Abstract
Value stream mapping (VSM) is based on an analysis of the times required to carry out production
processes throughout the customer-manufacturer-supplier logistics chain. The goal of VSM is to identify
wastes and eliminate them, thereby increasing the added value of a product. The paper presents an
extension of the VSM concept which is based on determining the costs associated with the necessary
operations and determining, based on said costs, the total costs of the entire production process. When
eliminating those activities that represent waste, we can, by simulating the total costs, determine the
contribution of the implemented measure to the reduction of lead time and, above all, the reduction of
costs and thus the economic efficiency of the production process. For the presentation, by simulating
the identified cost effects of the anticipated changes, we can calculate the leanness cost index and, using
portfolio analysis of the leanness of the production system, analyse the effects. The application of the
proposed methodology is shown in the case of transition from individual to lean and agile series
production of ceramic capacitors.
(Received in June 2020, accepted in August 2020. This paper was with the authors 1 week for 1 revision.)
Key Words: Lean Production, Value Stream Mapping (VSM), Simulation, Leanness Cost Index,
Portfolio Analysis of Production System Leanness
1. INTRODUCTION
Lean thinking usually refers to 3 important areas of business: lean management, lean product
and process development, and lean production.
If we look at production processes in detail, the processes can be, in terms of leanness,
divided into those that add value (value added), those that do not add value, but are absolutely
necessary for the implementation of processes that add value (necessary non-value added), and
those that contribute nothing to the added value of the product (non-value added), but consume
time, resources, space and bind capital. The latter is simply called wastes.
Wastes can be divided into strategic, organizational and operational wastes. To eliminate
waste at the strategic level, it is important for the management to choose the right strategies
regarding the type and quantity of products that can be sold in the market, and select the right
processes that enable development and manufacturing that are of interest to the customer in
terms of quality and price. Organizational waste is mainly due to the wrong organizational
structure of the company, poorly defined and non-transparent business processes, lack or
underutilization of production resources, poorly selected technology and lack of knowledge or
experience of middle management. Operational waste is related to hyper production or
premature production, waiting, storage, transport, work process, movement and production of
defective products.
Value stream mapping is most often used for waste analysis, which systematically describes
the entire logistics chain of the production process from suppliers, production, storage to
delivery to the customer.
Value stream mapping is based primarily on the analysis of time losses. However, a time
loss does not indicate what the consequence of the waste is expressed in money. For example,
the loss of one working day due to waiting at the disposal location before the next operation is,
https://doi.org/10.2507/IJSIMM19-3-527 458
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
in terms of money, significantly lower than the loss of one working day due to too long machine
set-up time. So, in addition to time analysis, it is necessary to perform a cost analysis of wastes.
Even in practice, to eliminate waste is not enough, it is increasingly important to create added
value.
The paper will show the method of expanding the classic VSM with a cost analysis of the
entire production process. By using simulation of different scenarios of waste elimination, the
cost effects of the transition to lean production can be determined by calculating the leanness
cost index and using a portfolio analysis of the production system leanness.
2. LITERATURE REVIEW
Based on the latest literature review for the use of value stream mapping and simulation
regarding the non-value added and value-added time, the following papers dealing with this
topic were found:
As described in [1], VSM is a visualization tool for the supply chain and value stream, based
on the Toyota Production System, and is of great help in successfully implementing a lean
system. VSM is a mapping tool for a set of activities (value added, non-value added and
necessary non-value added) needed to bring the product from a raw material to a finished
product, which the customer requires [2]. Heravi and Firoozi [3] confirmed that the ultimate
goal of lean philosophy is to eliminate or decrease wastes and deliver value to the customer.
Often the Poka Yoke methodology is used in production processes and has become a synonym
for error prevention, which is also one of the major wastes, since errors are prevented before
reaching the customers [4]. According to [5], lean scheduling is conceptually similar to lean
manufacturing and revolves around elimination of wastes, continuous improvement, total
preventive maintenance and quick changeover. The implementation of lean in job shop
reflected that lean scheduling is possible in job shop as well and can bring positive impact on
manufacturing activity. It may be helpful to reduce the long lead times with reduction in non‐
processing times and implementation of ‘One piece flow’. Kuhlang et al. [6] stated that the
interaction of Value Stream Mapping and the Hybrid Optimisation of Added Value at different
levels of detail consideration contributes to the identification, elimination and avoidance of
waste and thus leads to a design of efficient and effective processes. The joint mutual benefit
of the combined application arises from the increase in productivity, from the standardisation
of processes, from the reduction in lead time/inventory and from the accurately determined
times; it also enables and ensures the predictability and the capability to assess the target status.
