreement, jurisdiction and scope of the Tribunal to deal with
the dispute (s) submitted to arbitration, applicability of time ‘limitation’ to any dispute, any violation
219
of agreed procedure regarding conduct of the arbitral proceedings or plea for interim measures of
protection and record its orders in day to day proceedings. A copy of the proceedings duly signed by
all the members of tribunal should be provided to both the parties.
64.(3)(d)(i): The arbitral award shall state item wise, the sum and reasons upon which it is based. The
analysis and reasons shall be detailed enough so that the award could be inferred therefrom.
64.(3)(d)(ii): A party may apply for corrections of any computational errors, any typographical or
clerical errors or any other error of similar nature occurring in the award of a Tribunal and
interpretation of a specific point of award to Tribunal within 60 days of receipt of the award.
64.(3)(d)(iii): A party may apply to Tribunal within 60 days of receipt of award to make an additional
award as to claims presented in the arbitral proceedings but omitted from the arbitral award.
64.(4): In case of the Tribunal, comprising of three members, any ruling on award shall be made by a
majority of members of Tribunal. In the absence of such a majority, the views of the Presiding
Arbitrator shall prevail.
64.(5): Where the arbitral award is for the payment of money, no interest shall be payable on whole or
any part of the money for any period till the date on which the award is made.
64. (6): The cost of arbitration shall be borne by the respective parties. The cost shall inter-alia include
fee of the arbitrator(s), as per the rates fixed by RLDA/Railway Board from time to time and the fee
shall be borne equally by both the parties, provided parties sign an agreement in the format given at
Annexure XV to these conditions after/ while referring these disputes to Arbitration. Further, the fee
payable to the arbitrator(s) would be governed by the instructions issued on the subject by
RLDA/Railway Board from time to time irrespective of the fact whether the arbitrator(s) is/are
appointed by RLDA/Railway Administration or by the court of law unless specifically directed by
Hon’ble court otherwise on the matter.
220
64.(7) Subject to the provisions of the aforesaid Arbitration and Conciliation Act 1996 and the rules
thereunder and relevant para of the Standard General Conditions of Contract and any statutory
modifications thereof shall apply to the appointment of arbitrators and arbitration proceedings under
this Clause.
64.(8) In case arbitration award is challenged by a party in the Court of Law, 75% of award amount,
pending adjudication by Court of Law, shall be made by party to other party. In case payment is to be
made by RLDA to Contractor, the terms & conditions as incorporated in the Ministry of Railways
letter No. 2016/CE(I)/CT/ARB/3(NITI Aayog)/Pt. dated 08th Mar,2017 as amended from time to time,
shall be followed. In case Contractor has to pay to RLDA, then 75% of the award amount shall be
deducted by RLDA from the Contractor’s bills, Performance Guarantee/ Security Deposit or any other
dues of Contractor with the Government of India.
221
PART-II ANNEXURES
ANNEXURE – VII
Reference Para 17B
Registered Acknowledgement Due
PROFORMA FOR TIME EXTENSION
No. _______________________ Dated: _________________
Sub: (i) _____________________________________________________(name of work).
(ii) Acceptance letter no. _________________________________________________
(iii) Understanding/Agreement no. __________________________________________
Ref: _______________________________________ (Quote specific application of Contractor for
extension to the date received) ___________________________________________
Dear Sir,
1. The stipulated date for completion of the work mentioned above is _______________. From
the progress made so far and the present rate of progress, it is unlikely that the work will be completed
by the above date (or ‘However, the work was not completed on this date’).
2. Expecting that you may be able to complete the work if some more time is given, the competent
authority, although not bound to do so, hereby extends the time for completion from ______________
to _______________.
3. Please note that an amount equal to the liquidated damages for delay in the completion of the
work after the expiry of _______________________ (give here the stipulated date for completion
with/without any liquidated damage fixed earlier) will be recovered from you as mentioned in Clause
17B of the Standard General Conditions of Contract for the extended period, notwithstanding the grant
of this extension. You may proceed with the work accordingly.
4. The above extension of the completion date will also be subject to the further condition that no
increase in rates on any account will be payable to you.
5. Please intimate within a week of the receipt of this letter your acceptance of the extension of
the conditions stated above.
6. Please note that in the event of your declining to accept the extension on the above said
conditions or in the event of your failure after accepting or acting upto this extension to complete the
work by ______________ (here mention the extended date), further action will be taken in terms of
Clause 62 of the Standard General Conditions of Contract.
Yours faithfully
For and on behalf of RLDA
222
ANNEXURE – VIIA
(Reference Clause 40(A)
Registered Acknowledgement Due
PROFORMA OF 14 DAYS NOTICE FOR OFFLOADING OF PART OF CONTRACT
WORK
RLDA
(Without Prejudice)
To
M/s _____________________________
_________________________________
Dear Sir,
Contract Agreement No. _____________________________________________
In connection with _________________________________________________
In spite of repeated instructions to you by the subordinate offices as well as by this office
through various letters of even no. ________________, dated __________; you have failed to show
adequate progress of work so as to complete the contract within the original / extended date of
completion of contract and part(s) of contract work are yet to be started/ still lagging behind the agreed
program of work, listed as under:
(Details of part(s) of work which is delayed and can be executed independently, to be mentioned).
2. Your attention is invited to this office letter no. ___________ ________, dated __________ in
reference to your representation, dated ____________.
3. As you have failed to abide by the instructions issued to commence the work /to show adequate
progress of work, you are hereby given 14 days’ notice in accordance with Clause 40A of the Standard
General Conditions of Contract to deploy adequate resources i.e. (the details of resource requirement,
to be mentioned) and commence / to make good the progress for part(s) of works detailed above, failing
which action as provided in Clause 40A of the Standard General Conditions of Contract shall be
commenced after expiry of 14 days’ notice period viz. to offload few/ all part(s) of work mentioned
above to any of the existing or new contractor without your participation and at your Risk & Cost, not
exceeding the value of Performance Guarantee of this contract, which may please be noted.
223
ANNEXURE – VIIB
RLDA
(Without Prejudice)
To
M/s _____________________________
_________________________________
Dear Sir,
Contract Agreement No. _____________________________________________
In connection with _________________________________________________
1. Fourteen days’ notice under Clause 40A of the Standard General Conditions of Contract was
given to you under this office letter of even no., dated ____________; but you have taken
no/inadequate action to deploy adequate resources to commence the part(s) of work/show adequate
progress of the part(s) of work, mentioned therein.
As you have failed to abide by the instructions issued to commence the part(s) of work/show
adequate progress of the part(s) of work even at the lapse of 14 days’ notice period under Clause 40A
of the Standard General Conditions of Contract, few part(s) of the work under the contract have been
offloaded and being executed by other mode(s) at the cost detailed below:
Or,
1. Please refer your request letter no….. dated ….., wherein it was requested under clause 40 A
of the Standard General Conditions of Contract to offload part(s) of works at your risk & cost. The
details of part(s) of the work under the contract which have been offloaded and being executed by
other mode(s) at the cost detailed below:
(List of Part(s) of work offloaded, Details of mode of execution of such offloaded work alongwith
approximate cost thereof to be mentioned)
2. The final measurement of work(s) already executed for above part(s) of work recorded as per clause
45 (A) or/and 45 (B) of the Standard General Conditions of Contract is enclosed herewith.
4. The additional cost in execution of offloaded work through mode(s) mentioned in para (1) above is
determined as Rs. ___________, over& above the cost of execution under this contract (including the
224
PVC amount payable as per contract, as on the date of issue of this notice). This additional cost shall
be recovered from your next on account bill(s) or any other dues payable to you under contract.
6. You are requested to continue with the balance work in the contract subsequent to offloading of
above part(s) of work.
225
ANNEXURE – VIII
I certify that he/she is fit for employment in a factory or on a work requiring manual labour as
an adult/child.
9. Reasons for :
(a) Refusal to grant certificate, or ____________
(b) Revoking the certificate _________________
Note: In case of physical disability, the exact details and cause of the physical disability should be
clearly stated.
226
ANNEXURE – IX
RLDA
(Without Prejudice)
To
M/s _____________________________
_________________________________
Dear Sir,
Contract Agreement No. _____________________________________________
In connection with _________________________________________________
In spite of repeated instructions to you by the subordinate offices as well as by this office
through various letters of even no. ________________, dated __________; you have failed to start
work/show adequate progress and/or submit detailed programme for completing the work/ part of work
(details of part of work to be mentioned).
2. Your attention is invited to this office letter no. ___________ ________, dated __________ in
reference to your representation, dated ____________.
3. As you have failed to abide by the instructions issued to commence the work /to show adequate
progress of work you are hereby given 7 days’ notice in accordance with Clause 62 of the Standard
General Conditions of Contract to commence works / to make good the progress, failing which further
action as provided in Clause 62 of the Standard General Conditions of Contract viz. to terminate your
Contract and complete the balance work without your participation will be taken.
227
ANNEXURE – X
Reference Para 62(1)
Registered Acknowledgement Due
PROFORMA OF 48 HRS. NOTICE FOR WHOLE WORK
RLDA
(Without Prejudice)
To
M/s _____________________________
_________________________________
Dear Sir,
Seven days’ notice under Clause 62 of the Standard General Conditions of Contract was given
to you under this office letter of even no., dated ____________; but you have taken no action to
commence the work/show adequate progress of the work.
2. You are hereby given 48 hours’ notice in terms of Clause 62 of the Standard General Conditions
of Contract to commence works / to make good the progress of works, failing which and on expiry of
this period your above contract will be rescinded and the work under this contract will be carried out
independently without your participation and your Security Deposit shall be forfeited and Performance
Guarantee shall also be encashed and any other consequences which may please be noted.
Yours faithfully
228
ANNEXURE – XI
Reference Para 62.(1)
Registered Acknowledgement Due
PROFORMA OF TERMINATION NOTICE
RLDA
(Without Prejudice)
No. ________________________________ Dated ____________
To
M/s _____________________________
_________________________________
Dear Sir,
Forty-eight hours (48 hrs.) notice was given to you under this office letter of even no., dated
_______________; but you have taken no action to commence the work/show adequate progress of
the work.
Since the period of 48 hours’ notice has already expired, the above contract stands rescinded
in terms of Clause 62 of the Standard General Conditions of Contract and the balance work under this
contract will be carried out independently without your participation. Your participation as well as
participation of every member/partner in any manner as an individual or a partnership firm/JV is
hereby debarred from participation in the tender for executing the balance work and your Security
Deposit shall be forfeited and Performance Guarantee shall also be encashed.
229
ANNEXURE – XII
1. Seven days’ notice under Clause 62 of the Standard General Conditions of Contract was given
to you under this office letter of even no., dated ____________; but you have taken no action to
commence the work/show adequate progress of the part of work…………………..(details of part to
be mentioned).
2. You are hereby given 48 hours’ notice in terms of Clause 62 of the Standard General Conditions
of Contract to commence works / to make good the progress of works, failing which and on expiry of
this period your above part of work…………………(Details of part to be mentioned) in contract will
be rescinded and the work will be carried out independently without your participation.
3. Your full Performance Guarantee for the contract shall be forfeited and you shall not be issued
any completion certificate for the contract. However, no additional Performance Guarantee shall be
required for balance of work being executed through the part terminated contract.
4. The contract value of part terminated contract shall stands reduced to ………………………..
Yours faithfully
230
ANNEXURE – XIII
1. Forty eight hours (48 hrs.) notice was given to you under this office letter of even no., dated
_______________; but you have taken no action to commence the work/show adequate
progress of the part of work…………………..(details of part to be mentioned).
3. Your full Performance Guarantee for the contract shall be forfeited and you shall not be issued
any completion certificate for the contract. However, no additional Performance Guarantee
shall be required for balance of work being executed through the part terminated contract.
231
ANNEXURE – XIV
232
the Security Deposit by the party hereto of the first part to the party hereto of the second part
against all outstanding dues and claims for all works done under the aforesaid principal
agreement, the party hereto of the second part have no further dues of claims against the party
hereto of the first part under the said Principal Agreement.
(Applicable in case Final Supplementary Agreement is signed before release of Final Payment)
5. It is further agreed and understood by and between the parties that the arbitration clause
contained in the said principal agreement shall cease to have any effect and/or shall be deemed
to be non-existent for all purposes.
Signature of the Contractor/s for and on behalf of RLDA
Witnesses
_______________________
ADDRESS:______________
233
ANNEXURE-XV
I/we...........do/do not agree to waive off applicability of section 12(5) of Arbitration and
Conciliation (Amendment) Act.
234
ANNEXURE-XVI
1. Name:
2. Contact Details:
4. I do not have more than ten on-going Arbitration cases with me.
5. I hereby certify that I have retired from RLDA/Railway w.e.f. _____ and empanelled as
RLDA/Railway’s Arbitrator as per ‘The Arbitration and Conciliation Act- 1996’.
6. I have no any past or present relationship in relation to the subject matter in dispute, whether
financial, business, professional or other kind.
Or
I have past or present relationship in relation to the subject matter in dispute, whether financial,
business, professional or other kind. The list of such interests is as under:
7. I have no any past or present relationship with or interest in any of the parties whether financial,
business, professional or other kind, which is likely to give rise to justifiable doubts as to my
independence or impartiality in terms of The Arbitration and Conciliation Act-1996.
Or
I have past or present relationship with or interest in any of the parties whether financial,
business, professional or other kind, which is likely to give rise to justifiable doubts as to my
independence or impartiality in terms of The Arbitration and Conciliation Act-1996. The details
of such relationship or interests are as under:
8. There are no concurrent Circumstances which are likely to affect my ability to devote sufficient
time to the arbitration and in particular to finish the entire arbitration within twelve months.
Or
There are Circumstances which are likely to affect my ability to devote sufficient time to the
arbitration and in particular to finish the entire arbitration within twelve months. The list of such
circumstances is as under:
235
ANNEXURE-B
LIST OF DRAWINGS
236
37 RLDA-KCPL-ES-AR-303 Section 2 - Part 1 & 2
38 RLDA-KCPL-ES-AR-304 Section 2 - Part 3 & 4
39 RLDA-KCPL-ES-AR-305 Section 3 - Part 1 & 2
40 RLDA-KCPL-ES-AR-306 Section 4 - Part 1 & 2
41 RLDA-KCPL-ES-AR-307 Section 5 - Part 1 & 2
42 RLDA-KCPL-ES-AR-308 Section 6 - Part 1 & 2
43 RLDA-KCPL-ES-AR-309 Sectional Details
44 RLDA-KCPL-ES-AR-400 Site Sections
45 RLDA-KCPL-ES-AR-401 Site Section 01
46 RLDA-KCPL-ES-AR-402 Site Section 01
47 RLDA-KCPL-ES-AR-403 Site Section 02
48 RLDA-KCPL-ES-AR-404 Site Section 03
49 RLDA-KCPL-ES-AR-405 Site Section 03
50 RLDA-KCPL-ES-AR-406 Site Section 04
51 RLDA-KCPL-ES-AR-407 Site Section 04
52 RLDA-KCPL-ES-AR-408 Site Section 04
53 RLDA-KCPL-ES-AR-409 Site Section 04
54 RLDA-KCPL-ES-AR-410 Site Section 04
55 RLDA-KCPL-ES-AR-600 Door Window Details
56 RLDA-KCPL-ES-AR-700 Basement - Male Toilet
57 RLDA-KCPL-ES-AR-701 Basement – Female Toilet
58 RLDA-KCPL-ES-AR-702 Basement – Accessible Toilet
59 RLDA-KCPL-ES-AR-703 Ground - Male Toilet
60 RLDA-KCPL-ES-AR-704 Ground - Female Toilet
61 RLDA-KCPL-ES-AR-705 Ground – Accessible Toilet
62 RLDA-KCPL-ES-AR-706 Ground - Station Master Toilet
63 RLDA-KCPL-ES-AR-707 Concourse - Male Toilet
64 RLDA-KCPL-ES-AR-708 Concourse - Female Toilet
65 RLDA-KCPL-ES-AR-709 Concourse – Accessible Toilet
66 RLDA-KCPL-ES-AR-800 Staircase Detail - ST 1
67 RLDA-KCPL-ES-AR-801 Staircase Detail - ST 2
68 RLDA-KCPL-ES-AR-802 Staircase Detail - ST 3
69 RLDA-KCPL-ES-AR-803 Staircase Detail - ST 4
70 RLDA-KCPL-ES-AR-804 Staircase Detail - ST 5
71 RLDA-KCPL-ES-AR-805 Staircase Detail - ST 6
72 RLDA-KCPL-ES-AR-808 Lift Details - L1
73 RLDA-KCPL-ES-AR-809 Lift Details - L2 & L3
74 RLDA-KCPL-ES-AR-810 Lift Details - L4 & L5
75 RLDA-KCPL-ES-AR-812 Escalator Detail E1
Structure- Foundation, column &
76 RLDA-KCPL-ES-ST-001
Subway Detail
Structure
Structure-Foundation, Column &
77 RLDA-KCPL-ES-ST-002
Subway Detail
237
Structure - Ground & Concourse Beam
78 RLDA-KCPL-ES-ST-003
7 Details
79 RLDA-KCPL-ES-ST-004 General Details & Staircase Details
80 RLDA-KCPL-ES-ST-005 Foundation Plan Platform Side
81 RLDA-KCPL-ES-ST-006 Foundation Plan Platform Side
82 RLDA-KCPL-ES-ST-007 Sectional Elevation of Foundation
83 RLDA-KCPL-ES-ST-008 Column Plan & Detail Platform Side
84 RLDA-KCPL-ES-ST-009 Concourse Floor Beam & Plan
85 RLDA-KCPL-ES-ST-010 Concourse Floor Beam & Plan Details
86 RLDA-KCPL-ES-ST-011 Section Details
87 RLDA-KCPL-ES-ST-012 Section Details
88 RLDA-KCPL-ES-ST-013 Section Details
Stair, lift & Escalator Plan & Details
89 RLDA-KCPL-ES-ST-014
(Concourse)
90 RLDA-KCPL-ES-ST-015 Section Details
91 RLDA-KCPL-ES-ST-016 Foundation, Column & Subway Details
Ground & Concourse Beam, slab and
92 RLDA-KCPL-ES-ST-017
stair details
93 RLDA-KCPL-ES-ST-501 Station Building Hold Portion
94 RLDA-KCPL-ES-ST-502 Station Building Hold Portion
95 RLDA-KCPL-ES-EL-101 Single Line Diagram
Basement Floor Electrical Cable Tray
96 RLDA-KCPL-ES-EL-102
Plan
Ground Floor Electrical Cable Tray
97 RLDA-KCPL-ES-EL-103 Electrical
Plan
Ground Floor Electrical Lighting
98 RLDA-KCPL-ES-EL-104
Layout Plan
99 RLDA-KCPL-ES-EL-105 First Floor Electrical Cable Tray Plan
100 RLDA-KCPL-ES-HVAC-101 Station Building – Section HVAC Plan
Station Building – Basement HVAC
101 RLDA-KCPL-ES-HVAC-102
Plan
HVAC System
102 RLDA-KCPL-ES-HVAC-103 Station Building – Ground HVAC Plan
Station Building – Concourse HVAC
103 RLDA-KCPL-ES-HVAC-104
Plan
Station Building – Basement Level Fire
104 RLDA-KCPL-ES-FF-101
Fighting Layout
Station Building – Basement Level Fire
105 RLDA-KCPL-ES-FF-102
Fighting Layout
Station Building – Basement Level Fire
106 RLDA-KCPL-ES-FF-103
Fighting Layout
Station Building – Basement Level Fire
107 RLDA-KCPL-ES-FF-104
Fighting Layout
Fire Fighting
Station Building – Basement Level Fire
108 RLDA-KCPL-ES-FF-105
Fighting Layout
Station Building – Basement Level Fire
109 RLDA-KCPL-ES-FF-106
Fighting Layout
Station Building – Ground Level Fire
110 RLDA-KCPL-ES-FF-107
Fighting Layout
Station Building – Ground Level Fire
111 RLDA-KCPL-ES-FF-108
Fighting Layout
238
Station Building – Ground Level Fire
112 RLDA-KCPL-ES-FF-109
Fighting Layout
Station Building – Concourse Level
113 RLDA-KCPL-ES-FF-110
Fire Fighting Layout
Station Building – Concourse Level
114 RLDA-KCPL-ES-FF-111
Fire Fighting Layout
Basement Level Water Services
115 RLDA-KCPL-ES-WS-101
Layout
116 RLDA-KCPL-ES-WS-102 Ground Level Water Services Layout
Concourse Level Water Services
117 RLDA-KCPL-ES-WS-103
Layout
Basement Level Typ. Toilet Block
118 RLDA-KCPL-ES-WS-104
Water Services Layout
Basement Level Typ. Toilet Block
119 RLDA-KCPL-ES-WS-105
Water Water Services Layout
Services Ground Level Typ. Toilet Block Water
120 RLDA-KCPL-ES-WS-106
Services Layout
Ground Level Typ. Toilet Block Water
121 RLDA-KCPL-ES-WS-107
Services Layout
Concourse Level Typ. Toilet Block
122 RLDA-KCPL-ES-WS-108
Water Services Layout
Concourse Level Typ. Toilet Block
123 RLDA-KCPL-ES-WS-109
Water Services Layout
Station Building - Schematic Layout
124 RLDA-KCPL-ES-WS-110
Plan
Station Building – Basement Level
125 RLDA-KCPL-ES-DR-101
Drainage Layout
Station Building – Basement Level
126 RLDA-KCPL-ES-DR-102
Drainage Layout
Station Building – Basement Level
127 RLDA-KCPL-ES-DR-103
Drainage Layout
Station Building – Basement Level
128 RLDA-KCPL-ES-DR-104
Drainage Layout
Station Building – Basement Level
129 RLDA-KCPL-ES-DR-105
Drainage Layout
Station Building – Basement Level
130 RLDA-KCPL-ES-DR-106
Toilet Detail- A
Station Building – Basement Level
131 RLDA-KCPL-ES-DR-107
Toilet Detail- B
Station Building – Ground Level
132 RLDA-KCPL-ES-DR-108 Drainage
Drainage Layout
Station Building – Ground Level
133 RLDA-KCPL-ES-DR-109
Drainage Layout
Station Building – Ground Level
134 RLDA-KCPL-ES-DR-110
Drainage Layout
Station Building – Ground Level
135 RLDA-KCPL-ES-DR-111
Drainage Layout
Station Building – Ground Level
136 RLDA-KCPL-ES-DR-112
Drainage Layout
Station Building – Ground Level Toilet
137 RLDA-KCPL-ES-DR-113
Detail- A
Station Building – Ground Level Toilet
138 RLDA-KCPL-ES-DR-114
Detail- B
Station Building – Ground Level Toilet
139 RLDA-KCPL-ES-DR-115
Detail- C
239
Station Building – Concourse Level
140 RLDA-KCPL-ES-DR-117
Drainage Layout
Station Building – Concourse Level
141 RLDA-KCPL-ES-DR-118
Drainage Layout
Station Building – Concourse Level
142 RLDA-KCPL-ES-DR-119
Drainage Layout
Station Building – Concourse Level
143 RLDA-KCPL-ES-DR-120
Drainage Layout
Station Building – Concourse Level
144 RLDA-KCPL-ES-DR-121
Toilet Detail
145 RLDA-KCPL-ES-DR-123 Station Building – Master Plan
240
DETAILED ESTIMATE
DEVELOPMENT OF BIJWASAN RAILWAY STATION AT BIJWASAN, NEW DELHI (BALANCE WORK)
SCHEDULE-A
CIVIL WORKS
1.00 EARTH WORK
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over
areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including
1.01
getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed
by Engineer-in-charge.
2.6.1 All kinds of soil Cum 95249.71 205.45 19,569,052.92
Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or
1.02
stacked materials.
All kinds of soil
2.26.1 1.5 to 3.0 Metre Cum 69928.91 104.50 7,307,571.10
2.26.1 3.0 to 4.5 Meter Cum 68959.38 104.50 7,206,255.21
2.6.1 4.5 to 5.0 Metre Cum 3147.38 104.50 328,901.21
2.6.1 5.0 to 6.5 Metre Cum 3147.38 104.50 328,901.21
2.6.1 6.5 to 8.0 Metre Cum 1609.36 104.50 168,178.12
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations
1.05 2.25 etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming Cum 32866.00 253.95 8,346,320.70
and watering, with all leads and lifts.
