Unit IG2: Risk Assessment
Unit IG2: Risk Assessment
Unit IG2: Risk Assessment
Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
The current project of this company is a construction of 4 floor shopping complex and I have
General description of the organisation
chosen the whole area of their current project for the risk assessment.
The usual works such as concrete works, flooring works, plumbing, electrical, excavation works,
loading and unloading works, welding, cutting, drilling and painting works are the works takes
place in the construction site. The different equipment’s used for different works are cranes,
conveyors, forklifts for moving the materials from one place to other.
The various machines used in this construction site are concrete mixers, jack hammer, driller,
welding and cutting machine.
There is only single day shift work for the workers and the shift timing starts from 9AM to 5PM and
Based on the information from ILO guidelines like ILO C167, ILO R 175, I referred to some
HSE’s Approved Code of Practice or Guidance documents https://www.ilo.org
www.hse.gov.uk , www.iso.org , https://labour.gov.in/labour-law-reforms . My Nebosh text
book added a great lot to my research on the same. helped me to decide additional control
measures
Hazard Who might be harmed What are you already doing? What further controls/actions Timescales Responsible
category and and how? are required? for further person’s job
hazard actions to be title
completed
(within …)
1.Work When equipment and Operators are made available 1) Machine guards should 1 month Construction
equipment and machines are not who are qualified. be provided to coordinator
machinery guarded concentrate cutters.
and poorly maintained, The workers who us equipment
Workers using operators and workers and machinery are 2) To ensure that the
concrete cutter are at a higher risk of provided with training and equipment and machinery
in the work site getting injured. awareness. are functioning properly, 4weeks site engineer
without proper From minor scrapes , third party inspection and
safety guard cut lacerations and A watchful eye is applied to maintenance must be done.
even amputation, machine and equipment
workers may suffer activities through supervision. 3) In order to ensure safe
injuries ranging from operation of the equipment, 1 month project
minor to severe provision for on a regular engineer
basis must be introduced
3.Movement of People working around All the papers in the vehicle 1) Enforce a system to 1 month project
people and the moving vehicles. surveyed and verified in every week construct separate manager
vehicle Visitors who are on the pedestrian way
site. Workers and other Provide work permit for vehicles to
construction site employers on site. do work Schedule time limit for 2) Provide appropriate crossing
vehicles and Drivers who are driving machinery to on and off + work time point where people and traffic 4weeks construction
pedestrian them. There might be a meets. estimator
move in same chance of people The company provided signal
single path so getting hit and run over person to each and every heavy 3) There are uneven surfaces
workers by the moving vehicles vehicles around site it must be levelled
around the site and and made firm to ensure 1 month General
also during careless Driver must provide proper training smooth traffic. contractor
driving carrying
overload. It will results 4) Make sure there is proper
in serious injuries and lighting every people and 4weeks Project
even result in traffic is working together. Assistant
fatality. There also the
risk of toxic fumes 5) Provide separate workspace
generated from the for the workers away from the 3weeks site engineer
vehicles which will traffic so that they might not
cause affect each other.
pollution and also
respiratory disorders 6) The vehicles must maintained
and serviced properly. 1 month Project
Manager
7) Drivers must be briefed about
7.Fire All the workers will No smoking boards provided 1) install automatic smock 1 month senior
affect detector with fire extinguisher manager
Absence of fire Proper training and awareness in the garage
fighting class conducted about fire hazard
equipment in workers smoke near 2) Introduce permit system for 4weeks project in
the storage area the storage area were Risk assessment carried out hot works charge
flammable materials
stored minor cigarette Emergency evacuation and monthly 3) appoint fire watcher in the 3weeks project in
spark lead major fire mock drills conducted regularly work site charge
explosion in the
storage area 4) establish a low against 4weeks Construction
Fire can cause tissue smoking Inside the work site senior
burn , death of workers manager
total destruction of the 5) create smock room with
company Burn injuries exhaust ventilation ,100meter 3weeks project
can affect muscles, away from the garage engineer
bones, nerves, and
blood vessels. The 6) apply fines against workers 1 month construction
respiratory system can smocking in the work site expediter
be damaged, with
possible airway 7) conduct awareness class 4weeks chief
obstruction, respiratory danger inside passive construction
failure and respiratory smocking officer
arrest. 3weeks
8) increase security near storage site manager
area to prevent the entry
8.Electricity Workers using electric Daily tool box meeting conducted 1) Install MCB in the work site 1 month project
tools main power lines manager
Use of damaged to work will affect about electrical hazards
electrical Accidental contact with Proper protective clothing such as 2) Provide and enforce use of
Equipment live parts (of wire and rubber gloves , boots , helmets industrial type sockets and 4weeeks construction
such as socket) can result in provided plug tops (to prevent estimator
welding , cutting electrical shock overloading)
and drilling incident. Overloading First aid box and first eider
machinery to sockets can provided 3weeks General
complete shut result in electric fires. If 3) Replacement of old sockets contractor
down work a worker receives an and un insulated wires of
electric shock, he will electrical appliances/tools
be suffering from 1 month Project
intense pain, severe 4) Install permit system for Assistant
burns, also electrical works
damage of
equipment‟s will 4weeks site engineer
5) provide regular maintenance
and of all machinery
3weeks Project
6) after every work shift all Manager
equipment‟s must kept in a
dry closed storage area
10.MENTAL All workers including No action taken 1) Create and maintain 1 month Contract
ILL HEALTH managers will affect dedicated, quiet spaces for Administrator
Continuous work and relaxation activities.
