This equipment must never be operated without reading this manual and the safety instructions.
Safe Operating Temperature is between 40°F – 105°F (4°C - 41°C) Operating Temperature
To maintain the lift and user safety, the responsibility of the owner is to read and follow these
instructions: Follow all installation and operation instructions. Make sure installation conforms
to all applicable Local, State, and Federal Codes, Rules, and Regulations; such as State and
Federal Regulations and Electrical Codes. Inspect the lift for proper operation and function.
Read and follow the safety instructions. Keep Instructions readily available for equipment
operators. Make certain all equipment operators are properly trained, understand how to safely
and correctly operate the unit, and are properly trained. Allow unit operation only with all parts
in place and operating safely. Carefully inspect the unit on a regular basis and perform all
maintenance as required. Service and maintain the unit only with authorized or approved
replacement parts. Keep all instructions permanently with the unit and all decals on the unit
clean and visible. Lift is Designed for Indoor Installation Only.
Table of contents
Page Description
3 Warning Paragraph
3 Important Information
3 Shipping Damage Claim
3 Hazard Descriptions
4 Warranty
5—6 Operator Training and Safe Practices
7 Safety Instructions
8 Safety Requirements
8 Safety Sticker Identification
9 Warning Labels
10 Lockout Procedure
11 Wire Rope Inspection
12 Concrete Foundation Specifications and Requirements
12 – 14 Expansion Anchors
13 Post Tension Concrete
15—16 Troubleshooting
16 Monthly Maintenance
16 Service Calls
17 Pre-Installation Procedure
17 Bay Size Requirements
17 Overall Dimensions
18 Installation Tools Required
18 Shipment Items
19—29 Installation Procedure
30 Post installation Procedure
31-32 Parts Diagram and Specifications
2
Warning Paragraph
The operation manual should be kept near the equipment at all times.
Please be sure to make sure that ALL USERS read this manual before use and operation.
Please read carefully the entire contents of this manual prior to installation and operation.
By proceeding you agree that you fully understand and comprehend the full contents of this manual.
Failure to operate this equipment as directed may cause injury or death.
The manufacturer is not responsible for any damages or injury caused by improper use or neglect.
Important Information:
Read this manual thoroughly before installing, operating, or maintaining this lift.
This lift is designed for indoor use only, and should not be installed in a pit or uneven surface.
The floor on which the lift is to be installed must be 4-¼” inch minimum thickness concrete,
with a minimum compressive strength of 3000 psi, and reinforced with steel bar.
(Contact your building architect for information before installing on pre-stress concrete.)
The lifts have specific electrical requirements as described in the Installation Instructions section of this manual.
This lift has a minimum ceiling height requirement as described in the Installation Instructions section of this manual.
Failure by the owner to provide the recommended shelter, mounting surface, electrical supply, and ceiling height
could result in unsatisfactory lift performance, property damage, or personal injury.
HAZARD DESCRIPTIONS
Identify the hazard levels used in this manual with the following definitions and signal words:
Immediate hazards which will result in severe liability or exposure to personal injury or death.
Hazards or unsafe practices which could result in severe personal injury or death.
Hazards or unsafe practices which may result in personal injury, product or property damage.
Use alertness and prudence in a hazardous situation; care; wariness.
3
Warranty
Keep a record of your lift here. Record the lift and power unit information.
This information is required when calling for parts or warranty issues.
Model # _____________________
Lift Serial # _____________________
Date of Mfg. _____________________
Power Unit Model # _____________________
Power Unit Date Of Mfg. _____________________
Power Unit Serial # _____________________
4
Operator Training and Safe Practices
Precautions and Safety should always be followed when Installing and Operating this lift.
READ AND UNDERSTAND ALL SAFETY INSTRUCTIONS
AND DECALS INCLUDED ON AND WITH THE LIFT.
READ AND FOLLOW ALL SAFETY WARNING PROCEDURES
IN THIS MANUAL BEFORE OPERATING LIFT.
