GXY PCM1 - Schedule Draft Update DD210830 (CP) Rev 0
GXY PCM1 - Schedule Draft Update DD210830 (CP) Rev 0
GXY PCM1 - Schedule Draft Update DD210830 (CP) Rev 0
Galaxy Sal de Vida Package 1 EPC Act Aug21 476 13-Jul-21 A 19-Dec-22
Actual Level of Effort Remaining Work Critical Remaining Work Page 1 of 3 TASK filter: Critical.
Actual Work Sub Critial Milestone © Oracle Corporation
Sal de Vida Lithium Brine Project
Package 1 Procurement & Constrution Schedule
(Critical Path)
Activity ID Activity Name Remaining Start Finish Indicators2021 2022 2023
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
A6220 SVWP20_07, Electrical Panel Installation 1 06-Dec-21 06-Dec-21
Well SVWP20_06 19 29-Nov-21 17-Dec-21
Construction 19 29-Nov-21 17-Dec-21
A2000 SVWP20_06, Earthworks 7 29-Nov-21 05-Dec-21
A2020 SVWP20_06, Well Pump Mounting 5 06-Dec-21 10-Dec-21
A2030 SVWP20_06, Precast Elements Mounting 5 06-Dec-21 10-Dec-21
A2050 SVWP20_06, Diesel Generator & Storage Mounting 3 11-Dec-21 13-Dec-21
A2060 SVWP20_06, Electrical Equipment Mounting & Wiring 5 13-Dec-21 17-Dec-21
A5970 SVWP20_06 Valve Installation on Well Head 1 12-Dec-21 13-Dec-21
A6080 SVWP20_06, Early SU 0 17-Dec-21
A6230 SVWP20_06, Electrical Panel Installation 1 13-Dec-21 13-Dec-21
Main Brine Duct & Interconnections 32 15-Nov-21 16-Dec-21
Construction 32 15-Nov-21 16-Dec-21
A2930 HDPE Pipe Laydown from Booster Station to Halite Ponds (5.000 Mts.) 24 15-Nov-21 08-Dec-21
A2940 Hydraulic Tests (HDPE) 15 28-Nov-21 13-Dec-21
A5890 SVWP20_08 to HDPE Main Pipeline PEX Pipe Laydown and Installation 2 08-Dec-21 09-Dec-21
A5900 SVWP20_07 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 10-Dec-21 11-Dec-21
A5910 SVWP20_06 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 11-Dec-21 12-Dec-21
A5920 SVWP20_08 to HDPE Pipe Tie In Installation 1 13-Dec-21 14-Dec-21
A5930 SVWP20_07 to HDPE Pipe Tie In Installation 1 14-Dec-21 15-Dec-21
A5940 SVWP20_06 to HDPE Pipe Tie In Installation 1 15-Dec-21 16-Dec-21
A6620 SVWP20_05 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 12-Dec-21 13-Dec-21
Actual Level of Effort Remaining Work Critical Remaining Work Page 2 of 3 TASK filter: Critical.
Actual Work Sub Critial Milestone © Oracle Corporation
Sal de Vida Lithium Brine Project
Package 1 Procurement & Constrution Schedule
(Critical Path)
Activity ID Activity Name Remaining Start Finish Indicators2021 2022 2023
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
A4320 PCK2.M001-1 - Thickener, Fabrication & Delivery 221 23-Nov-21 01-Jul-22
A4420 PCK2.M002 - Centrifuge, Quotations Reception 19 13-Aug-21 A 17-Sep-21
A4430 PCK2.M002 - Centrifuge, Bid Analysis & Po Placement 30 18-Sep-21 17-Oct-21
A4440 PCK2.M002 - Centrifuge, Fabrication & Delivery 346 18-Oct-21 28-Sep-22
A4450 PCK2.M001 - Conveyor, Request for Quotation (PWP & Issuance) 12 20-Aug-21 A 10-Sep-21
A4460 PCK2.M001 - Conveyor, Quotations Reception 21 11-Sep-21 01-Oct-21
A4470 PCK2.M001 - Conveyor, Bid Analysis & Po Placement 52 02-Oct-21 22-Nov-21
A4480 PCK2.M001 - Conveyor, Fabrication & Delivery 279 23-Nov-21 28-Aug-22
A4530 PCK2.M001-8 - Slaking Lime Package, Request for Quotation (PWP & Issuance) 12 13-Aug-21 A 10-Sep-21
A4540 PCK2.M001-8 - Slaking Lime Package, Quotations Reception 21 11-Sep-21 01-Oct-21
A4550 PCK2.M001-8 - Slaking Lime Package, Bid Analysis & Po Placement 52 02-Oct-21 22-Nov-21
A4560 PCK2.M001-8 - Slaking Lime Package, Fabrication & Delivery 154 23-Nov-21 25-Apr-22
Subcontracts 185 04-Aug-21 A 02-Mar-22
A4042 PCK2.W001 - EPC Contractor, Quotations Reception 25 04-Aug-21 A 23-Sep-21
A4044 PCK2.W001 - EPC Contractor, Bid Analysis & Po Placement 70 24-Sep-21 02-Dec-21
A4047 PCK2.W001 - EPC Contractor, Mobillisation 30 01-Feb-22 02-Mar-22
Liming 110 28-Mar-22 15-Jul-22
Construction 110 28-Mar-22 15-Jul-22
A5080 Early Liming, Equipment Mounting 45 27-Apr-22 10-Jun-22
A5240 Early Liming, Pumps Installation 15 01-Jun-22 15-Jun-22
A6680 Early Liming, Pipe Installation (Lime Plant to Muriate Buffer Pond) 15 16-Jun-22 30-Jun-22
A6681 Early Liming, Precomm / Com / Start Up 15 01-Jul-22 15-Jul-22
A6701 Early Liming, Precast Elements Mounting 30 28-Mar-22 26-Apr-22
Process Plant 291 03-Mar-22 19-Dec-22
Construction 291 03-Mar-22 19-Dec-22
A5095 Event Pond, Earthworks & Liner Installation 10 03-Mar-22 12-Mar-22
A5100 Process Plant, Earthworks 15 13-Mar-22 27-Mar-22
A5110 Process Plant, Precast Elements Mounting 120 28-Mar-22 25-Jul-22
A5120 Process Plant, Equipment Mounting 180 13-May-22 08-Nov-22
A5125 Process Plant, Steel Structures & Buildings Assembly 180 12-Jun-22 08-Dec-22
A5130 Process Plant, Racks Mounting 150 27-Apr-22 23-Sep-22
A5140 Process Plant, Piping Mounting & Interconnections 180 02-Jun-22 28-Nov-22
A5150 Process Plant, Electrical Trays Mounting 150 27-May-22 23-Oct-22
A5160 Process Plant, Instrumentation Trays Mounting 150 27-May-22 23-Oct-22
A5170 Process Plant, Electrical Equipment Mounting & Wiring 120 26-Jul-22 22-Nov-22
A5180 Process Plant, Instrumenation Mounting & Wiring 120 29-Jul-22 25-Nov-22
A5190 Process Plant, Hydraulic Tests 90 10-Sep-22 08-Dec-22
A5200 Process Plant, Instrumentation Calibration & Tests 90 07-Sep-22 05-Dec-22
A5210 Process Plant, Precommissioning 30 09-Nov-22 08-Dec-22
A5220 Process Plant, Commissioning 30 19-Nov-22 19-Dec-22
Actual Level of Effort Remaining Work Critical Remaining Work Page 3 of 3 TASK filter: Critical.
Actual Work Sub Critial Milestone © Oracle Corporation