Gunduz and Naser [7] have introduced and developed a concept to calculate the cost of
Value Stream Mapping on a weekly basis. This technique can be utilized to understand the
construction progress status and future expectations. Moreover, it can be used to calculate the
cost of similar projects for tendering purposes. The paper attempts to address the application of
Value Stream Mapping to a real-life problem of an underground pipeline project. It analysed
the improvement of value-added times and reduction in non-value-added times compared with
the cycle time. They studied the reduction opportunity in total lead time.
According to [8], small and medium scale enterprises are under a constant pressure to
improve the product quality in order to meet customer requirements. They stated that the Lean-
Kaizen using VSM was found as an effective technique to reduce the cost.
Carmignani [9] suggested a new methodology called Scrap Value Stream Mapping (SVSM)
which combines the concepts from the standard VSM approach with other tools deriving from
World Class Manufacturing and Lean Production. In particular, the framework is structured to
analyse the accounting and the physical stream of the Supply Scrap Management Process
(SSMP) in order to optimise them, by proposing implementable improvements. Furthermore,
459
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
the SVSM proposes a monitoring methodology to keep two components of non-capital carrying
costs that are affected by SSMP, namely Storage Space costs and Inventory Risk costs low.
The presented simulation model from Onofrejeva et. al. [10] for the qualitative approach to
management decisions related to the evaluation of key parameters (productivity and throughput
of the manufacturing system) was based on the simulation results on optimizing the production
capacity by selecting constrains, with the goal to increase productivity and setting the
production to maximize sales profit using the Simplex method.
The Theory of Constrains (TOC) is another widely known management concept used also
by the study of Urban [11] who concluded that, if a company wants to meet a new level of
productivity, the manufacturing system needs to have an adopted and improved solution mix
consisting of a variety of means and methods. As described in [12], the main implementation
weakness of production management methods as Lean, Six Sigma or TOC lies with over
focussing on particular method, so those methods are usually used solitary, and the complex
approach is usually underestimated. This can be changed only with changing the way of
thinking within all levels of company’s management. The authors have been focussing on the
use of basic principles of process thinking connected with design, technology and
manufacturing logistics with emphasizing the role of standardization. They concluded that the
process thinking development should be the creation of a methodology to support the systematic
implementation of process thinking and process-oriented methods at all levels of the company.
It is not only the throughput time that is important, but also the production system
availability shown by Zhou et al. [13]. By flexibly changing the production configuration, the
improvement of system availability is possible [14] using the genetic algorithm for efficient
optimisation by changing the production configuration (workers, machines, buffers and
transporter allocations). Based on the research by [15] contingency factors in terms of company
size, batch size, product complexity, included as control variables in analyses, proved
insignificant for technologies’ use and their effect on profits before tax, decrease in the scrap
rate, material and staff costs. On the other hand, advanced manufacturing technology has impact
on material consumption, scrap rate and profits, but not in a positive hypothesised relationship.
In the paper [16] a business planning model with feedback was presented, were the model
includes planning, monitoring and harmonization of business operations which is also
appropriate for unstable conditions, regarding the essential influences from the business
environment, thus adapting the company's operations.
Sremcev et al. [17] presented an application of VSM and discrete event simulation to
improve the company’s performance new system design in terms of accepted quotations,
resource utilisation, delivery time, work in process, non-value-added time and number of
required operators.
The costs in connection with VSM were most comprehensively recorded by Gracanin et al.
[18], particularly the costs of material, labour and waiting and the course of costs was shown
in a cumulative histogram. The advantage of such presentation is that a time-dependent
cumulative cost generation can be presented. In this way, it is possible to show the cost and
time effects of measures implemented on the value flow.
Based on this literature review, we came to a conclusion that the cost aspect of the VSM
influence is not well studied or developed, so this paper proposes a model based on the VSM
methodology with simulation based on the cost aspect as shown in the next chapter.