The absence of work pressure lead to
sufficient breaks employee mentally sick 2) Give employees opportunities
and weekend this will increase the to participate in decisions 4weeks Contract
holiday loose of concentration about issues that affect job Manager
while working this will stress.
increase the mistakes
and cause of major 3) Provide free or subsidized 3weeks Project
industrial accident lifestyle coaching, self- manager
management programs.
Specific legal arguments The organization needs to satisfy the particular prerequisites of the ILO show Guarding of
Machinery Convention C199. Article 6 plainly expresses that the utilization of apparatus any
perilous piece of which, including the mark of activity, is without proper gatekeepers will be
precluded by public laws or guidelines or forestalled by other similarly powerful measures.
Hardware will be so protected as to guarantee that public guidelines and norms of word related
security and cleanliness are not encroached. Furthermore, ILO Recommendation R118 Guarding of
Specific legal arguments The ILO‟s convention C1720 recommendation R177 requires “The protection of workers from the
top of height its an exposure to hazardous has always been a major concern for ILO. Hazard which
may the virtue of mental and physically health of people. And also property damaged The ILO code
practices “recording and notification of occupational health and diseases”. These codes of conduct
keep for safe system. ILO‟s convention C155 and Recommendation R164 which states that
machines and equipment are safe for the system that works. At the moment ARCADIS is in
contravention of the ILO Convention and Recommendations as well as the country specific
legislation by conducting work in the roof edges without guard rail so the company may face
enforcement actions from the federal agency
Consideration of likelihood AND severity The likelihood of working at height during construction is very high since there is a lot of work at
height involved. Painting, electrical work, and various construction activities may be carried out on
types of injury or ill health the roofs and scaffolds by 30 workers as part of their daily 4 to 6 hours work routine. Workers are
number of workers at risk working continuously for a long period, No fall protection device has been provided and rooftop
how often the activity is carried edges are not protected, therefore the likelihood of occurrence increases.
out
The risk affect in the roof edges and in the ground area
how widespread the risk is
Severity categorizes as
• Very low: no injury or damage occurred
• Low: injury requiring first aid and/ or sight damage caused to plant/equipment/buildings
• High: injury requiring hospital treatment/ stay and/ or significant damage caused to plant/
equipment or buildings
• Very high: death and /or irreparable damage to plant / equipment / building
The severity level of the Hazard is set very high It is possible to die if one falls from six feet to the
wrong body part or surface. Those who fall from more than 30 feet have nearly no chance of
Specific legal arguments ILO convention (C170), Recommendation (R177), ILO convention C155 and Recommendation
R164 Occupational safety associated with accidents. The Management are responsible for
providing a special walk away for pedestrians and vehicles. If the company breaches any
regulations and standards they will strictly get enforcement actions and criminal prosecutions. It will
affect the reputation and may lead closure to the company , At the moment ARCADIS India Ltd
using same path way for workers and vehicles it is a contravention of the ILO Convention and
Recommendations as well as the country specific legislation so the company may face enforcement
actions from federal agency’s for violating the laws
Consideration of likelihood AND severity The likelihood of getting accidents in between vehicles and pedestrians are high. Heavy vehicles
such as excavators, bulldozers and 75 workers work in the ground area on weekly 3to 4 days in
types of injury or ill health morning shift continuous 6 hours of work lead to lose of concentration to both drivers and vehicles
number of workers at risk so the probability of collision Is very high
how often the activity is carried
The risk affect in the vehicle rout ways
How you will follow up on the risk I will set schedule reminder in my PC for 10 days before each activity must be finished, and
assessment to check that the actions examine with each responsible person all works for finishing before cut-off times. I will follow up
have been carried out each activity and make vital guidelines to concerned capable individual in the work. I will periodicall
look at any postponement of target time, If I found any issue in regards to delaying of work, I will
see it out the explanation for the delay, for example, delay due to financial, assets and labour.
Then, at that point, I settle those issues by communicating with concerned individual in charge to
fulfil time constraints. If I discover any activity that is extremely delayed, I will report to Associate
Project Manager.