Iosh Osha Interveiw Session11
Iosh Osha Interveiw Session11
Iosh Osha Interveiw Session11
Hazard:
Anything which has potential to cause harm (Injury, ill health etc).
Mechanical Hazards
Non-Mechanical Hazards
Chemical hazards
Physical Hazards
Biological Hazards
Electrical Hazards
Ergonomic Hazards
Radiation Hazards
Pollution hazards
Welfare:
Provision of basic facilities such as drinking water, washing toilet facilities.
Health:
Absence of diseases is known as health.
Risk:
The product of the Likelihood of a hazard resulting in an adverse event, times the severity of the
event.
1
Why we manage health and safety?
It is moral, legal duty of employer to provide health and safety to workers. If employer did not
provide safety to workers then financially company will be in loss and face value, reputation of
company will be down.
Safety signs:
Incident:
Any unplanned unwanted event that may or may not result in personal injury or property
damage.
Accident:
Any unplanned unwanted event that result in personal injury or property damage. For example
spillage of toxic acid in workplace and worker got their skin damaged.
Near misses:
Any unplanned unwanted event that had potential to cause harm but did not in fact. For example
fall of object from height on the ground where a already a task is being done.
Injury:
Injury, also known as physical trauma, is damage to the body caused by an external force.
2
Major LTI
Minor LTI
Risk Assessment:
3
Is the level of risk acceptable or does it needs to be reduced?
Risk = likelihood × severity
Likelihood Severity
4
5
Tool box talk (TBT):
The safety talk conducted just before starting of work is known as TBT. It is basically on site
refresher training. TBT has two types.
Mass TBT
Local TBT
6
Lock out tag out (LOTO)
Lock out, tag out is a safety procedure used in industry ensure that dangerous machines are
properly shut off and not able to be started up again prior to the completion of maintenance or
repair work.
Safety Categories:
Design Safety
Process Safety
Project Safety
General Safety
Level of Safety:
Plant Safety
Worker Safety
Consumer Safety
Turn Around (TRA):
A scheduled and periodic shutdown (total or partial) of a plant. They stop daily plant operations
completely during the duration of turnaround maintenance work and instead the focus shifts to
maintenance related activities, cleaning, inspection, repair, and replace.
7
Shutdown Names:
Turn Around(TRA)
Annual Maintenance
General Maintenance
Shutdown
Shutdown Phase (Activities):
Pre-Shutdown
Shutdown
Post-Shutdown
HSE Plan
Risk-Assessments
8
Cold Cutting:
Cutting of any material by using high pressure water.
Hydro-jetting Gun (1200-1300 Bar) 20000 Psi=1300 bar
Sand grit blasting:
The process of removing rust dust, dirt, scales and old prints from the old surface using
Compressed air is called sand blasting.
9
Painting:
The process after sand blasting is called painting.
Hydro-Testing:
Hydro testing is a way of checking the integrity of pressure vessels such as natural gas pipelines,
gas cylinders, boilers, storage tanks as well as fuel tanks. With the help of this test, pressure,
tightness, strength and any leakages are checked.
N2 Pressure Testing:
It is leak test for gas pipelines.
-For Liquid (use water with same procedure) it is called hydro testing
Method Statement:
Purging:
To exit a gas from System.
First inlet is known as kick line.
Firstly nitrogen purging and then passes steam flushing or fresh air.
All the gases remove from system and ignited by flare system.
It is pre shutdown activity.
Standard heights flare system 120 ft.
10
Spading/ De Spading:
It is Mechanical Isolation in which use blind plate for block two pipeline flange then apply
LOTO (Lock Out Tag out)
11
Noise:
Measure by: Audiometer
Wind Speed:
Measure By: Anemo-Meter
Unit:Knot
Atmospheric Pressure:
Measure by: Baro Meter
Vibration Types:
Hand Arm Vibration
Whole Body Vibration
6mm/sec
H2S safety
World’s Dangerous Gases:
Co2(carbon Mono-oxide)
H2S (Hydrogen Sulphide)
NH3 (Ammonia
H2S names:
Flammable Gas
Toxic Gas
Killer Gas
Silent Killer
Swamp Gas
H2S Concentration:
0.13 PPM it smell like rotten egg
Around 100 PPM it kill sense of smell
12
100 PPM as IDLH (Immediate dangerous to Life and health)
500-700 PPM man become Unconsciousness
1000 PPM death on the Spot
Density Of H2S:
H2S molecular weight: 34 gm /mole
Air Molecule weight: 29.32 gm./mole
Carbon monoxide molecular weight: 28 g/mol
Ammonia molecular weight: 17 g/mol
It is heavier than air due to this we give more priority to H2S than other gases.
