ShaftWall 0
ShaftWall 0
ShaftWall 0
ShaftWall
Shaft and duct encasement system
british-gypsum.com
ShaftWall
ShaftWall
ShaftWall provides a lightweight, fire resistant
60 120
structure to protect elements in confined spaces mins
The system can also be built horizontally to Refer to C01. S01. P08
Specialist partitions
provide a fire rated membrane.
Key benefits
— Horizontal membranes are built entirely from below
— A ShaftWall variant with non-combustible
C05
Glasroc F firecase board linings is available
— High level commonality with GypWall partition
components, particularly 70mm stud solutions
— Higher certainty of installed acoustic performance
due to laboratory tests incorporating deflection heads
— Can be used where access is limited to one side at
the head, e.g. M & E cages already installed in corridors
Refer to gyproc.ie
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P291
ShaftWall performance
ShaftWall
1 2 3 4
Gypframe 60, 70 or 92mm ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud Gypframe 60, 70 or 92mm ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud
framework with Gyproc CoreBoard framework with Gyproc CoreBoard framework with Gyproc CoreBoard framework with Gyproc CoreBoard
between studs, secured by Gypframe between studs, secured by Gypframe between studs, secured by Gypframe between studs, secured by Gypframe
Retaining Channel. 25mm Retaining Channel. 25mm Retaining Channel. 25mm Retaining Channel. 25mm
Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional).
Lining boards to non-shaft side, see Lining boards to non-shaft side, see Lining boards to non-shaft side, see Lining boards to non-shaft side, see
table. Studs at 600mm centres. table. Studs at 600mm centres. table. Studs at 600mm centres. table. Studs at 600mm centres.
Specialist partitions
Detail Partition Lining boards Max. Stud Sound insulation RwdB3 Duty Approx. System
thickness to non-shaft side1 partition size rating5 weight reference
mm Board type Lining height2 mm kg/m²
No insulation Sealed structure plus
thickness mm
25mm Isover Acoustic
mm Roll 4
For further assistance in choosing the right solution for your project, try our System Selector; an online tool that enables quick and easy
filtering by performance criteria. It provides system specific information downloads including BIM (Revit) objects. Go to gyproc.ie
1
For improved durability and impact resistance, the outer layer of Gyproc FireLine can be replaced with a layer of 15mm Gyproc DuraLine.
2
The maximum heights quoted are limited by the fire state field of application or by limiting deflection of L/240 at 200 Pa, whichever is the more onerous.
3
The acoustic performance figures quoted include ShaftWall partitions with deflection heads.
4
Gyproc CoreBoard and first layer of lining board are bedded onto Gyproc Sealant, as required for pressurised air shafts, in addition to normal sealing.
5
Estimated rating from non-shaft side only.
The fire resistance and sound insulation performances are for imperforate partitions, but incorporating deflection heads, with all joints taped and filled,
or skimmed according to Gyproc’s recommendations. The quoted performances are achieved only if Gyproc and Isover components are used throughout, and
the Company’s fixing recommendations are strictly observed. Any variation in the specifications should be checked with Gyproc.
Gypframe Extra Deep Flange Floor & Ceiling Channel or Gypframe ‘J’ Channel should be used at the head. For the base Gypframe Folded Edge Standard
Floor & Ceiling Channel should be used for heights up to 4200mm, Gypframe Deep Flange Floor & Ceiling Channel should be used for heights between
4200mm and 8000mm, Gypframe Extra Deep Flange Floor & Ceiling Channel should be used for heights in excess of 8000mm.
ShaftWall
For details of when
to specify fire
Vertical elements resistance using BS
Refer to C02. S01. P18
Table 1b — Solutions to satisfy requirements of BS 476: Part 22: 1987
1 2 3 4
Gypframe 60, 70 or 92mm ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud Gypframe 60, 70 or 92mm ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud
framework with Gyproc CoreBoard framework with Gyproc CoreBoard framework with Gyproc CoreBoard framework with Gyproc CoreBoard
between studs, secured by Gypframe between studs, secured by Gypframe between studs, secured by Gypframe between studs, secured by Gypframe
Retaining Channel. 25mm Retaining Channel. 25mm Retaining Channel. 25mm Retaining Channel. 25mm
Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional).
Lining boards to non-shaft side, see Lining boards to non-shaft side, see Lining boards to non-shaft side, see Lining boards to non-shaft side, see
table. Studs at 600mm centres. table. Studs at 600mm centres. table. Studs at 600mm centres. table. Studs at 600mm centres.
Specialist partitions
Detail Partition Lining boards Max. Stud Sound insulation RwdB3 Duty Approx. System
thickness to non-shaft side1 partition size rating5 weight reference
mm Board type Lining height2 mm kg/m²
No insulation Sealed structure plus
thickness mm
25mm Isover Acoustic
mm Roll 4
C05
1 77 Gyproc FireLine 1 x 15 4200 60 39 42 Heavy 30 A306001/010
For further assistance in choosing the right solution for your project, try our System Selector; an online tool that enables quick and easy
filtering by performance criteria. It provides system specific information downloads including BIM (Revit) objects. Go to Gyproc.ie
1
For improved durability and impact resistance, the outer layer of Gyproc FireLine can be replaced with a layer of 15mm Gyproc DuraLine.
