NTDCL SYSTEM CONSTRAINTS 01-Mar-11 31-Dec-23 23-Feb-16 A 01-Dec-25 42.81% 7.11% -701
NTDC LAND ACQUISITION 01-Aug-19 14-Aug-21 16-Jan-18 A 17-Apr-22 89.89% 43.92% -218
DISCO'S SYSTEM CONSTRAINTS 02-May-11 31-Jan-22 02-May-11 A 26-Oct-25 82.01% 64.53% -1212
Islamabad Electric Supply Company Limited 15-Mar-18 02-Sep-21 15-Mar-18 A 30-Nov-21 65.63% 40.87% -78
Faisalabad Electric Supply Company Limited 01-Apr-19 30-Jun-21 01-Apr-19 A 29-Sep-21 92.05% 64.53% -81
Gujranwala Electric Supply Company Limited 01-Jul-11 31-Jan-22 01-Oct-11 A 26-Oct-25 93.82% 68.62% -1212
Multan Electric Supply Company Limited 29-Jan-16 15-Apr-21 29-Jan-16 A 09-Jun-22 79.76% 73.66% -373
Hyderabad Electric Supply Company Limited 01-Feb-18 31-Dec-21 01-Feb-18 A 02-Dec-22 94.93% 14.71% -298
Sukkur Electric Supply Company Limited 01-Dec-15 15-Dec-18 01-Dec-15 A 06-Oct-21 100% 75.2% -1025
132KV TL RATODERO TO LODRA-LARKANA TL (6.7-KM) 30-Sep-16 15-Jun-17 30-Sep-16 A 18-Jun-21 100% 69.2% -1463 R.O.W. DISTCT MNGMNT TO INVOLVE
132KV SDT GUDDU TPS-DAHARKI-LIBERTY TL (65 KM) 30-Sep-16 05-Apr-18 30-Sep-16 A 06-Oct-21 100% 72.94% -1279 TOWER MTRL & ROW
132KV SDT SHIKARPUR(LODRA)-SUKKUR ARAIN TL (43-KM) 01-Dec-15 01-Mar-18 01-Dec-15 A 06-May-21 100% 79.95% -1161 R.O.W ISSUE AT DIFF LOCATIONS
132KV SUKKUR SITE-ARAIN ROAD TL (15 KM) 01-Jan-18 15-Dec-18 01-Jan-18 A 07-Sep-21 100% 82.76% -996 R.O.W BY SML INDSTRY & LANDLORDS
Quetta Electric Supply Company Limited 01-Feb-16 31-Oct-21 01-Feb-16 A 02-Jun-22 74.99% 44.43% -214
National Transmission & Dispatch Company Ltd. 02-May-11 07-Feb-21 02-May-11 A 01-Apr-22 95.28% 14% -418
OWN RESOURCES DISCOS PROJECTS 01-Jul-11 20-Oct-23 01-Jul-11 A 09-Apr-23 74.15% 31.53% 194
OTHER FUNDED PROJECTS (2015-2018) 07-Apr-14 01-May-22 07-Apr-14 A 02-Apr-24 59.38% 5.8% -501