· ONLY TRAINED and AUTHORIZED PERSONNEL should operate the lift. Do not allow
customers or unauthorized personnel to operate the lift or remain in the lift area.
· Review regularly the safety rules and guidelines with personnel. All non-trained personnel
should be kept away from work area. Never let non-trained personnel come in contact with,
or operate lift.
· Understand the vehicle lift operating controls before use.
· Do not leave the operational controls while the lift is still in motion.
· Do not stand in front of the vehicle or in the bay when vehicle is being loaded or driven into
position.
· Do not attempt to work on the vehicle or go near vehicle when lift is being raised or
lowered.
· Be aware. Watch what you are doing. Use common sense.
· Stay clear of lift when raising or lowering vehicle.
· Clear the area if vehicle is in danger of falling
· Keep hands and feet clear. Remove hands and feet from any moving parts. Keep feet clear of
lift when lowering to avoid bodily harm or any pinch points.
· Do not raise or lower the vehicle unless tools, materials and people are clear. Clean up
grease and oil spills immediately. When the lift is being lowered, make sure everyone is
standing at least six feet away. Be sure there are no jacks, tools, equipment, left under the lift
before lowering. Always lower the vehicle down when
· Inspect for damaged parts. Do not use lift if any components are broken or damaged. Check
all moving parts for any type of damage that may affect misalignment or operation of lift.
· INSPECT THE LIFT DAILY. Do not operate if potential problems have been identified or lift
malfunctions. Do not operate if lift has damaged or broken components. Never walk or work
under the lift unless all safety locks are completely engaged. A daily inspection of the lift
should be completed prior to its any use. Safety mechanisms, operating controls, lifting arms,
ramps and any other critical parts should be inspected prior to using the lift.
· ALWAYS KNOW YOUR LOAD LIMIT. Use caution so that you do not overload the lift. It is
important that you know the load limit. To check the rated capacity, decals are located on
one of the lift columns or contact the manufacturer. The hydraulic system on this lift is not de-
signed to be a load holding device. Mechanical safety locks must be engaged before proceed-
ing under the lift, with vehicle servicing, or system maintenance. Never override operating
controls. This is unsafe and will void the warranty, before driving a vehicle between the col-
umns, position all arms to insure unobstructed entry. Do not hit or run over arms as this could
damage the lift and/or vehicle.
· Always make sure you have proper overhead clearance
5
Operator Training and Safe Practices
IMPORTANT INFORMATION:
· USE LIFT CORRECTLY. Use lift in the proper manner. Never use lifting adapters other than what
is approved by the manufacturer.
After positioning the vehicle on the lift runways, set the emergency brake, make sure the
ignition is off, the doors are closed, overhead obstructions are cleared
· Use all 4 arms to raise a vehicle or make sure vehicle is positioned correctly so all four corners
of vehicle are stationary with wheel stops. Position all lift pads to contact vehicle man-
ufacturers’ recommended lifting points. Raise lift slowly until all pads contact the vehicle.
Check all pads for complete and secure contact with the vehicle. Check all arm restraints to
insure they are engaged properly. Check that the vehicle is stable on the lift. Only after
confirming these procedures, raise the lift to desired working height.
· Some vehicle maintenance and repair activities may cause the vehicle to shift. Follow the man-
ufacturer’s guidelines when performing these operations. The use of jack stands or alter-
nate lift points may be required when completing some repairs. Special care must be used
when lifting light duty trucks. Optional truck adapters may be required for each man-
ufacturer’s recommended lifting points. Always use these lifting points. Running boards and
other installed accessories may also require optional adapters. Insure vehicle is balanced when
lifting light duty trucks failure to do so can cause injury and/or death.
· Removal or installation of heavier parts can change the vehicle's center of gravity on the lift
resulting in a critical load shift. The vehicle may then be unstable. Plan ahead for this
possibility to insure continued safety and refer to the vehicle manufacturers’ service manual for
recommended procedures.
· Always keep the lift area free of obstructions and debris.