2
Based on limiting deflection of L/240 at 200 Pa.
3
The acoustic performance figures quoted include ShaftWall partitions with deflection heads.
4
Gyproc CoreBoard and first layer of lining board are bedded onto Gyproc Sealant, as required for pressurised air shafts, in addition to normal sealing.
5
Estimated rating from non-shaft side only.
The fire resistance and sound insulation performances are for imperforate partitions, but incorporating deflection heads, with all joints taped and filled,
or skimmed according to Gyproc’s recommendations. The quoted performances are achieved only if Gyproc and Isover components are used throughout, and
the Company’s fixing recommendations are strictly observed. Any variation in the specifications should be checked with Gyproc.
Gypframe Extra Deep Flange Floor & Ceiling Channel or Gypframe ‘J’ Channel should be used at the head. For the base Gypframe Folded Edge Standard
Floor & Ceiling Channel should be used for heights up to 4200mm, Gypframe Deep Flange Floor & Ceiling Channel should be used for heights between
4200mm and 8000mm, Gypframe Extra Deep Flange Floor & Ceiling Channel should be used for heights in excess of 8000mm.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P293
ShaftWall performance (continued)
ShaftWall
1 2 3 4
Gypframe 60, 70 or 92mm ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud Gypframe 60, 70 or 92mm ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud
framework with 20mm Glasroc F firecase framework with 20mm Glasroc F firecase framework with 20mm Glasroc F firecase framework with 20mm Glasroc F firecase
between studs, secured by Gypframe between studs, secured by Gypframe between studs, secured by Gypframe between studs, secured by Gypframe
Retaining Channel. 25mm Retaining Channel. 25mm Retaining Channel. 25mm Retaining Channel. 25mm
Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional).
Lining boards to non-shaft side, see Lining boards to non-shaft side, see Lining boards to non-shaft side, see Lining boards to non-shaft side, see
table. Studs at 600mm centres. table. Studs at 600mm centres. table. Studs at 600mm centres. table. Studs at 600mm centres.
Specialist partitions
Detail Partition Lining boards Max. Stud Sound insulation RwdB3 Duty Approx. System
thickness to non-shaft side1 partition size rating5 weight reference
mm Board type Lining height2 mm kg/m²
No insulation Sealed structure plus
thickness mm
25mm Isover Acoustic
mm Roll4
For further assistance in choosing the right solution for your project, try our System Selector; an online tool that enables quick and easy
filtering by performance criteria. It provides system specific information downloads including BIM (Revit) objects. Go to gyproc.ie
1
For a non-combustible solution on the shaft side use only the Glasroc F firecase. On the non-shaft side this can be replaced with a layer of 15mm Gyproc FireLine
or Gyproc DuraLine.
2
The maximum heights quoted are limited by the fire state field of application or by limiting deflection of L/240 at 200 Pa, whichever is the more onerous.
3
The acoustic performance figures quoted include ShaftWall partitions with deflection heads.
4
20mm Glasroc F firecase and first layer of lining board are bedded onto Gyproc Sealant, as required for pressurised air shafts, in addition to normal sealing.
5
Estimated rating from non-shaft side only.
The fire resistance and sound insulation performances are for imperforate partitions, but incorporating deflection heads, with all joints taped and filled,
or skimmed according to Gyproc’s recommendations. The quoted performances are achieved only if Gyproc and Isover components are used throughout, and
the Company’s fixing recommendations are strictly observed. Any variation in the specifications should be checked with Gyproc.
Gypframe Extra Deep Flange Floor & Ceiling Channel or Gypframe ‘J’ Channel should be used at the head. For the base Gypframe Folded Edge Standard
Floor & Ceiling Channel should be used for heights up to 4200mm, Gypframe Deep Flange Floor & Ceiling Channel should be used for heights between
4200mm and 8000mm, Gypframe Extra Deep Flange Floor & Ceiling Channel should be used for heights in excess of 8000mm.
ShaftWall
For details of when
to specify fire
Vertical elements — non-combustible board linings resistance using BS
Refer to C02. S01. P18
Table 2b — Solutions to satisfy requirements of BS 476: Part 22: 1987
1 2 3 4
Gypframe 60, 70 or 92mm ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud Gypframe 60, 70 or 92mm ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud
framework with 20mm Glasroc F firecase framework with 20mm Glasroc F firecase framework with 20mm Glasroc F firecase framework with 20mm Glasroc F firecase
between studs, secured by Gypframe between studs, secured by Gypframe between studs, secured by Gypframe between studs, secured by Gypframe
Retaining Channel. 25mm Retaining Channel. 25mm Retaining Channel. 25mm Retaining Channel. 25mm
Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional). Isover Acoustic Roll in cavity (optional).