It is found in Basement, pits, culvert, confined space, vessels, pipelines, tunnels, columns, heat
exchanger, reactors.
Solubility:
H2S+H2O=H2SO4
Don’t give water in case of H2S victim because it forms concentrated sulphuric acid.
Flammability:
H2S+Oxygen to form sulpher dioxide->SO2
13
Flammability Zone:
Zone 0 = Continuously Flammable e.g distillation column, boiler, furnance
Exposure Limit:
The allowable amount amount of hazardous substance at workplace is known as exposure limit.
Types of Emergency:
Plant
Personal
In both type of Emergency follow same Procedure.
Emergency procedure:
Stop the Work
Manage your equipment
See the wind direction(wind sock)
-Up wind=coming Air side
-Downwind=out Air side
use your emergency escape hood
Go perpendicular to the wind direction towards near Assembly Point
14
Assembly Point names:
Assembly Point
Safe Point
Master Point
Marching Point
Natural Disaster
Accident
Mock-Drill
Incident, nearmiss
Consecutive day do not work
work condition change
15
16
Fire safety
Fire is a chemical reaction in which fuel and oxygen combine in presence of ignition source.
Fire triangle:
Classification of Fire
Class A= which burns Solid material such as -Wood, Paper, Clothes, Rubber
Class B= which burns Flammable Liquid such as -Oil, Grease, Paint, Petroleum.
Class C= which burns Flammable Gases such as -Acetylene, Ethane, Methane.
Class D= which burns Combustible Metal such as -Sodium, Magnesium, Potassium
Class F= Kitchen/Vegetable Fats
17
PASS:
Apply PASS for operating fire extinguisher.
RACE:
R= Rescue
A= Alarm
C= Confine
18
E= Extinguish
Fire-Fighting Equipment:
Fire-Alarm
Sprinkler System
Water/Fire Hydrant
Emergency Light
Hose Reels
Fire-Extinguisher
Fire Truck
Fire-Fighting Arrangement:
Emergency/Exit Doors
Evacuation Plan
Fire Blanket
Fire-fighting Team
Fire-Marshal
Assembly Area
Emergency Contact Numbers
19
Confine Space
Any Enclosed place which is not designed for long term human occupancy in which
ventilation and access egress may be difficult.
2- Oxygen Enriched
20
Greater than 23% can be fire
3- Toxic Material
Carbon Monoxide
Hydrogen Sulfide
Welding fumes
Corrosives
4- Combustible
Methane
Hydrogen
Acetylene
5- Electricity
Electrical Sources
6- Mechanical Hazards
Rotating/reciprocating parts
7- Sharp Objects
8- Entanglement
9- Drawing-In
10- Engulfment
11- Suffocation
21
Control measures:
Barricade the area
22
Use intrinsically safe electrical equipment not more than 24 volt
Maintain minimum lighting lux level inside confined space
Ensuring that worker working inside confined space is with proper PPES.
Maintain oxygen level from 19.5 % to 23.5 % by volume
Isolate in feed and out feed points of confined space
Do mechanical, electrical, and elastic potential energy isolation inside confined space.
Do nitrogen purging and steam flushing for removing toxic gases.
Make proper acess egress of confined space
Maintain life line communication with entrant
One time pull = Are you ok
Two time pull = your time is completed come out
Three time pull = There is emergency
Provide standby man
Provide induced draft and forced draft fan for proper ventilation.
Hole watcher has two more names such standby man attendant.
23
One time pull = Are you ok
Two time pull = your time is completed come out
Three time pull = There is emergency
Check confined space entry permit
Maintain log sheet
In case of emergency call SCBA resuer.
Crane lifting
Types of Crane:
Mobile Crane
Tower Crane
Crawler Crane (In Desert)
Over Head Crane
Jib Crane
Boom Truck Crane
Gantry Crane (At Port)
Luffing Crane (Multi-Boom)
24
Types Of Lifting:
Light Lifting (Below 10 Ton)
Heavy Lifting (More than 10 Ton)
Critical Lifting
Tandem Lifting/Head to tail Lifting
Critical Lifting:
Any Lift in which the load exceed the 85% of the crane capacity is known as Critical Lifting
Tandem Lifting:
Any lift in which two or more than two crane use to lift the same object at the same time
25
Types Of Riggers:
LMI/Tripping Device
Control measures:
Barricade the area
Put safety signs
Provide TBT before starting of work
26
Make proper risk assessment and JSA (job safety analysis)
Take valid crane lifting permit.