· Never raise a vehicle with passengers inside. Before lowering a vehicle, check the lift and lift
area and remove all obstructions. Before removing vehicle from the lift or lift area, position
arms to the drive through position and confirm an unobstructed exit.
· Use of jack stands or other load supporting devices will help in preventing load shifts. Man-
ufacturer recommends that jack stand or other load supporting devices are used at all times
for additional security.
· Make sure the vehicles center of gravity is always safe before raising vehicle. Any points of
contact on vehicle that are not in good contact with lifting pads or contact with lift should
always be double checked. Always make sure the vehicle is secure before lifting using vehicle
manufacturers’ recommended lifting points.
· Do not rock the vehicle while on working on or around lift.
· Do not remove any heavy component from vehicle that may cause excessive weight shift.
· Verify that all safety latches are engaged and lowered on to the safety ladders before any
attempt is made to work on or near vehicle.
· NEVER override self-operating lift controls.
· NEVER remove any safety related components parts from the lift. Does not use the lift if any
safety related components parts are damaged or missing.
· Pay attention when walking under a vehicle that is raised on the vehicle lift.
6
Safety Instructions:
1. Do not raise a vehicle on the lift until the installation is completed as described in this manual.
2. Technicians should be trained to use and care for the lift by familiarizing themselves with the publications
listed above. The lift should never be operated by an untrained person.
3. Always position the lifting arms, ramps , adapters and accessories properly out of the way before pulling the
vehicle into or out of the bay. Failure to do so could damage the vehicle and/or the lift.
4. Positioning the vehicle is very important. Only trained technicians should position the vehicle on the lift.
Never allow anyone to stand in the path of the vehicle as it is being positioned.
5. Position the lifting arms, ramps , adapters and accessories to the vehicle manufacturer’s recommended
pickup points. Raise the lift until contact is made with the vehicle. Make sure that the lifting arms, ramps ,
adapters and accessories have been properly engaged the vehicle before raising the lift to a working height.
6. Do not overload the lift. The capacity of the lift is shown on the cover of this document and on the lift’s
serial number tag.
7. Keep everyone clear of the lift when the lift is in operation, the locking mechanism is disengaged, or the
vehicle is in danger of
falling.
8. Never override the mechanical workings or components of lift.
9. Unauthorized personnel should never be in the shop area when the lift is in use.
10. Inspect the lift daily. The lift should never be operated if components are damaged or malfunctioning. Only
qualified technicians should service the lift. Replace damaged components with manufacturer’s certified parts.
11. Keep the area around the lift clean and free of debris.
12. Use additional lifting equipment or stands when removing or installing heavy vehicle components.
13. Avoid rocking of the vehicle when it is on the lift.
14. Large vehicles, such as limousines, RV’s, and long wheelbase vehicles, may not be suitable for lifting on this
equipment.
15. Warning reduce the risk of personal injury, keep hair, loose clothing, fingers, and all body parts away from
moving parts.
16. Warning reduce the risk of electric shock, do not use the lift when wet. The lift should not be exposed to
the rain.
17. Warning reduce the risk of fire, do not operate equipment in the close proximity of open containers
containing
flammable liquids (example: Gasoline, flammable solvents).
18. Use the lift only as described in this manual. use only manufacturer’s recommended attachments.
19. Anyone who will be in the vicinity of the lift when it is in use should familiarize themselves with following
Caution, Warning, and Safety related decals supplied with this lift and replace them if the are illegible or
missing:
20. Anyone who will be in the vicinity of the lift when it is in use should read and refer to publications supplied
with this lift:
21. The troubleshooting and maintenance procedures described in this manual can be done by the lift’s own-
er/employer. Any other procedure should only be performed by trained lift service personnel. These restrict-
ed procedures include, but are not limited to, the following: cylinder replacement, carriage and safety latch
replacement, arm replacement, overhead structure replacement.