Lining boards to non-shaft side, see Lining boards to non-shaft side, see Lining boards to non-shaft side, see Lining boards to non-shaft side, see
table. Studs at 600mm centres. table. Studs at 600mm centres. table. Studs at 600mm centres. table. Studs at 600mm centres.
Specialist partitions
Detail Partition Lining boards Max. Stud Sound insulation RwdB3 Duty Approx. System
thickness to non-shaft side1 partition size rating5 weight reference
mm Board type Lining height2 mm kg/m²
No insulation Sealed structure plus
thickness mm
25mm Isover Acoustic
mm Roll4
C05
1 77 Glasroc F firecase 1 x 15 4200 60 38 41 Heavy 32 G306001/010
For further assistance in choosing the right solution for your project, try our System Selector; an online tool that enables quick and easy
filtering by performance criteria. It provides system specific information downloads including BIM (Revit) objects. Go to gyproc.ie
1
For a non-combustible solution on the shaft side use only the Glasroc F firecase. On the non-shaft side this can be replaced with a layer of 15mm Gyproc FireLine
or Gyproc DuraLine.
2
Based on limiting deflection of L/240 at 200 Pa.
3
The acoustic performance figures quoted include ShaftWall partitions with deflection heads.
4
20mm Glasroc F firecase and first layer of lining board are bedded onto Gyproc Sealant, as required for pressurised air shafts, in addition to normal sealing.
5
Estimated rating from non-shaft side only.
The fire resistance and sound insulation performances are for imperforate partitions, but incorporating deflection heads, with all joints taped and filled,
or skimmed according to Gyproc’s recommendations. The quoted performances are achieved only if Gyproc and Isover components are used throughout, and
the Company’s fixing recommendations are strictly observed. Any variation in the specifications should be checked with Gyproc.
Gypframe Extra Deep Flange Floor & Ceiling Channel or Gypframe ‘J’ Channel should be used at the head. For the base Gypframe Folded Edge Standard
Floor & Ceiling Channel should be used for heights up to 4200mm, Gypframe Deep Flange Floor & Ceiling Channel should be used for heights between
4200mm and 8000mm, Gypframe Extra Deep Flange Floor & Ceiling Channel should be used for heights in excess of 8000mm.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P295
ShaftWall performance (continued)
ShaftWall
Vertical elements
Table 3 — Limiting heights at various air pressure and allowable deflections
1 2 3 4 5 6 7
Gypframe 60 I 70 ‘I’ Gypframe 70 I 70 ‘I’ Gypframe 92 I 90 ‘I’ Gypframe 60 I 70 ‘I’ Gypframe 70 I 70 ‘I’ Gypframe 92 I 90 ‘I’ Gypframe 146 TI
Stud framework with Stud framework with Stud framework with Stud framework with Stud framework with Stud framework with 90 Tabbed ‘I’ Stud
one layer of 15mm one layer of 15mm one layer of 15mm two layers of 12.5mm two layers of 12.5mm two layers of 12.5mm framework with two
Gyproc FireLine1. Gyproc FireLine1. Gyproc FireLine1. Gyproc FireLine1. Gyproc FireLine1. Gyproc FireLine1. layers of 12.5mm
Gyproc FireLine1.
Specialist partitions
Detail System Allowable Limiting height (mm) at stated air pressure (Pa) System
deflection 200 240 300 360 400 480 500 600 650 reference
L/125 5000 4700 4400 4100 4000 3800 3700 3500 3400
1 ShaftWall L/240 4200 4000 3700 3500 3300 3200 3100 2900 2800 A306001/010
L/360 3700 3500 3300 3100 2900 2800 2700 2600 2500
L/125 5000 4700 4400 4100 4000 3800 3700 3500 3400
C05
Based on
2 ShaftWall L/240 4200 4000 3700 3500 3300 3200 3100 2900 2800
A306001/010
L/360 3700 3500 3300 3100 2900 2800 2700 2600 2500
L/125 7500 7100 6600 6200 6000 5700 5500 5200 5100
3 ShaftWall L/240 6000 5700 5300 5000 4800 4600 4400 4200 4100 A306004/011
L/360 5200 4900 4600 4300 4200 4000 3900 3600 3500
L/125 5200 4900 4600 4300 4200 4000 3800 3600 3500
4 ShaftWall L/240 4400 4100 3800 3600 3500 3300 3200 3000 2900 A306002/012
L/360 3800 3600 3300 3100 3000 2900 2800 2600 2500
L/125 5200 4900 4600 4300 4200 4000 3800 3600 3500
Based on
5 ShaftWall L/240 4400 4100 3800 3600 3500 3300 3200 3000 2900
A306002/012
L/360 3800 3600 3300 3100 3000 2900 2800 2600 2500
L/125 7900 7400 6900 6500 6300 5900 5800 5500 5300
6 ShaftWall L/240 6400 6000 5600 5200 5000 4800 4700 4400 4300 A306005/014
L/360 5600 5200 4900 4600 4400 4200 4100 3900 3800
L/125 9800 9200 8600 8100 7800 7300 7200 6800 6600
7 ShaftWall L/240 7900 7400 6900 6500 6200 6000 5800 5500 5300 A306008/020
L/360 6900 6500 6000 5600 5500 5200 5100 4800 4600
For further assistance in choosing the right solution for your project, try our System Selector; an online tool that enables quick and easy
filtering by performance criteria. It provides system specific information downloads including BIM (Revit) objects. Go to gyproc.ie
1
Gyproc FireLine can be replaced with Gyproc DuraLine or Glasroc F firecase.
