PMT 10306
PMT 10306
PMT 10306
Note: The source of the technical material in this volume is the Professional
Engineering Development Program (PEDP) of Engineering Services.
Warning: The material contained in this document was developed for Saudi
Aramco and is intended for the exclusive use of Saudi Aramco’s employees.
Any material contained in this document which is not already in the public
domain may not be copied, reproduced, sold, given, or disclosed to third
parties, or otherwise used in whole, or in part, without the written permission
of the Vice President, Engineering Services, Saudi Aramco.
Contents Pages
INTRODUCTION................................................................................................................ 1
Project Closeout........................................................................................................ 1
Project Acceptance.................................................................................................... 1
Service Date and ERC Date....................................................................................... 1
Contract Closeout ..................................................................................................... 2
Financial Closeout ..................................................................................................... 2
SP Account Set Up and Closing ................................................................................ 2
SP Account Set Up and Closing ................................................................................ 3
Other Closeout Considerations .................................................................................. 4
FINAL PROJECT COST REPORT...................................................................................... 5
Content of the Final Cost Report ............................................................................... 5
Documents to be Included ......................................................................................... 5
Engineering Details ................................................................................................... 6
Out-of-Kingdom Engineering .................................................................................... 6
In-Kingdom Engineering ........................................................................................... 6
Material Details ......................................................................................................... 6
Construction Details.................................................................................................. 7
GLOSSARY......................................................................................................................... 8
INTRODUCTION
This module introduces the Participant to the closeout process, which is used at Saudi Aramco to
ensure that all known costs are included in the final cost of capital projects. This module also
introduces the Participant to the preparation of the final project cost report, which is used at
Saudi Aramco to gather and preserve historical cost information. To accomplish these objectives,
we will discuss the applicable Company methods, procedures and guidelines.
Project Closeout
When a capital project is deemed mechanically complete, the SAPMT begins the closeout
activities. When closeout starts, many of the members of the project management team have been
moved to other projects. It has been determined that few uncompleted physical tasks remain for
the contractor to finish. The remaining activities constitute the collection of outstanding costs,
setting up a special project (SP) account, and the closing all accounts in the financial master.
Project Acceptance
After mechanical completion, an acceptance committee prepares a Mechanical Completion
Certificate (MCC). The MCC signifies that the project is ready for commissioning and startup.
Commissioning is the process of testing each portion of the facility to ensure that safety tolerances
are met, equipment operates according to vendor warranties, and all operating manuals and
operator training is completed. Startup is the process of placing the facility or process in operation
and producing the product at the rate that is specified in the design basis scoping paper.
After approval of the mechanical completion certificate, no other charges are initiated against the
budget item or job order except costs that are associated with commissioning and startup
activities.
A partial mechanical completion certificate may be submitted for a portion of a facility that can be
treated as a separate entity. That condition usually arises when management desires an early
onstream date for one or more processes in a facility.
Startup and commissioning activities are followed by an operating shakedown period to
demonstrate the project's performance. Once the project meets performance specifications, a
Performance Acceptance Certificate is issued. The performance acceptance certificate signifies
that the project is accepted by the operating proponent for commercial operation, even though
minor exceptions items may be outstanding.
Service Date and ERC Date
The service date on the mechanical completion certificate indicates when the facility is ready for
startup. For financial accounting purposes, the service date is the date when plant depreciation
starts.
The ER Completion (ERC) date is coincidental with the date that the performance acceptance
certificate is signed. Both the mechanical completion certificate and the performance acceptance
certificate dates are construction milestones and are not directly related to project financial close-
out.
Contract Closeout
While closely integrated with the project financial closeout activities, contract closeout efforts are
viewed independently. The SAPMT cost engineer works closely with the Contracting Department
and the representative whom the department has assigned to the project. From a contracting point
of view, a contract is closed out as soon as possible after the obligations of the parties to the
contract have been fulfilled. The contract closeout procedure is designed to release Saudi Aramco
from further obligations wherever possible and to ensure against further payments under the
contract.
There are two alternative methods of closing out a contract. The first method uses the Final
Release Agreement. The second method uses the Contract Closeout Document with a final
release agreement. All documents are initiated and signed by the contract proponent and signed by
the contractor.
Financial Closeout
To initiate financial closeout, the mechanical completion certificate must be approved and
submitted to the Fixed Assets and Work-in-Progress Accounting Department (FA&WIPAD). The
performance acceptance certificate does not need to be approved prior to starting the financial
closeout activities. Financial closeout should not be unreasonably delayed for projects that are
essentially complete and against which all major elements of cost have been recorded.
Accordingly, FA&WIPAD may open a special project account for financial closeout or
outstanding change orders and contract payments that can be reasonably estimated.
If the estimated cost of completion does not exceed five percent of the approved ER funds, a
special project account may be established. The estimated remaining costs are charged to a job
order within the ER and credited to the special project account. The estimated costs are identified
on the Special Project Account - Cost Estimate form, which provides separate columns for the
major cost elements of engineering, materials and construction. The SAPMT may subdivide these
columns into cost categories and provide cost estimates accordingly. Similarly, when the SAPMT
requires specific entry codes and phases to be charged, the SAPMT must indicate these
requirements in the provided columns. Figure 1 shows the Special Project Account - Cost
Estimate form.