7
Safety Requirements
DO NOT operate or repair this equipment without reading this manual. Failure to comply with these
Instructions can result in serious bodily harm and void product warranty. Make sure you have extra help or
heavy duty lifting equipment when unloading and assembling the lift. Please read the safety procedures and
operating instructions in this manual before installing or operating the equipment. Keep this manual near lift at
all times. Make sure all operators read this manual.
Manufacturer will assume no liability for loss or damage of any kind, expressed or implied resulting from
improper installation or use of this product. Do not attempt to install equipment unless you have been trained
on installation procedures. Never attempt to lift components without proper lifting tools such as forklift or
cranes. Stay clear of any moving parts that can fall and cause injury.
8
9
Lockout Procedure
Purpose
This procedure establishes the minimum requirements for the lockout of energy that could cause injury to personnel by
the operation of lifts in need of repair or being serviced. All employees shall comply with this procedure.
Responsibility
The responsibility for assuring that this procedure is followed is binding upon all employees and service personnel from
outside service companies (i.e., authorized installers, contactors, etc.). All employees shall be instructed in the safety
significance of the lockout procedure by the facility owner/manager. Each new or transferred employee along with
visiting outside service personnel shall be instructed by the owner/manager (or assigned designee) in the purpose and
use of the lockout procedure.
Preparation
Employees authorized to perform lockout shall ensure that the appropriate energy isolating device (i.e., circuit breaker,
fuse, disconnect, etc.) is identified for the lift being locked out. Other such devices for other equipment may be located
in close proximity of the appropriate energy isolating device. If the identity of the device is in question, see the shop
supervisor for resolution. Assure that proper authorization is received prior to performing the lockout procedure.
Sequence of Lockout Procedure
1) Notify all affected employees that a lockout is being performed for servicing or maintenance and that the lift must be
shut down and locked out to perform the servicing or maintenance
2) Unload the subject lift (remove vehicle). Shut it down and assure the disconnect switch is “OFF” if one is provided on
the lift.
3) The authorized lockout person operates the main energy isolation device removing power to the lift being taken out
of service. Stored or residual energy (such as capacitors, springs, elevated machine members, hydraulic systems, air, or
etc.) must be dissipated or restrained by methods such as grounding, repositioning, blocking, bleeding down, etc.
If this is a lockable device, the authorized lockout person places the assigned padlock on the device to prevent its
unintentional reactivation. An appropriate tag is applied stating the person’s name, at least 3” x 6” in size, an easily
noticeably color, and states not to operate device or remove tag.
If this device is a non-lockable circuit breaker or fuse, replace circuit with a “dummy” device and tag it appropriately as
mentioned above.
4) Ensure that the equipment is disconnected from the energy sources’ by first checking that no personnel are exposed,
then verify the isolation of the equipment by operating the push button or other normal operating controls’ or by
testing to make certain the equipment will not operate. . Be sure to return any switches to the “OFF” position.
5) The equipment is now locked out and ready for the required maintenance or service.
Restoring Equipment to Service
1) Check the lift and the immediate area around the lift to ensure that nonessential items have been removed
(clear all tools, vehicles and personnel) and that the completion of all lift components are operationally intact.
2) The authorized person can now remove the lock (or dummy circuit breaker or fuse) and tag. Activate the energy
isolating device so that the lift may again be placed into operation.
Rules for Using Lockout Procedure
All employees are required to comply with the restrictions and limitations imposed upon them during the use of lockout.
The authorized employees are required to perform the lockout in accordance with this procedure. All employees, upon
observing a piece of lifting equipment which is locked out to perform servicing or maintenance shall not attempt to start,
energize, or use that machine or equipment. The Lockout Procedure should be used whenever the lift is being
repaired or serviced, waiting for repair when current operation could cause possible injury to personnel, or for any other
situation when unintentional operation could injure personnel. No attempt shall be made to operate the lift when the
energy isolating device is locked out.
10
Wire Rope Inspection
(Knowing when to replace your cables!)
These pictures will help you assess when you will need to replace wire rope.