Don’t come under suspended load.
Don’t exceed SWL of crane.
Level the ground by soil compaction
Crane do not be overloaded
Sufficient clearance from obstruction and overhead when operating
Proper inspection and maintenance of crane
Use certified riggers
Crane should be third party certified
Implement LOP ( lifting operating plane), load angle chart, SLI ( safe load indicator)
LMI( Load moment indicator)
Isolate all type of power sources apply LOTO
Maintain minimum lighting LUX level
Don’t work in swear weather condition
Don’t work if Wind speed is 32 km/hr
Control swing hazard by load tag line
27
Crane should not be maneuvered with extended boom
Suspended load should not be left unattended
Excavation
Any man made cut trench or cavity formed by earth removal is known as excavation.
Manual excavation
Mechanical excavation
Trench:
28
Hazards of Excavation
1-Fall of Person
2-Fall of Object
5. Dust
6-Improper Communication
10-Poor Lighting
11-Poor Ventilation
12-Toxic Gases
14-Snake
15-Flooding
16-Cave-in
29
18-Fire & Explosion
20-Hazardous material
22 Noise , vibration
23 Flooding
30
Don’t work near adjacent structure
Do not contact with overhead services
Make proper access egress
Identify buried cables by metal cable detector
Use cargo lift or rope bag jin wheel system for shifting of material
31
Use benching sloping shoring for supporting sides of excavtion.
32
Ladder:
Ladder angle with wall 75 degree
Step Ladder
Single ladder
Extension Ladder
Ladder setup
Stairs
A-Type Ladder
Rope Ladder
Scaffolding
The temporary platform which is built for working at height is known as scaffolding.
Many types of scaffolds are available; each job requires a specific type of scaffolds.
Independent
Towers
Birdcages
Slung Scaffolds
Cantilever Scaffolds
33
Parts of scaffolding:
standard
Ledger
Transom
Bracing
Guard rails
Toe board
Base plate
Sole plate
34
Height of scaffolding:
Not more than 4 times of base area
Scaffolding tags:
The tag we put on scaffolding after inspection is known as scaffolding tags.
Yellow Tag: Can be use with 100% fall protection (is incomplete or cannot be completed)
Safety harness:
The belt we use to avoid fall from height is known as safety harness.
35
36
37
Fall Arrestive system:
Safety harness + life line is known as fall arrestive system.
Work at height
Any work which is 4 ft above or 4 ft below the ground is known as work at height. Them we
have take work at height permit (OSHA).
Control measures:
Barricade the area
Put safety signs
Provide TBT before starting of work
Make proper risk assessment and JSA (job safety analysis)
Take valid work at height permit.
Level the ground by soil compaction
Install Guard-rail toe board on scaffolding
Fall Arrest System, Housekeeping,
Electrical Isolation apply LOTO,
use insulated PPE’s and tools
38
Personal Lift (MEWP)(Ladder)(Cherry Picker)
Cargo Lift-Rope Bar-Gin Wheel System
Don’t Work at height if wind speed is 20 Knot
Maintain Minimum Lux Level
Don’t Exceed SWL of scaffolding
Do not work in swear weather condition.
Use radio walkie talkie for proper communication.
Make proper access and egress
Negative Pressure
Positive Pressure
Types of BA
Emergency escape set (4 names)
Saver Set
PP15( personal protective For 15 min)
EEBD=Emergency Escape Breathing Device
Emergency Escape Hood
-Fiber Glass
-Having 315 bar pressure
39
40
BA Trolley /BA Airline Trolley
-2 cylinders
One Weight Empty Cylinder=4.75KG
Gas Stored=2 KG
Cylinder With Gas=6.75KG
1800 Liter Gas Volume compressed in Cylinder
-207 bar pressure
Total Time=45 min
Working time= 33 minutes
Escape time= 12 minutes
2 gauges (Hi-Cylinder Pressure & Low- Breathing Pressure)
2 whistle (High-207 bar -Low-55 bar) Use by BA technician
60 Meter Hose Reel
3 KG of Equipment
2 KG of Compressed Air
4.75KG of empty Cylinder
41
Breaking Time= 33 min for working time 12 min for leave the Area
Donning:
Process of putting up SCBA is known as donning.
Doffing:
Process of putting of SCBA is known as doffing.
42
SCUBA (Self-Contained Under-water Breathing Apparatus)
43
44
45