Supplying and filling in plinth with sand under floors, including watering, ramming,
1.06 2.27 Cum 1350.00 2161.20 2,917,620.00
consolidating and dressing complete
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and
1.07 2.31 saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal Sqm 125067.03 14.50 1,813,208.35
of rubbish up to a distance of 50 m outside the periphery of the area cleared.
Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery
1.08 2.32 Sqm 125,067.03 7.40 925,496.02
of the area cleared.
Sub-Total of 1 60,459,343.80
Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1 cement :
2 coarse sand (zone-III): 4 graded stone aggregate 12.5mm nominal size) with and
2.02 4.10 including water proofing materials as ordered by the Engineer In Charge in the proportion Sqm 28.34 370.85 10,509.89
as specified by the manufacturer, proper completion of the work including proper curing and
shuttering as necessary
5.9.1 Foundations, footings, bases of columns, etc. for mass concrete Sqm 4059.43 307.95 1,250,101.47
Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc
5.9.2 Sqm 19978.53 669.55 13,376,624.76
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Suspended floors, roofs, landings, balconies and access platform. with water proof ply 12
5.9.3 Sqm 25568.84 766.55 19,599,794.30
mm thick
Lintels, beams, plinth beams, girders, bressumers and cantilevers. with water proof ply 12
5.9.5 Sqm 23748.15 608.35 14,447,187.05
mm thick
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
5.9.6 Columns, pillars, piers, abutments, posts and struts Sqm 22012.92 804.25 17,703,890.91
5.9.7 Stairs, (excluding landings) except spiral-staircases Sqm 1316.08 657.75 865,651.62
5.9.19 Weather shade, Chajjas, corbels etc., including edges Sqm 49.26 814.95 40,144.44
Vertical and horizontal fins individually or forming box louvers band, facias and eaves
5.9.13 Sqm 1100.40
boards.
5.9.14 Extra for shuttering in circular work (20% of respective centering and shuttering items) Sqm 300.00 153.31 45,993.00
Extra for additional height in centering, shuttering where ever required with adequate
bracing, propping etc., including cost of de-shuttering and decentering at all levels, over a
2.06 5.11
height of 3.5 m, for every additional height of 1 metre or part thereof (Plan area to be
measured).
5.11.1 Suspended floors, roofs, landing, beams and balconies (Plan area to be measured) Sqm 60653.72 319.25 19,363,700.11
Providing and laying in position machine batched and machine mixed design mix M-25
grade cement concrete for reinforced cement concrete work, using cement content as per
approved design mix, including pumping of concrete to site of laying but excluding the cost
of centering, shuttering, finishing and reinforcement, including admixtures in recommended
2.07 5.33
proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability
without impairing strength and durability as per direction of Engineer-in-charge.“(Note :-
Cement content considered in this item is @ 330 Kg/Cum.“Excess/ less cement used as per
design mix is payable/recoverable separately).
5.33.1 All works upto plinth level
a 5.33.1.1 Concrete of M25 grade with minimum cement content of 330 kg /cum Cum 22344.98 8683.80 194,039,337.32
2.08 5.33.2 All works above plinth level upto floor V level
5.33.2.1 Concrete of M25 grade with minimum cement content of 330 kg /cum Cum 10600.33 10306.20 109,249,121.05
Providing, hoisting and fixing above plinth level up to floor five level precast reinforced
cement concrete in mouldings as in cornices, windows sills etc, including setting in cement
mortar 1:3 (1cement:3 coarse sand) cost of required centering, shuttering but, excluding the
2.09 5.14 Cum 35.00 15777.40 552,209.00
cost of reinforcement, with 1:1.5:3 (1cement : 1.5 coarse sand (zone-III) derived from
natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural
sources).
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in
2.10 5.22
position and binding all complete at all levels.
Below Plinth Level
5.22.6 Thermo-Mechanically Treated bars of grade Fe-500D or more. kg 2743724 89.65 245,974,820.74
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness)
including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses,
string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills,
2.11 4.2.2 Cum 50.00 9793.75 489,687.30
fillets, sunken floor,etc., up to floor five level, excluding the cost of centering, shuttering and
finishing: 1:1½:3 (1 cement:1½ coarse sand:3 graded stone aggregate 20 mm nominal size)
Providing and fixing of expansion joint system related with floor location as per drawings
and direction of Engineer-In-Charge. The joints system will be of extruded aluminum base
members, self aligning / self centering arrangement and support plates etc. as per ASTM
B221-02. The system shall be such that it provides floor to floor /floor to wall expansion
control system for various vertical locations in load application areas that accommodates
multi directional seismic movement without stress to it's components. System shall consist
of metal profiles with a universal aluminum base member designed to accommodate various
project conditions and finish floor treatments. The cover plate shall be designed of width
2.12 and thickness required to satisfy projects movement and loading requirements and secured
to base members by utilizing manufacturer’s pre-engineered self-centering arrangement
that freely rotates / moves in all directions. The Self - centering arrangement shall exhibit
circular sphere ends that lock and slide inside the corresponding aluminum extrusion cavity
to allow freedom of movement and flexure in all directions including vertical displacement.
Provision of Moisture Barrier Membrane in the Joint System to have watertight joint is
mandatory requirement all as per the manufactures design and as approved by Engineer -in-
Charge. (Material shall conform to ASTM 6063).
Providing and fixing of expansion joint system related with wall joint (internal/ external)
location as per drawings and direction of Engineer-In- Charge. The joints shall be of
extruded aluminum base members, self aligning / centering arrangement and support plates
as per ASTM B221- 02. The material shall be such that it provides an Expansion Joints
2.13 System suitable for vertical wall to wall/ wall to corner application, both new and existing
construction in office Buildings & complexes with no slipping down tendency amongst the
components of the Joint System. The Joint System shall utilize light weight aluminum
profiles exhibiting minimal exposed aluminum surfaces mechanically snap locking the
multicellular to facilitate movement. (Material shall conform to ASTM 6063.)
5.45.1 Wall Joint of 100 mm gap Meter 200.00 4835.50 967,100.00
Providing and fixing of expansion joint system of approved make and manufactures for
various roof locations as per approved drawings and direction of Engineer-In-Charge. The
joints shall be of extruded aluminum base members with, self aligning and self centering
arragement support plates asper ASTM B221-02. The system shall be such that it provides
watertight roof to roof/roof to corner joint cover expansion control system that is capable of
accommodating multidirectional seismic movement without stress to its components.
System shall consist of metal profile that incorporates a universal aluminum base member
designed to accommodate various project conditions and roof treatments. The cover plate
shall be designed of width and thickness required to satisfy movement and loading
2.14
requirements and secured to base members by utilizing manufacturer’s pre-engineered self-
centering arrangement that freely rotates / moves in all directions. The Self centering
arrangement shall exhibit circular sphere ends that lock and slide inside the corresponding
aluminum extrusion cavity to allow freedom of movement and flexure in all directions
including vertical displacement. The Joint System shall resists damage or deterioration from
the impact of falling ice, exposure to UV, airborne contaminants and occasional foot traffic
from maintenance personnel. Provision of Moisture Barrier Membrane in the Joint System to
have water tight joint is mandatory requirement. (Material shall confirm to ASTM 6063.)
Supplying and fixing HSFG bolts of any dia and any length with suitable nuts including DTI
041030 of
3.02 washers conforming to IRS-B1-2001 for bridges and steel structures with contractors Kg 300.00 310.95 93,285.00
IRUSSOR 2019
labour, tools and plants and lead and lift etc., complete.
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc.,
3.03 10.16 including cutting, hoisting, fixing in position and applying a priming coat of approved steel
primer, including welding and bolted with special shaped washers etc. complete.
0.91mm Aluminium color coated profile with center to center pitch of 175 mm, depth of
46mm, top crest width of 41mm, bottom valley width of 80mm, overall profile width of
1144mm, cover width 1050mm.
Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in
0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO
12.66 designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the
sheet and polyester top coat 15-18 microns, using self drilling/ tapping SS screws of size 6
x 50mm with 3mm thick EPDM seal and SS plain washer complete :
12.66.2 Precoated/mill finish aluminium Flashings/ Aprons (upto 600 mm) meter 2983.00 885.50 2,641,446.50
12.66.5 Precoated/mill finish aluminium Crimp curve meter 5221.00 829.05 4,328,470.05
12.66.6 Precoated/mill finish aluminium Gutter (600 mm over all girth) meter 2983.00 1616.00 4,820,528.00
ROLLING SHUTTER
Supplying and fixing rolling shutters of approved make, made of required size M.S. laths,
interlocked together through their entire length and jointed together at the end by end locks,
mounted on specially designed pipe shaft with brackets, side guides and arrangements for
inside and outside locking with push and pull operation complete, including the cost of
3.05 10.6.1 sqm 9.00 3008.80 27,079.17
providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile
steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of
required thickness for rolling shutters. 80 mm x 1.25 mm MS laths with 1.25 mm thick top
cover
3.06 10.7 Providing and fixing ball bearing for rolling shutters each 486.00 424.20 206,161.20
Extra for providing grilled rolling shutters manufactured out of 8 mm dia MS bars instead of
3.07 10.9 Sqm 40.00 668.95 26,758.00
laths as per design approved by Engineer-In-Charge ( Area of grill to be measured)
Sub-Total of 3 606,275,470.03
Providing and laying autoclaved aerated concrete (AAC) blocks masonry with 150mm
to 300 mm thick with Grade 1 AAC blocks of density 551 to 650 Kg/Cum conforming
to IS: 2185 (Part 3) in super structure above plinth level up to floor V level with RCC band
4.04 6.47 cum 4225.79 7213.50 30,482,736.17
at sill level and lintel level with approved block laying polymer modified adhesive mortar all
complete as per direction of Engineer-in-Charge. (The payment of RCC band and
reinforcement shall be made for seperately).
Brick work with common burnt clay F.P.S. (non modular) bricks of class esignation 7.5 in
4.05 6.1.1 cum 210.00 6882 1,445,220.00
foundation and plinth in:
Cement Mortar 1:4 (1 cement : 4 coarse sand)
4.08 6mm cement plaster on RCC work & ceiling with mix
13.16.1 1:3 (1 cement : 3 fine sand) sqm 22371.00 253.05 5,660,910.52
Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand
(zone - III) : 6 graded stone aggregate 20 mm nominal size) over 75mm thick bed of dry
4.09 4.17 brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sqm 430.00 681.65 293,109.50
sand, including necessary excavation, levelling & dressing & finishing the top smooth.
Extra for providing lipping with 2nd class teak wood battens 25 mm minimum depth on all
4.12 9.23 sqm 215.52 401.40 86,509.73
edges of flush door shutters (over all area of door shutter to be measured).
Extra for providing vision panel not exceeding 0.5 sqm in all type of flush doors (cost of
4.13 9.24.1 Sqm 91.96 173.93 15,994.78
glass excluded) (overall area of door shutter to be measured): Rectangular or square
Extra if louvers (not exceeding 0.2 sqm) are provided in flush door shutters(overall area
4.14 9.25 Sqm 215.52 354.55 76,413.37
of door shutters to be measured).
BUTT HINGES
Providing and fixing IS : 12817 marked stainless steel butt hinges with stainless
4.15
steel screws etc. complete :
Item Code 125x64x1.90 mm
Each 516.00 31.00 15,996.00
8215
DOOR STOPPER
Providing and fixing 150 mm bright finished floor brass door stopper with rubber cushion,
necessary brass screws etc. to suit shutter
4.16 14.34 Each 92.00 233.10 21,445.20
thickness complete
DOOR CLOSER
Providing and fixing aluminium extruded section body tubular type
universal hydraulic door closer (having brand logo with ISi, IS : 3564,
4.17 9.84 embossed on the body, door weight upto 36 kg to 80 kg and door width Each 92.00 856.30 78,779.60
from 701 mm to 1000 mm), with double speed adjustment with necessary
accessories and screws etc. complete.
SLIDING DOOR BOLT
Providing and fixing aluminium sliding door bolts, ISI marked anodised (anodic coating not
less than grade AC 10 as per IS : 1868), transparent or dyed to required colour or shade,
4.18
with nuts and screws
etc. complete
9.96 250 X 16 MM Each 76.00 234.90 17,852.40
MORTICE LOCK
Providing and fixing bright finished brass 100 mm mortice latch and
lock, ISI marked, with six levers and a pair of anodised (anodic coating
4.19 9.103 Each 76.00 739.80 56,224.80
not less than grade AC 10 as per IS : 1868) aluminium lever handles of
approved quality with necessary screws etc. complete.
KICKING PLATE
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Providing and fixing 50 cm long aluminium kicking plate of size 100x3.15 mm, anodised
4.20 9.99 (anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed to required Each 76.00 212.85 16,176.60
colour or shade, with necessary screws etc. complete.
ALUMINIUM FRAME FOR WINDOW
Providing and fixing aluminium work for doors, windows, ventilators and partitions
with extruded built up standard tubular sections/ appropriate Z sections and other sections
of approved make conforming to IS: 733 and IS: 1285, fixing with dash fasteners of required
dia and size, including necessary filling up the gaps at junctions, i.e. at top, bottom and
sides with required EPDM rubber/ neoprene gasket etc. Aluminium sections shall be
4.21 21.1.1.2 smooth, rust free, straight, mitred and jointed mechanically wherever required including kg 504.00 466.30 235,015.20
cleat angle, Aluminium snap beading for glazing / paneling, C.P. brass / stainless steel
screws, all complete as per architectural drawings and the directions of Engi neer-in-
charge.For Fixed Portion (Glazing, paneling and dash fasteners to be paid for separately)
:Powder coated aluminium (minimum thickness of powder coating 50 micron)
Providing and fixing glazing in aluminium door, window, ventilator shutters and
partitions etc. with EPDM rubber / neoprene gasket etc. complete as per the architectural
4.22 21.3.3 drawings and the directions of engineer-in-charge . (Cost of aluminium snap beading shall sqm 64.80 1496.15 96,950.52
be paid in basic item): With float glass panes of 8 mm thickness (weight not less than 20 kg/
sqm) including the glazing work in Vestibule Area
Providing and fixing double glazed hermetically sealed glazing in aluminium windows,
ventilators and partition etc. with 6 mm thick clear float glass both side, having 12 mm air
4.23 21.10 gap, including providing EPDM gasket, perforated aluminium spacers, desiccants, sealant sqm 65.00 4013.35 260,867.75
(Both primary and secondary sealant) etc. as per specifications, drawings and direction of
Engineer-in-charge complete.
Providing and fixing 12mm thick frameless toughened glass door shutter of approved brand
and manufacture, including providing and fixing top & bottom pivot & double acting
4.24 21.18 hydraulic floor spring type fixing arrangement and making necessary holes etc. for fixing sqm 4640.51 4540.70 21,071,141.05
required door fittings, all complete as per direction of Engineer in charge (Door handle, lock
and stopper etc. to be paid separately)
Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm
diameter bolts, nuts and wooden plugs and embedding in cement concrete block
4.25 9.53 300x100x150cm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm Nos 456.00 194.35 88,623.60
nominal size).
Providing and fixing fire resistant door frame of section 50 x 60 mm on horizontal side & 35
x 60 mm on vertical sides having built in rebate made out of 1.6 mm thick GI sheet ( Zinc
coating not less than 120gm/m²) suitable for mounting 120 min Fire Rated Glazed Door
Shutters. The frame shall be filled with Mineral wool Insulation having density min 96Kg/m³ .
The frame will have a provision of G.I. Anchor fastners 14 nos ( 5 each on vertical style & 4
4.26 9.161 Meter 16.80 1791.05 30,089.64
on horizontal style of size M10 x 80 ) suitable for fixing in the opening along with Factory
made Template for SS Ball Bearing Hinges of Size 100x89x3mm for fixing of fire rated
glazed shutter . The frame shall be finished with a approved fire resistant primer or Powder
coating of not less than 30 micron in desired shade as per the directions of Engineer - in-
charge . (Cost of SS ball bearing hinges is excluded).
FIRE DOOR SHUTTER
Providing and fixing 60 mm thick glazed fire resistant door shutters of 120 min Fire Rating
confirming to IS:3614 (Part II) or EN1634-1:1999, tested and certified as per laboratory
approved by Engineer-in-charge, with suitable mounting on door frame, consisting of
vertical styles, top rail & side rail 60 mm x 60 mm wide and bottom rail of 110 mm x 60 mm
made out of 1.6mm thick G.I. sheet (zinc coating not less than 120gm/m²) duly filled mineral
4.27 9.162 wool insulation having density min 96 kg/m³ and fixing with necessarystainless steel ball Sqm 28.80 9736.05 280,398.24
bearing hinges of size 100x89x3mm of approved make, including applying a coat of
approved fire resistant primer or powder coating not less than 30 micron etc all complete as
per direction of Engineer-in-charge (panelling to be paid for seperately).
PANIC BAR
Providing and fixing panic bar / latch (Double point) fitted with a single body, Trim Latch &
Lock on back side of the Panic Latch of reputed brand and manufacture to be approved by
4.29 9.139 Sqm 40.00 7145.90 285,836.00
the Engineer- in- charge, all complete.
Forming groove of uniform size from 12x12mm and upto 25x18mm in plastered
surface as per approved pattern using wooden battens, nailed to the under layer
4.30 13.76 including removal of wooden battens, repairs to the edges of plaster panel and Meter 320.19 88.70 28,400.85
finishing the groove complete as per specifications and direction of the Engineer-in-
Charge.
PLASTER OF PARIS
Providing and applying plaster of paris putty of 4 mm thickness over plastered
surface to prepare the surface even and smooth complete. putty (JK wall care, Birla putty,
4.31 13.26 SARA wall putty or approved equivalent) and grinding the surface smooth with sand paper sqm 55952.89 214.30 11,990,530.08
to get an even and smooth finish including cost and cartage of all materials, labour charges,
scaffolding, sundries etc. complete.
WHITE WASH
4.32 13.37.1 White washing with lime to give an even shade. New work ( three or more coats) sqm 12000.00 32.45 389,400.00
EPOXY PAINT ON STRUCTURAL STEEL
Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per
manufacturer's specifications including appropriate priming coat, preparation of surface, etc.
4.33 13.52.1 Sqm 20423.20 201.70 4,119,359.44
complete.
On steel work
GRANITE CLADDING
Stone tile work for wall lining upto 10 m height with special adhesive over 12 mm thick bed
4.34 7.38 of cement mortar 1:3 (1 cement : 3 coarse sand), including pointing in white cement with an
admixture of pigment to match the stone shade
7.38.1 18mm thick (mirror polished and machine cut edge)
Granite stone of any colour and shade
7.38.1.1 Sqm 8684.00 4200.00 36,472,800.00
STAINLESS STEEL CRAMP
Providing and fixing cramps of required size & shape in RCC/ CC / Brick masonry backing
with cement mortar 1:2 ( 1 cement :2 coarse sand),
4.35
including drilling necessary hole in stones and embedding the cramp in
the hole (fastener to be paid separately).
8.7.2 Stainless steel cramps kg 1700.00 624.95 1,062,415.00
HOLD FASTNERS
Providing and fixing expansion hold fasteners on C.C. /R.C.C./Brick masonry surface
4.36
backing including drilling necessary holes and the cost of bolt etc. complete in all respect.
8.8.1.2 Fastener with threaded dia 10 mm Each 29000.00 33.80 980,200.00
INTERNAL ACRYLIC EMULSION
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Finishing walls with 100% Premium acrylic emulsion paint having VOC less than 50 gm/litre
4.37 and UV resistance as per IS 15489:2004, Alkali & fungal resistance, dirt resistance exterior
paint of required shade (Company Depot Tinted) with silicon additives.
New work (Two or more coats applied @ 1.43 litre/ 10 sqm. Over and including priming coat
13.48A Sqm 21450.00 154.45 3,312,952.50
of exterior primer applied @ 0.90 litre/10 sqm.
4.38 13.45 Finishing walls with textured exterior paint of required shade :
New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including priming coat of
13.45.1 sQM 17000.00 245.00 4,165,000.00
exterior primer applied @ 2.20kg/10 sqm
4. On this, 1st coat of melamine polish is applied with spray gun using melamine clear
polish and melamine thinner in required proportion. This 1st coat is allowed to dry for 24 hrs
then this dry surface is again fine wet rubbed smooth, which is further allowed to dry for 12
13.116 hrs. The final melamine polish is applied with compressor pressure spray gun using Sqm 500.00 1156.55 578275.00
melamine clear polish and melamine thinner mixed in required proportion complete as per
direction of Engineer-in-Charge. (Final coat to be done in 1 or 2 layers without gap of time.)
GI Metal Ceiling Lay in perforated Tegular edge global white color tiles of size 595x595 mm
and 0.5 mm thick with 8 mm drop; made of GI sheet having galvanizing of 100 gms/sqm
(both sides inclusive) and 20% perforation area with 1.8 mm dia holes and having NRC
12.52.2 Sqm 8486.5 1746.25 14,819,550.63
(Noise Reduction Coefficient ) of 0.5, electro statically polyester powder coated of thickness
60 microns (minimum), including factory painted after bending and perforation, and backed
with a black Glass fiber acoustical fleece.
the perimeter of ceiling fixed to wall/partition with the help of rawl plugs at 450 mm centre,
with 25mm long dry wall screws @ 230 mm interval, including fixing of gypsum board to
ceiling section and perimeter channel with the help of dry wall screws of size 3.5 x 25 mm at
230 mm c/c, including jointing and finishing to a flush finish of tapered and square edges of
the board with recommended jointing compound , jointing tapes , finishing with jointing
compound in 3 layers covering upto 150 mm on both sides of joint and two coats of primer
suitable for board, all as per manufacturer's specification and also including the cost of
making openings for light fittings, grills, diffusers, cutouts made with frame of perimeter
channels suitably fixed, all complete as per drawings, specification and direction of the
Engineer in Charge but excluding the cost of painting with :
12.5 mm thick tapered edge gypsum plain boardconforming to IS: 2095- (Part I) :2011
12.45.1 Sqm 17000.00 1145.95 19,481,150.00
(Board with BIScertification marks)
Providing and fixing plain multipurpose cement board(Hight pressure steam cured) with
4.43 12.26 suitable screws for cement particle board in ceiling etc. complete (frame work to be paid
seperatately).
12.26.1 6 mm thick Cement fiber board as per IS: 14862 Sqm 8900.00 773.40 6,883,260.00
FLOORING WORKS
GRANITE COUNTERS
Providing and fixing 18 mm thick gang saw cut, mirror polished, premoulded and
prepolished, machine cut for kitchen platforms, vanity counters, window sills, facias and
similar locations of required size, approved shade, colour and texture laid over 20 mm thick
4.44
base cement mortar 1:4 (1 cement : 4 coarse sand), joints treated with white cement, mixed
with matching pigment, epoxy touch ups, including rubbing, curing, moulding and polishing
to edges to give high gloss finish etc. complete at all levels.
Granite stone slab of all colour and texture except black, Cherry/
8.2.3.2 sqm 200.00 3301.45 660,290.00
Ruby red (over 0.5 sqm)
EDGE MOULDING COUNTERS
Providing edge moulding to 18 mm thick marble stone counters, Vanities etc., including
4.45 8.3 machine polishing to edge to give high gloss finish etc. complete as per design approved by
Engineer-in-Charge.
8.3.2 Granite work Metre 2500.00 418.85 1,047,116.84
Extra for providing opening of required size & shape for wash basin/ kitchen sink in
kitchen platform, vanity counter and similar location in marble/ Granite/ stone work,
4.46 8.5 each 119.00 808.15 96,169.85
including necessary holes for pillar taps etc. including moulding, rubbing and polishing of
cut edges etc. complete.
VDC FLOORING
Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching
plant. The ready mixed concrete shall be laid and finished with screed board vibrator,
Derived from vacuum dewatering process and finally finished by floating, brooming with wire brush etc.
4.47 Cum 9352.00 8989.73 84,071,942.21
16.75 complete as per specifications and directions of Engineer-in- charge. (The panel shuttering
work shall be paid for separately) with floor hardener @ 2 ltr per 50 kg of cement
(Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used
as per design mix is payable/ recoverable separately).