11
Concrete Foundation Specifications and Requirements
Less than 10,000 lbs 2-Post Models 4 Inch Min. Thickness / 3,000 PSI (4000 PSI Recommended)
FOUNDATION and ANCHORING REQUIREMENTS
Before installing your new lift, check the following.
Selecting Lift Location: Always use architects building plans when available. Check layout dimension against
floor plan requirements making sure that adequate space is available.
Floor Requirements: The lift should be located on a relatively level floor of less than 3 degrees slope. If slope is
questionable, consider a survey of the site and/or the possibility of pouring a new level concrete slab. Failure
to do so could cause personal injury or death.
Ceiling Requirements: The area where the lift will be located should be free of overhead obstructions such as
heaters, building supports, electrical lines, etc…
Defective Concrete: Visually inspect the site where the lift is to be installed and check for cracked or defective
concrete. If site is in question contact a local inspection agency before installing lift.
DO NOT install on asphalt or other similar unstable surface. Columns are supported only by anchoring to
concrete floor.
Manufacturer will not be held responsible for any concrete that may not meet slope requirements and will not
be responsible for any charges relating to new concrete slabs pouring or leveling or damage.
12
POST TENSION CONCRETE
DO NOT CUT OR DRILL THROUGH A POST TENSION CABLE.
Do not disturb, bolt up, or apply load to adhesive anchors prior to the full cure of the adhesive.
Metal anchors and fasteners will corrode and may lose load-carrying capacity when installed in corrosive
environments or exposed to corrosive materials. There are many environments and materials which may cause
corrosion including ocean salt air, fire-retardants, fumes, fertilizers, preservative-treated wood, dissimilar
metals, and other corrosive elements.
Finished Diameters for Rotary and Rotary Hammer Carbide Tipped Concrete Drills per ANSI B212.15
(Locate any post tension cables before you drill)
5
3
14
Troubleshooting
The power unit does not run:
- Check electrical supply breaker or fuse.
- Check to see if limit switch is being contacted by a tall vehicle.
- Check micro-switch and connections in motor control box.
- Check voltage to the motor.
- Check micro-switch and connections on the overhead switch.
The power unit runs but does not raise the lift:
- Check the oil level.
- Check that the lowering valve is not stuck open.
- Check the connections and components on the suction side of the pump.
The power unit raises the lift empty but will not lift a vehicle.
- Make sure the vehicle is not above the rated capacity of the lift.
- Make sure the vehicle is positioned properly.
- Clean the lowering valve by running the power unit for 30 seconds while holding the lowering valve open.
- Check the motor voltage.
Lift lowers slowly down.
- Check for oil leaks.
- Clean the lowering valve by running the power unit for 30 seconds while holding the lowering valve open.
Repeat this procedure a few times.
- Clean the check valve seat .
Slow Lifting and/or oil foaming up.
- Check that oil used meets the specification in the Installation Instruction section of this manual.
- Tighten all suction line fittings.
- Not enough oil in tank and air has been transferred into the hoses and cylinder. (Complete bleed system and
replace oil.)
Anchors continually work loose
- If holes were drilled too large, relocate the lift per the Installation Instruction section of this manual.
- Floor is not sufficient to provide the necessary resistance. Remove an area of concrete and re-pour as
described in the Expansion Anchor Installation Instruction section of this manual.
Lift does not raise and lower smoothly.
- Reposition vehicle for a more even weight distribution.
- Check the four inside corners of the two columns for roughness. Any rust or burrs must be removed with
emery cloth.
- Lubricate the four corners with heavy duty bearing grease.
- Use a level to check the columns for vertical alignment both side to side and front to back. Shim the columns
as necessary per the Installation Instruction section of this manual.
- Check the oil level.
- Inspect that there is no air in the hydraulic lines. Bleed the hydraulic system as described in the Installation
Instruction section of this manual.
15
Troubleshooting
The lift will only lower completely to 1” from the floor.
-Check that the safety latches are disengaged.