ShaftWall
Vertical elements
Table 3 — Limiting heights at various air pressure and allowable deflections (continued)
8 9 10 11
Gypframe 60 I 70 ‘I’ Stud Gypframe 70 I 70 ‘I’ Stud Gypframe 92 I 90 ‘I’ Stud Gypframe 146 TI 90 Tabbed ‘I’ Stud
framework with two layers of framework with two layers of framework with two layers of framework with two layers of
15mm Gyproc FireLine1. 15mm Gyproc FireLine1. 15mm Gyproc FireLine1. 15mm Gyproc FireLine1.
Specialist partitions
Detail System Allowable Limiting height (mm) at stated air pressure (Pa) System
deflection 200 240 300 360 400 480 500 600 650 reference
L/125 5200 4900 4600 4300 4100 4000 3800 3600 3500
8 ShaftWall L/240 4500 4200 3900 3700 3500 3400 3300 3100 3000 A306003/023
L/360 3900 3700 3400 3200 3100 3000 2900 2700 2600
L/125 5200 4900 4600 4300 4100 4000 3800 3600 3500
Based on
9 ShaftWall L/240 4500 4200 3900 3700 3500 3400 3300 3100 3000
C05
A306003/023
L/360 3900 3700 3400 3200 3100 3000 2900 2700 2600
L/125 8400 7900 7300 6900 6600 6300 6200 5800 5600
10 ShaftWall L/240 6700 6300 5900 5500 5300 5100 5000 4700 4500 A306006/025
L/360 5600 5300 4900 4600 4500 4200 4100 3900 3800
L/125 9900 9300 8600 8100 7800 7400 7200 6800 6600
11 ShaftWall L/240 7900 7400 6900 6500 6300 6000 5800 5500 5300 A306009/028
L/360 6900 6500 6000 5700 5500 5200 5100 4800 4700
For further assistance in choosing the right solution for your project, try our System Selector; an online tool that enables quick and easy
filtering by performance criteria. It provides system specific information downloads including BIM (Revit) objects. Go to gyproc.ie
These tables give the limiting heights for ShaftWall systems when subjected to air pressures ranging from 200 Pa through to 650 Pa and at three allowable
deflection levels - L/125, L/240, L/360. Partition heights are normally quoted for air pressures of 200 Pa at an allowable deflection of L/240.
When the fire performance of ShaftWall is specified in terms of EN 1364-1: 1999, then the maximum height cannot exceed that given in the relevant table in
this book, irrespective of air pressure or allowable deflection.
1
Gyproc FireLine can be replaced with Gyproc DuraLine or Glasroc F firecase.
Gypframe Extra Deep Flange Floor & Ceiling Channel or Gypframe ‘J’ Channel should be used at the head. For the base Gypframe Folded Edge Standard
Floor & Ceiling Channel should be used for heights up to 4200mm, Gypframe Deep Flange Floor & Ceiling Channel should be used for heights between
4200mm and 8000mm, Gypframe Extra Deep Flange Floor & Ceiling Channel should be used for heights in excess of 8000mm.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P297
ShaftWall performance (continued)
ShaftWall
1 2 3
Gypframe 60, 70 or 92mm ‘I’ Stud or Gypframe Two Gypframe 146 TI 90 Tabbed ‘I’ Stud frames at Two Gypframe 146 TI 90 Tabbed ‘I’ Stud frames at
146 TI 90 Tabbed ‘I’ Stud frames at 600mm centres 600mm centres with Gyproc CoreBoard between 600mm centres with Gyproc CoreBoard between
Specialist partitions
with Gyproc CoreBoard between studs, secured by studs, secured by Gypframe Retaining Channel. 25mm studs, secured by Gypframe Retaining Channel. 25mm
Gypframe Retaining Channel. 25mm Isover Acoustic Isover Acoustic Roll in cavity (optional). On the lower Isover Acoustic Roll in cavity (optional). On the lower
Roll in cavity (optional). Gypframe MF5 Ceiling framework only, Gypframe MF5 Ceiling Sections fixed framework only, Gypframe MF5 Ceiling Sections fixed
Sections fixed to ceiling side at 450mm centres. Lining to ceiling side at 450mm centres. Lining boards to to ceiling side at 450mm centres. Lining boards to
boards to ceiling side, see table. ceiling side, see table. ceiling side, see table.