GLAZED VITRIFIED TILE 600mm x 600mm
Providing and laying Vitrified tiles in floor in different sizes (thickness to
be specified by the manufacturer) with water absorption less than 0.08% and conforming to
IS:15622, of approved brand & manufacturer, in all colours and shade, laid on 20 mm thick
cement mortar 1:4 (1 cement: 4 coarse sand) jointing with grey cement slurry @3.3 kg/sqm
4.48 11.41A including grouting the joints with white cement and matching pigments etc. The tiles must be
cut with the zero chipping diamond cutter only . Laying of tiles will be done with the notch
trowel, plier, wedge, clips of required thickness, leveling system and rubber mallet for
placing the tiles gently and easily.
11.41A.2.1 Glazed vitrified floor tiles polished finish of size of Tile 600 x 600 mm sqm 9200.00 1359.20 12,504,640.00
Providing and fixing 10 mm thick acid and/or alkali resistant tiles of approved make and
colour using acid and/or alkali resisting mortar bedding, and joints filled with acid and/or
4.50 11.21
alkali resisting cement as per IS : 4457, complete as per the direction of Engineer-in-
Charge.
11.21.1 In flooring on a bed of 10 mm thick mortar 1:4 (1 acid proof cement : 4 coarse sand)
11.21.1.1 Acid and alkali resistant tile sqm 1515.45 sqm 25.00 1515.00 37,875.00
11.21.2 In dado/skirting on 12 mm thick mortar 1:4 (1 acid proof cement : 4 coarse sand) sqm 40.00 1637.00 65,480.00
Acid and alkali resistant tile
(a) Providing at required spacing to form modular framework, pedestals made out of GI tube
of thickness minimum 2 mm and 25 mm outer diameter, fully welded on to the G.I. Base
plate of size 100mm x 100mm x 3mm at the bottom of the pedestal tube, G.I. pedestal head
of size 75mmx75mmx3.5 mm welded with GI fully threaded stud 16mm outer diameter with
two GI Check nuts screwed on the stud for level adjustment upto 50mm, locking and
stabilizing the pedestal head in position at the required level. The pedestals shall be fixed
to the subfloor (base) through base plate using epoxy based adhesive of approved make or
the machine screw with rawl plug.
(b) Stringers system in all steel construction hot dipped galvanized of rectangular size
570x20x30x0.80mm thick having holes at both ends for securing the stringers on to the
pedestal head using fully threaded screws ensuring maximum lateral stability in all
directions, the grid formed by the pedestal and stringer assembly shall receive the floor
panel, this system shall provide adequate solid, rigid support for access floor panel, the
system shall provide a minimum clear uninterrupted clearance between the bottom of the
floor for electrical conduits and wiring etc. all complete as per the architectural drawings, as
specified and as directed by the Engineer-in-charge.
(c) Providing and fixing Access Floor panel of 600x600x32 mm medium grade Filled Steel
anti static high pressure Lamination of 800H grade (FS800H). Access Floor panel shall be
steel welded construction with an enclosed bottom pan with uniform pattern of 64
hemispherical cones. The top and bottom plates of Steel Gauges: top 0.6 mm and bottom
0.7 mm fused spot welded together (minimum 64 welds in each dome and 20 welds along
each flange). The panel should be Corrosion resist epoxy coated for lifetime rust protection
and cavity formed by the top and bottom plate is filled with Pyrogrip noncombustible
Portland cementitious core mixed with lightweight foaming compound. The access floor
shall be factory finished with Anti-static High Pressure laminate with Non Warp technology
upto 1mm thickness for superior adhesion and Surface flatness within 0.75mm. The panel is
to withstand a Concentrated Load of 363 kgs applied on area 25mm x 25mm without
collapse in the centre of the panel which is placed on four steel blocks. The panel will
withstand and Uniformly Distributed Load (UDL) minimum 1250 kg/sqm and an impact load
of 50kg all complete as per the approved manufacturers specification and as per the
direction of Engineer-in-charge. All specification must be printed on the side of the panel to
ensure the quality of the product.
11.54.1 300 mm Finished Floor Height (FFH) sqm 25.00 5094.10 127,352.50
Providing and laying Vitrified tiles in different sizes (thickness to be specified by the
manufacturer), with water absorption less than 0.08% and conforming to IS: 15622, of
approved brand & manufacturer, in all colours and shade, in skirting, riser of steps, laid with
4.52 11.46
cement based high polymer modified quick set tile adhesive (water based) conforming to IS:
15477, in average 6 mm thickness, including grouting of joints
(Payment for grouting of joints to be made separately)
11.46.2 Size of Tile 600 x600 mm Sqm 8,813.00 1466.50 11,978,629.60
Grouting the joints of flooring tiles having joints of 3 mm width, using epoxy grout mix of
0.70 kg of organic coated filler of desired shade (0.10 kg of hardener and 0.20 kg of resin
4.53 11.48
per kg), including filling / grouting and finishing complete as per direction of Engineer-in-
charge.
11.48.2 Size of Tile 600 x 600 mm Sqm 11700.00 258.65 3,026,206.26
Cement plaster skirting (upto 30 cm height) with cement mortar 1:3 (1 cement : 3 coarse
4.56 11.6.1 sqm 935.20 570.75 533,765.40
sand) finished with a floating coat of neat cement. 18 mm thick
TACTILE FLOORING
Providing and laying tactile tile (for vision impaired persons as per standards) of size
300x300x9.8mm having with water absorption less than 0.5% and conforming to IS:15622 of
approved make in all colours
4.57 16.90 and shades in for outdoor floors such as footpath, court yard, multi modals location etc., laid Sqm 1600.00 1,719.00 2,750,400.00
on 20mm thick base of cement mortar 1:4 (1 cement : 4 coarse sand) in all shapes &
patterns including grouting the joints with white cement mixed with matching pigments etc.
complete as per direction of Engineer-in-Charge.
STRUCTURAL GLAZING
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Designing, fabricating, testing, protection, installing and fixing in position semi (grid)
unitized system of structural glazing (with open joints) for linear as well as curvilinear
portions of the building for all
heights and all levels, including:
(a) Structural analysis & design and preparation of shop drawings for the specified design
loads conforming to IS 875 part III (the system must passed the proof test at 1.5 times
design wind pressure without any failure), including functional design of the aluminum
sections for fixing glazing panels of various thicknesses, aluminium cleats, sleeves and
splice plates etc. gaskets, screws, toggles, nuts, bolts, clamps etc., structural and weather
silicone sealants, flashings, fire stop (barrier)- cum-smoke seals, microwave cured EPDM
gaskets for water tightness, pressure equalisation & drainage and protection against fire
hazard including:
(b) Fabricating and supplying serrated M.S. hot dip galvanised /
Aluminium alloy of 6005 T5 brackets of required sizes, sections
4.59 25.2 and profiles etc. to accommodate 3 Dimentional movement Sqm 9700.00 3111.35 30,180,095.00
for achieving perfect verticality and fixing structural glazing
system rigidly to the RCC/ masonry/structural steel framework
of building structure using stainless steel anchor fasteners/
bolts, nylon seperator to prevent bimetallic contacts with nuts
and washers etc. of stainless steel grade 316, of the required
capacity and in required numbers.
(c) Providing and filling, two part pump filled, structural silicone
sealant and one part weather silicone sealant compatible with
the structural silicone sealant of required bite size in a clean
and controlled factory / work shop environment, including double
sided spacer tape, setting blocks and backer rod, all of
approved grade, brand and manufacture, as per the approved
sealant design, within and all around the perimeter for holding
glass.
Providing, assembling and supplying vision glass panels (IGUs) comprising of hermetically-
sealed 6-12- 6 mm insulated glass (double glazed) vision panel units of size and shape as
required and specified, comprising of an outer heat strengthened float glass 6mm thick, of
approved colour and shade with reflective soft coating on surface # 2 of approved colour
and shade, an inner Heat strengthned clear float glass 6mm thick, spacer tube 12mm wide,
dessicants, including primary seal and secondary seal (structural silicone sealant) etc. all
complete for the required performances, as per the Architectural drawings, as per the
approved shop drawings, as specified and as directed by the Engineer-in-Charge. The
IGUs shall be assembled in the factory/ workshop of the glass processor.
(Payment for fixing of IGU Panels in the curtain glazing is included in
cost of item No.25.2)
For payment, only the actual area of glass on face # 1 of the glass
4.60 25.3 Sqm 9743.59 3377.50 32,908,975.23
panels (excluding the areas of the grooves and weather silicone
sealant) provided and fixed in position, shall be measured in sqm.
(i) Coloured tinted float glass 6mm thick substrate with reflective
soft coating on face # 2, + 12mm Airgap + 6mm Heat
Strengthened clear Glass of approved make having properties
as visible Light transmittance (VLT) of 25 to 35 %, Light
reflection internal 10 to 15%, light reflection external 10 to 20
%, shading coefficient (0.25- 0.28) and U value of 3.0 to 3.3 W/
m2 degree K etc. The properties of performance glass shall be
decided by technical sanctioning authority as per the site
requirement.
Extra for openable side / top hung vision glass panels (IGUs) including providing and
supplying at site all accessories and hardwares for the openable panels as specified and of
the approved make such as heavy duty stainless steel friction hinges, min 4 -point cremone
4.61 25.4 locking sets with stainless steel plates, handles, buffers etc. including necessary stainless Sqm 1455.00 3309.05 4,814,667.75
steel screws/ fasteners, nuts, bolts, washers etc. all complete as per the Architectural
drawings, as per the approved shop drawings, as specified and as directed by the
Engineer-in-Charge.
Providing, fabricating and supplying shadow box of required size and shape, for fixing in the
spandrel portion of the structural glazing, in linear as well as curvilinear portions of the
building by providing semi-rigid, inorganic, non-combustible fibre glass wool insulation 50
mm thick, conforming to IS: 8183 and BS: 3958 Part 5. The insulation layer shall have
4.62 25.50 facing (factory bonded on surface # 1 of the fibre glass insulation layer), of black non-woven Sqm 974.36 1954.30 1,904,189.79
fibre glass tissue of nominal thickness 0.5 mm and nominal mass not less than 60 gm /sqm,
made of randomly oriented glass fibres distributed in a binder by a wet-lay process
including fixing 1.5 mm thick solid aluminum sheet backing using, 6 mm thick cement board
including SS rivets, nuts, bolts, washers etc complete.
HEAT RESISTANCE TILES
Providing and fixing Heat Resistant Terrace Tiles (300 mm x 300 mm x 20 mm) with SRI
(solar refractive index) > 78, solar reflection > 0.70 and initial emittance > 0.75 on
waterproof and sloped surface of terrace, laid on 20 mm thick cement sand mortar in the
4.63 12.55 ratio of 1:4 (1 cement : 4 coarse sand) and grouting the joints with mix of white cement & Sqm 9200.00 1444.90 13,293,066.35
marble powder in ratio of 1:1, including rubbing and polishing of the surface upto 3 cuts
complete, including providing skirting upto 150 mm height along the parapet walls in the
same manner.
MS FOOT REST
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete
4.64 19.15.1 blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as Each 73.00 461.35 33,678.55
per standard design : With 20x20 mm square bar
Sub-total of 4 431,405,035.01
Extra for compaction of earth work in embankment under optimum moisture conditions
5.02 16.2 cum 25,013.41 20.55 513,948.52
to give at least 95% of the maximum dry density (proctor density).
Banking excavated earth in layers not exceeding 20 cm in depth, breaking clods, watering,
rolling each layer with ½ tonne roller, or wooden or steel rammers, and rolling every 3rd and
top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for
5.03 2.3 Cum 25,000.00 543.40 13,585,000.00
roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and lift upto 1.5 m
:
All kinds of soil
Providing, laying, spreading and compacting graded stone aggregate (size range 53
mm to 0.075 mm) to wet mix macadam (WMM) specification including premixing the
material with water at OMC in mechanical mix plant, carriage of mixed material by
5.05 16.79 mechanical transport to site, for all leads & lifts, laying in uniform layers with mechanical cum 18,750.00 2803.65 52,568,437.50
paver finisher in sub- base /base course on well prepared surface and compacting with
vibratory roller of 8 to 10 tonne capacity to achieve the desired density, complete as per
specifications and directions of Engineer-in-Charge.
Providing and laying bituminous macadam using crushed stone aggregates of specified
grading premixed with bituminous binder, transported to site by tippers, laid over a
previously prepared surface with paver finisher equiped with electronic sensor to the
required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem
rollers as per specifications to achieve the desired compaction and density, complete as per
5.06 16.55.1 Cum 8,496.10 7756.40 65,899,181.07
specificatons and directions of Engineer-in-Charge.
Providing and laying factory made chamfered edge Cement Concrete paver blocks in
footpath, parks, lawns, drive ways or light traffic parking etc, of required strength, thickness
& size/ shape, made by table vibratory method using PU mould, laid in required colour &
pattern over 50mm thick compacted bed of sand, compacting and proper embedding/laying
5.09 16.91 sqm
of inter locking paver blocks into the sand bedding layer through vibratory compaction by
using plate vibrator, filling the joints with sand and cutting of paver blocks as per required
size and pattern, finishing and sweeping extra sand. complete all as per direction of
Engineer-in-Charge
60 mm thick C.C. paver block of M-35 grade with approved color design and pattern.
16.91.1 sqm 10,640.00 932.35 9,920,204.00
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Providing and laying at or near ground level factory made kerb stone of M-25 grade cement
concrete in position to the required line, level and curvature, jointed with cement mortar 1:3
(1 cement: 3 coarse sand), including making joints with or without grooves (thickness of
5.10 16.69 joints except at sharp curve shall not to more than 5mm), including making drainage cum 930.77 8613.55 8,017,216.71
opening wherever required complete etc. as per direction of Engineer-in-charge (length of
finished kerb edging shall be measured for payment). (Precast C.C. kerb stone shall be
approved by Engineer-in-charge).
Providing and laying 500x500x40 mm thick Turf paver (Turfpave XD) on 150 mm thick sub
grade of compacted bed of 20 mm thick nominal size stone aggregate and base course and
filling with 150 mm thick jamuna sand, including spreading, well ramming, consolidating and
5.11 11.45 Sqm 2,200.00 1613.00 3,548,600.00
finishing smooth etc. all complete as per direction of Engineer-in-charge.
Making bell mouth opening/ entrance of size 100x50x50 cm for drainage pipe under
footpath, including providing cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded
stone aggregate 20 mm nominal size) for shape of bell mouth, including plastering providing
5.12 16.49 and fixing precast R.C.C./ S.F.R.C. slab including plastering with cement mortar 1:3 (1 Each 200.00 2712.20 542,440.00
cement : 3 fine sand) of 6 mm thickness on exposed surface of the slab & bell mouth
including centring, shuttering & neat cement punning inside the bell mouth etc. all complete
Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement
concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size)
5.13 16.63 over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and Sqm 5400.00 529.80 2,860,920.00
grouted with fine sand, including finishing the top smooth etc. complete and as per direction
of Engineer-in-charge
Providing and placing in position 100 mm thick factory made machine batched & machine
mixed Precast RCC Rectangular Covers on drains of footpath of various sizes, of M-25
grade cement concrete for RCC work, including cost of centering, shuttering, reinforcement
of 8 mm dia TMT bars of Fe 500 grade @ maximum 100mm c/c on both ways , neat cement
5.14 16.93 punning on finished surface, properly encased on all edges with 1.6 mm thick , 100 mm sqm 200.00 2617.15 523,430.00
wide MS sheet duly painted over priming coat , reinforcement to be welded at edges with
MS sheet and providing 2 Nos. 12 mm dia bar for hooks etc i/c cost of cartage, all leads &
lift, handling at site etc. all complete as per direction of Engineer-in-Charge.
Sub-total of 5 253,511,304.21
6.03 18.53.1 Providing and fixing C.P. brass angle valve of approved quality conforming to IS:8931 Each 348.00 500.35 174121.80
13.19 Providing and fixing custom made mirror in superior class complete with 6mm thick
6.04 hard board ground fixed to plastic cleats with CP brass screws and washers complete 75.00 Square Meter 1817.20 136290.00
as per directions of Engineer-Incharge.
Providing and fixing water closet squatting pan (Indian type W.C. pan) with 100 mm sand
cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern, including flush pipe,
with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and
6.05 17.1.1 Each 1.00 5781.35 5781.35
fixtures complete, including cutting and making good the walls and floors wherever required
White Vitreous china Orissa pattern W.C. pan of size 580x440 mm with integral type foot
rests
Providing and fixing custom made mirror in superior class complete with 6mm thick hard
6.06 17.32.4 board ground fixed to plastic cleats with CP brass screws and washers complete as per Sqm 75.00 1817.20 136290.00
directions of Engineer-Incharge.
Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and
6.07
making good the walls etc (Internal work). Exposed on wall
18.10.3 25mm nominal bore Meter 10.00 103.85 1038.50
18.10.4 32 mm nominal bore Meter 5.00 123.80 619.00
18.10.5 40mm nominal bore Meter 5.00 144.40 722.00
18.10.6 50mm nominal bore Meter 5.00 203.00 1015.00
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Providing and fixing chlorinated polyvinyl chloride (CPVC) pipes having thermal stability for
hot and cold water supply including all CPVC plain and brass threaded fittings i/c fixing the
pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step
6.08
CPVC solvent cement and testing of joints complete as per direction of Engineer-Incharge.
Internal work - exposed on wall
Providing and fixing chlorinated polyvinyl chloride (CPVC) pipes having thermal stability for
hot and cold water supply including all CPVC plain and brass threaded fittings i/c fixing the
pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step
6.09
CPVC solvent cement and testing of joints complete as per direction of Engineer-Incharge.
Concealed work including cutting chases and making good the walls etc.
Constructing brick masonry Chamber for underground CI Inspection chamber and bends
with bricks in cement mortar 1:4 (1 cement : 4 coarse sand) CI cover with frame
455x610mm internal dimensions, total weight of cover with frame to be not less than 38 KG
(23kg& 15kg for cover & frame respectively), RCC top slab with 1:1.5:3 (1 cement : 1.5 fine
6.10
sand : 3 graded stone aggregate 20mm nominal size), foundation concrete 1:5:10 (1
cement : 5 fine sand : 10 graded stone aggregate 40mm nominal size) and inside plastering
with cement mortat 1:3 (1cement :3 coarse sand) 12mm thick finished with a floating coat of
neat cement complete as per standard design.
Inside dimensions 500x700 mm and 45 cm deep for pipe line with one or two inlets, With
19.30.2 Each 1.00 7308.15 7308.15
F.P.S. bricks of class designation 7.5
Providing and fixing in position precast R.C.C. manhole cover and frame of required shape
6.11
and approved quality
L D- 2.5
19.19.1.1 a) Circular shape 60mm internal diameter Each 16.00 699.15 11186.40
Providing orange colour safety foot rest of minimum 6mm thick plastic encapsulated as per
IS : 10910 on 12mm dia steel bar conforming to IS : 1786 having minimum cross section as
23 mmx25mm and over all minimum length 263mm and width as 165mm with minimum
112mm space between protruded legs having 2 mm tread on top surface by ribbing or
chequering besides necessary and adequate anchoring projections on tail length on 138
6.12 19.16 Each 80.00 487.10 38968.00
mm as per standard drawing and suitable to with stand the bend test and chemical
resistance test as per specifications and having manufacture's permanent identification
mark to be visible even after fixing, including fixing in manholes with 30x20x15 cm cement
concrete block 1:3:6 ( 1 cement :3 coarse sand :6 graded stone aggregate 20 mm nominal
size ) complete as per design.
Providing and Placing in position suitable PVC water stops conforming to IS:12200 for
6.13 construction/ expansion joints between two RCC members and fixed to the reinforcement
with binding wire before pouring concrete etc. complete :
22.4.2 a) Dumb bell with central bulb (180mm wide, 8mm thick) Meter 10.00 232.05 2320.50
Painting sand cast iron/ centrifugally cast (spun) iron soil, waste
vent pipes and fittings with two coats of synthetic enamel paint of
6.17
any colour such as chocolate grey, or buff etc. over a coat of primer (of approved quality)
for new work :
17.65.1 100 mm diameter pipe Meter 1835.00 69.55 127624.25
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Providing and fixing trap of self cleansing design with screwed down or hinged grating with
6.18 or without vent arm complete, including cost of cutting and making good the walls and floors
:
17.60.1.1 100mm Inlet & 100mm Outlet Sand cast iron S&S as per IS: 3989 Each 125.00 1604.10 200512.50
17.60.2.1 100mm Inlet & 75mm Outlet Sand cast iron S&S as per IS: 3989 Each 10.00 1671.00 16710.00
Providing and fixing G.I. Pipes for waste complete with G.I. Fittings and clamps, including
6.19
cutting and making good the walls etc. (Internal work)
18.10.4 32 mm dia. nominal bore Meter 205.00 563.60 115538.00
18.10.5 40 mm dia. nominal bore Meter 75.00 725.15 54386.25
18.10.6 50 mm dia. nominal bore Meter 305.00 893.20 272426.00
Painting G.I. pipes and fittings with synthetic enamel white paint
6.20 with two coats over a ready mixed priming coat, both of approved
quality for new work
18.38.4 32 mm dia. nominal bore Meter 205.00 30.70 6293.50
18.38.5 40 mm dia. nominal bore Meter 75.00 36.05 2703.75
18.38.6 50 mm dia. nominal bore Meter 305.00 43.05 13130.25
Providing and fixing plain bend of required degree with insertion rubber washer 3 mm thick,
6.31
bolts and nuts complete.
17.39.2.2 75 mm dia Centrifugally Cast (spun) Iron S&S. Each 35.00 298.20 10437.00
17.39.1.2 100 mm dia Centrifugally Cast (spun) Iron S&S. Each 660.00 439.75 290235.00
Providing and fixing single equal junction of required degree with access door, insertion
6.34
rubber washer 3 mm thick, bolts & nuts complete.
17.43.1.2 100x100x100 mm Centrifugally Cast (spun) Iron S&S. Each 15.00 731.40 10971.00
Providing and fixing single Reducing junction of required degree with access door, insertion
6.35
rubber washer 3 mm thick, bolts & nuts complete.
17.47.1.2 100x100x75 mm Centrifugally Cast (spun) Iron S&S. Each 15.00 932.10 13981.50
Providing lead caulked joints to spun iron or C.I. pipes and specials, including testing of
6.37
joints but excluding the cost of pig lead :
18.28.1 100 mm Each 1662.00 410.25 681835.50
Providing and laying non pressure NP2 class (Medium duty) R.C.C. pipes with S & S
6.38 jointed with stiff mixture cement mortar in the proportion of 1:2 (1 cement: 2 fine
sand) including testing of joints etc. complete.
19.6.2 150 mm dia Meter 2530.00 493.10 1247543.00
19.6.3 250 mm dia Meter 7935.00 811.15 6436475.25
19.6.4 300 mm dia Meter 2070.00 902.05 1867243.50
19.6.5 450 mm dia Meter 10.00 1481.55 14815.50
19.6.7 600 mm dia Meter 10.00 2098.10 20981.00
19.6.8 700 mm dia Meter 715.00 2629.35 1879985.25
19.6.9 800 mm dia Meter 150.00 3144.45 471667.50
19.6.10 900 mm dia Meter 50.00 4260.35 213017.50
19.6.11 1000 mm dia Meter 50.00 5007.00 250350.00
19.6.12 1100 mm dia Meter 50.00 5625.95 281297.50
19.6.13 1200 mm dia Meter 10.00 6334.40 63344.00
15.24 Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including
6.38 collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1
cement : 2 fine sand) including testing of joints etc. complete
Providing and laying cement concrete 1:5:10 mix (1 cement: 5 coarse sand: 10
6.40 graded stone aggregate 40 mm nominal size) up to haunches of S.W. /RCC pipes including
bed concrete as per standard design.