- Adjust cable as needed to assure that cables have not been over tightened and check that both safety latches
are disengage.
Safety lock are out of adjustment.
- If the equalization cables are out of adjustment, the carriages are out of sync. When the lift is at full rise, one
of the safety latches may not have the clearance to disengage and allow the lift to lower. Readjust cables as
described in manual.
At full rise the safety latch will not disengage and the lift cannot be lowered.
- Check oil level.
- If the equalization cables are out of adjustment, the carriages are out of sync. When the lift is at full rise, one
of the safety latches may not have the clearance to disengage and allow the lift to lower.
-Other issues please contact a Service Representative
Power Unit will not stop running
Switch is damaged. Turn off power to the lift and replace switch.
Monthly Maintenance
Automotive vehicle lifts an important part to the operation and profitability of your business. Make sure
safety is used with this lift and other lifts in your shop is critical in preventing employee injuries and damage
to customer’s vehicles. Automotive lifts should always be used safely.
This will help increase the profitability, productivity and safety in your shop.
Lubricate the four inside corners of the columns with heavy duty bearing grease.
Lubricate all chains and cables weekly.
Check safety latch synchronization: Safety latches should click at the same time. If necessary
adjust equalizing cables as described in the Installation Instruction section of this manual.
Check tightness of all bolts.
Check expansion anchor tightness. If the anchor bolts are loose, they should be re-torque to
100ft/lbs.
Check the Hardware for tightness monthly per inspection schedules.
Replace damaged, broken or wearing parts with lift manufacturer’s OEM parts or their equiv-
alent.
While lift is lowered, check the hydraulic fluid level. If necessary, add oil as described in the
Installation Instruction section of this manual.
Service Calls
The manufacturer can provide on site service to your lift product by a qualified lift service
technician. The owner is responsible for all costs and direct payment to the contractor at the time the
work is completed. It is the owner’s responsibility to return any parts to the manufacturer for
warranty validation. Repairs should only be completed by a qualified lift technician.
16
Pre-Installation Procedures
Before beginning your installation make sure you read the installation manual and insure all instructions and
safety guidelines are fully understood. Check that all component parts are accounted for. Locate the installa-
tion area, identify the center line of the bay and mark the floor. Also mark the center of bay entrance door.
Connect these two points with a short chalk line in the area where lift will be located. Draw a second chalk line
at 90° to locate the positions of both lift columns. (Refer to lift dimensions on this page)
Keep this manual with lift at all times.
DO NO INSTALL LIFT ON ASPHALT OR ANY OTHER SURFACE THAN A CONCRETE FLOOR CONFORMING TO THE
MINIMUM REQUIREMENTS DETAILED IN THIS MANUAL. DO NOT INSTALL THIS LIFT ON CONCRETE WITH
SEAMS OR CRACKS OR DEFECT. IF YOU HAVE QUESTION AND CONCERN CONTACT YOUR ARCHITECT.
Use safety protective clothing and protective wear when installing lift.
17
Floor Plan
Fig 1
Fig 2
18
INSTALLATION PROCEDURE
STEP 1: After unloading the lift, place it near the intended in-
stallation location.
STEP 2: Remove the shipping bands and packing materials from the
lift. The power unit will be unpacked from the top. Note: Be care-ful
not to drop power unit on heavy end
STEP 3: Open the wrapping, remove the parts and parts boxes from
the packaging. Unbolt the structure from the shipping brackets. Fig 3
(Use proper lifting devices, cranes or a forklift to lift off of shipping
brackets.)
Fig 5
Fig 4
Fig 6
Fig 7
STEP 5: Install the hydraulic fittings on the Cylinders inside the columns. DO NOT remove the stop plug
from the non-power side column cylinder.
