Residential Towers: M3M-65Th Avenue, Gurgaon Annexure 2 - Staff Deployment Schedule

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

M3M- 65th AVENUE, GURGAON

ANNEXURE 2 - STAFF DEPLOYMENT SCHEDULE

Pre Construction & Procurement Construction Post Construction

1 mth

2 mth

3 mth

1 mth

2 mth

3 mth

4 mth

5 mth

6 mth

7 mth

8 mth

9 mth

10 mth

11 mth

12 mth

13 mth

14 mth

15 mth

16 mth

17 mth

18 mth

19 mth

20 mth

21 mth

22 mth

23 mth

24 mth

25 mth

26 mth

27 mth

28 mth

29 mth

30 mth

1 mth

2 mth

3 mth
Man Months

Designation

May-18

May-19

May-20
Nov-18

Nov-19

Nov-20
Feb-18

Mar-18

Aug-18

Dec-18

Feb-19

Mar-19

Aug-19

Dec-19

Feb-20

Mar-20

Aug-20

Dec-20
Apr-18

Sep-18

Oct-18

Apr-19

Sep-19

Oct-19

Apr-20

Sep-20

Oct-20
Jan-18

Jun-18

Jan-19

Jun-19

Jan-20

Jun-20
Jul-18

Jul-19

Jul-20
739

1 Project Director 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 31

2 Project Coordinator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 33

3 Manager - Billing 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 33

4 Engineer - Billing 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 31

5 Document Controller 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 34

6 Manager - QA / QC 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 30

7 Engineer - QA / QC 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 30

8 Safety Officer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 31

9 Safety Officer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 31

Residential Towers

10 Engineer - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 29

11 Supervisor - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 28

12 Supervisor - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 26

13 Engineer - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 30


SITE TEAM

14 Supervisor - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 32

15 Supervisor - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 26

16 Engineer - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 29

17 Supervisor - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 31


Build-up Area - 42,89,885 sqft

18 Supervisor - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 26

Commercial / Nursery / EWS

19 Engineer - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 27

20 Supervisor - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 27

21 Supervisor - Civil / Finishes 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 25

Services Team

22 Manager - Services 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 19

23 Engineer - Electrical 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 26

24 Engineer - Mechnical 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 21

25 Supervisor - Services 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 29

26 Supervisor - Services 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 24

Site Expenses 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Design Coordination

Overview - Regional Head (4days) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Architect / Design Head - Ashish Yadav (8days) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

MEP Head - Neeraj Sharma (8days) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1


Offsite Team

Safety Manager - Deepak Chawla (2days) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Quality Manager - (2days) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Procurement Coordination

Manager Contracts (Civil / MEP) - (11days) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Assitant Contracts and Controller - (11days) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Head office Support 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Number of Staff 1 1 6 11 13 17 18 21 22 22 23 23 24 24 25 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 23 22 9 9 9 739

Proposed Fee Per Month 10,00,000 10,00,000 10,00,000 22,00,000 36,00,000 36,00,000 36,00,000 36,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 48,00,000 22,00,000 22,00,000 22,00,000 15,10,00,000
Note: Above Manpower Deployment Schedule is Tentative and may Vary according to construction schedule.