19.3.5 300 mm dia Meter 2530.00 1089.10 2755423.00
Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand
) with R.C.C. top slab with 1:1.5:3 mix (1 cement : 1.5 coarse sand (zone-III) : 3
graded stone aggregate 20 mm nominal size), foundation concrete 1:4:8 mix (1
cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size),
6.41
inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand)
finished with floating coat of neat cement and making channels in cement concrete
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
finished with a floating coat of neat cement complete as per standard design :
Inside size 90x80 cm and 45 cm deep including C.I. cover with frame (light duty)
455x610 mm internal dimensions, total weight of cover and frame to be not less than
19.7.1.1 38 kg (weight of cover 23 kg and weight of frame 15 kg) : Each 2.00 11687.10 23374.20
With common burnt clay F.P.S. (non modular)
bricks of class designation 7.5
Inside size 120x90 cm and 90 cm deep including C.I. cover with frame (medium duty)
500 mm internal diameter, total weight of cover and frame to be not less than 116 kg
6.42 19.7.2.1 (weight of cover 58 kg and weight of frame 58 kg) : Each 85.00 24405.90 2074501.50
With common burnt clay F.P.S. (non modular)
bricks of class designation 7.5
Size 90x80 cm
6.43 19.8.1.1 Mtr 0.50 8127.45 4063.73
With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Size 120x90 cm
6.44 19.8.2.1 Mtr 21.00 9744.25 204629.25
With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Constructing brick masonry circular type manhole 0.91m internal dia at bottom and
0.56 m dia at top in cement mortar 1:4 (1cement: 4coarse sand), inside cement
plaster 12 mm thick with cement mortar 1:3 (1 cement: 3 coarse sand) finished with
6.45 19.9.1.1 a floating coat of neat cement, foundation concrete 1:3:6 mix (1 cement: 3 coarse
sand: 6 graded stone aggregate 40 mm nominal size), and making necessary channel
in cement concrete 1:2:4 (1 cement :2 coarse sand : 4 graded stone aggregate 20
mm nominal size) finished with a floating coat of neat cement as per standard design.
0.91 m deep with S.F.R.C cover and frame (Heavy duty, HD-20 grade designation)
560 mm internal diameter conforming to I.S.12592, total weight of cover and frame
not to be less than 182 kg. fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand Each 68.00 11886.45 808278.60
: 4 graded stone aggregate 20 mm nominal size) including centering, shuttering and
disposal of surplus earth all complete.
With FPS bricks class designation 7.5.
Extra depth for circular type manhole 0.91 m internal dia (at bottom ) 0.91 to 1.67 m
6.46 19.10.1 Mtr 29.00 6989.80 202704.20
With FPS bricks class designation 50.
Constructing brick masonry circular type manhole 1.22m internal dia at bottom and
0.56 m dia at top in cement mortar 1:4 (1cement: 4 coarse sand), inside cement
plaster 12 mm thick with cement mortar 1:3 (1 cement: 3 coarse sand) finished with
6.47 19.11.1.1 a floating coat of neat cement, foundation concrete 1:3:6mix (1 cement:3 coarse
sand: 6 graded stone aggregate 40 mm nominal size), and making necessary channel
in cement concrete 1:2:4 (1 cement :2 coarse sand : 4 graded stone aggregate 20
mm nominal size) finished with a floating coat of neat cement as per standard design.
1.68 m deep with S.F.R.C cover and frame (heavy duty, HD-20 grade designation)
560 mm internal diameter conforming to I.S.12592, total weight of cover and frame
not to be less than 182 kg, fixed in cement concrete 1:2:4 (1 cement : 2 coarse Each 45.00 22951.95 1032837.75
sand : 4 graded stone aggregate 20 mm nominal size) including centering, shuttering
and disposal of surplus earth all complete.
With FPS bricks class designation 50.
Extra depth for circular type manhole 1.22 m internal dia (at bottom ) With FPS
6.48 19.12.1 Mtr 23.00 9068.35 208572.05
bricks class designation 50. Beyond 1.68 m to 2. 29 m
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Constructing brick masonry circular type manhole 1.52m internal dia at bottom and
0.56 m dia at top in cement mortar 1:4 (1cement: 4 coarse sand), inside cement
plaster 12 mm thick with cement mortar 1:3 (1cement: 3 coarse sand) finished with a
6.49 19.13.1.1 floating coat of neat cement, foundation concrete 1:3:6mix (1 cement:3 coarse sand:
6 graded stone aggregate 40 mm nominal size), and making necessary channel in
cement concrete 1:2:4 (1 cement :2 coarse sand : 4 graded stone aggregate 20 mm
nominal size) finished with a floating coat of neat cement as per standard design.
2.30 m deep with S.F.R.C cover and frame (heavy duty, HD-20 grade designation)
560 mm internal diameter conforming to I.S.12592, total weight of cover and frame
not to be less than 182 kg, fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand Each 46.00 49193.00 2262878.00
: 4 graded stone aggregate 20 mm nominal size) including centering, shuttering and
disposal of surplus earth all complete.
With FPS bricks class designation 50.
Extra depth for circular type manhole 1.52 m internal dia (at bottom ) With FPS
6.50 19.14.1 Mtr 25.00 21103.40 527585.00
bricks class designation 50. Beyond 2.30 m
Providing orange colour safety foot rest of minimum 6 mm thick plastic encapsulated asper
IS: 10910 on 12mm dia steel bar conforming to IS :1786 having minimun cross section as
23 mm x 25 mm and over all minimum length 263mm and width as 165mm with minimum
112mm space between protruded legs having 2mm tread on top surface by ribbing or
chequering besides necessary and adequate anchoring projections on tail length on
6.51 19.16 Each 60.00 487.10 29226.00
138mm as per standard drawing and suitable to with stand the bend test and chemical
resistance test as per specifications and heaving manufacture"s permanent identification
mark to be visible even after fixing " incluting fixing in manholes with 30x20x15 cm cement
concrete block 1:3:6: (1 cement :3 coarse sand :6 graded stone aggregate 20mm nominal
size )complete as per design.
Providing M.S. foot rests including fixing in manholes with 20x20x10 cm cement concrete
6.52 19.15.1 blocks 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) as Each 10.00 461.35 4613.50
per standard design With 20x20 mm square bar
19.21.1 For pipes 100 to 250 mm diameter Each 1.00 683.70 683.70
19.21.2 For pipes 250 to 300 mm diameter Each 1.00 785.90 785.90
19.21.3 For pipes 350 to 450 mm diameter Each 1.00 1134.65 1134.65
19.21.1 For pipes 500 to 600 mm diameter Each 1.00 683.70 683.70
19.21.2 For pipes 650 to 700 mm diameter Each 1.00 785.90 785.90
19.21.3 For pipes 750 to 1200 mm diameter Each 1.00 1134.65 1134.65
Constructing brick masonry road gully chamber 50x45x60 cms with bricks of class
6.54 19.27.1 designation 75 in cement mortar 1:5 (1cement : 5 fine sand) including 500x450 mm Each 325.00 5589.45 1816571.25
pre cast RCC horizontal grating with frame, complete as per standard design with
FPS bricks.
Providing and laying Double Flanged (screwed / welded) Centrifugally (Spun) Cast
Iron, Class B (IS : 1536) :
18.71.4 250 mm dia C.I. Double Flanged Pipe Mtrr 69.00 5498.05 379365.45
18.71.5 300 mm dia C.I. Double Flanged Pipe Mtrr 395.00 7027.50 2775862.50
18.71.10 600 mm dia C.I. Double Flanged Pipe Mtrr 25.00 24977.15 624428.75
Providing push-on-joints to Centrifugally (Spun) Cast Iron Pipes or Ductile Iron Pipes
including testing of joints and the cost of rubber gasket :
18.70.4 250 mm dia C.I. Double Flanged Pipe Joint 25.00 280.15 7003.75
18.70.5 300 mm dia C.I. Double Flanged Pipe Joint 95.00 357.60 33972.00
18.70.10 600 mm dia C.I. Double Flanged Pipe Joint 12.00 961.25 11535.00
Supplying, installation, testing and commissioning of diesel engine driven main fire pump
6.56 suitable for automatic operation and consisting of following, complete in all respects, as
required : (Diesel Driven Pump)
Horizontal type, multistage, centrifugal pump of cast of iron body and bronze impeller with
stainless steel shaft, mechanical seal conforming to IS 1520.
Suitable HP, 1500 RPM water cooled with radiator, diesel engine conforming to relevant IS
standard complete with auto starting mechanism, 12 /24 volts electric starting equipment,
diesel tank, exhaust pipe extended upto 10 m outside pump house duly insulated 50 mm
thick glass wool with 1.0 aluminium sheet cladding, residential silencer, instruments and
protection as per standard specification, stop solenoid for auto stop in the event of fault with
audio indications, painted with post office red colour etc. as required.
M.S fabricated, common base plate, coupling, coupling guard, foundation bolts etc. as
required. Suitable cement concrete foundation duly plastered and with anti vibration pads.
Note: * The head of the pump is selected in a manner so as to give a minimum 3.5kgf/cm2
pressure at the highest/ farthest point.
18.2.1 2850 lpm at 88 m Head Set 1.00 684923.00 684923.00
Supplying, installation, testing and commissioning of electric driven pressurisation pump
6.57 suitable for automatic operation and consisting of following, complete in all respects, as
required : (Jockey Pump)
Horizontal type, multistage, centrifugal pump of cast iron body and bronze impeller with
stainless steel shaft, mechanical seal conforming to IS : 1520.
Suitable HP squirell cage induction motor TEFC type suitable for operation on 415 volts, 3
phase 50 Hz AC supply with IP 55 class of protection for enclosure, horizontal foot mounted
type with Class-'F' insulation, conforming to IS : 325.
M.S.fabricated Common base plate, coupling, coupling guard, foundation bolts etc. as
required. Suitable cement concrete foundation duly plastered and with anti vibration pads.
18.3.1 180 lpm at 88 m Head Set 2.00 127148.00 254296.00
Fabrication, supply, Insallation testing & commissioning of Electrical control panel of cubical
construction, floor mounted type, fabricated out of 2mm thick CRCA sheet,
compartmentalised with hinged lockable doors, dust and vermin proof, powder coated of
approved shade after 7 tank treatment process, cable alley, inter- connection with suitable
6.58 size copper conductor cable/solid copper strip, having switchgears and accessories,
mountings and internal wiring, earth terminals, numbering etc. complete in all respect,
suitable for main fire pump, pressurisation pump & diesel pump set complete as per CPWD
specification with following in coming and Outgoings, suitable for operation on 415V, 3
phase, 50Hz Ac Supply with enclosure protection class IP 42 as required :
Incomings
630A, 50kA 4 Pole MCCB, Ics=100% Icu rating Digital Voltmeter 0-500V with selector
switch Ammeter (0-630 A) with selector swtich & CTs etc. LED type RYB phase indicating
lamps, ON, OFF, trip indicating lamps
Set of Copper Bus Bar 800Amps
Outgoings
( Note : All outgoing feeders for pumps should have
digital Ammeter with selector switches, and LED type
ON, OFF, trip indicating lamps)
Main Fire Pump
2No. 250 A, 50kA TPN MCCB, Ics=100% Icu, with fully automatic Star/Delta starter suitable
for 100 hp pump with overload protection, current sensing type single phase preventor
complete with all acceessories and internal wiring required for automatic operation, selector
switch for local/remote, auto/manual/OFF operation.
Jockey Pump
2No. 125 A, 50kA TPN MCCB, Ics=100% Icu, with Suitable HP fully automatic Star/Delta
starter with overload protection, current sensing type single phase preventor complete with
all acceessories and internal wiring required for automatic operation, selector switch for
local/remote, auto/manual/OFF operation.
Diesel Engine Control
Control for diesel engine comprising - Automatic/Manual selctor switch & 3 attempts starting
device, timers and relays as required, push buttons, start/stop in manual mode
Indicating lamp for high/ Low Lub. Oil pressure, High Water Temp and Engine on indication
Battery charger suitbale for 12V/24 V DC with boost and trickle selector switch, 0-30 V DC
volt meter, and 0- 20 A DC Ammeter
All standard relays and accessories for automatic operation of diesel engine
System Controller
Designing, Supply, Installation, Testing and commissioning of system controller to control
operation of main electric fire pump, diesel pump, Pressurization pump, Terrace pump in
18.5.3 Set 1.00 322960.00 322960.00
sequence as per specification consisting of relays, timers. Sensors, annunciation window
for fault indication, complete as per specification
Providing, laying, testing & commissioning of 'C' class heavy duty MS pipe conforming to IS
3589/IS 1239 including Welding, fittings like elbows, tees, flanges, tapers, nuts bolts,
6.59 gaskets etc. in ground welding, excavation & providing cement concrete block as supports,
anti-corrosive treatment with coaltar / asphalt tape as per IS 10221, refilling the trench etc
of following sizes and complete as required :
18.6.1 200 mm. dia (wall thickness = 6.3 mm) m 4500.00 5561.00 25024500.00
18.6.2 150 mm. Dia m 150.00 3804.00 570600.00
Providing, laying, testing & commissioning of 'C' class heavy duty MS pipe conforming to IS
3589/IS 1239 including Welding, fittings like elbows, tees, flanges, tapers, nuts bolts,
6.60 gaskets etc. and fixing the pipe on the wall/ceiling with suitable clamp/support frame and
painting with two or more coats of synthetic enamel paint of required shade complete as
required :
18.7.1 25 mm dia m 3100.00 744.00 2306400.00
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Drum and brackets for fixing the equipmets on wall. Connections from riser with 25 mm dia
stop gun metal valve & M.S. Pipe and socket.
18.17.1 30 m Set 1.00 8675.00 8675.00
18.17.2 40 m Set 50.00 12073.00 603650.00
Supplying & fixing 63 mm dia gun metal short branch pipe with 20 mm nominal internal
6.69 diameter size nozzle conforming to IS 903 suitable for instantaneous connection to
interconnect hose pipe coupling as required :
18.18.1 Gun metal Nos. 1.00 2416.00 2416.00
18.18.2 Stainless Steel (Grade 304) Nos. 150.00 1662.00 249300.00
Supplying and fixing of fire brigade connection of cast iron body with gun metal male
6.70 instantaneous inlet couplings complete with cap and chain as reqd. for suitable dia MS pipe
connection conforming to IS 904 as required :
18.19.1 2 way-100 mm dia M.S. Pipe Set 1.00 6742.00 6742.00
18.19.2 4 way - 150 mm dia M.S. Pipe Set 4.00 13974.00 55896.00
18.19.3 3 way - 150 mm dia M.S. Pipe Set 1.00 9455.00 9455.00
Supplying and fixing air vessel made of 250 mm dia, 8 mm thick MS sheet, 1200 mm in
height with air release valve on top and flanged connection to riser, drain arrangement with
6.71 18.20 Set 25.00 18244.00 456100.00
25 mm dia gun metal wheel valve with required accessories, pressure gauge and
paintingwith synthetic enamel paint of approved shade as required.
Providing, fixing, testing & commissioning of 15mm dia quartzoid bulb type sprinklers of
rating 68 degree centigrade with required accessories :
18.21.1 Pendent Sprinkler No. 10.00 522.00 5220.00
18.21.2 Upright Sprinkler No. 1250.00 522.00 652500.00
18.21.3 Horizontal side wall sprinkler No. 1.00 617.00 617.00
18.21.4 Concealed sprinkler No. 1.00 1435.00 1435.00
Providing & fixing of pressure switch in M.S. pipe line including connection etc. as required.
6.72 18.22 No. 6.00 1546.00 9276.00
Providing & fixing flow switch in following sizes M.S. pipe including connection etc as
required.
18.23.1 100mm dia No. 1.00 7514.00 7514.00
18.23.2 150mm dia No. 6.00 9021.00 54126.00
Providing, fixing, testing & commissioning of installation control valve of cast iron body,
brass/bronze working parts comprising of water motor alarm, bronze seat clapper, clapper
arm and hydraulically driven mechanical gong bell to sound continuous alarm when the wet
6.73 riser/sprinkler system activates, pressure gauges, emergency releases, strainer, pressure
switch, cock valve complete with drain valve and bypass, test control box, ball valves, MS
pipe of required size, flanges, orifice plate, gasket etc of follwing sizes as required :
SCHEDULE-B
HVAC WORK
VRV/VRF System
Outdoor Units
Supply Installation, Testing & Commissioning of modular type Variable Refrigerant
Flow/Variable Refrigerant Volume air cooled Outdoor units suitable for cooling and heating,
having all hermetically sealed inverter type Scroll Compressor(s), minimum two
compressors for above 14 HP modules, microprocessor based Controller, top discharge
type condensing unit(s), with R 410 A Refrigerant, vibration isolators, with suitable
1.01 DSR VRF-1
foundation etc. complete as required. The unit shall deliver the rated capacity at AHRI
Conditions and work even at 50°C ambient temperature without tripping. The unit shall be
suitable to work on 400V +/- 10%, 3 Phase, 50Hz AC power supply. The unit shall be filled
with first charge of the refrigerant and ready for use as required. The COP at AHRI
conditions shall not be less than 3.1 and IEER not less than 6.5 .
1 ODU - 60 HP Nos. 1.00 984900.00 984900.00
ODU - 56 HP Nos. 1.00 853580.00 853580.00
ODU - 50 HP Nos. 2.00 722260.00 1444520.00
ODU - 44 HP Nos. 1.00 590940.00 590940.00
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Supply, installation, balancing and commissioning of fabricated at site GSS sheet metal
rectangular/round ducting complete with neoprene rubber gaskets, elbows, splitter
1.05
dampers, vanes,hangers, supports etc. as per approved drawings and specifications of
following sheet thickness complete as required.
3060 Thickness 0.63 mm (24G) sheet sq.m 500.00 398.14 199070.00
3061 Thickness 0.80 mm (22G) sheet sq.m 22.00 530.85 11678.70
3062 Thickness 1.0 mm (20G) sheet sq.m 100.00 664.32 66432.00
Supply, installation, testing and commissioning of GI volume control duct damper complete
1.06 16.13 with neoprene rubber gaskets, nuts, bolts, screws linkages, flanges etc., as per sq.m 25.00 7046.00 176150.00
specifications.
Supplying & fixing of powder coated extruded aluminium Supply Air Grills with aluminium
1.07 16.15 sq.m 100.00 9105.00 910500.00
volume control dampers as per specifications.
Supplying & fixing of powder coated extruded aluminium Return/Exhaust Air Grills with
1.08 16.16 sq.m 100.00 5910.00 591000.00
louvers but without volume control dampers complete as required.
Supplying, fixing testing commissioning of supply air diffusers of powder coated aluminium
1.09 16.17 with aluminium volume control sq.m 50.00 12184.00 609200.00
dampers with anti smudge ring & removable core.
Supplying, fixing testing commissioning of Return air diffusers of powder coated aluminium
1.10 16.18 without volume control dampers sq.m 1.00 8121.00 8121.00
with anti smudge ring & removable core.
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Supply and fixing of acoustic lining of supply air duct and plenum with 25 mm thick resin
bonded glass wool having density of 32 kg/m³, with 25 mm X 25 mm GI section of 1.25 mm
thick, at 600 mm centre to centre covered with Reinforced Plastic tissue paper and 0.5 mm
1.11 16.21 sq.m 1000.00 708.00 708000.00
thick perforated aluminum sheet fixed to inside surface of ducts with cadmium plated nuts,
bolts, stick pins, CPRX compound etc. complete as required and as per specifications.
Supplying and fixing of following thickness duly laminated aluminum foil of mat finish closed
cell Nitrile rubber (Class “O”) insulation on existing duct after applying suitable adhesive for
1.12 Nitrile rubber. The joints shall be sealed with 50 mm wide and 3 mm thick self adhesive
nitrile rubber tape insulation complete as per specifications and as required.
Supply, Installation, Testing and commissioning of factory built floor mounted chilled
water double skin type horizontal/vertical air handling units made of 25mm thick
panels consisting of pre plasticized G.l. casing of thickness 0.8mm outside layer and
0.8 mm inside layer with polyurethane foam (PUF) insulation factory injected between
them by injection moulding machine, complete with blower section with blower
suitable for static pressure as required, minimum 2 bend GSS/PVC eliminators,
cooling coil section with aluminium finned copper tubes (tubes thickness not less than
1.14 16.26 0.5mm) cooling coil of 6 row deep, filter section with 50mm thick metal viscous/
washable synthetic type air prefilters, belt drive package with TEFC drive motor of
efficiency class IE3 suitable for 415 ± 10% volts, 50Hz, 3 Phase AC supply suitably
designed for variable frequency drive applications, drain connections, stainless steel
(18G) drain pan with PUF insulation, 150 mm dia. dial type pressure gauges (2
nos.)and industrial type thermometers (2 nos.) at the inlet and outlet of coil, auto
purge valve wherever required, necessary vibration isolation arrangement etc.
complete as per specification and of following capacities.
16.26.13 16500 CFM (28050 CMH) 46.5 TR 50 MM SP No. 14.00 401576.00 5622064.00
NON - RETURN VALVE with duel plate of C I body SS plates vulcanized NBR seal
1.18 16.7.3 flanged end & PN 16 pressure rating for chilled / hot water circulation including
insulation as specified.
16.7.3.1 200 mm dia No. 6.00 14492.00 86952.00
16.7.3.2 150mm dia No. 1.00 9209.00 9209.00
16.7.3.3 125mm dia No. 1.00 7867.00 7867.00
16.7.3.4 100 mm dia No. 1.00 6160.00 6160.00
Y - STRAINER of Ductile Cl Body flanged ends with stainless steel strainer for chilled
1.19 16.7.4
/ hot water circulation including insulation as specified
16.7.4.1 200mm dia No. 6 49724.00 298344.00
16.7.4.2 150mm dia No. 1 28033.00 28033.00
16.7.4.3 125mm dia No. 2 21924.00 43848.00
16.7.4.4 100 mm dia No. 14 14687.00 205618.00
16.7.4.5 80 mm dia No. 14 9882.00 138348.00
Providing and fixing in position the industrial type pressure gauges with gun metal / No. 50 1196.00 59800.00
1.20 16.8
brass valves complete as required
16.9 Providing & fixing in position the mercury in glass industrial type thermometers. No. 50 1043.00 52150.00
Supplying, Fixing, testing and commissioning of fire dampers in supply air duct/main
branch and return air path as and where required of required sizes i/c control wiring,
the damper shall be motorized and spring return so as to close the damper in the
1.22 16.20 event of power failure automatically and open the same in case of power being
restored. The spring return action shall be inbuilt mechanism and not externally
mounted. The damper shall also be closed in the event of fire signal complete as
required and as per specifications.
16.20.1 Fire damper sqm 28 10659.00 298452.00
16.20.2 Actuator No. 50 9948.00 497400.00
Sub-total of 1 66,802,587.70
Wiring for twin control light point with 1.5 sq.mm FR PVC insulated copper conductor single
core cable in surface / recessed medium class PVC conduit, 2 way modular switch, modular
2.02 1.11 Point 200 1562.0 312400.0
plate, suitable GI box and earthing the point with 1.5 sq.mm. FR PVC insulated copper
conductor single core cable etc as required.
Wiring for light/ power plug with 2X4 sq. mm FR PVC insulated copper conductor single
2.03 1.12 core cable in surface/ recessed medium class PVC conduit alongwith 1 No 4 sq. mm FR Metre 21750 334.0 7264500.0
PVC insulated copper conductor single core cable for loop earthing as required.
Wiring for circuit/ submain wiring alongwith earth wire with the following sizes of FR PVC
2.04 1.14 insulated copper conductor, single core cable in surface/ recessed medium class PVC
conduit as required
1.14.1 2 X 1.5 sq. mm + 1 X 1.5 sq. mm earth wire Metre 1310 233.0 305230.0
1.14.2 2 X 2.5 sq. mm + 1 X 2.5 sq. mm earth wire Metre 13845 275.0 3807375.0
1.14.3 2 X 4 sq. mm + 1 X 4 sq. mm earth wire Metre 3600 334.0 1202400.0
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Supplying and drawing co-axial TV cable RG-6 grade, 0.7 mm solid copper conductor PE
2.05 1.19 insulated, shielded with fine tinned copper braid and protected with PVC sheath in the Metre 1500 47.0 70500.0
existing surface/ recessed steel/ PVC conduit as required.
Supplying and fixing of following sizes of medium class PVC conduit along with accessories
2.06 1.21 in surface/recess including cutting the wall and making good the same in case of recessed
conduit as required.
1.21.1 20 mm Metre 100 128.0 12800.0
1.21.2 25 mm Metre 1550 145.0 224750.0
1.21.3 32 mm Metre 250 184.0 46000.0
Supplying and fixing following modular switch/ socket on the existing modular plate & switch
2.07 1.24
box including connections but excluding modular plate etc. as required.
1.24.1 5/6 amps switch Each 500 103.0 51500.0
1.24.4 3 pin 5/6 amp socket outlet Each 500 122.0 61000.0
1.24.6 Telephone socket outlet Each 250 148.0 37000.0
1.24.7 TV antenna socket outlet Each 60 148.0 8880.0
1.24.8 Bell push Each 140.0
Supplying and fixing two module stepped type electronic fan regulator on the existing
2.08 1.25 modular plate switch box including connections but excluding modular plate etc. as Each 400 369.0 147600.0
required.