Detail Thickness Lining boards Max. Stud Sound insulation RwdB Approx. System
mm to non-shaft side span1 size weight reference
mm mm kg/m²
C05
For further assistance in choosing the right solution for your project, try our System Selector; an online tool that enables quick and easy
filtering by performance criteria. It provides system specific information downloads including BIM (Revit) objects. Go to gyproc.ie
1
Based on fire state field of application, or by a limiting deflection of L/400, whichever is greater.
The fire resistance and sound insulation performances are for imperforate ceilings incorporating boards, with all joints taped and filled,
or skimmed according to Gyproc’s recommendations. The quoted performances are achieved only if Gyproc and Isover components are used throughout, and
the Company’s fixing recommendations are strictly observed. Any variation in the specifications should be checked with Gyproc.
ShaftWall used horizontally should not be used for materials storage or access for personnel, or to provide support to services.
Gypframe Extra Deep Flange Floor & Ceiling Channel or Gypframe ‘J’ Channel should be used at perimeter.
ShaftWall
For details of when
to specify fire
Horizontal elements resistance using BS
Refer to C02. S01. P18
Table 4b – Solutions to satisfy requirements of BS 476: Part 22: 1987
1 2 3
Gypframe 60, 70 or 92mm ‘I’ Stud or Gypframe Two Gypframe 146 TI 90 Tabbed ‘I’ Stud frames at Two Gypframe 146 TI 90 Tabbed ‘I’ Stud frames at
146 TI 90 Tabbed ‘I’ Stud frames at 600mm centres 600mm centres with Gyproc CoreBoard between 600mm centres with Gyproc CoreBoard between
Specialist partitions
with Gyproc CoreBoard between studs, secured by studs, secured by Gypframe Retaining Channel. 25mm studs, secured by Gypframe Retaining Channel. 25mm
Gypframe Retaining Channel. 25mm Isover Acoustic Isover Acoustic Roll in cavity (optional). On the lower Isover Acoustic Roll in cavity (optional). On the lower
Roll in cavity (optional). Gypframe MF5 Ceiling framework only, Gypframe MF5 Ceiling Sections fixed framework only, Gypframe MF5 Ceiling Sections fixed
Sections fixed to ceiling side at 450mm centres. Lining to ceiling side at 450mm centres. Lining boards to to ceiling side at 450mm centres. Lining boards to
boards to ceiling side, see table. ceiling side, see table. ceiling side, see table.
Detail Thickness Lining boards Max. Stud Sound insulation RwdB Approx. System
mm to non-shaft side span1 size weight reference
mm mm kg/m²
C05
Board type Lining No insulation Sealed structure plus
thickness 25mm Isover
mm Acoustic Roll
For further assistance in choosing the right solution for your project, try our System Selector; an online tool that enables quick and easy
filtering by performance criteria. It provides system specific information downloads including BIM (Revit) objects. Go to gyproc.ie
1
Based on a limiting deflection of L/400.
The fire resistance and sound insulation performances are for imperforate ceilings incorporating boards, with all joints taped and filled,
or skimmed according to Gyproc’s recommendations. The quoted performances are achieved only if Gyproc and Isover components are used throughout, and
the Company’s fixing recommendations are strictly observed. Any variation in the specifications should be checked with Gyproc.
ShaftWall used horizontally should not be used for materials storage or access for personnel, or to provide support to services.
Gypframe Extra Deep Flange Floor & Ceiling Channel or Gypframe ‘J’ Channel should be used at perimeter.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P299
ShaftWall design
ShaftWall
ShaftWall comprises Gypframe 'I' Studs and Gypframe Starter The floor channel must have continuous support along its length
Channels within Gypframe Floor & Ceiling Channels. to maintain specified performance levels. If continuous support is
not provided by the structure, e.g. Z-sections running transverse to
The shaft-side boards are retained between the Gypframe Floor a steel beam, the designer should detail the installation of a rigid
& Ceiling Channels and adjacent studs using Gypframe Retaining non-combustible material between the Z-sections. Z-sections need
Channels; which enables construction from the side only. to be protected and remain in-situ in the event of a fire, taking into
account any loads they are supporting.
Planning – key factors
In situations where the floor channel is fixed to diagonal structural
The position of services should be pre-determined and their
steel, the studs should be accurately scribed to the rake of the
installation planned into the frame erection stage. Timber sole
channel to maintain the full bearing surface.
plates should be considered, if appropriate, where the floor is uneven.
Important information
Limiting heights at different air pressures
For ShaftWall systems utilising Gypframe
The maximum heights quoted in the performance tables for vertical
60 I 70 'I' Studs, Gypframe 62 JC 70 'J'
elements are based on a limiting deflection of L/240 at 200 Pa, or by
Channel with its asymmetrical legs is
the fire state field of application. In practice, deflection from L/125
needed at the head to facilitate the
to L/360 may be allowed and pressure conditions between 200 Pa
installation of the Gyproc CoreBoard. The
and 650 Pa may be encountered. These variations will affect the
shorter leg is installed facing the non-
maximum wall height. Refer to table 3.
shaft side. For ShaftWall systems that use
wider Gypframe 'I' studs, the appropriate
Gypframe Extra Deep Flange Floor and
Ceiling Channel should be used.