NOTE: Use Teflon Tape on Pipe fitting connect to cylinder port .(Fig. 4, 5, 6, 7)
19
Lifting Chain
Step 6: Verify that chain is connected and
secure. The Manufacturer has pre-adjusted
the chain and should not be removed. (Fig 8)
Safety Latches
Step 8: Pull safety latch cable on front of lift-
ing carriage. This will allow you to release
safety latches. There is one safety latch on
each lifting carriage. Once carriages raise
the safety release latch will flip over. This will
engage the safety lock when lowered. To
lower lift raise carriage to a point where
safety lock can be released. After the safety
release cable has been pulled the safety
Fig 8
release latch will flip over. This will allow
safety lock to glide down post with-out
engaging. (Fig 9)
Important : Always verify that Both Safety Locks are release before lowering vehicle.
Fig 9
20
Columns
STEP 9: Raise the columns and position the columns facing each
other. The outside base plates measurements are as shown for
each unit (Fig. 1, 2) for correct measurement to your lift). Square
using a chalk line and measuring from rear points on base plates
(mark your positioning within 1/16”). Minimum Concrete Strength
3,000 psi 4” thick.
STEP 11: Using a level, check column for side-to-side plumb and front-to-back plumb. If needed, use shims
provided by placing shims underneath the base plate and around the anchor bolt. This will prevent bending
the column bottom plates (Shim thickness must not exceed 3/8”). Tighten 3/4” anchor bolts to 100 ft-lbs. of
torque. (see page 14) (Fig 10)
STEP 12: Using a tape measure, measure from back corner of the base to the opposite back corner to insure
columns are square. After confirming dimensions, drill and install the anchors on the Non-Powerside Column.
(Fig 11)
Floor Plan
Fig 11
21
Equalizing Cables
STEP 14: After the columns have been securely fastened. Raise the both lifting carriages to second safety lock
position. (Double check to make sure carriage is secure before routing cable.)
STEP 15: (see Fig. #2) After raising the columns route the cables in each column cables as illustrated (Fig #?).
Route the cable from the front tie off point of the carriage, the stop connector will seat on the front
stop mount. Make sure the cable is routed up toward the pulley through the top mounting plate then
routed back down the rear of column. Route Cable through bottom sheave in direct line with upper
sheave. Remove all the cable slack by lowering the lifting carriage and pulling the cable tight. Wind
the remaining cable into the column. This will make installing the cables easier before raising
columns. IMPORTANT: make sure chain is secured and routed around pulley before lowering carriage.
(Fig. 12)
A. Connect the equalizing cables as shown in the cable diagram below on.
B. Connect top front tie off point first. Route cable to top Sheave.
C. Remove the top sheave so the cable will seat.
D. Wrap the equalizer cable over sheave and replace sheave on roll pin. The cable must be routed down the
back of the column through the top of the carriage. Route cable through lifting to bottom sheave.
E. Wrap the cable through bottom sheave. Completely pull slack out of cable.
F. Route the remaining lengths of cables around opposite column bottom sheave and up carriage to tie of
point. Secure with nut.
G. Fasten cable facing up on opposite side column rear tie off point.
H. Fasten cable end with flat washer on end of cable until. Pull cable through carriage until properly seated.
I. Repeat steps A thru H for other cable.
J. ( if your lift provides and access panel on the front of carriage replace at this time.)
Note: make sure not to cross cable over each other so cable is routed back down opposite side column.
(review Step# 12 process for detailed instructions for adjusting cables.
(Fig 12)
Step 16: Repeat Step 15 for second equalizing cable. (Fig 12)
Step 17: Adjust the carriage cable tension. This is accomplished by tightening the carriage tie off nut. The left
post carriage nut adjusts the right column carriage, and the right column carriage nut adjusts the left column
carriage. Adjust each cable to approximately 1/2” side-to-side play. Check both safety latches to insure the
carriage is still engaged in the appropriate safety latch. See step 15 for more information.
22
Fig 12
Fig 12
23
Power Unit and Hydraulic System
STEP 18: Mount the power unit on the side powerside column bracket
using the four M10 x 20mm bolts and nuts. (Fig 14)
A. Install the #6 SAE o-ring fitting on the
power port. (Fig 13)
B. Connect the power unit hose to the
power unit fitting.