3. METHODOLOGY
The cost analysis of waste according to VSM should include all costs that occur in the
production logistics chain of one product. The costs incurred are divided into costs that add
value, costs that enable the creation of added value and costs that represent a waste.
460
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
461
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
Based on the calculated cost-effectiveness index and the known index of overall equipment
efficiency OEE, the leanness of a production process can be determined using the portfolio
analysis [19] (Fig. 1).
OEE
[%]
100
Lean
high Improve PEc production
process
Unlean
Improve
low production
OEE
process
462
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
AS IS state
portfolio analysis of leanness
Yes
production? One piece flow
production
No
FIFO lines,
Yes
Cells, lines KANBAN,
supermarket..
No
Transition is not
possible
Figure 2: Transition from the existing state to a target state of a production process.
Measures
4. CASE STUDY
We will look at the simulation of a transition from the existing state to a target state on an
example of transition from individual production to series lean and agile production. We will
focus on the case of production of ceramic capacitors, which the company now produces in
smaller quantities (1500 pieces/month), yet there is a possibility of a large increase in the
quantities of up to 80,000 pieces per month in the future.
The goal of the company's management is to make a transition from the current individual
production of a workshop type to series lean and agile production. As a measurable goal, the
company determined that the economic efficiency index of the new PEc production method
should be more than 0.5 and the product lead time should be less than 15 working days.
The company performed an AS IS VSM analysis for this product with proposed measures
for the TARGET state, i.e. the transition to series lean and agile production. Based on the
portfolio analysis of the current state (Fig. 2), the company decided to first determine what the
economic impact would be if all the planned measures were taken to approach the flow
production and what measures could be taken to opt for line production or cell production.
However, it should be borne in mind that in the future the production of significantly larger
quantities is expected and that the selling price will probably have to be drastically reduced,
otherwise the company will not be competitive in the market.
463
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
The company made an in-depth analysis of the VSM results and possible measures for
improvement and thus prepared a simulation programme and data for cost efficiency simulation
and portfolio analysis. First, the AS IS state was analysed and then, with numerous iterations
of the simulation, the possibilities of transition to flow or cell or line production. The VSM-
based cost simulation showed how much each improvement contributes to the cost effect of
production.
Table I shows the data that we need to simulate the cost efficiency of a transition from the
existing – AS IS state to a desired new state and part of calculated values.
Table I: Data for the implementation of simulation and partial results.
Values of data
Name of data
AS IS state Flow production Cell or line prod.
Produced quantity [pieces/month] 1500 80,000 80,000
Lead time (from VSM) [Wd] 73.85 7.3 9.12
Lead time without processing, preparation [Wd] 72.77 7.06 8.88
Sum of processing times [min] 18.22 2.34 2.34
Sum of preparation times [h] 7.51 1.67 1.67
Transport path [m] 888 159 233.8
Investment [€] 0 1,163,800 113,800
Depreciation cost – 3 years [€/piece] 0 0.448 0.044
Selling price [€/piece] 11 11/ 4 11/ 4
Number of operations needed 54 32 32
Number of workplaces 23 16 16
Material purchase price [€] 0.5 0.5 0.5
Cost of warehousing + stocking [€/piece, Wd] 0.00034 0.00040 0.00040
Workplace cost [€/h] 30 30 30
Machine cost [€/h] 17.8 17.8 17.8
Worker cost [€/h] 12.2 12.2 12.2
Walking time [min] 20.72 3.71 5.46
Transport cost [€/piece] 0.0009 0.00001 0.00002
Cost of technological operations [€/piece] 9.11 1.17 1.17
Preparation cost [€/piece] 0.15 0.001 0.001
Cost of warehousing + stocking [€/piece] 0.025 0.0028 0.0036
Capital binding interest rate [%] 3 3 3
Total cost [€/piece] 10.37 2.22 1.82
464
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
465
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
Figure 5: Portfolio analysis for the case of flow production (for PC is 11 € and 4 €).
The reason is that the transition to flow production would be associated with large
investment funds, which would have a significant impact on the total cost of the product through
depreciation. The calculation using the break-even point method showed that the investment in
flow production would be profitable only at an output of 15,600,000 products per year
(1,300,000 products per month).
Since such quantities are impossible to produce, we decided to perform a simulation for the
case of a transition to cell or line production without full automation and expensive machines.