Where 120 mins is required to BS 476: Part 22, replace the inner layer of 15mm Gyproc FireLine (corridor side) with 19mm Gyproc CoreBoard, fixed horizontally.
1
ShaftWall
Connection to the structure Deflection heads
Structural steelwork and its associated connections often result in Deflection heads, by definition, must be able to move and,
complex junctions around shafts. If ShaftWall is built on the same therefore, achieving an airtight seal is difficult. Inevitably, this will
line as the beamwork framing the shaft, problems may arise in have a detrimental effect on the acoustic performance of any wall
trying to seal the wall up to the steelwork. It is recommended that, that incorporates deflection at the head. In most cases, a suspended
wherever possible, the wall should be located to one side of the ceiling will assist in minimising loss of performance.
beams, and fixed from structural floor to structural soffit.
Refer to construction details 11-17 for standard head details.
Specialist partitions
Door openings
Deflection criteria
In the case of both normal access doors and lift doors, the door and
Partitions built to a maximum height based on L/125 at 200 Pa
frame assembly must have been shown by a fire resistance test
will exhibit greater deflection compared to partitions built to
to achieve the required standard of performance in this form of
a maximum height based on L/240 at 200 Pa. Partitions with
construction.
deflection characteristics outside the standard L/240 criteria
will exhibit more flex during installation and in general use,
Lift doors must be substantiated in conjunction with ShaftWall
C05
and therefore we recommend you verify the acceptability of the
complete with their framing members and transom panels. To
deflections with the relevant interested parties before specifying /
achieve a satisfactory level of compatibility, a suitable starter
installing partitions based on L/125 criteria.
channel should be mechanically fixed to the door frame at 300mm
centres.
Services
Refer to construction details 23-25 within this section.
Penetrations
Penetrations of fire-resistant constructions for services should be
Pressurised airshafts and service ducts
minimised, however if essential, careful consideration should be
The use of pressure conditions in various types of shaft / duct given to ensure that the integrity of the element is not impaired,
requires that the boards should be sealed into the framing and that the services themselves do not act as the mechanism of
members using Gyproc Sealant in addition to the normal sealing of fire spread.
the framing to adjoining structures. It is essential that these areas
Refer to C02. S01. P41 – Service installations.
are identified at a very early stage of the contract, and that other
trades are instructed to recognise the need for the application of
Independent support
sealant and its replacement if subsequently damaged or removed.
When designing for the installation of services such as fire dampers
In order that the integrity of the pressurised system can be
and associated ductwork through ShaftWall, consideration should
maintained, Gyproc Sealant should be specified for all
be given to the size and weight of the damper – this will determine
board-to-metal applications, and the sealing of Gyproc CoreBoard
whether it can be supported directly from the partition or needs to
(or Glasroc F firecase) to the framing.
be independently supported from the structure.
Refer to construction details 17-20 within this section.
Refer to C04. S01. P122 – Partitions introduction, construction
details 29-31.
Control joints
Control joints may need to be considered in conditions where Openings bridging studs
excessive movement is likely to occur, or to coincide with Openings should be constructed using channels for the trimming
constructional expansion joints. In order that the deflection criteria members. The web of the channel should be rebated to allow
can be maintained throughout the building, it is necessary to the flanges to oversail the stud. The flanges are secured with two
introduce horizontal movement joints in the lining where this fixings. Channels are cut and inserted to maintain the 25mm gap
would normally be required to extend through the height of the surround and fixed to the trimming channels.
building, e.g. stairwells.
Refer to construction detail 21 within this section.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P301
ShaftWall design (continued)
ShaftWall
Important information For access doors, openings should be framed to avoid impairing
the structural or fire-resistant properties of ShaftWall. To provide
The quoted sound insulation an opening ready to receive a door set, the jambs to storey height
performances of ShaftWall, detailed should be capped with Gypframe ‘J’ Channel incorporating a
in the preceeding performance tables, plasterboard packer. A pre-formed spandrel panel assembled
incorporate a deflection head as part between starter channels should be inserted between jambs
of the tested construction. Therefore, and engaged into the head channel, retaining the 15mm gap for
this effectively downgrades the sound deflection at the head.
insulation performance of the system. Refer to construction detail 23 within this section.
To minimise the loss, install Gypframe
GA4 Steel Angle at the head, which Support is provided by a Gypframe ‘J’ Channel transom. The door
will improve the performance by frame is secured to both Gypframe ‘I’ Stud and Gypframe ‘J’ Channel
approximately 2-3dB, refer to jambs and also to the transom member.
C02. S01. P21 – Building acoustics.
Refer to construction detail 25 within this section.
Specialist partitions
Board finishing
Gypframe 99 FC 50 Fixing Channel should be cut to bridge adjoining Supporting partitions should be of at least the same fire resistance
studs, with the edges flattened to permit fixing. The fixing channel period as the horizontal ShaftWall.
should be backed with stone mineral wool. Gyproc FireLine (or
Glasroc F firecase) linings should be cut to allow a close fitting entry
of the switch box which can be secured to the fixing channel.