The Special Project Account - Cost Estimate form is transmitted to FA&WIPAD with a cover
letter from the SAPMT that includes:
• The estimated completion date of the activity that is covered by the special project
account.
• A brief comment that explains the need for a special project account. Examples would
be: a late charge, surplus material problem, or exception item construction work.
• An identification of any work that will be performed by the project proponent and
charged to the special project account.
• Upon receipt of the special project account - cost estimate and cover letter,
FA&WIPAD reviews the request and ensures that:
• All major project facilities are mechanically complete, with approved mechanical
completion certificate(s) on file.
• The intent of the special project is not to build a major facility or to perform work
outside the approved project scope.
• The special project account - cost estimate does not exceed five percent of the
approved ER amount, and this estimate incudes any previously opened special project
accounts for the same ER.
SAPMTs are responsible for monitoring and controlling their special project accounts until
formally closed by FA&WIPAD. The SAPMT must write an extension letter to FA&WIPAD to
explain any need to extend the completion date of the special project account.
SAPMTs must ensure that all outstanding material commitments are resolved as early as possible
prior to financial closeout. With DC material, early consideration is given to the declaration of
surplus material, transfers to other jobs and transfers to reclamation. With SAMS material, early
attention is directed to the cancellation of open material allocations, returns to stock, transfers to
other jobs, and transfers to reclamation. All SCECO connection fees must be recorded or an
estimated cost that is included for each JO prior to closure.
The final project cost report provides an historical record of the actual cost of a project. related
schedule, contract, and other project planning and control information. The information that is
taken from the report is used to update various data bases that are used for cost estimating and
schedule forecasting purposes. The information is also used to revise associated procedures and
methods that could assist project management in maintaining better project controls.
A final project cost report is prepared by the SAPMT for those projects that have an ER value
that exceeds $20 million. An abbreviated final project cost report is optional for projects of less
than $20 million.
Assistance to the SAPMT is available from the Project Controls Division, Project Support &
Controls Department. The Project Controls Division maintains copies of the budget brief, AFEs,
change orders, all monthly project status reports, the various cost estimates, and the project
completion schedules. These documents are the source of much of the information that is required
to complete the final project cost report.
Upon completion of the project proposal engineering effort, the first section of the final project
cost report is submitted. The first section of the final project cost report is intended to collect and
report data on expenditures that were incurred under type code 68 funding. Submission of the
first section of the final cost report also provides initial information several years earlier than
would be provided if only a final report is submitted at project completion.
The final project cost report is submitted within three months of the final Monthly Project Update
report. The information that is contained in the interim report, if prepared, does not need to be
repeated.
A copy of the final project cost report is kept by the project department, and the original report is
sent to the Project Controls Division of Project Support & Controls Department.
The format of the final project cost report is found in Saudi Aramco Engineering Procedure
(SAEP) 23, which is shown in the Addendum.
Documents to be Included
As a minimum, the final project cost report should include the following:
• A copy of the final Project Planning Update Report (PPU), Monthly Project
Update Report (MPU), Project Completion Schedule (PCS), Proposal
Engineering Statistics Report (PES) and/or Design Engineering Statistics
(DES), and the final UI04 microfiche.
Engineering Details
Engineering is divided between project proposal and detail design. The purpose of separately
collecting information on project proposal engineering is to permit the submission of a partial cost
report.
Out-of-Kingdom Engineering
Expenses that are incurred by the SAPMT, out-of-Kingdom, will include average yearly cost per
man. Also shown are such miscellaneous costs as office rental and business trip expenses. In
addition to cost information, the number of man-hours per activity is required.
Contractor engineering requires the separation of drawings from other activities with the man-
hours and total dollars for each drawing. Also, the average man-hours per drawing is to be
provided. Schedule dates for award and completion of both proposal and design are to be
provided.
In-Kingdom Engineering
In-Kingdom engineering details are the same as for out-of-Kingdom engineering details, except
that information on soil and laboratory testing, vehicle usage and surveying is added.
Material Details
Major items of direct charge material, by phase number, are to be furnished with the purchase
order number, description, purchase order value, LDF cost, and total cost.
Construction Details
The SAPMT man-hours and total dollars are to be provided. Also, the same information is
required for supporting organizations such as the in-Kingdom program management contractor
activity. Inspection, pre-commissioning, and startup activities are to be reflected in both man-
hours and total dollars. The special project account funding (TC67) is to be shown as a total.
GLOSSARY
Exception Item A minor amount of mechanical work that remains near the
completion of a capital project. The exception item does
not affect startup or commissioning of the project.
Special Project Funds that are set up for the completion of the final 5% or
less of a project and in an amount not exceeding $5
Account million. Special project funds are also known at type code
67 (TC-67).
Surplus Material Direct charge material that was purchased but not required
for a capital project. This material must be declared as
surplus to the project, and it must be transferred to the
surplus material yard for partial credit.