4.3 Portfolio analysis of cell or line production
In this analysis, we decided to introduce into production, in addition to FIFO lines, also
KANBAN and the supermarket principle, which are characteristic of cell or line production.
The goals of production renewal remain unchanged, i.e. to achieve a lead time of less than
15 Wd for 80,000 pieces per month and to achieve an index of economic efficiency of
production PEci more than 50 %. Due to the high investment in flow production, it was analysed
which investment costs can be waived in order to still achieve the set goals.
It was found that the investment can be reduced by as much as 90 % and we will still be
able to produce a quality product. There are still plenty of reserves in terms of lead time and it
can be increased if necessary. Above all, we retained all measures aimed at eliminating wastes.
The simulation data are shown in Table I (column 4).
The calculation of the cost-effectiveness index of the production process at the unchanged
selling price (11 €/piece) is:
PEci (11 €) = (SPi – ∑ci) / SPi = (11 – 1.82) / 11 = 0.83
and for a possible selling price in the most unfavourable market conditions (4 €/piece]:
PEci (4 €) = (SPi - ∑ci)/ SPi = (4-2.22)/4 = 0.55
Presumably, the OEE will still remain at 0.65. The portfolio analysis of the state that would
allow for cell or line production is shown in Fig. 6.
466
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
It can be established that the lead time has increased to 9.12 Wd compared to the flow
production, which is still less than the target value of 15 Wd. Regarding the economic efficiency
of production, it can be concluded that the set goal is achieved with both selling prices, which
is more than 50 %.
4.4 Comparison of results
Table II provides an overview of the simulation results for the transition from the current
individual production to lean series production. According to the AS IS state, two possibilities
of transition were analysed: 1) to flow production and 2) to cell or line production.
Table II makes us conclude that only the transformation of the production process into cell
or line production fully meets the set goals for the transition from individual to lean series
production. For comparison, Table II also provides information on the time efficiency of
production (sum of processing times / lead times), which is obtained by the VSM analysis. It
can be concluded that this information is of no use in making decisions for the transition to lean
production. The structure of value-added shares is also interesting (Table III).
Table II: Comparison of results of simulated transition.
AS IS state Flow production Cell or line production
Quantity [pcs/month] 1500 80,000 80,000
Selling price [€/piece] 11 11 4 11 4
Total costs [€/piece] 10.36 2.22 1.82
Lead time [Wd] 73.8 7.3 9.12
OEE [%] 54 65 65
Economic efficiency [%] 6 80 44 83 55
Time efficiency [%] 0.057 0.075 0.060
As can be seen from Table III, the percentages of added value are relatively high, but the
total costs in the AS IS state are absolutely too high and would soon become higher than the
selling price in the long run. It is also evident that the decision for a cell or line production is
also the most appropriate decision in terms of shares of added value.
According to [18], the results achieved can also be shown in the cost-time profile (Fig. 7).
It shows how radical the introduced changes were on the account of the reduced lead time and
the overall production cost per product unit.
467
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
Fig. 7 shows that the flow time in the cost-time profile is reduced from 73.8 Wd to 9.12 Wd,
whereby the cost-profile of the product has decreased from 9.11 €/piece to 1.17 €/piece.