ShaftWall
2
1 2
2 5
6
8
7
1
11
Specialist partitions
Base Junction with other elements
3 4
2
C05
4 2
8 4
10
1
5 6
3
9
2 2
4 4
Intermediate stud (framework showing Gypframe Tabbed 'I' Stud) Partition junction (on-stud)
1
Replace with 15mm Glasroc F firecase for systems with non-combustible linings.
2
Replace with 20mm Glasroc F firecase for systems with non-combustible linings.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P303
ShaftWall construction details (continued)
ShaftWall
7 8
3
10
4
2
2
4 8
1 7
6
9
1
Specialist partitions
5
10
C05
4
1
2
10
2
1
5
10
4
External corner
1
Replace with 15mm Glasroc F firecase for systems with non-combustible linings.
2
Replace with 20mm Glasroc F firecase for systems with non-combustible linings.
ShaftWall
Head details incorporating 15mm downward deflection
11 12
7 7
8 8
15mm 15mm 9
15mm
15mm
5 6
10 15mm
20mm 10
20mm 15mm
3
3
2
Specialist partitions
1
4
4
1
2
C05
60mm framework (live loads)3 70mm framework (live loads)
13 14
7
7
8
15mm
8
9
15mm
15mm 9
6 15mm
15mm 6
15mm
20mm 10
20mm 2
3
10
2
4
4
1
1
11
1
Replace with 15mm Glasroc F firecase for systems with non-combustible linings. 3
Vertical fire-stops are not recommended for non-combustible linings, use
2
Replace with 20mm Glasroc F firecase for systems with non-combustible linings. horizontal fire-stops similar to detail 12.
No fixings should be made through the boards into the flanges of the head channel. The arrow ( ) denotes the position of the uppermost board fixing.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P305
ShaftWall construction details (continued)
ShaftWall
15 16
12 12
8 8
9 9
13 14
3 3
4 4
2 2
1 1
Specialist partitions
Head incorporating Gypframe G108 Retaining Clip (92mm) Head incorporating Gypframe G109 Retaining Clip (146mm)
17 8 18
10
3
7
C05
9 2
2 4
1
4
Head (sealed structure). Example shows 60mm stud3 Intermediate stud (sealed structure)
19 20 2
4
7
2 5
1
4
7
6 11
7 1
Base (sealed structure) Junction with other elements (sealed structure)
ShaftWall
21
Section W-W
W
6
X X
Specialist partitions
W
5
Section X-X
3
4
C05
1
2
22
Section Y-Y
7
Y
Z Z
3
2
Section Z-Z
1
7
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P307
ShaftWall construction details (continued)
ShaftWall
23 24
6
7
3
2
2
4
8 4
1
1
5
5
Specialist partitions
Access door - spandrel panel Lift door (Gypframe Starter Channel mechanically fixed to frame)
25
2
6
C05
3
9
8
4
1
1
Replace with 15mm Glasroc F firecase for systems with non-combustible linings.
2
Replace with 20mm Glasroc F firecase for systems with non-combustible linings.
ShaftWall
26
16
2
3
15
Specialist partitions
Retro-fit non-performance partition junction
27 28
C05
2
4
5
15
12
14 9
9
15
6
10
7
13
2 11
7
4
1
Fixing head channel to Z-section at underside of beams3 Control joint at floor slab junction where lining boards continue
1
Replace with 15mm Glasroc F firecase for systems with non-combustible linings. 3
Use alternative deflection head detail for systems with non-combustible
2
Replace with 20mm Glasroc F firecase for systems with non-combustible linings. linings.
No fixings should be made through the boards into the flanges of the head channel. The arrow ( ) denotes the position of the uppermost board fixing.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P309
ShaftWall construction details (continued)
ShaftWall
29 30
9 2
10 1
15 12
11 4
15
8
10
Specialist partitions
7
11
5
13
6
14
2
4
3 7
1
C05
1
Replace with 15mm Glasroc F firecase for systems with non-combustible linings.
2
Replace with 20mm Glasroc F firecase for systems with non-combustible linings.
No fixings should be made through the boards into the flanges of the head channel. The arrow ( ) denotes the position of the uppermost board fixing.
ShaftWall
31
400mm
Specialist partitions
3
10mm
C05
160mm
200mm
56 / 66 / 88mm
Fixing zone
20mm
10mm
20mm
Overlap of studs
200mm
160mm
3
400mm
60 / 70 / 92mm
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P311
ShaftWall construction details (continued)
ShaftWall
32
50mm
2
1
Specialist partitions
4 4
C05
50mm
1000mm
50mm
3
50mm
1
50mm
3
50mm
ShaftWall
Horizontal ShaftWall (ShaftWall used horizontally should not be used for material storage or access for personnel)
33 34
10 11 9 4 2 4 2
Specialist partitions
1 7 3 9 8 5 1 3 7
C05
Gyproc CoreBoard joint Perimeter detail 1
35
2 4
9 8 6 1 7 3
Perimeter detail 2
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P313
ShaftWall construction details (continued)
ShaftWall
Horizontal ShaftWall (ShaftWall used horizontally should not be used for material storage or access for personnel)
36
1 8 7 6 3 2 4 5
Specialist partitions
C05
Reflected ceiling
ShaftWall
Gypframe metal components
Gypframe ‘I’ Studs (60 I 70, 70 I 70, 92 I 90, Gypframe Retaining Channel (G102, G105, G110)
146 TI 90 Tabbed) Insert channel to provide support for the
Enhanced strength stud that allows for partition Gyproc CoreBoard located within the Gypframe ‘I’
height, without increasing partition width. Designed stud. G102 for 60 I 70 and 146 TI 90 'I' Studs.
