PMP Good
PMP Good
PMP Good
How Unique?
Product characteristics are progressively elaborated.
The product or service is different in some way from other product or services.
How Temporary?
It has a definite beginning and end. effort.
It is not an ongoing effort such as in operations.
It ceases when objective has been attained.
The team is disbanded upon project completion.
Example
Building a road is an example of a project. The process of building a road takes a finite amount
of time, and produces a unique product.
Operations, on the other hand, are repetitive. Generating bills every month, and broadcasting
news everyday are examples of operations.
Project management is accomplished through the use of the processes such as:
Initiating
Planning
Executng
Monitor and Controlling
Closing
Project managers or the organization can divide projects into above phases to provide better
management control with appropriate links to the ongoing operations of the performing
organization. Collectively, these phases are known as the project life cycle.
Scope
Schedule
Quality
Resources
Customer Satisfaction
Risk
These all are so intertwined that a change in one will most often cause a change in at least one of
the others
For example:
Changes to any of these legs sets off a series of activities that are needed to integrate the change
across the project.
Program management involves centrally managing and coordinating groups of related projects to
meet the objectives of the program.
In some cases Project Management is a subset of Program Management. The project manager
may report to the program manager in such cases. A portfolio consists of multiple programs.
Senior managers or senior management teams typically take on the responsibility of portfolio
management for an organization.
Portfolio management encompasses managing the collections of programs and projects in the
portfolio. This includes weighing the value of each project, or potential project, against the
portfolio's strategic objectives.
Portfolio management also concerns monitoring active projects for adherence to objectives,
balancing the portfolio among the other investments of the organization, and assuring the
efficient use of resources.
Each Knowledge area has certain processes. There are a total of 47 processes in PMBOK 5. Each
process has following three important parts.
Inputs
Tools & Techniques
Outputs
The PMBOK covers each of the 10 knowledge areas and 47 processes with their inputs, outputs,
and tools & techniques.
These are:
Initiating
Planning
Executing
Monitoring and Controlling
Closing
Each process is part of one of these five project phases. It is important to know the process group
for each of the 47 processes.
Here is a list of sample questions which would help you to understand the pattern of questions on
Project Integration Management being asked in PMP Certification Exams.
(1) A planning method, which provides details of the work to accomplish, but also provide some
preliminary description of the work to be done in later phases is called :
1. Expert Judgment
2. Rolling wave
3. Strategic
4. Operational
Answer:B
Hint:In Rolling wave, high level plan is made and detailed plans are made for activities just a
little before they have to be executed.
(2) What is the term used for the area that entails processes and activities that define, combine,
unify and coordinate the processes and project activities carried out within the various Project
Management Process Groups?
Answer: A
(3) When Integration is used under Project Management, it includes all of the following activities
except for.
1. Unification
2. Consolidation
3. Communication
4. Review
Answer: D
Answer:C
(5) During the planning development process, at times it is necessary to make certain
assumptions to enhance the project plan when the data is not available. In regard to making those
assumptions, which one of the following is most true for project planning purposes?
Answer:A
(6) A project planning methodology is any structured approach used to guide the project team
during development of the project plan. What is an example of this methodology?
Answer: A
(7) Ahmar, a project manager in a construction company has been authorized to apply the
organizational resources to project activities. The authorization comes in the form of.
(8) The process of defining, preparing and organizing all subsidiary plans along with integrating
them into the comprehensive project plan is known as.
Answer: B
(9) The project closing process is essential to overall project planning. What is considered one of
the most important steps in closing the project?
Answer: D
Hint: All the requirements must be fulfilled before the closing process
1. Tasks.
2. Milestones
3. Deliverables
4. Life cycles
Answer: C
Hint: Some deliverables are produced as outputs from processes performed to complete project
work.
(11) Abdullah, a project engineer is working on an IT project that requires him to direct the
project activities and initiate the approved changes in the project work. He is executing which
activity of the Project Integration Management Process.
Answer: C
(12) A project manager in a construction company identified the project activities that were not
giving output as per the performance goals outlined in the project management plan. The finding
is the result of:
Answer: A
(13) Murli, a project manager in a Telecom Company got all the project related information
listed and improvised in the Organizational Process Assets (OPA) along with its communication
across the organization. The process undertaken by him is known as:
Answer: C
(14) Rahim, a project manager on a Distribution and Logistic Project is devising a cost estimate
for a contingency plan. He will resort to integration of the following except for:
Answer: D
1. Cost Management
2. Time Management
3. Performance of Corporate Social Responsibility
4. Scope Management
Answer: C
(16) For the developing a project charter of an IT project, the project manager utilized various
inputs for it that exclude?
Answer: D
(17) Rahim, a project manager in a manufacturing company has devised the project management
plan for a project on construction of company premises. The project management plan that will
guide project execution and control has been developed on the basis of the following inputs but.
1. Project Charter
2. Work Performance Information
3. Outputs from other processes
4. Enterprise Environmental Factors
Answer: B
(18) A project manager is directing and managing a project. While doing that, he is utilizing
some tools and techniques. The tools and techniques guiding him do not include.
Answer: A
Hint: Change Control Tools are used in Perform Integrated Change Control process
(19) While directing and managing a project, the activities undertaken by the project manager
got the following output that excludes.
Answer: B
(20) Monitor and Control Project Work is a process that utilizes various inputs for detecting and
correcting the shortcomings in any of the areas to ensure achievement of the goals of the project.
Which of the following inputs is used for the process?
1. Agreements
2. Approved Change Requests
3. Validated Changes
4. Accepted Deliverables
Answer: C
Hint: See Monitor and Control Project Work inputs, Page 65, PMBOK 5