C. Connect the power unit hose to the
back side of power side cylinder Fig 13
fitting.
D. Connect the long non-powerside hose to the powerside cylinder
port fitting.
E. Route the long hose between cables on the ground.
F. Connect the long hose to the non-power side fitting. Fig 14
G. Secure hose . Important: Make sure hose does not touch equalizing
cable under Base Plate.
(Fig 15 Steps 18 A—G )
Fig 15
STEP 19: Remove the vent plug from the power unit and fill the reservoir. Use a non-foaming, non-detergent
hydraulic fluid Ten Weight (ISO AW32)(Example: Pure Power!® Extreme High Performance Longlife Hydraulic
Oil ISO AW32is specifically formulated to provide superior anti-wear and rust inhibiting qualities, while
prolonging oxidation performance for extended drain intervals.). The unit will hold approximately 4 to 5 gallons
depending on tank size different amounts of fluid required. (Fig. 16)
24
STEP 20: Connect the Electrical hookup to the power unit; 220V Single Phase. It is recommended that a
220 Volt, 30 Amp twist lock plug be installed in the power line just ahead of the power unit. Use wire
capable of supporting a 30-amp circuit.
Warning: – A certified electrician must install the electrical wiring to the power
unit. Protect each circuit with time delay fuse or circuit breaker; 208v-230v
single phase 60 Hz 20 amp. Verify that wiring must comply with local code.
Fig 16
25
Base Plate
Step 21: Install base plate with 4 - M8 x 15mm Countersink Screws. (Fig 17)
Fig 17
Arms
STEP 22: The “half moon” gear restraints on each lifting
arm are already installed. Loosen Allen Screws Gear re- Fig 18
straints will need to be adjusted once installed on lifting
carriages. Position the lifting arms on the carriages using
the included securing arm pins . Check for proper engage-
ment of the arm restraints – arm lock and safety gear re-
straints should fully engage the gear on the arm. After
checking that the safety gear restraints and arm lock en-
gage properly, tighten Allen bolts on gear restraints.
(Fig 18, 19)
Fig 19
26
Step 23: Install lifting carriage arm drop pins. (Fig. 20)
Fig 20
STEP 25: Raise lift and LISTEN. You will hear the latches begin to hit and release as the lift is being raised. After
3 or 4 clicks you will hear the latches synchronizing at the same time. If the safety latches are out of synchroni-
zation you will have to re-adjust the equalizing cables . Operate lift and apply pressure to cable to insure cable
adjustment is correct. Note: Without weight the lift will lower slowly.
(Step 15)
27
Step 26: Bleed screw instructions. (Fig. 21)
For models QJY230C and QJY240B there is NOT a bleeder screw. Follow the same instructions as stated
below and the air will automatically bleed out. These models have an internal automatic bleeder valve to
regulate the air bleeding operation.
Fig 21
Fig. 22
28
Microswitch
Step 27 : If this unit includes a safety microswitch “VERIFY AND TEST OPERATION”. Verify that micro switch
is operating correctly. Operate lift and apply pressure to micro switch with a piece of non-conductive material
to push down on switch. A chance of shock could occur if wiring has not been installed incorrectly. This will
insure motor shuts off prior to any part of vehicle coming in contact with overhead crossbeam or preset
height restrictions microswitch location. When motor shuts off while pushing “ON” button the motor will stop
automatically.
Lock Out Electrical Supply Before Installing Any Electrical Components To Lift.
Fig. 39
Do not ever allow power supply to be connected when working on or repairing lift.
29
Post Installation Procedure:
Check Box
31
Parts List
32
NOTES:
_______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
33
NOTES:
_______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
34
NOTES:
_______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
35
Torin Jacks, Inc.
Ontario, CA 91761
FOR CUSTOMER SERVICE
PARA EL SERVICIO PARA EL CONSUMIDOR
1-888-44-TORIN
Made in China Hecho En China