G105 for 92 I 90 'I' Studs.
to receive fixing of board to one side (face fixed) and
G110 for 70 I 70 'I' Studs.
to accommodate Gyproc CoreBoard within its flange.
Gypframe Folded Edge Standard Floor & Ceiling Gypframe Retaining Clips (G108, G109)
Channels (62 FEC 50, 72 FEC 50, 94 FEC 50, 148 FEC 50) Used within Gypframe ‘I’ studs at deflection heads.
Standard floor channels for retaining the Gypframe G108 for 92 I 90 'I' Studs.
studs at floor junctions for heights not exceeding G109 for 146 TI 90 'I' Studs.
4200mm.
Specialist partitions
Gypframe Deep Flange Floor & Ceiling Channels Gypframe GA3 Steel Angle
(62 DC 60, 72 DC 60, 94 DC 60, 148 DC 60) Steel angle providing framing stability and
Floor and ceiling channels with deep flanges for board support. Used at horizontal joints of
retaining the Gypframe studs at floor and ceiling Gyproc CoreBoard.
junctions for partitions 4200mm to 8000mm high.
Also used around openings and in deflection heads
(maximum 30mm deflection). Also accommodates Gypframe 99 FC 50 Fixing Channel
C05
Gypframe Retaining Clips / Channels and where A versatile metal fixing channel used to support
applicable used around the perimeter in horizontal medium weight fixtures on walls.
applications.
Gypframe Extra Deep Flange Floor & Ceiling Gypframe GFT1 Fixing T
Channels (72 EDC 80, 94 EDC 70, 148 EDC 80) Used to support horizontal board joints.
Floor and ceiling channels with extra deep flanges
for retaining the Gypframe studs at floor and ceiling
junctions for partitions over 8000mm high. Also used
around openings and in deflection heads (maximum Gypframe Service Support Plate
50mm deflection). Also accommodates Gypframe For installation of 18mm plywood within
Retaining Clips / Channels and where applicable used a partition cavity to support medium to
around the perimeter in horizontal applications. heavyweight fixtures.
Gypframe Tabbed Starter Channel (146 TSC 90) Gypframe MF6 Perimeter Channel
Vertical stud used at abutments and openings to Perimeter section to support Gypframe MF5 Ceiling
receive fixing of board. Section and fixing of board.
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P315
ShaftWall system components (continued)
ShaftWall
Board products
1
Glasroc F firecase boards used to replace Gyproc CoreBoard on the shaft side of the system must be cut to 598mm wide (+0mm / -3mm).
2
Also available in a Moisture Resistant (mr) version. mr boards are specified in intermittent wet use areas.
Specialist partitions
Fixing products
less than 0.8mm thick (‘I’ Studs less than 0.6mm greater (‘I’ Studs 0.6mm thick and greater).
thick).
Plasterboard accessories
ShaftWall
Finishing products
Insulation products
Specialist partitions
Isover Acoustic Roll
Glass mineral wool for enhanced acoustic and
thermal performance.
C05
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P317
ShaftWall installation overview
ShaftWall
The appropriate Gypframe channels, are Gypframe Starter Channels are suitably Gypframe ‘I’ Studs or Gypframe Tabbed 'I'
suitably fixed to the floor and soffit of the fixed to vertical abutments. The perimeter Studs are friction fitted into the channels at
structure. Gyproc FireStrip is used on the of the partition is sealed with 600mm required centres. Gyproc CoreBoard
Specialist partitions
channel at the soffit. Gyproc Sealant. or 20mm Glasroc F firecase is fitted between
the studs on the shaft side, and held in
place with appropriate Gypframe Retaining
Channels. Door openings are formed to the
ShaftWall Access Door Details.
C05
Gyproc Sealant
Gypframe GA3
Steel Angle
Pressurised shafts and service ducts are Horizontal board joints are fire stopped Isover Acoustic Roll can be added to the
sealed using Gyproc Sealant. This is applied using Gypframe GA3 Angle and strips of partition cavity for increased acoustic
to all board-to-metal junctions. Gyproc CoreBoard from the non-shaft side. performance.
Additional information
For full installation details, refer to the
Gyproc Installation Guide, available to
download from gyproc.ie
ROI: 1800 744480 NI: 0845 3990159 tech.ie@saint-gobain.com C05. S02. P319