Supplying and fixing modular blanking plate on the existing modular plate & switch box
2.09 1.26 Each 770 40.0 30800.0
excluding modular plate as required.
Supplying and fixing following size/ modules, GI box alongwith modular base & cover plate
2.10 1.27
for modular switches in recess etc as required.
1.27.1 1 or 2 Module (75mmX75mm) Each 560 298.0 166880.0
1.27.4 6 Module (200mmX75mm) Each 150 402.0 60300.0
Supplying and fixing following Modular base & cover plate on existing modular metal boxes
2.11 1.28
etc. as required.
1.28.1 1 or 2 Module Each 560 133.0 74480.0
1.28.4 6 Module Each 150 182.0 27300.0
Supplying and fixing suitable size GI box with modular plate and cover in front on surface or
in recess, including providing and fixing 3 pin 5/6 amps modular socket outlet and 5/6 amps
2.12 1.31 Each 1725 477.0 822825.0
modular switch, connection etc. as required. (For light plugs to be used in non residential
buildings).
Supplying and fixing suitable size GI box with modular plate and cover in front on surface or
2.13 1.32 in recess, including providing and fixing 6 pin 5/6 & 15/16 amps modular socket outlet and Each 1450 586.0 849700.0
15/16 amps modular switch, connection etc. as required.
Supplying and fixing 3 pin, 5 amp ceiling rose on the existing junction box/ wooden block
2.14 1.33 Each 100 87.0 8700.0
including connection etc as required.
2.15 1.34 Supplying and fixing brass batten/ angle holder including connection etc. as required. Each 241 131.0 31571.0
Installation ,Testing, Commissioning of wall bracket /ceiling fittings of all sizes and shapes
2.16 1.35 containing upto two GLS/CFL/LED lamps per fitting, complete with all accessories including Each 2767 119.0 329273.0
connections etc. as required.
Supplying and fixing call bell/ buzzer suitable for single phase, 230 volts, complete as
2.17 1.38 Each 99.0
required.
Installation, testing and commissioning of ceiling fan, including wiring the down rods of
standard length (upto 30 cm) with 1.5 sq. mm FR PVC insulated, copper conductor, single
2.19 1.45 Each 400 339.0 135600.0
core cable, including providing and fixing phenolic laminated sheet cover on the fan box etc.
as required.
Supplying and fixing extra down rod of 10 cm length G.I. pipe ,15 mm dia, heavy gauge
2.20 1.47 including painting etc. as required. (Note : More than 5 cm length shall be rounded to the Each 300 46.0 13800.0
nearest 10 cm and 5 cm or less shall be ignored)
Supplying and fixing extra conduit down rod of 20 cm length G.I. pipe 15 mm dia, heavy
2.21 1.48 gauge including painting etc. as required. (Note : More than 5 cm length shall be rounded to Each 100 52.0 5200.0
the nearest 10 cm and 5 cm or less shall be ignored)
2.22 1.49 Numbering of ceiling fan/ exhaust fan/ fluorescent fittings as required. Each 642 57.0 36594.0
Installation of exhaust fan in the existing opening, including making good the damage,
2.22 1.50
connection, testing, commissioning etc. as required.
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Wiring for group controlled (looped) light point/fan point/exhaust fan point/ call bell point
(without independent switch etc.) with 1.5 sq. mm FRLS PVC insulated copper conductor
2.23 1.54 single core cable in surface/ recessed steel conduit, and earthing the point with 1.5 sq. mm
FRLS PVC insulated copper conductor single core cable etc. as required.
Providing and fixing following rating and breaking capacity and pole MCCB with
2.24 2.2 thermomagnetic release and terminal spreaders in existing cubicle panel board including
drilling holes in cubicle panel, making connections, etc. as required.
2.2.14 125 A,36KA,FPMCCB Each 11 8209.0 90299.0
Supplying and fixing following way, single pole and neutral, sheet steel, MCB distribution
board, 240 V, on surface/ recess, complete with tinned copper bus bar, neutral bus bar,
2.25 2.3
earth bar, din bar, interconnections, powder painted including earthing etc. as required. (But
without MCB/RCCB/Isolator
2.3.2 8 way , Double door Each 6 2573.0 15438.0
2.3.3 12 way , Double door Each 10 2315.0 23150.0
Supplying and fixing following way, horizontal type three pole and neutral, sheet steel, MCB
distribution board, 415 V, on surface/ recess, complete with tinned copper bus bar, neutral
2.26 2.4
bus bar, earth bar, din bar, interconnections, powder painted including earthing etc. as
required. (But without MCB/RCCB/Isolator)
2.4.1 4 way (4 + 12), Double door Each 10 4091.0 40910.0
2.4.2 6 way (4 + 18), Single door Each 10 4974.0 49740.0
2.4.3 8 way (4 + 24), Single door Each 20 5967.0 119340.0
Supplying and fixing of following ways surface/ recess mounting, vertical type, 415 V, TPN
MCB distribution board of sheet steel, dust protected, duly powder painted, inclusive of 200
2.27 2.5 A tinned copper bus bar, common neutral link, earth bar, din bar for mounting MCBs (but
without MCBs and incomer ) as required . (Note :Vertical type MCB TPDB is normally used
where 3 phase outlets are required.)
2.5.1 4 way (4 + 12), Double door Each 6 7512.0 45072.0
2.5.2 8 way (4 + 24), Double door Each 12 10165.0 121980.0
2.5.3 12 way (4 + 36), Double door Each 11 12833.0 141163.0
Supplying and fixing 5 amps to 32 amps rating, 240/415 volts, "C" curve, miniature circuit
2.28 2.10 breaker suitable for inductive load of following poles in the existing MCB DB complete with
connections, testing and commissioning etc. as required.
2.10.1 Single pole Each 1672 256.0 428032.0
2.10.3 Double pole Each 455 656.0 298480.0
Supplying and fixing single pole blanking plate in the existing MCB DB complete etc. as
2.29 2.11 Each 122 13.0 1586.0
required.
Supplying and fixing following rating, double pole, 240 volts, isolator in the existing MCB DB
2.30 2.12
complete with connections, testing and commissioning etc. as required.
2.12.1 40 amps Each 6 435.0 2610.0
2.12.2 63 amps Each 10 527.0 5270.0
Supplying and fixing following rating, four pole, 415 volts, isolator in the existing MCB DB
2.31 2.13
complete with connections, testing and commissioning etc. as required.
2.13.1 40 A Each 16 970.0 15520.0
2.13.2 63 A Each 22 1034.0 22748.0
2.13.3 100 A Each 31 1227.0 38037.0
Supplying and fixing following rating, double pole, (single phase and neutral), 240 volts,
residual current circuit breaker (RCCB), having a sensitivity current upto 300 milliamperes
2.32 2.14
in the existing MCB DB complete with connections, testing and commissioning etc. as
required.
2.14.2 40 amps Each 66 2642.0 174372.0
Supplying and fixing 20 amps, 240 volts, SPN industrial type, socket outlet, with 2 pole and
earth, metal enclosed plug top alongwith 20 amps "C" curve, SP, MCB, in sheet steel
2.33 2.18 Each 55 1621.0 89155.0
enclosure, on surface or in recess, with chained metal cover for the socket out let and
complete with connections, testing and commissioning etc. as required.
Supplying and fixing 30 A, 415 V, TPN Industrial type socket outlet, with 4 pole and earth,
metal enclosed plug top alongwith 30 A "C" curve, TPMCB, in sheet steel enclosure, on
2.34 2.20 Each 60 4107.0 246420.0
surface or in recess, with chained metal cover for the socket out let and complete with
connections, testing and commissioning etc. as required
Providing and fixing M.V. danger notice plate of 200 mm X 150 mm, made of mild steel, at
2.35 2.21 least 2 mm thick, and vitreous enameled white on both sides, and with inscription in single Each 20 269.0 5380.0
red colour on front side as required.
Providing and fixing H.T. danger notice plate of 250 mm X 200 mm, made of mild steel, at
2.36 2.22 least 2 mm thick, and vitreous enameled white on both sides, and with inscription in single Each 8 292.0 2336.0
red colour on front side as required.
Supplying, installation, testing & commisioning of following capacity Plug In/ tap off box on
the existing Air Insulated Compact Type bus trunking/ rising mains for use on 3 phase 4
2.38 3.12 wire 415 volts, 50Hz A.C. supply made with 1.6mm thick sheet steel enclosure (IP54) duly
powder coated with provision of MCCB/ACB (but without MCCB/ACB) complete etc. as
required
3.12.4 400 A 35kA SC for 1 sec Each 5 10350.0 51750.0
3.12.5 500 A 50kA SC for 1 sec Each 5 14919.0 74595.0
3.12.6 630 A 50kA SC for 1 sec Each 5 14919.0 74595.0
Supplying and installing following size of perforated painted with powder coating M.S. cable
trays with perforation not more than 17.5%, in convenient sections, joined with connectors,
2.40 4.1
suspended from the ceiling with M.S. suspenders including bolts & nuts, painting
suspenders etc as required.
4.1.2 150 mm width X 50 mm depth X 1.6 mm thickness Mtr. 400 604.0 241600.0
4.1.4 300 mm width X 50 mm depth X 1.6 mm thickness Mtr. 350 777.0 271950.0
4.1.10 450 mm width X 62.5 mm depth X 2.0 mm thickness Mtr. 1000 1244.0 1244000.0
4.1.11 600 mm width X 62.5 mm depth X 2.0 mm thickness Mtr. 544 1463.0 795872.0
4.1.12 750 mm width X 62.5 mm depth X 2.0 mm thickness Mtr. 600 1685.0 1011000.0
Supplying and installing following size of perforated painted with powder coating M.S. cable
trays bends with perforation not more than 17.5%,, joined with connectors, suspended from
2.41 4.2
the ceiling with M.S. suspenders including bolts & nuts, painting suspenders etc as required
Supplying and installing following size of perforated painted with powder coating M.S. cable
trays Tee with perforation not more than 17.5%, joined with connectors, suspended from the
2.42 4.3
ceiling with M.S. suspenders including bolts & nuts, painting suspenders etc as required.
EARTHING
Earthing with G.I. earth pipe 4.5 metre long, 40 mm dia including accessories, and providing
2.43 5.1 masonry enclosure with cover plate having locking arrangement and watering pipe etc. (but Each 40 5368.0 214720.0
without charcoal/ coke and salt ) as required.
Earthing with G.I. earth plate 600 mm X 600 mm X 6 mm thick including accessories, and
2.44 5.4 providing masonry enclosure with cover plate having locking arrangement and watering Each 25 7472.0 186800.0
pipe of 2.7 metre long etc. with charcoal/ coke and salt as required.
Supplying and laying 25 mm X 5 mm G.I strip at 0.50 metre below ground as strip earth
electrode, including connection/ terminating with G.I. nut, bolt, spring, washer etc. as
2.45 5.8 Mtr. 1495 972.0 1453140.0
required. (Jointing shall be done by overlapping and with 2 sets of G.I. nut bolt & spring
washer spaced at 50mm)
LIGHTNING CONDUCTOR
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Providing and fixing of lightning conductor finial, made of 25mm dia 300 mm long, G.I. tube,
2.46 6.1 having single prong at top, with 85 mm dia 6 mm thick G.I. base plate including holes etc. Each 100 518.0 51800.0
complete as required.
Providing and fixing G.I. tape 20 mm X 3 mm thick on parapet or surface of wall for lightning
2.47 6.7 Mtr. 2000 126.0 252000.0
conductorcomplete as required.(For horizontal run)
Providing and fixing G.I. tape 20 mm X 3 mm thick on parapet or surface of wall for lightning
2.48 6.8 Mtr. 2100 197.0 413700.0
conductorcomplete as required.(For vertical run)
Providing and fixing testing joint, made of 20 mm X 3 mm thick G.I. strip, 125 mm long, with
2.49 6.12 Each 800 121.0 96800.0
4 nos. of G.I. bolts, nuts, chuck nuts and spring washers etc. complete as required.
Supplying, installation, testing & commissioning of repeater panel wih 320 character/ Touch
2.52 17.2.3 screen LCD display with inbuilt reset, acknowledge and silence switches complete as Each 1.0 108688.0 108688.0
required.
Supplying, installation, testing & commissioning of fault isolator complete with base as
2.55 17.2.7 Each 50.0 3270.0 163500.0
required.
2.58 17.2.14 Supplying, installation, testing & commissioning of addressable manual call point complete as required.
Each 36.0 3871.0 139356.0
Supplying, installation, testing & commissioning of 1.5/3/6W metal box ceiling/wall speakers
2.61 17.3.3 Each 50.0 1793.0 89650.0
complete as required.
Supplying, installation, testing & commissioning of digital audio amplifier 75 Watt, 25V rms
2.62 17.3.7 Each 4.0 145793.0 583172.0
operating at 240 Volt AC Supply complete as required.
Supplying, installation, testing & commissioning of Voice command keypad 6 zone, with
2.63 17.3.9 Each 2.0 81756.0 163512.0
microphone assembly complete as required.
INTERNAL LIGHTING FIXTURES
Supply, Installation, Testing and Commissioning of 1200 mm sweep, BEE 5 star rated,
ceiling fan with Brush Less Direct Current (BLDC) Motor, class of insulation: B, 3 nos.
blades, 30 cm long down rod, 2 nos. canopies, shackle kit, safety rope, copper winding,
Power Factor not less than 0.9, Service Value (CM/M/W) minimum 6.00, Air delivery
2.64 19.1 minimum 210 Cum/Min , 350 RPM (tolerance as per IS : 374-2019), THD less than 10%, Each 400.0 2730.0 1092000.0
remote or electronic regulator unit for speed control and all remaining accessories including
safety pin, nut bolts, washers, temperature rise=75 degree C (max.), insulation resistance
more than 2 mega ohm, suitable for 230 V, 50 Hz, single phase AC Supply, earthing etc.
complete as required.
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
8 H V CABLE LAYING
Laying of one number XLPE power cable of 33 KV grade of following size direct in ground
2.65 8.5 including excavation, sand cushioning, protective covering and refilling the trench etc as
required.
8.5.2 Above 120 sq. mm and upto 400 sq. mm Metre 3000 582.0 1746000.0
Supplying and making indoor cable end termination with heat shrinkable jointing kit
2.66 10.7 complete with all accessories including lugs suitable for following size of 3 core, XLPE
aluminium conductor cable of 33 KV grade as required :
10.7.3 240 sq. mm Each 9 34216.0 307944.0
Supplying and making outdoor cable end termination with heat shrinkable jointing kit
2.67 10.8 complete with all accessories including lugs suitable for following size of 3 core, XLPE
aluminium conductor cable of 33 KV grade as required :
10.8.3 240 sq. mm Each 3 71644.0 214932.0
Supplying and making straight through cable jointing with heat shrinkable jointing kit
2.68 10.9 complete with all accessories including ferrules suitable for following size of 3 core, XLPE
aluminium conductor cable of 33 KV grade as required :
10.9.3 240 sq. mm Each 15 98622.0 1479330.0
7 MV CABLE LAYING
Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 1.1 KV
2.69 7.3 grade of following size direct in ground including excavation and refilling the trench etc as
required, but excluding sand cushioning and protective covering.
7.3.1 Upto 35 sq. mm Metre 7280 200.0 1456000.0
7.3.2 Above 35 sq. mm and upto 95 sq. mm Metre 2150 217.0 466550.0
7.3.3 Above 95 sq. mm and upto 185 sq. mm Metre 1500 234.0 351000.0
7.3.4 Above 185 sq. mm and upto 400 sq. mm Metre 3200 287.0 918400.0
Laying of one number additional PVC insulated and PVC sheathed / XLPE power cable of
1.1 KV grade of following size direct in ground in the same trench in one tier horizontal
2.70 7.4
formation including excavation and refilling the trench etc as required, but excluding sand
cushioning and protective covering.
7.4.1 Upto 35 sq. mm Metre 800 126.0 100800.0
7.4.3 Above 95 sq. mm and upto 185 sq. mm Metre 1250 161.0 201250.0
7.3.4 Above 185 sq. mm and upto 400 sq. mm Metre 1250 213.0 266250.0
Laying and fixing of one number PVC insulated and PVC sheathed / XLPE power cable of
2.71 7.7
1.1 KV grade of following size on wall surface as required.
7.7.1 Upto 35 sq. mm (clamped with 1mm thick saddle) Metre 1605 55.0 88275.0
7.7.2 Above 35 sq. mm and upto 95 sq. mm (clamped with 25x3mm MS flat clamp) Metre 260 130.0 33800.0
Laying and fixing of one number PVC insulated and PVC sheathed / XLPE power cable of
2.72 7.8
1.1 KV grade of following size on cable tray as required.
7.8.1 Upto 35 sq. mm (clamped with 1mm thick saddle) Metre 280 45.0 12600.0
Supplying and fixing cable route marker with 10 cm X 10 cm X 5 mm thick G.I. plate with
2.73 7.10 inscription there on, bolted /welded to 35 mm X 35 mm X 6 mm angle iron, 60 cm long and each 454 508.0 230632.0
fixing the same in ground as required.
Supplying and laying of following size DWC HDPE pipe ISI marked along with all
2.74 14.15 accessories like socket, bend, couplers etc. conforming to IS 14930, Part II complete with
fitting and cutting, jointing etc. in the existing trench, complete as required.
90 mm dia (OD-90 mm & ID-76 mm nominal) Mtr. 1500 149.0 223500.0
COST OF PANEL BOX MADE OUT OF I6/14SWG MS SHEET POWDER COATED 1P42
2.76 CLASS ENCLOSRE AS PER APPROVED DESIGN (CPRI APPROVED FEBRICATOR Each 1 120000.0 120000.0
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
Providing and fixing following rating and breaking capacity and pole MCCB with
2.77 2.2 thermomagnetic release and terminal spreaders in existing cubicle panel board including
drilling holes in cubicle panel, making connections, etc. as required.
2.2.8 315 A, 35 KA,TPMCCB Each 2 21586.0 43172.0
2.2.18 400 A,50KA,FPMCCB Each 11 42665.0 469315.0
2.2.10 500 A, 35 KA,TPMCCB Each 9 25554.0 229986.0
COST OF PANEL BOX MADE OUT OF I6/14SWG MS SHEET POWDER COATED 1P42
2.78 CLASS ENCLOSRE AS PER APPROVED DESIGN (CPRI APPROVED FEBRICATOR Each 1 485000.0 485000.0
C. OUTGOING :
Providing and fixing following rating and breaking capacity and pole MCCB with
2.79 2.2 thermomagnetic release and terminal spreaders in existing cubicle panel board including
drilling holes in cubicle panel, making connections, etc. as required.
2.2.13 100 A,30KA,FPMCCB Each 72 7723.0 556056.0
2.2.14 125 A,36KA,FPMCCB Each 16 8209.0 131344.0
2.2.3 150 A, 16 KA,TPMCCB Each 16 5992.0 95872.0
2.2.15 200 A,36KA,FPMCCB Each 16 15206.0 243296.0
COST OF PANEL BOX MADE OUT OF I6/14SWG MS SHEET POWDER COATED 1P42
2.80 CLASS ENCLOSRE AS PER APPROVED DESIGN (CPRI APPROVED FEBRICATOR Each 4 405000.0 1620000.0
HVAC Panel
Providing and fixing following rating and breaking capacity and pole MCCB with
2.81 thermomagnetic release and terminal spreaders in existing cubicle panel board including
drilling holes in cubicle panel, making connections, etc. as required.
2.2.10 500 A, 35 KA,TPMCCB Each 1 25554.0 25554.0
C. OUTGOING :
Supplying and fixing following rating, double pole, (single phase and neutral), 240 volts,
residual current circuit breaker (RCCB), having a sensitivity current upto 300 milliamperes
2.82 2.14
in the existing MCB DB complete with connections, testing and commissioning etc. as
required.
2.14.2 40 amps Each 12 2642.0 31704.0
2.14.3 63 amps Each 12 2722.0 32664.0
COST OF PANEL BOX MADE OUT OF I6/14SWG MS SHEET POWDER COATED 1P42
2.83 CLASS ENCLOSRE AS PER APPROVED DESIGN (CPRI APPROVED FEBRICATOR Each 1 132500.0 132500.0
C. OUTGOING :
Supplying and fixing following rating, four pole, 415 volts, isolator in the existing MCB DB
2.84 2.13
complete with connections, testing and commissioning etc. as required.
2.13.1 40 A Each 12 970.0 11640.0
2.13.2 63 A Each 20 1034.0 20680.0
COST OF PANEL BOX MADE OUT OF I6/14SWG MS SHEET POWDER COATED 1P42
2.85 CLASS ENCLOSRE AS PER APPROVED DESIGN (CPRI APPROVED FEBRICATOR Each 1 45000.0 45000.0
C. OUTGOING :
Providing and fixing following rating and breaking capacity and pole MCCB with
2.87 2.2 thermomagnetic release and terminal spreaders in existing cubicle panel board including
drilling holes in cubicle panel, making connections, etc. as required.
2.2.13 100 A,30KA,FPMCCB Each 24 7723.0 185352.0
COST OF PANEL BOX MADE OUT OF I6/14SWG MS SHEET POWDER COATED 1P42
2.88 CLASS ENCLOSRE AS PER APPROVED DESIGN (CPRI APPROVED FEBRICATOR Each 4 70000.0 280000.0
Escalator Panel
Providing and fixing following rating and breaking capacity and pole MCCB with
2.88 thermomagnetic release and terminal spreaders in existing cubicle panel board including
drilling holes in cubicle panel, making connections, etc. as required.
2.2.8 315 A, 35 KA,TPMCCB Each 4 21586.0 86344.0
C. OUTGOING :
Providing and fixing following rating and breaking capacity and pole MCCB with
2.89 2.2 thermomagnetic release and terminal spreaders in existing cubicle panel board including
drilling holes in cubicle panel, making connections, etc. as required.
2.2.13 100 A,30KA,FPMCCB Each 24 7723.0 185352.0
DSR 2021 DSR 2021 Rate
Item No. DESCRIPTION OF ITEM Unit Approximate Qty. Amount (in Rs.)
Reference (in Rs.)
COST OF PANEL BOX MADE OUT OF I6/14SWG MS SHEET POWDER COATED 1P42
2.90 CLASS ENCLOSRE AS PER APPROVED DESIGN (CPRI APPROVED FEBRICATOR Each 4 57500.0 230000.0
C. OUTGOING :
Providing and fixing following rating and breaking capacity and pole MCCB with
2.92 2.2 thermomagnetic release and terminal spreaders in existing cubicle panel board including
drilling holes in cubicle panel, making connections, etc. as required.
2.2.13 100 A,30KA,FPMCCB Each 48 7723.0 370704.0
COST OF PANEL BOX MADE OUT OF I6/14SWG MS SHEET POWDER COATED 1P42
2.93 CLASS ENCLOSRE AS PER APPROVED DESIGN (CPRI APPROVED FEBRICATOR Each 3 132500.0 397500.0
FAÇADE LIGHTING
Supply, Installation, Testing and Commissioning of LED RGB/RGBW floodlighting luminaire
for facade lighting with Die-cast aluminium housing, powder-coated finish, of following
wattage. Luminaire shall be capable of producing dynamic color changing light for with 16
million colors by DMX/Ethernet based control. The beam angle of the fitting shall be narrow,
medium, wide or asymmetric as per the requirement. Luminaire shall be complete with
driver and capable of operating at line voltage without any separate power supply from 100-
2.94 1 270 V AC, 50 Hz with power factor > 0.9 . Fixture shall be suitable to operate at an ambient
temperature range of - 10°C to +50°C and shall be IP 65 and IK 06 rated. Lifetime shall be
at least L70:50000 burning hours at 50°C. Luminaire shall be conforming to BIS (IS 10322)
and shall be complete with all necessary accessories required for proper working of fixture
including weather proof connection cables, water proof connectors etc. as required.
Supply, Installation, Testing and Commissioning of LED RGB/RGBW Linear Wall Washer
luminaire for Facade lighting with aluminium extruded housing, of following wattage.
Luminaire shall be capable of producing dynamic color changing light with 16 million colors
by DMX/Ethernet based control. The beam angle of the fitting shall be narrow, medium,
wide or asymmetric as per the requirement. Luminaire shall be complete with driver and
capable of operating at line voltage without any separate power supply from 100 to 270 V
2.95 2 AC, 50 Hz, power factor > 0.9 . Fixture shall be suitable to operate at ambient temperature
range of -10°C to +50°C and shall be IP 65 and IK06 rated. Lifetime should be at least
L70:50000 burning hours at 50°C. Luminaire shall be conforming to BIS and shall be
complete with all necessary accessories required for proper working of fixture including
weather proof connection cables, water proof connectors etc. as required.