REFERENCES
[1] Teichgräber, U. K.; de Bucourt, M. (2012). Applying value stream mapping techniques to eliminate
non-value-added waste for the procurement of endovascular stents, European Journal of
Radiology, Vol. 81, No. 1, 47-52, doi:10.1016/j.ejrad.2010.12.045
[2] Rother, M.; Shook, J. (2003). Learning to See: Value - Stream Mapping to Add Value and Eliminate
Muda, Lean Enterprise Institute, Cambridge
[3] Heravi, G.; Firoozi, M. (2017). Production process improvement of buildings’ prefabricated steel
frames using value stream mapping, The International Journal of Advanced Manufacturing
Technology, Vol. 89, 3307-3321, doi:10.1007/s00170-016-9306-9
[4] Lazarevic, M.; Mandic, J.; Sremcev, N.; Vukelic, D.; Debevec, M. (2019). A systematic literature
review of poka-yoke and novel approach to theoretical aspects, Strojniski vestnik – Journal of
Mechanical Engineering, Vol. 65, No. 7-8, 454-467, doi:10.5545/sv-jme.2019.6056
[5] Haider, A.; Mirza, J. (2015). An implementation of lean scheduling in a job shop environment,
Advances in Production Engineering & Management, Vol. 10, No. 1, 5-17, doi:10.14743/
apem2015.1.188
468
Jordan, Berlec, Rihar, Kusar: Simulation of Cost Driven Value Stream Mapping
[6] Kuhlang, P.; Edtmayr, T.; Sihn, W. (2011). Methodical approach to increase productivity and
reduce lead time in assembly and production-logistic processes, CIRP Journal of Manufacturing
Science and Technology, Vol. 4, No. 1, 24-32, doi:10.1016/j.cirpj.2011.02.001
[7] Gunduz, M.; Naser, A. F. (2017). Cost based value stream mapping as a sustainable construction
tool for underground pipeline construction projects, Sustainability, Vol. 9, No. 12, Paper 2184, 20
pages, doi:10.3390/su9122184
[8] Kumar, S.; Dhingra, A. K.; Singh. B. (2018). Cost reduction by value stream mapping using Lean-
Kaizen concept: a case study, International Journal of Productivity and Quality Management, Vol.
24, No. 1, 12-32, doi:10.1504/IJPQM.2018.091166
[9] Carmignani, G. (2017). Scrap value stream mapping (S-VSM): a new approach to improve the
supply scrap management process, International Journal of Production Research, Vol. 55, No. 12,
3559-3576, doi:10.1080/00207543.2017.1308574
[10] Onofrejova, D.; Janekova, J.; Grincova, A.; Soltysova, Z. (2020). Simulation and evaluation of
production factors in manufacturing of fireplaces, International Journal of Simulation Modelling,
Vol. 19, No. 1, 77-88, doi:10.2507/IJSIMM19-1-504
[11] Urban, W. (2019). TOC implementation in a medium-scale manufacturing system with diverse
product rooting, Production & Manufacturing Research, Vol. 7, No. 1, 178-194, doi:10.1080/
21693277.2019.1616002
[12] Koblasa, F.; Šírová, E.; Králíková, R. (2019). The use of process thinking in the industrial practice
– Preliminary survey, Technical Gazette, Vol. 26, No. 3, 786-792, doi:10.17559/TV-
20150617135306
[13] Zhou, B.-H.; Liu, Y.-W.; Yu, J.-D.; Tao, D. (2018). Optimization of buffer allocation in unreliable
production lines based on availability evaluation, Optimal Control Applications and Methods, Vol.
39, No. 1, 204-219, doi:10.1002/oca.2341
[14] Yang, S. L.; Xu, Z. G.; Wang, J. Y. (2019). Modelling and production configuration optimization
for an assembly shop, International Journal of Simulation Modelling, Vol. 18, No. 2, 366-377,
doi:10.2507/IJSIMM18(2)CO10
[15] Prester, J.; Buchmeister, B.; Palčič, I. (2018). Effects of advanced manufacturing technologies on
manufacturing company performance, Strojniski vestnik – Journal of Mechanical Engineering,
Vol. 64, No. 12, 763-771, doi:10.5545/sv-jme.2018.5476
[16] Ivanisevic, A.; Katic, I.; Buchmeister, B.; Leber, M. (2016). Business plan feedback for cost
effective business processes, Advances in Production Engineering & Management, Vol. 11, No. 3,
173-182, doi:10.14743/apem2016.3.218
[17] Stremcev, N.; Stevanov, B.; Lazarevic, M.; Mandic, J.; Tesic, Z.; Kuzmanovic, B. (2019).
Improving process of quotation creation through value stream mapping and simulation,
International Journal of Simulation Modelling, Vol. 18, No. 4, 563-573, doi:10.2507/
IJSIMM18(4)484
[18] Gracanin, D.; Buchmeister, B.; Lalic, B. (2013). Using cost-time profile for value stream
optimization, Proceedings of the 24th DAAAM International Symposium on Intelligent
Manufacturing and Automation, 1225-1231
[19] Jordan, E.; Kušar, J.; Rihar, L.; Berlec, T. (2019). Portfolio analysis of a Lean Six Sigma production
process, Central European Journal of Operations Research, Vol. 27, No. 3, 797-813,
doi:10.1007/s10100-019-00613-4
469