SCHEDULE-C
CIVIL WORK INCLUDING PLUMBING & FIRE FIGHTING
WORKS
Internal Paint & Texture
EXTERNAL PAINT
Providing and applying surface texture with natural ceramic chips and/or granite stone
textured 'finish (Ceramic/stoney/magic or equivalent make of the similar specification of
materials) of approved shade comprising of water-borne, penetrating, water repellent
Exterior Masking Primer (EMP) with water based Fluorocarbon resin, silicon resin clear
dirt, dust resistant protection coat, clear coat or equivalent in two coats, which shall be
highly water repellant, anti-algae, anti-fungal in nature to external wall surfaces. The
coating shall also cover hairline cracks with following application method.'Which includes
one coat of External Masking Primer, one coat of natural granite, Ceramic 'chips texture,
1.01 all in approved natural shade and texture with a final two coats coat of 'fluorocarbon
–silicon resin clear coat. It shall also include preparation of surface, appropriate primer
coat etc. applied as per manufacturer's instruction as well as per direction of Engineer in
charge. The finish shall be in natural color and non pigmented, water repellant, resistant to
ultra violet, alkali and condensate formation, nothing extra shall be paid on account of
scaffolding etc. and complete work is to be done as per the instruction and direction of
Engineer-in-charge. The measurement of the work shall be done for the finished portion
only for payment.
Ceramic/stoney/magic finish
MR Sqm 500.00 2600.00 1300000.00
WATERPROOFING TERRACE
Waterproofing for Horizontal and Vertical Surfaces
For Horizontal Surface:-
a) Substrate preparation :
Cleaning the plain cement concrete surface to make it aggregate, dust and sludge free,
removing any extended portions by grinding using suitable equipments. Any voids and
depressions more than 10 mm shall be treated with latex SBR
b) Providing and applying a 1.5 mm thick double sided, modified bitumen waterproofing
membrane with cross laminated PE film for wet application on Podium. The membrane
shall be applied after making concrete wall in saturated surface dry condition and applying
1.02 MR a bonding slurry ( 2-3 kg /sqm). The membrane is then unrolled and pressed into the fresh Sqm 9400 1150 10810000.00
slurry after removal of the release liner. Both long and short edges of the membrane are
overlapped by min. 80 mm and firmly pressed together using a roller with staggered
overlaps. The membrane shall have tensile strength 4 N/mm according to ASTM D412
mod; elongation 200 % according to ASTM D412 mod; resistance to tear 23 N according
to ASTM D624; joint peel resistance 700 N/m according to ASTM D1876 at 23 °C; joint
shear resistance 220 N according to ASTM E154; low temperature flexibility of -15 °C over
crack tested for 100 cycles according to ASTM ; resistance to lateral water migration 70 m
according to ASTM.The measurement of the work shall be done for the visible finished
waterproofed portion only for payment.
Retaining Wall Waterproofing
Concrete substrates must be prepared mechanically using abrasive blast cleaning
equipment to remove Cement laitance and achieve an open textured surface.Required
minimum pull off strength is 1,5N/mm²Repairing surface irregularities, damaged concrete
1.03 MR Sqm 8600.00 85 731000.00
in base slab, if any, with an latex polymer, modified repair mortar including a coat of
bonding agent of the same with cement slurry including all material, labour, tools and
tackles complete.
Providing and applying a two‐part, crack bridging, elastic, ultra-fast curing polyurethane
waterproofing membrane system spray applied at an average thickness of 1.5 mm- 2mm
including compatible primer and all and the waterproofing membrane having the following
1.04 MR key performance properties and conforming to standards and approvals as by the Sqm 8600.00 1850 15910000.00
manufacturer and acceted by Engineer.The measurement of the work shall be done for
the visible finished waterproofed portion only for payment.
Door leaf shall be 60mm thick fully flush double skin step design door, insulated with or
without vision lite. Door leaf shall be manufactured from 1.2mm (18guage) minimum thick
galvanised steel sheet. The internal construction of the door should be rigid reinforcement
pads for receiving appropriate hardware. The infill material shall be 120kg high density
mineral wool insulation material. Intumescent seals 15 x 1.5mm to be provided. All doors
shall be factory prepped for receiving appropriate hardware and provided with necessary
reinforcement for hinges, locks, and door closers. The edges should be interlocked with a
bending radius of 1.4mm. For pair of doors integrated astragals has to be provided on the
meeting stile for both active and inactive leaf. Vision lite wherever applicable shall be
maximum 200 x 300mm (or max 0.06sq.mt) with clear borosilicate fire rated glass of 6mm.
Glass shall be fixed with suitable gasket and with clip-on arrangement.
Door and frames shall be finished Pure Polyster Powder coated and shall have passed
minimum 500 hours of salt sprey test.
PATCH LOCK
Patch lock for glazed doors: corner lock, prepared for Europrofile cylinder, single throw,
bolt projection 20 mm including epc both side key operation and lock keeper plate, Satin
1.07 MR Stainless Steel Finish etc. complete in all respect and as per direction of Engineer-in- Each 20.00 6000.00 120000.00
charge
PULL HANDLE
SS glass door pull handle: back to back (set of 2 nos.) with 350mm CTC, adjustable fixing
for glass, wood and metal doors in satin stainless steel. The pull handles should have
1.08 MR supporting washer with raised bevelling on the outer surface. Length=450mm, 25mm dia, Each 20.00 4800.00 96000.00
SS304 etc. complete in all respect and as per direction of Engineer-in-charge
False Ceilings
OPEN CELL CEILING
Providing and installation of approved quality linear cell ceiling made out of 0.5 mm thick
Aluminum. The assembled cell ceiling panels shall be made out of main blades in 15mm
(W) x 40mm (H) in 1200mm (L), installed at 200 mm c/c. and cross connected to
secondary blades in 15mm(W) x 40mm(H) in 600mm(L) with 100 mm pitch. The
assembled cell ceiling panels shall be clipped into U-94 carriers in GMS, pre-coated in
black enameled finished at 1200mm c/c. Wire clips shall hold the cell ceiling panels into
the U-94 carriers. The Primary angles made out of GMS, type U1040 are cross connected
to the U-94 carriers at 1200mm c/c., for lateral bracing the whole ceiling shall be
1.14 MR suspended by M6 threaded rods. All panel modules must be hinge able through wire clips Sqm 300.00 2450.00 735000.00
& grid should not be visible from bottom. Black soundex tissue to be pasted at the back of
the panels to block visibility of internal service piping installed on ceiling.
Finish of cell ceiling panels: Metallic silver in RAL 9006/White in RAL 9016/Natural
Aluminum finish (Black or as approved). including Providing and installation of 50mm thick
resin bonded glass wool (24 kg/cum)with GI frame fixed on roof slab with frame held on
24G x 10 GI wire mesh covered with black jute fabric over open Cell Metal Ceiling.The
measurement of the work shall be done for the visible finished portion only for payment.
BAFFLE CEILING
Providing & installation of approved quality vertical linear baffle ceiling made out of folded
Aluminum. The baffle units shall be in size of 50mm (W) x 150mm (H) and 1000mm x
4500mm x 1mm (thk), non-perforated. The ceiling baffle units shall be installed at a
distance of 300mm c/c in one direction. The baffle units shall be attached to C-channel
1.15
carriers spaced at 1200mm c/c. The C-channel carriers shall then be cross connected to
perforated L-angle primary grid and suspended with M6 threaded rod hangers spaced at
1200mm c/c.
Baffle finished with RAL 9016 polyester powder coat with minimum 60 microns paint
thickness.The measurement of the work shall be done for the visible finished portion only
MR Sqm 1500.00 8000 12000000.00
for payment.
Providing and laying Full body homogenous Vitrified tiles in floor in different sizes
(thickness to be specified by the manufacturer) with water absorption less than 0.08% and
conforming to IS:15622, of approved brand & manufacturer, in all colours and shade, laid
on 20 mm thick cement mortar 1:4 (1 cement: 4 coarse sand) jointing with grey cement
1.17
slurry @3.3 kg/sqm including grouting the joints with white cement and matching pigments
etc. The tiles must be cut with the zero chipping diamond cutter only . Laying of tiles will be
done with the notch trowel, plier, wedge, clips of required thickness, leveling system and
rubber mallet for placing the tiles gently and easily.
Derived Glazed/matt vitrified floor tiles polished finish of size of Tile 600 x 600 mm x 16 mm
form DSR thk.The measurement of the work shall be done for the visible finished portion only for sqm 1500.00 2030.06 30,45,089.54
11.41A.1.1 payment.
Flamed Granite flooring
Providing and laying flamed finish Granite stone flooring in required design and patterns,
in linear as well as curvilinear portions of the building all complete as per the architectural
drawings with 18 mm thick stone slab over 20 mm (average) thick base of cement mortar
1.18 1:4 (1 cement : 4 coarse sand) laid and jointed with cement slurry and pointing with white
cement slurry admixed with pigment of matching shade including rubbing, curing and
polishing etc. all complete as specified and as directed by the Engineer-in-Charge :
25 mm thick Flamed finish granite stone slab Jet Black, Cherry Red, Elite Brown, Cat Eye
MR or equivalent.The measurement of the work shall be done for the visible finished portion Sqm 500.00 3637.98 1818989.74
only for payment.
Extra for Grooves in Tread of Steps @3 Nos. (6mm width & 6mm depth) along the length
1.19 MR Rmt 6880.00 125.00 860000.00
of tread complete under direction of Engineer-In-Incharge
Providing and fixing of 2 mm thick Aluminium gutter with double side vulcanised rubber
Expansion joints at every 12m length or as per the requirement. Necessary down take
MR RM 460.00 4387.5 2018250.00
spout with diameter upto 150 mm at required intervals & other accessories like Cover
plate, end caps and welding at joints. The Girth of gutter would be upto 1200mm.
Supply and Fixing of Deck Strip Flashing around the openings and of appropriate size and
MR as per the drawing, specification and instruction of Engineer-In-charge RM 520.00 1650.0 858000.00
POLYCARBONATE SHEET
Providing and fixing of minimum 22 mm thick 5 cells and 6 walls UV protected Multicell
Polycarbonate Panel System over structural steel / MS purlin as per approved
colour/shade and as per drawing, Specification and instruction of Engineer-In-charge
1.21 MR complete in all respect. Sqm 800.00 4500.00 3600000.00
The visible finished portion of the work shall only be measured for payment purpose.
The Contractor shall provide curtain wall with aluminium sheet cladding, having all the
performance characteristics all complete, as per the Architectural drawings, as per item
description, as specified, as per the approved shop drawings and as directed by the
Engineer-in-Charge. However, for the purpose of payment, only the actual area on the
external face of the curtain wall with Aluminum sheet Cladding (including width of groove)
shall be measured in sqm up to two decimal places.The visible finished portion of the work
shall only be measured for payment purpose.
ARCHITECTURAL STEEL WORKS
INTERNAL S.S RAILING GRADE 304
Supply and installation of modular and component (Weld free) based system of satin
finish stainless steel AISI 304 SS handrail and balustrade system having minimum 38mm
dia tube handrail (1.5mm thickness) (app weight 1.5 kgs per Rmt) handrail connected with
unified stem keys in bead blasted finish to 12X54 mm stain free finish solid (approx
weight 7.5 to 7.7 Kgs) flat vertical member to be fixed on the side of staircase (2-point
fixed) with circular solid bosses of 50 mm dia at max c/c distance of 1800 mm with anchor
1.23 MR Mtr 506.16 11500.00 5820840.00
fasteners to the wall complete with all necessary bends and termination. Ht. 900-1000
mm. System as per tested and recommended by BS certification of BS 6180:1995 from
British Standard Institute and as per MTC. Rate for the complete unit is payable in running
meter and includes Handrail Tube, Uprights Solid, unified Cherry/Maple key etc, including
installation and making good the floors if required as per direction of E-I-C.
The visible finished portion of the work shall only be measured for payment purpose.
EXTERNAL S.S RAILING GRADE 316
Supply and installation of modular and component (Weld free) based system of satin
finish stainless steel AISI 316 SS handrail and balustrade system having minimum 38mm
dia tube handrail (1.5mm thickness) (app weight 1.5 kgs per Rmt) handrail connected with
unified stem keys in bead blasted finish to 12X54 mm stain free finish solid (approx
weight 7.5 to 7.7 Kgs) flat vertical member to be fixed on the side of staircase (2-point
fixed) with circular solid bosses of 50 mm dia at max c/c distance of 1800 mm with anchor
1.24 MR Mtr 1611.06 13000.00 20943780.00
fasteners to the wall complete with all necessary bends and termination. Ht. 900-1000
mm. System as per tested and recommended by BS certification of BS 6180:1995 from
British Standard Institute and as per MTC. Rate for the complete unit is payable in running
meter and includes Handrail Tube, Uprights Solid, unified Cherry/Maple key etc, including
installation and making good the floors if required as per direction of E-I-C.
The visible finished portion of the work shall only be measured for payment purpose.
EXTERNAL S.S RAILING AROUND WALL
Supply and installation of modular and component (Weld free) based system of satin
finish stainless steel AISI 304 SS handrail system having minimum 38mm dia tube
1.25 MR Mtr 1777.14 3450.00 6131133.00
handrail (1.5mm thickness) (app weight 1.5 kgs per Rmt) handrail connected with
intermediate supports around wall face complete under the direction of E-I-C.
GLASS RAILING
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
"Supply and installation of modular and component (Weld free) based system of satin
finish stainless steel AISI 316 SS handrail and balustrade system having minimum 38mm
dia tube handrail (1.5mm thickness) (app weight 1.5 kgs per Rmt) handrail connected with
unified stem keys in bead blasted finish to 12X54 mm stain free finish solid (approx
weight 7.5 to 7.7 Kgs) flat vertical member to be fixed on the side of staircase (2-point
fixed) with circular solid bosses of 50 mm dia at max c/c distance of 1800 mm with anchor
fasteners to the wall having infill of minimum 10 mm thick toughened glass complete with
1.26 MR all necessary bends and termination. Ht. 900-1000 mm. System as per tested and Mtr 439.26 12500.00 5490750.00
recommended by BS certification of BS 6180:1995 from British Standard Institute and as
per MTC. Rate for the complete unit is payable in running meter and includes Handrail
Tube, Uprights Solid, unified Cherry/Maple key, Toughened glass etc, including installation
and making good the floors if required as per direction of E-I-C.
The visible finished portion of the work shall only be measured for payment purpose.
PLUMBING WORK
1.27 Sub Head XIII: Sanitary Fixtures
Providing & fixing of white vitreous China wall mounting cascade type water closet with CP
bolts, nuts, CI chair hanging arrangements, bakelite soft closing seat & cover with CP
hinges & rubber buffers, CP brass screw, washer with all accessories with WC connector
with Rubber Lip / Buffer and side gap filled with silicon sealant wherever required with
1.28 MR Each 85.00 23159.20 1968532.00
concealed type cistern having dual flush chrome finished brass flush plate comprising of
actuator button facia assembly including brass / SS screws and washer complete
including cutting, making good the walls, floors, slab wherever required and complete
work as per direction of Engineer-Incharge.
Providing & fixing of white vitreous china below counter oval wash basin/circular basin
with CP brass waste assembly, CP cast brass bottle trap with extension piece with CP
brass waste assembly, wall flanges and rubber adapters for waste connection complete
1.29 MR Each 120.00 5742.82 689138.88
including CI/MS brackets duly painted, nuts, washers, cutting and making good the walls
floors wherever required as per direction of Engineer-Incharge.
Providing & fixing sensor based automatic electrically operated electronic sensor tap
chrome finished for wash basin with solenoid valve at inlet, Doppler based sensor,
1.30 MR Each 120.00 10256.00 1230720.00
control box complete with all flexible pipes & accessories as per direction of Engineer-
Incharge.
Providing & fixing of CP brass self closing pressmatic pillar tap complete with all assembly
1.30 MR and fixing as per direction of Engineer-Incharge. Each 10.00 2892.00 28920.00
Providing & fixing Health Faucet shower complete with 1.2m meter chrome plated
1.31 MR Each 86.00 1552.00 133472.00
extension chord and assembley and as per direction of Engineer-Incharge.
Providing & fixing white vitrous china flat back urinal with automatic flushing systems
comprising of all plumbing, electronic and electrical items. CP brass flush pipe with CP
brass elbow, CP brass spreader, CP wall flange, infrared photo cells, eyes electrically
operated solenoid valve, step down transformer / equipment and any other item required
1.32 MR Each 58.00 22744.00 1319152.00
to provide satisfactory functioning including necessary wall cutting / chasing and making
good, as required for urinal flushing complete as mentioned above as per direction of
Engineer-Incharge.
Providing & fixing unplasticised PVC connection pipe with brass unions of 45cm length &
1.33 MR Each 348.00 240.00 83520.00
15mm nominal bore.
Providing & fixing C.P. brass robe hook fixed to wall/door with plastic rawl plugs and C.P
1.34 MR brass screws including cutting and making good the walls wherever required as per Each 85.00 966.40 82144.00
direction of Engineer-Incharge.
Providing & fixing stainless steel jumbo roll toilet tissue dispenser with stainless steel roller
1.35 MR complete including cutting and making good the walls and floors wherever required as per Each 85.00 3132.00 266220.00
direction of Engineer-Incharge.
1.36 MR Providing & fixing recessed liquid soap dispenser as per direction of Engineer-Incharge. Each 10.00 3132.00 31320.00
1.37 MR Providing & fixing push type liquid soap dispenser as per direction of Engineer-Incharge. Each 75.00 1900.00 142500.00
Providing & fixing electrically operated Hand Dryer with completed assebly and providing
1.38 MR the electrical connection as per the requirement and direction of Engineer-Incharge. Each 12.00 24340.00 292080.00
Providing & fixing lavatory wash basin for handicapped toilet for handicap toilet complete
with brackets, tracks, waste pipes and other accessories complete as required as per
1.39 MR Each 9.00 10826.40 97437.60
direction of Engineer-Incharge.
Providing & fixing of 760mm long stainless steel grab bar as per directions of Engineer-
1.40 MR EACH 9.00 8099.20 72892.80
Incharge.
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
Providing & fixing of 1065mm long stainless steel grab bar as per directions of Engineer-
1.41 MR EACH 9.00 6940.00 62460.00
Incharge.
Providing & fixing urinal partitions 1050mm x 450mm with toughened ceramic
1.42 MR
frittted (coloured) glass of 8mm thick. The system shall be held on two brackets. EACH 50.00 6926.40 346320.00
including all fittings and accessories required as per direction of Engineer-Incharge.
MR
Providing & fixing recessed paper towel dispenser and waste receptable as per EACH 20.00 35788.80 715776.00
1.43
direction of Engineer-Incharge.
1.44 Providing & fixing recessed sanitary napkin disposal as per direction of Engineer-
MR EACH 6.00 18502.40 111014.40
Incharge.
Providing, laying, jointing and testing in position the following HPDE (PE-100) as per
IS:4984. Pipes for water supply cut to required lengths making proper connections of
1.46 required depths. Cost shall be inclusive of providing support arrangements as per
specification All work complete as per specification and as directed by Engineer-In-
Charge.
MR 65mm DN pipes M 150.00 678.40 101760.00
MR 80mm DN pipes M 85.00 1021.60 86836.00
MR 100mm dia nominal bore M 300.00 1472.00 441600.00
MR 150mm dia nominal bore M 350.00 2158.40 755440.00
Providing, laying, jointing and testing in position the following HPDE (PE-100) as per
IS:4984. Pipes for water supply cut to required lengths making proper connections of
required depths. Cost shall be inclusive of providing support arrangements as per
1.47
specification with providing thrust block. Cost shall be inclusive of trenching and refilling,
excavation, dewatering, backfilling, ramming, etc. All work complete as per specification
and as directed by Engineer-In-Charge.
MR 100mm dia nominal bore M 10.00 1576.00 15760.00
MR 150mm dia nominal bore M 200.00 2283.20 456640.00
Providing & fixing full way lever operated forged brass ball valve of brass body with
forged brass hard chromeplated steel ball tested to a pressure not less than 15 Kg / sqcm
1.48
with threaded / flanged joints complete with nuts, bolts, gaskets, washers etc. as per
direction of Engineer-Incharge.
MR 15 mm dia. Nominal bore EACH 1.00 391.20 391.20
MR 20 mm dia. Nominal bore EACH 30.00 556.00 16680.00
MR 25 mm dia. Nominal bore EACH 15.00 847.20 12708.00
MR 32 mm dia. Nominal bore EACH 5.00 1413.60 7068.00
MR 40 mm dia. Nominal bore EACH 15.00 2036.80 30552.00
MR 50 mm dia. Nominal bore EACH 10.00 2904.00 29040.00
Providing & fixing butterfly valve (Body : Grey Cast Iron, Shaft : SS, Disc : SG Iron
(Rilson coated), Liner : HT - EPDM) (upto 150mm dia with hand lever operation & above
1.49
with gear box operation). Tested to a pressure not less than 15 Kg/Sq.cm. Including
rubber gasket, flanges, nuts, bolts, washers & painting complete as required.
MR 65 mm dia. Nominal bore EACH 1.00 2736.00 2736.00
MR 80 mm dia. Nominal bore EACH 1.00 3723.20 3723.20
MR 100 mm dia. Nominal bore EACH 22.00 4892.80 107641.60
MR 150 mm dia. Nominal bore EACH 10.00 8627.20 86272.00
Providing and fixing in position of approved quality high pressure rated Gun Metal Float
1.50 Valve with ball float and brass rods of required length suitable for test pressure of not less
than 15 Kg/sqcm of the following sizes:
MR 50 mm dia. Nominal bore EACH 1.00 2600.80 2600.80
MR 100 mm dia. Nominal bore EACH 8.00 5721.76 45774.08
Providing & fixing Auto Air vent for cold water supply risers, suitable for pressure not less
1.51
than 15 Kg/Sq.cm.
MR 15 mm dia EACH 12.00 900.80 10809.60
Providing and fixing 600 mm dia cast iron (heavy duty) water tank circular cover with
1.52 MR frame (Total WT of cover and frame tobe not less than 85 kg) with lockable arrangement EACH 8.00 11113.60 88908.80
complete as per direction of Engineer-Incharge.
Providing and fixing in position GI vent with hot dip galvanised brass mosquito proof
1.53 coupling and air filter including return bend, complete as required as per direction of
Engineer-Incharge.
MR 100 mm dia EACH 16.00 1208.00 19328.00
Providing &, testing & commissioning of dial type pressure gauge with pressure scale of
1.54 MR 0 to 15 kg / sq.cm. Provision of isolation cock suitable for maximum pressure of 15 kg / EACH 10.00 512.00 5120.00
sq.cm shall be included in cost.
Providing and fixing hot dipped galvanised M.S. puddle flanges confirm to BS10 Table E
1.55 of 650 mm long pipe pieces to R.C.C. water tanks wall / slab as per direction of Engineer-
Incharge.
MR 25 mm dia (Screwed ends MS plate 6 mm thick; 100 mm x 100 mm plus dia of pipe). EACH 16.00 594.40 9510.40
MR 40 mm dia (Screwed ends MS plate 6 mm thick; 100 mm x 100 mm plus dia of pipe). EACH 1.00 743.20 743.20
MR 50 mm dia (Screwed ends MS plate 6 mm thick; 100 mm x 100 mm plus dia of pipe). EACH 1.00 897.60 897.60
MR 65 mm dia (Flanged ends MS plate 6 mm thick; 100 mm x 100 mm plus dia of pipe). EACH 1.00 1031.20 1031.20
MR 80 mm dia (Flanged ends MS plate 6 mm thick; 100 mm x 100 mm plus dia of pipe). EACH 1.00 1168.80 1168.80
MR 100 mm dia (Flanged ends MS plate 6 mm thick; 250 mm x 20 mm plus dia of pipe). EACH 36.00 1552.00 55872.00
MR 150 mm dia (Flanged ends MS plate 6 mm thick; 250 mm x 20 mm plus dia of pipe). EACH 25.00 1984.80 49620.00
MR 200 mm dia (Flanged ends MS plate 6 mm thick; 250 mm x 20 mm plus dia of pipe). EACH 1.00 2724.00 2724.00
MR 250 mm dia (Flanged ends MS plate 6 mm thick; 250 mm x 20 mm plus dia of pipe). EACH 2.00 3706.40 7412.80
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
Since the RCC retaining wall work of the plant room is completely done at site, contractor
shall ensure that the quoted rates are inclusive of providing and installing puddle flange in
1.56
existing retaining wall as required including water proofing and making good.
Providing & fixing Cast Iron `Y' Strainer (screwed/ flanged) with stainless steel fine wire
1.57 mesh perforated sheet basket with necessary flange/ unions nuts, bolts and washers
complete as per direction of Engineer-Incharge.
MR 80 mm dia EACH 1.00 7733.60 7733.60
MR 100 mm dia EACH 1.00 10567.20 10567.20
MR 150 mm dia EACH 6.00 21575.20 129451.20
Providing & fixing in position Vane type mechanical water flow meter as per direction of
1.58
Engineer-Incharge.
MR 150 mm dia EACH 2.00 21858.40 43716.80
Providing & fixing dual plate Cast Iron wafer type check valve tested to a pressure of 15
1.59 Kg/sqcm. Including rubber gasket, flanges, union, nuts, bolts, washers & painting
complete as per direction of Engineer-Incharge.
MR 100 mm dia EACH 10.00 6838.40 68384.00
MR 150 mm dia EACH 1.00 9126.40 9126.40
Providing and fixing GI Heavy class header complete for pump suction / discharge
manifold comprising of expansion bellows, flanges, unions, check nuts, tee elbow etc.
1.60 including all flanged connections as per drawing / site requirement. Supports from wall,
floor and ceiling etc. Including dead end flanged connection complete as required and as
directed by Engineer-In-Charge.
MR 80mm nominal bore M 5.00 1298.40 6492.00
MR 100mm nominal bore M 250.00 1540.00 385000.00
MR 150mm nominal bore M 250.00 1804.80 451200.00
Providing & fixing electronic type water level indicator & controller with LED panel
1.61 MR NOS. 8.00 8702.40 69619.20
mounted as required complete with probes & all control wiring etc.
Providing, fixing, testing & commissioning in position G.I. pipe and fittings of heavy class '
C ' conforming to IS:1239 (for waste pipe from individual fixtures to floor trap / floor drain &
vent pipe) Including fixing at wall /ceiling level supported by galvanized clamps and
1.62
hangers etc., cutting chases in wall and filling with 1:1 cement mortar, paiting two coats of
anti-corrosive bitumastic paint over one coat of primer wapping with one layer of 400
micron sheet and finally one apply one coat of anti-corrosive paint
MR 32 mm dia M 10.00 604.80 6048.00
MR 40 mm dia M 10.00 761.60 7616.00
MR 50 mm dia M 150.00 898.40 134760.00
Providing & fixing wall face unplasticised rigid PVC rain water pipes conforming to IS:
1.63 4985 : 1988 for working pressure of 6 Kg/sq.cm.including all acesseries as per direction of
Engineer-Incharge.
MR 100 mm diameter M 10.00 760.00 7600.00
MR 160 mm diameter M 10.00 841.60 8416.00
MR 200 mm diameter M 10.00 1028.80 10288.00
MR 250 mm diameter M 10.00 1260.00 12600.00
Providing & fixing wall face unplasticised rigid PVC moulded fittings/accessories for
1.64
unplasticised - rigid PVC rain water pipes conforming to IS : 4985.
1.65 Coupler
MR 160 mm diameter EACH 1.00 572.00 572.00
MR 200 mm diameter EACH 1.00 748.80 748.80
MR 250 mm diameter EACH 1.00 956.80 956.80
1.67 Bend
MR 160 mm diameter EACH 1.00 576.00 576.00
MR 200 mm diameter EACH 1.00 816.00 816.00
MR 250 mm diameter EACH 1.00 1040.00 1040.00
Painting sand cast iron/ centrifugally cast (spun) iron soil, waste
vent pipes and fittings with two coats of synthetic enamel paint of
1.68
any colour such as chocolate grey, or buff etc. over a coat of primer (of approved quality)
for new work :
MR 50 mm diameter pipe M 205.00 52.00 10660.00
MR 150 mm diameter pipe M 2000.00 65.60 131200.00
MR 200 mm diameter pipe M 150.00 76.80 11520.00
Providing and fixing G.I. inlet fitting with 1 or 2 inlets fabricated from 100 mm dia G.I.
1.69 MR pipes and welded G.I. sockets fixed to C.I. trap with lead caulked joint and set in cement EACH 125.00 2800.00 350000.00
concrete as per drawing complete as per direction of Engineer-Incharge.
Providing and fixing floor drain made out of 100x50 mm G.I. Elbow connected to G.I.
1.70 MR EACH 65.00 2560.00 166400.00
Pipe complete as per direction of Engineer-Incharge.
Providing and fixing Heavy class SS grating with Cockroach proof SS strainer of
1.71 approved design including setting in floor with cement motor to match with floor finish as
per direction of Engineer-Incharge.
MR Size 100 mm x 100 mm EACH 65.00 1520.00 98800.00
MR Size 127mm diameter EACH 125.00 1760.00 220000.00
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
Providing and fixing cast brass clean out plug with suitable insert keys for opening,
1.72
male threaded joint with G.I socket caulked for centrifugally Cast (spun) Iron pipes
MR 100 mm dia EACH 20.00 2480.00 49600.00
MR 150 mm dia EACH 5.00 3360.00 16800.00
Providing and fixing cleaning eye on horizontal CI soil & waste pipes, for med of 300 mm
long GI pipe with one plain end lead caulked in to the collar of CI pipe and the other end
1.73 with flange which in covered by neoprene rubber gasket and blank flange, complete with
nuts, bolts etc and hot dip galvanization after fabrication to the satisfaction of and as
direction of Engineer-In-Charge.
MR 100 mm dia EACH 15.00 2080.00 31200.00
MR 150 mm dia EACH 25.00 2800.00 70000.00
Providing and fixing plain bend of required degree with insertion rubber washer 3 mm
1.74
thick, bolts and nuts complete.
MR 150 mm dia Centrifugally Cast (spun) Iron S&S. EACH 140.00 600.00 84000.00
Providing and fixing single Reducing junction of required degree with access door,
1.77
insertion rubber washer 3 mm thick, bolts & nuts complete.
MR 150x150x100 mm Centrifugally Cast (spun) Iron S&S. EACH 25.00 600.00 15000.00
MR 100x100x50 mm Centrifugally Cast (spun) Iron S&S. EACH 60.00 668.00 40080.00
MR 150x150x50 mm Centrifugally Cast (spun) Iron S&S. EACH 1.00 1000.00 1000.00
Providing lead caulked joints to spun iron or C.I. pipes and specials, including testing of
1.78
joints but excluding the cost of pig lead :
MR 75mm EACH 121.00 300.00 36300.00
MR 150 mm EACH 643.00 464.00 298352.00
Providing, fixing, testing & commissioning of installation control valve of cast iron body,
brass/bronze working parts comprising of water motor alarm, bronze seat clapper, clapper
arm and hydraulically driven mechanical gong bell to sound continuous alarm when the
1.80 wet riser/sprinkler system activates, pressure gauges, emergency releases, strainer,
pressure switch, cock valve complete with drain valve and bypass, test control box, ball
valves, MS pipe of required size, flanges, orifice plate, gasket etc of follwing sizes as
required :
MR 200mm dia Set 1.00 76872.00 76872.00
Providing & fixing controlled percolation fire hose pipe (as per IS:8423) of 63 mm dia and
15 meter length rated for brust pressure of 35.7 Kg/sqcm. The hose shall be tested for
1.81 MR flame resistance test in accordance to IS:8423. Hose shall be complete with ISI marked No. 100.00 11768.00 1176800.00
brass male & female coupling (IS:903) bound & riveted to hose pipe with copper rivets &
1.5 mm copper wire (Location : External fire hydrant)
Providing and fixing weather proof lockable cabinet of size not less than 0.9 x 0.6 x 0.45
mtr made out of MS sheet of 16 gauge thickness having central opening and 4 mm thick
glazed glass doors (Two No.) suitably marked on the outside with the letters "FIRE
1.82 MR No. 205.00 20125.00 4125625.00
HOSE" including necessary locking arrangement and shall be painted with one coat of
primer and two coats of synthetic enamel paint of approved shade. (The aesthetics and
design of the cabinet shall be as per the architect / Client).
Providing, fixing, testing and commissioning of gun-metal fire brigade suction hose
coupling (draw-out connection) with nut for female coupling as per IS: 902-1974 complete
with 100 mm dia GI suction pipe and 100 mm dia foot valve (to be connected to static
1.83 MR No. 2.00 20356.00 40712.00
tank). Provision of GI drop pipe and foot valve shall be made in all the fire water static
storage tanks (4 No) (GI pipe to be paid separately through appropriate item while cost of
foot valve to be included).
Providing, fixing, testing & commissioning of 5 mm thick glass door (with M.S. frame) of
size 2.1 m x 0.9 m with center opening for fire hose cabinet. Suitably marked on the
outside with the letters "FIRE HOSE" including looking arrangement. All M.S. work to be in
1.84 MR No. 50.00 14433.00 721650.00
Red P.O. colour over appropriate primer. The above item is only for masonary fire station.
(The aesthetics and design of the door with frame shall be as per the architect / Client).
Providing, fixing, testing and commissioning of spring loaded relief valve suitable for
1.85 pressure of 16 Kg / sq.cm including flanges nuts bolt and washer etc., painted complete
as required.
MR 25 mm dia Set 6.00 5986.00 35916.00
MR 50 mm dia Set 1.00 12191.00 12191.00
Providing, fixing, testing & commissioning of forged brass ball valve with forged brass ball
1.86 suitable for test pressure of not less than 20 kg / sq.cm of the following size with nuts,
bolts, gaskets, necessary accessories, union, flanged connection, etc as required.
MR 25 mm dia Set 15.00 1984.00 29760.00
MR 50 mm dia Set 10.00 4681.00 46810.00
Providing, fixing, testing & commissioning of dial type (100 mm) pressure gauge with
1.87 MR isolation ball valve suitable for working pressure of 250 PSI with no Syphon. Cost shall be Set 25.00 1166.00 29150.00
inclusive of providing any short pieces, nipples, elbows etc as required.
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
Providing, fixing, testing & commissioning of automatic Air release valve with 15mm dia
1.88 MR stop cock, flanged inlet connection, pressure gauge with gun metal stop cock complete No. 15.00 1805.00 27075.00
with all accessories as required and conforming to IS IS : 12992 (Part 1).
Providing & fixing MS Class ‘C’ diesel engine exhaust pipe (including all fittings, clamps,
steel support) of 100mm dia for the engine. The pipe shall be insulated with 100 mm thick
1.100 MR m 35.00 6325.00 221375.00
mineral wool insulation wrapped in chicken mesh and clad with 24 gauge aluminium
sheet.
Providing and fixing inspectors test assembly complete with test valve, sight glass
1.101 MR sectional drain valve, union with corrosion resistant orifice all complete strictly as per No. 18.00 14375.00 258750.00
drawing and as per specifications.
Supply, installation, testing and commissioning ISI marked (IS:940) portable chemical fire
extinguisher, water (gas pressure) type capacity 9 litres with gun metal cap and nozzle
1.102 MR No. 200.00 4717.00 943400.00
and complete in all respects including initial fill and wall suspension brackets as required
as per specifications.
Supply, installation, testing and commissioning ISI marked (IS:2878) Fire Extinguisher,
Carbon-di-oxide type capacity 4.5 Kg. Flat base including valve, discharge hose of not
1.103 MR less than 10 mm dia, 1M long and complete in all respects including initial fill with CO2 gas No. 200.00 9431.00 1886200.00
conforming to IS:307-1966 and walll suspension braket as required as per specifications.
Supply, installation, testing and commissioning ABC (Powder Type) 6 kg Fire Extinguisher.
Mild Steel Cylinders ISI marked TAC approved fitted with pressure indicating gauge,
internal tube, squeeze lever type valve fully charged with ABC powder (Mono Ammonium
1.104 MR No. 200.00 4508.00 901600.00
Phosphate) pressured by Nitrogen complete in all respects including wall suspension
bracket and conforming to IS:1349-1993 as required as per specifications.
Supply, installation, testing and commissioning Mechanical Foam type Fire Extinguisher.
50L Mild Steel Cylinders ISI marked TAC approved fitted with pressure indicating gauge,
1.105 MR internal tube, squeeze lever type valve fully charged complete in all respects including wall No. 10.00 24723.00 247230.00
suspension bracket / trolley mounted and conforming to IS:910 as required as per
specifications.
Supplying and installing fire buckets of 24 gauge galvanized steel sheet, standard 9 litre
capacity and 4 buckets of round bottom shape, painted white inside and red outside and
1.106 MR black on the bottom at approved location inscribed with letters “FIRE” in black and gold No. 20.00 4194.00 83880.00
color including providing MS stand duly painted over a coat of primer as required as per
specifications.
Supply, installation, testing and commissioning Mechanical Foam type Fire Extinguisher
1.107 MR (AFFF) of 9 liters, plastic coated as required for electrical rooms and substation as No. 20.00 5870.00 117400.00
required as per specifications.
Providing & fixing Electronic type water level indicator with LED panel mounted as
1.108 MR No. 4.00 13512.00 54048.00
required complete with probes & all control wiring etc.
2 Nos Stainless Steel Perforated, Corrugated Bar Screen with suitable lifting arrangement
non clogging type submersible pumps capable of handling solids upto 35mm having SS
casing & SS impeller complete with all accessories, motor of required capacity.
Air diffusion system comrpising of blowers, piping, air dispersion system of required
capacity
MBR Membrane
Valves, isolation control valves
Note :
Air dispersion system shall be provided for Sewage Sump, aeration tank and Sludge
Holding Tank.
Tube settler
Cholrine dosing
Ultravoilet dis-infection unit.
Tertiary treatment pumps, filters, activated carbon filter, softener, filter press, centrifuge,
3.00 Set 20585000.00 61755000.00
etc required treatment in line with consultant and engineer in charge.
MR Sub Head XVII: Water supply pumps and Water Treatment plant
a. Vertical, In-Line, Multisage, centrifugal pumps with SS-304 casing and impeller and SS-
316 shaft, CI base & head TEFC motor (with mechanical seal)
(Vendor to submit performance curves and technical catalog of the proposed model for
review & information)
The pump shall be selected for performance at best efficiency point. However, the pump
selection shall be suitable for performance with set point @ + 20% of the rated head.
d. Accessories like pressure gauge, MS base frame (Synthetic enamel painted over a
coat of primer)
e. GI suction and delivery header with flanges for inlet connection, common outlet header
with flanges for outlet connections as required, and inter connecting piping with flexible
connections, eccentric type reducers etc. all necessary indigenous accessories as
required to complete the installation.
Note:
Contractor to note that the suction header is required to have inlet connection from the
Puddle Flange @ water tanks and to the pump suction. Provision of delivery header is
1.111 required to have outlet connection from the pumps. Suitable outlet flanges from the
delivery mainfold / header shall be provided as required.
Supplying and installing in the sump pit pump installation and lifting assembly suitable for
2 no. of submersible ejector pumps including ready made electro-galvanized MS lifting
chain & sliding guide rail. The installation shall be complete with provision of anit-vibrator
1.113 17.3
flexible connector, auto coupling union flange provision on discharge pipeline for feasibility
of removing the pumps and all necessary indigenous accessories as required to complete
the installation.
17.3.1 For pumps as per Item No. 17.2 (a) 5 Set 75000 375000.00
Note: Shop drawing for the installation to be approved by the Project Manager prior to execution.
Providing, fixing, testing & commissioning of vertical MSEP filter with adequate dirt
holding capacity. The filter shall be complete having PVC frontal piping with 50 mm
1.115 17.5 multiport valve including all supporting structure with initial charge filter media. The filter
shall be provided with set of internals for raw water inlet and bottom collecting system.
Velocity in frontal piping and valves shall be 1.50 m/sec.
Providing, fixing, testing & commissioning of MSEP water softening plant (suitable for 3
Kg/Sqcm working pressure) complete with initial charge with T-40 NA Resin, multiport
valve with built in ejector for controlling all operations), regeneration system and HDPE
1.1160 17.6
tank, pressure gauge at inlet, outlet and back wash (each with isolation cock), valves,
fittings and water hardness testing kit & associated works. Velocity in frontal piping and
valves shall be 1.50 m/sec. Softener shall be suitable for the following duty.
Supplying, installing, testing and commissioning of chlorine dosing system (for domestic
water treatment plant) consisting of one HDPE tank of 100 litres capacity with a positive
displacement diphragm dosing pump having variable flowrate of 0-6 lph. The motor shall
1.1170 17.7 3 Set 115000 345000.00
be suitable for operation at 240 V/Single phase/50 Hz. Supply. The pump shall be
supplied complete with necessary polypropylene piping, valves, strainers, low level switch
and injection fittings. The pump shall be speed & stroke control..
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
Supply, installing, testing and commissioning of annunciation and indication panel with
interlocking arrangement complete in accordance to specification with level controller (In
1.1180 17.8 1 Lot 75000 75000.00
Raw Water, Treated Water and Soft Water Tank : High / Low Level Controller) etc with
control cabling from field to MCC as required.
Providing, fixing, testing & commissioning pressure switch for water pumps to start/stop
1.1190 17.9 the pump at set pressure. Including wiring, cabling from pump to panel & all other 15 No. 1546 23190.00
accessories as required to operate the system automatically.
Supply, installation, testing and commissioning of tanker inlet connection complete with 80
mm dia GI inlet piping, hose inlet connection, MS cabinet enclosure (epoxy painted after
1.1200 17.10 5 No. 1546 7730.00
fabriction), pad locking arrangement, inlet flexible hose complete with all necessary
arrangement.
Incoming
b. 0-400 amps 96 x 96 mm square ammeter with selector switch and 400/5 amps 10 VA
CL:1 CTs. 1 Set
Bus Bar
500 amps TPN aluminium bus bar with heat shrinkable insulation sleeves.
Outgoings
a. 4 No. suitable rating MPCB for 7.5 KW DOL starter and outgoing feeder to Filter feed
pump (including 1 No. as standby). Each compartment shall contain auto / manual
selector swtich and indicating / pushbutton lamps with MCB for ON / OFF / TRIP of motor.
b. 1No. 250 amps TPN MCCB outgoing feeder to 1No. Domestic Water Hydro-pneumatic
system.
c. 2 No. suitable rating MPCB for 5 KW DOL starter and outgoing feeder to sump pumps
in plant room. Each compartment shall contain auto / manual selector swtich and
indicating / pushbutton lamps with MCB for ON / OFF / TRIP of motor - 4
d. 3 No. suitable rating MPCB for 5 KW DOL starter and outgoing feeder to rainwater
sump pumps in basement. Each compartment shall contain auto / manual selector swtich
and indicating / pushbutton lamps with MCB for ON / OFF / TRIP of motor. - 2 Set
Necessary cable alleys, control cables, cable tray, internal wiring, and interlocking,
earthing from all pumps and equipments shall also be included.
Notes :
a. All MPCBs / MCCBs shall be of 25 KA breaking capacity and suitable for motor duty
application.
b. Provision shall be made for providing potential free contacts to all pumps starters for
connection to BAS
c. Provision shall be made to ensure system protection from dry running of the pump
SCHEDULE-D
1.00 Electrical, HVAC, includuing Escalators
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
HVAC WORK
Supply, installation, testing & comissioning of Central Controller system for monitoring &
1.01 controlling of all indoor & outdoor units at central point or engineering control room. No. 1.00 121230.00 121230.00
Gateway/ connectivity facility required in central controller to connect with PC.
Commission of VRV systems including topping R410A gas per site requirements
1.02 Gas charging kg 260.00 1257.30 326898.00
Note :
Quoted price shall include the following:
i. All AHU shall be provided with 6 row deep coil & suitable for floor mounted
ii. All AHU shall be suitable for ceiling Mounted.
iii. AHU’s shall be supplied with hydrophillic coating on fins
iv. Frame-work for coils of all AHU’s shall be SS-304 construction.
v. AHU shall be provide with refrigerant control kit for connecting DX unit based with AHU
Supplying, installing and testing of UPVC pipe ( heavy duty) with 6 mm thick nitrile
rubber insulation with protective coating on condensing water piping and fitting like
1.05 MR
bends, elbow, tee and union, etc. as per the approved shop drawings and
specifications.
25 mm dia Rm 93 231.30 21510.9
32 mm dia Rm 215 307.80 66177
40 mm dia Rm 60 359.10 21546
Communication wiring of 2 core x 0.75 sqmm copper sheilded cable including PVC
1.07 MR conduits/ rasway/ cable tray/ trench between indoor and out door units and master RM 600 231.30 138780
controllers.
Supply, installation, testing and balancing of inlet/Outlet air louvers with bird screen
1.09 MR and volume damper for fresh/Exhaust air as per approved drawings and SQMT 126 12186.9 1535549.4
specifications.
Supplying, installing, testing and commissioning of normal & fire extract fans as per
specifications. Fan shall be with direct driven tube/ vane axial fan.Fan and casing
shall be suitable for normal & fire exhaust application, so that it is not exposed to
smoke stream & thermally rated for 250 Deg C for 2 hour as per [BS-7346 Part-2 :
1090] Class-H Motors shall be suitable for 415+10% volts, 50 cycles, 3 phase AC
1.11 MR supply with high efficiency, IE-2 type and External static pressure shall be 20 mm
(WC) minimum and Total static pressure shall be check by vendor. The fan shall be
equipped with mounting bracket & outlet cone required at discharge. Fan shall be
with flexible fire proof flexibel connection at inlet and outlet.Cost of spring isolators &
back drift damper for the installation of the fans needs to be included. Fan shall be
activated receiving signal from fire alarm system. Fan capacity shall be as follows:
10000 CFM ESP 20MM (WC) 7.5 HP Nos. 12 67080.6 804967.20
11000 CFM ESP 20MM (WC) 7.5 HP Nos. 8 68465.7 547725.60
Modular Double skin Floor mounted air washer units made of 23+2mm thick PUF
insulated panels extruded aluminum hollow profiles with 0.8mm thick pre-coated GI
Outer Sheet & 0.8mm thick Plain GI (270gsm) inner sheet comprising of Al
Wiremesh filter section, Wet section made of 20g SS Tank, Single Phase Pump
(1w+1s), PVC internal piping, Distribution system, 200mm deep Cellulose Pads & 2
1.13 MR bend PVC eliminators. Blower section with DIDW Aerofoil/ Backward/ Forward
curved fans, drive set with V- belts, Spring type vibration isolators, wire guard on
Fan section access door, fire retardant canvass connection at fan outlet, IE-2 motor
(TEFC type & suitable for VFD operation) & LED lamps for blower section, limit
switch for the fan section access door with a view port and damper at the outlet of
unit.
All dampers shall be low leakage aluminum aerofoil design and suitable for manual /
motorised operation.
The End Plates/Casing/blank offs of Pads & Eliminators shall also be made of SS.
40000 CFM (40mm of wg Total St. Pressure) Nos. 1312487.1
Supplying and erecting Star-Delta Starter 400V. 3 phase, 50 cycles with no volt coil
1.14 MR and overload element with necessary materials and connected to supply upto 12.5 Nos. 14 14944.50 209223.00
H.P.
1.15 MR Supplying and erecting D.O.L. Starter 400V. 3 phase, 50 cycles with no volt coil and Nos. 6 3970.80 23824.80
overload element with necessary materials and connected to supply upto 3 H.P.
1.16 MR Supplying and erecting D.O.L. Starter 400V. 3 phase, 50 cycles with no volt coil and Nos. 4 3970.80 15883.20
overload element with necessary materials and connected to supply upto 5 H.P.
1.17 MR Supplying and erecting D.O.L. Starter 400V. 3 phase, 50 cycles with no volt coil and Nos. 20 3970.80 79416.00
overload element with necessary materials and connected to supply upto 7.5 H.P
Supply, Installation, Testing and Commissioning of air cooled chiller package of 260
TR actual capacity, comprising of rotary screw compressor/s with direct drive
motor with VFD, phase reversal kit, insulated shell and tube type plain tube chiller,
independent sets of coil and fin type air cooled condensers complete with direct
driven propeller fan/s with IP-55 protection. Evaporator shall have provided with
32mm thick insulation using closed cell elastomeric insulation material having class
1.18 MR 'O' properties. The chiller package shall be installed on a fabricated mild steel base
frame assembled to form a compact assembly. The chiller package shall also be
complete with microprocessor based control panel comprising of all adaptive
controls, indication lights, over load and under load protection, TPN isolator for
termination of incoming power cable, necessary control wiring, disconnect switch,
grooved (mechanical) couplings at in and out of heat exchanger, DP switches for
heat exchanger & vibration isolation arrangement all complete as per the
specifications. The condenser shall be coated with anti-corrosion treatment.
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
The motor shall be suitable for operation on 415 ± 10% volts, 50 Hz, 3 Phase, AC
power supply. The chiller package shall be BMS compatible. The water cooled
screw chillers shall meet the following design parameters:
All wiring, control & power cable, cable tray and GI earthing of motors from the
panel shall be included. Please refere specification for cable size.
Note: For billing purposes, entire panel shall be considered as one item.
1 No. 1250 amps 4P, EDO ACB microprocessor based release unit with all
protecation as per specification and following accessories:
b. 0 - 1250 amps 96 x 96 sq mm digital ammeter with 3 No. 1250 / 5 amps CT’s and
selector switch. - 1Set
1600 TPN Aluminium bus bar with colour coded heat shrinkable insulated sleeves -
1 set
Maximum density of Aluminium bus bars for current carrying capacity shall be 1.0
amp per square mm.
Outgoing
3 No. 630 amps TPN MCCB as outgoing to 2 No. (260 TR) 338 kW each of
chilling unit compressor motor. The MCCB compartment shall contain CT operated
digital ammeter of 0- 630 amps range with selector switch and an indicating lamp
with MCB for ‘ON’ status of chiller motor.
2 No. 400 amps TPN MCCB as outgoing for 2 No. 150 kW starter of Hot water
Generator . The MCCB compartment shall contain CT operated digital ammeter of 0-
400 amps range with selector switch and an indicating lamp with MCB for ‘ON’
status.
3 No. MPCB, suitable rating Star Delta starter for 3 No. 10 HP motor, over load
relay with built in single phasing protection and outgoing feeder to Primary chilled
water pump motor. The compartment shall contain an indicating lamp with MCB for
‘ON’ status of fan motor. (2W+1SB)
3 No. MCCB, outgoing feeder to 3 No. 25 HP Motor for Secondary water pump
with VFD. The compartment shall contain an indicating lamp with MCB for ‘ON’
status of fan motor. (2W+1SB)
1 No. MPCB, suitable rating Star Delta starter for 1 No. 25 HP motor, over load
relay with built in single phasing protection and outgoing feeder to Condenser water
pump motor. The compartment shall contain an indicating lamp with MCB for ‘ON’
status of fan motor.
ELECTRICAL WORK
TELE-COMMUNICATION & SERVER
MR SITC of Duplicated Server Based IP PBX System along with complete set of
Servers, Switches, Gateways, Cards, Modules & Interface cable/accessories etc.as
equipped with the following configuration:
Analog User Ports : 500 Nos
IP User Licenses : 10 Nos
Central Office Trunk Ports : 08 Nos
1.23 PRI Trunk Ports : 02 Nos Nos. 1 2283057.6 2283057.64
IP Phone : 01 No
IP Operator Console : 01 Set
Expandable up to min 1000 ports with multiple IP locations as per detailed scope of
work & technical specification as per NINL/CIAT/TEL/012
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
MR Supply & Installation of RJ-45 Information outlets Jack ABS FR grade with spring
1.24 loaded collapsible shutters in jack recess suitable for Cat 6 application with
terminator caps for tooless termination .
Single Outlet Nos. 250 536.9 134216.12
MR Supply , Installation and Testing of 4 pair, 100 Ohm impedance, Cat 6/6A patch
cords should be constructed of minimum 23/24 AWG, stranded bare Copper cable
with FRPVC/LSZH Jacket, with an enhanced performance by factory moulded RJ45
connectors as per ANSI/TIA/EIA 568 suitable for Cat 6/6A application complying to
latest ammendments Category 6/6A Standards, According. to TIA568, minimum
1.25
requirement for 1G BASE-T/ 10G BASE-T performance. Patch cords shall be
straight
thru cable compatible with both T568-A and T568-B wiring schemes, Minimum 750
to 1000 mating cycles in plug contacts for long durability complete in all respect. All
as per pre approved by Engineer in charge.
1 Mtr Nos. 250 508.5 127124.80
MR Supply , Installation, Testing and Comissioning of Rack mounted 19", Cat 6 UTP,1.5-
1.6 MM CRS chasis , powder coated Modular Patch Panels with collapsible shutters
on jacks to support latest ammendments of TIA / EIA Cat 6 Specifications in
1.27
Existing Communication Rack along with necessary connections of Cat 6 UTP
Cables, With Rear Cable management trays and clamps.
MR Supply, Drawing and Testing, of stranded Single mode (9/125 µm) glass optic fiber
cable, as per latest ammendments of TIA/EIA 568/ISO/IEC 11801:2011/ IEC 60794-
1- 2, construction of LSZH outer sheath cable, cable should be used for LAN and
1.28 WAN back bones, . With its LSZH sheathing these cables should be ideal for
indoor/outdoor installations in existing MS/PVC /HDPE Conduits/ slotted channels
with ferruling at both ends for identification complete in all respect. All as per pre
approved by Engineer in charge.
6Fiber P. Mtr. 2000 123.4 246711.20
MR Supply, Drawing and Testing, of stranded Single mode (9/125 µm) glass optic fiber
1.29 SFP Module as per latest ammendments of TIA/EIA 568/ISO/IEC 11801:2011/ IEC Nos. 50 1522.0 76101.92
60794-1- 2,
MR Supply, Installation, OTDR Testing & Fusion Splicing of Fiber Singlemode Pigtail
(9/125 µm) made of glass fiber optic, should be fitted at one end with any one type
of single ST/E-2000/SC/LC/MT-RJ/PC type connector in acc. with IEC 61754-20, as
1.30 Nos. 100 138.4 13836.71
per latest ammendments of TIA/EIA 569 Standard Specification as per requirments
complete in all respect. All as per pre approved by Engineer in charge.
MR Supply, Installation, & Testing of Indoor duplex Singlemode patch cord (9/125 µm
made of glass fiber optic with LSZH jacket, Multimode G652.D Mounted on both
sides with ST/E-2000/SC/LC/MT-RJ/PC type Duplex connectors in acc. with IEC
1.31
61754-20 as per latest ammendments of TIA/EIA 569B.3, as per requirements
complete in all respect. All as per pre approved by Engineer in charge.
MR Ceiling Design Access Point 2.4G 450Mbps & 5.8G 1300Mbps Compliant with PoE
1.33 Nos. 5 4151.0 20755.07
802.3 at Centralized management for WI-FI
Access Point Controller For WI-FI Nos. 50 7201.3 360065.86
Zyxel Hotspot Gateway (UAG2100 Business WLAN w/o printer) Nos. 3 15912.2 47736.66
MR Supply & Installation of GI Under Floor Traunking or Raceway 25/38mm Height for Data,
1.36
Telephone & Ups.
300 X 38 X 1.6/3 Compartment Mtr. 750 2283.1 1712293.23
MR Supply & Installation of juction box for Data, Telephone & Emergency Wiring for PC point
1.37
with including all necessery all check nut lid , screw washer etc.
300 X300 X65 MM Nos. 125 2490.6 311326.04
CCTV NETWORK
MR 8 Megapixel Fixed Lens Camera PTZ Type: 2/3" progressive scan CMOS, Up to
4096 × 2160 resolution at 25fps, 2.8mm Fixed lens, 0.028 Lux at F1.2, ICR,
ONVIF, support H.265, H.264, MJPEG, 120db WDR, 3D Digital Noise Reduction,
1.38 Three individually configurable stream, 12 VDC & PoE, IR range: 40m, Support on- Nos 30 245137.7 7354131.57
board storage up to 128 GB (SD card not included), IP67, IK10, Edge Anlalytics-
Line crossing detection, Intrusion detection, Motion detection, Scene change
detection, video tampering, UL, CE, FCC certified.
MR 24 Port Network Switch Gigabit POE: 24 × Gigabit PoE ports, 1 × Gigabit RJ45 port,
1.44 Nos 4 18457.7 73830.61
and 1 × Gigabit SFP fiber optical port, IEEE 802.3at/af standard.
MR 16 Port Network Switch Gigabit POE: 16 × gigabit PoE ports, 1 × gigabit RJ45 port,
1.45 Nos. 18 13184.0 237312.68
and 1 × gigabit SFP fiber optical port, IEEE 802.3at/af standard
MR 8 Port Network Switch Gigabit POE: 8 × Gigabit PoE ports, 1 × Gigabit RJ45 port,
1.46 Nos. 8 7910.4 63283.38
and 1 × Gigabit SFP fiber optical port, IEEE 802.3at/af standard.
1.47 MR Supply of connector Nos. 374 31.0 11587.45
1.48 MR Supply of Hard Disc 4 TB Nos. 68 8240.0 560321.61
1.49 MR Supply of high resolution led monitor 32" complete as required. Nos. 21 17706.3 371831.51
1.56 MR Bracket for Locks: U-Bracket of Magnetic Lock Nos. 32 1383.7 44277.48
MR Supply & laying 6 core 1 sqmm, multi strand, copper conductor, shielded, PVC
1.58 Mtr 400 13.7 5482.47
insulated Cable (For reader to controller)
MR Supply & laying 4 core 1 sq.mm, multi strand, copper conductor, shielded, PVC
1.59 Mtr 400 11.7 4660.10
insulated Cable. (For EML+contacts to controller)
MR Supply, Install, test and provide of IP20 LED batten type light fixture made from
CRCA sheet steel housing suitable for moutning LED tube system (integral driver),
1.60 Power Consumption of 18W / 36W 1500-3000 lumens, system lumen efficiency 80 Nos 1497 330.3 494459.10
lm/Watt output, life time of 50,000 burning hours with 70% initial lumen maintained.
CCT 3000°K, 4000°K & 6000°K..
MR Provide & Fixing of IP66 LED Midbay light with die-cast aluminum housing & Heat
Sink for heat dissipation, high purity reflector with external driver having efficiency >
85% and High Performance electronic driver ensure Zero Maintenance with 4KV
1.62 High Surge Protection. Power Consumption of ≤ 70W-100W with ~ 9000-10000 Nos 520 7141.5 3713593.46
lumens, System Lumen efficacy of 130 lm / watt output , life time of 50000 Burning
Hours with 70% of intial Lumen maintaned. CCT 3000°K , 4000°K & 6000°K.
Fixture shall be CE compliance.
MR Provide of Aesthetically Designed linear LED mirror light with a high output PMMA
1.63 Diffuser for glare free output including making connection testing etc. as required No 70 219.8 15385.56
Dimension-300mm
MR Provide of energy efficient / energy saving direct fit (Retrofit) Inverter LED Bulb .
1.64
MR Provide of Heavy duty capacitor start 900/1400 RPM single phase ISI marked
1.65 Exhaust fan,IS:2312 marked in existing opening including making connections Each 92 1454.3 133793.24
testing etc. as required. 300 mm Sweep 9 900 RPM)
MR Provide & Fixing of capacitor start, wall mounting fan of following sweep with the
1.67
help of anchor bolts including making connection testing etc. as required.
400 mm sweep( oscillating type) Each 150 3659.3 548894.14
MR All doors/ opening are sealed with neoprene/EPDN gaskets. The enclosure has
built in fuel tank, residential silencer (isolated from main DG chamber) with
protection and tripping of DG set against temperature of more than 50 degree
centigrade. All controls for operation of DG set are from outside the enclosure with
1.72
DG control panel mounted inside enclosure , visible and accessible from outside.
The enclosure should be suitable for following capacity DG sets and alternator.
Noise level shall be less than 75 db(A) at a distance of 1 Mtrs. duly certified by
authorised agency etc. complete in all respect of following capacity:
Radiator cooled and Turbo charged
1010 KVA at 0.8 pf 415V 50Hz 3-Ø Each 4 8021514.3 32086057.13
Note : The rate shall be inclusive of providing necessary consumables including
fuel, lube oil etc. for 8 hours trials, testing and commissioning of DG sets and
required coordination with other agencies.
The quoted rate for above items shall be inclusive of obtaining all the required
statutory approvals including Chief Explosive Authority.
MR Supply, drawing of XLPE insulated & sheathed cable of 1.1 kV grade with Copper/
1.74 Aluminium conductor of approved makeon wall / Cable Tray with GI Saddles
,making necessary connections including testing etc. as required
6 Sq.mm 2.0 core Armoured Aluminium. Cable p.Mtr. 1250 114.4 143058.23
6 Sq.mm 3.0 core Armoured Aluminium. Cable p.Mtr. 355 132.3 46953.94
6 Sq.mm 3.0 core Unarmoured Aluminium. Cable p.Mtr. 200 89.1 17818.03
25 Sq.mm 3.0 core Armoured Aluminium. Cable p.Mtr. 600 223.4 134046.42
185 Sq.mm 3.0 core Armoured Aluminium. Cable p.Mtr. 300 1142.4 342722.98
95.00 Sq.mm 3.5 core armoured Al. Cable p.Mtr. 1200 712.0 854443.13
70.00 Sq.mm 3.5 core armoured Al. Cable p.Mtr. 950 570.2 541668.15
185.0 Sq.mm 3.5 core armoured Al. Cable p.Mtr. 1500 1305.5 1958270.17
240.Sq.mm 3.5 core armoured Al. Cable p.Mtr. 1250 1661.9 2077342.59
300.Sq.mm 3.5 core armoured Al. Cable p.Mtr. 3200 2021.7 6469315.99
25.00 Sq.mm 4.0 core armoured Al. Cable p.Mtr. 1980 276.2 546835.38
16.00 Sq.mm 4.0 core armoured Al. Cable p.Mtr. 1500 211.8 317640.67
10.00 Sq.mm 4.0 core armoured Al. Cable p.Mtr. 800 178.9 143092.50
10.00 Sq.mm 4.0 core Unarmoured Al. Cable p.Mtr. 3000 135.0 405017.56
C. OUTGOING :
DG Panel
MR 1600 A FP ACB 50 KA WITH MICROPROCESSOR BASED TRIP UNIT Ics=Icu = Icw for
1 sec OVERLOAD SETTINGS with adj. time delay , SHORT CIRCUIT SETTINGS with adj.
time delay, INSTANTANEOUS, EARTH FAULT & NEUTRAL PROTECTION with adj. time
1.79 delay, inbuilt LED indication for each type of fault, inbuilt electrical & mechanical anti Each 4 270517.7 1082070.68
pumping, soft rating plug, 100% neutral rating, UV release with delay. ACB shall conform
to IEC 60947-2 having combined test sequence certificate and release shall conform to
EMI/EMC standard.
MR 1 No. Multifunction/Kwh Meter with all functions & communication Port. 7930.79
1.80 3 Nos. CT's 500/5A accuracy Class-I, 15VA Burden Each 1 7930.8
LED type, Three phase indication lights (R,Y,B), with MCB.
MR 1 No. Multifunction/Kwh Meter with all functions & communication Port. 15538.84
1.81 3 Nos. CT's 200/5A accuracy Class-I, 15VA Burden Each 2 7769.4
LED type, Three phase indication lights (R,Y,B), with MCB.
MR 1 No. Multifunction/Kwh Meter with all functions & communication Port. 31077.68
1.82 3 Nos. CT's 200/5A accuracy Class-I, 15VA Burden Each 4 7769.4
LED type, Three phase indication lights (R,Y,B), with MCB.
MR 1 No. Multifunction/Kwh Meter with all functions & communication Port. 31723.17
1.83 3 Nos. CT's 400/5A accuracy Class-I, 15VA Burden Each 4 7930.8
LED type, Three phase indication lights (R,Y,B), with MCB.
MR 1 No. Multifunction/Kwh Meter with all functions & communication Port. 23792.38
1.84 3 Nos. CT's 500/5A accuracy Class-I, 15VA Burden Each 3 7930.8
LED type, Three phase indication lights (R,Y,B), with MCB.
MR Supply and erection of Galvanized Iron pole with galvanizing done in single dipping
(Average coating thickness Minimum 65 Microns) continuously tapered poles having
Octagonal / Circular cross-sections designed to withstand the maximum wind speed
as per IS 875, The pole shaft shall be made from sheet steel (HT Steel Conforming
to grade S355JO) and shall be continuously tapered with single longitudinal welding.
There shall not be any circumferential welding. The welding of pole shaft shall be
done by Submerged Arc Welding (SAW) process. pole shafts shall be provided with
the rigid flange plate of suitable thickness (Fe 410 conforming to IS 226 / IS 2062)
1.85 with provision for fixing 4 no. foundation bolts, This base plate shall be fillet welded
to the pole shaft at two locations i.e. from inside and outside.The octagonal Poles
shall have lockable door of approximate 500 mm length at the elevation of 500 mm
from the Base plate with bakelite sheet having 6A SP MCB and 16 sqmm stud type
connector ( 4 nos) inside theyment purpose../ MS with Hot Dip Galvanised with
serrations and serrated washers to arrest the wind load movement, fasteners, SS
316 Pins and anchor bolts of approved make in SS 316, Nylon separators to
prevent bi-metallic
MR Providing & Fixing of IK08, IP 66 protected LED Street Light Luminaire on existing
bracket/pole. Fixture made of powder coated single piece pressure die cast
aluminum material with heat dissipation fins on housing with UV stabilized PC (UV
stablization report submitted for UV cover ) /Toughened Glass cover and
secondary lens on each LED & should be SMD type of 3 to 5 watt each . The
System efficacy >=125 lm/ wt and potted driver & has a unique BIS R number with
Input Voltage AC 120 to 270 V AC with High voltage Cutoff @>=300 V AC and Auto
1.87
resetting Safety , Power Factor >0.95 driver Efficiency >85% ,THD(I) <10%
Humidity 10% to 90% RH Working Temp -5C to 45C . driver current <750mA. The
luminaire shall be BIS certified and Trade mark certified. Life Expectancy Equal or
more than 50000 burning hrs with Minimum 70% lumen maintened , CRI >70 and
CCT 5700K +355K. Surge protection shall be min ≥ 4 KV internal and min 10 KV
external inside driver compartment. driver should be Phase to phase protection
ofyment purpose../ MS
42Watt LED Street Light fixture with Minimum lumen output 7500 lm Each 289 3773.7 1090613.04
MR Supply installation testing & Commissioning of high mast lighting system consisting
of totally hot dip galvanised by piecewise single dipped method high mast, lantern
carriage suitable for up to 09 nos luminaries with welded arm (excluding luminares),
mast head frame assembly with full cover, including 1 No. LED 15 Watts aviation
obstruction lights, double drum type self sustaining winch, integral power tool
accesible from door with padlocking arrangement (winch motor with control circuit)
hot dipped galvanised heavy duty pipe lightening finial, Stainless steel 6 mm dia.
1.88
wire ropes (AISI 316, 7 / 19 costruction 3 no. rope for lantern carrage & 2 no. rope
for winch assembly ) foundation bolt, torque limiter,EPR insulated PCP sheathed 5
core x 2.5 Sq.mm trailing cable, including outdoor type control panel for auto on /
off, reverse / forward motor operation. The mast is constructed from mild steel
plates (as per IS 5986 Gr. 510 ) cut and folded to form a polygonal section,
telescopic jointed and welding as peion arrangement all complete as per the
specifica
16.0 Mtr HM (in 2 section) suitable for 9 No. Luminaries 2 no. rope for lantern carrage & 2 no. rope
Eachfor winch assembly
8 258386.5 2067092.01
MR Providing & Fixing of IK08 IP-66 protected high power LED flood light system with
single piece Pressure diecast aluminium housing, toughened glass diffuser with
suitable lenses on LED to achieve various beam angles, of high power LED of 3 to
5 watt each . Integrated potted driver as a unique BIS R number having efficiency
more than 85 % and in compliance to BIS certified and Trade mark certificate. The
System level Luminaire efficacy >=125 lm/ wt. LED driver Input Voltage AC 120 to
270 V AC with High voltage Cutoff @>=300 V AC and Auto resetting Safety .Power
Factor >0.95 , THD(I) <10% , driver current <=750mA. driver should be Phase to
phase protection of 440 V for 4 Hrs. Electrical Connector , Surge Protection Min
1.89 >=4KV internal and 10KV external but inside driver compartment, System life of
50000 Burning hours with 70% of Initial Lumens maintained, CRI>70 and CCT
5700K ±355K. Manufactures Word Mark/Name Engraved/Embossing/Screen
printing on die cast housing to allow traceability/authenticity. Fixturyment purpose../
MS with Hot Dip Galvanised with serrations and serrated washers to arrest the wind
load movement, fasteners, SS 316 Pins and anchor bolts of approved make in SS
316, Nylon separators to prevent bi-metallic contacts all complete required to
perform as per specification and drawing The item includes cost of all material &
labour component, the cost of all moc
195 Watt High Power LED Flood Light Minimum lumen output 22400 lm Each 72 9759.7 702697.82
1.90 MR Provide & fixing of 85 inch LCD/LED / Plasma intelligent monitor with built in controller Nos 3 430840.6 1292521.75
1.91 MR Provide & fixing of 55 inch LCD/LED / Plasma intelligent monitor with built in controller Nos 130 61960.1 8054814.89
1.92 MR Provide & fixing of Single Line double face train arrival/departure display board Nos 25 15345.4 383635.69
1.93 MR Provide & fixing of double face coach guidence display board Nos 240 14165.0 3399602.40
30 KVA UPS
MR SITC of 30KVA (3ph i/p & 3ph o/p) ON Line UPS with inbuilt Isolation tranformer
having Input supply voltage 400-450 Volts , Output voltage 420 volt +/- 1% ,30MIN
1.94 Nos 4 438113.1 1752452.54
battery back up time with battery rack etc. and as per enclosed specification .
Rating -30KVA
Input supply voltage:-400-450 Volts
Output voltage:-420V+/-1%
Voltage Regulation:-Less than or equal to +/- 1%
Input frequency :-50 Hz +/- 10%
Output frequency :-50 Hz +/- 0.05 Hz
Type of cooling :-Forced air cooled
Over load capacity :-110 % for 10 min, 400% for 1/2 cycle
Invertor Efficiency :-Better than 92%
Output Power factor :-0.8
Metering :-LCD Display
Backup time :-30MIN
D.C. Voltage :120VDC
SMF Battery :12V-200AH-10NOS
Battery VAH :-24000VAH
Item No. MR DESCRIPTION OF ITEM Unit Approximate Qty. Rate (in Rs.) Amount (in Rs.)
Isolation Transformer required at inverter circuit of UPS
PASSENGER ELEVATOR
MR Design, Fabrication, Supply, Installation, Testing & Commissioning of Electric Traction
Type fully automatic Machine room less (MRL) Passenger Elevator having SS Enclosure
(Grade 304) with AC variable voltage & variable frequency drive unit suitable for operation
on 415 +/- 10 % V, 3 Phase, 50 Hz. AC supply, having speed of 1.5 MPS, power operated
SS center opening type car & landing doors, electro-magnetic brake system, operating
panel with luminous buttons, overload warning indicator, battery operated alarm bell,
1.95 emergency light, intercom suitable for hook up to Facility's EPABX, infrared red sensing Nos 12 2160000.0 25920000.00
door protection for full height (min 2100mm height) & mechanical safety by pressure
sensor, reverse phase relay on controller, fire man's switch at ground floor, digital car
positions indicator in car with up / down direction indications, light fixtures, ventilation fan,
landing sill, main beam in shaft for machine, pit ladder, provision of lighting in elevator
shaft etc. complete with all accessories serving different floors in the lift shaft alongwith
Automatic Rescue Device (20 Passanger)
ESCALATOR
MR Design, Fabrication, Supply, Installation, Testing & Commissioning of Electric
Traction Heavy Duty Type fully automatic) Passenger Escalator for the floor to floor
vertical height of 5.50 meter with variable voltage & variable frequency drive unit
suitable for operation on 415 +/- 10 % V, 3 Phase, 50 Hz. AC supply, etc. and in
1.96 Nos 2 5850000.0 11700000.00
compliant of RDSO specification No. RDSO/PE/SPEC/TL/0095 (Rev.'3'-2019).
Digitally signed
by HEMANT
KUMAR
Date:
2022.12.15
15:50:59 IST
Reason: PDF
Authenticated