Pro Safety By : YASIR IQBAL 1

Pro-Safety Aramco
Safety officer/Supervisor/Rigger
Topic : Lifting/Rigging Hardwares

1. What information is written on web sling?


a) Serial /ID #✔️

b) SWL✔️

c) Safety factor ✔️
d) Length ✔️
e) Width✔️
f) Rigger’s Name
g) Date of manufacturing ✔️
2. SWL stands for?
a) Sling with length
b) Safe web load
c) Safe Working Load ✔️
d) Sling Work load
3. While selecting Sling for safe lifting, We’ll confirm it’s SWL through ?
a) Sling’s Length
b) Sling’s Width
c) Only Tag ✔️
d) Lines of thread
e) Its color
4. What documents required with lifting gears for daily use?
a) Manufacturer’s Certificate(Load Proof Test)
b) Third party Certificates

Pro Safety By : YASIR IQBAL 2


c) Daily Armaco Checklist
d) All above ✔️
5. Safety factor for all rigging hardwares should be……. Minimum?
a) 6:1
b) 4:1
c) 1:5
d) 5:1✔️
6. Third party inspection should be done after every……. Months for lifting
gears?
a) 4
b) 12
c) 6✔️
d) 3
7. Which Document tells us the load test of the rigging hardwares?
a) Daily Inspection
b) Third party certificate
c) Manufacturer’s Certificate ✔️
d) Work Permit
8. Slings should be tested minimum……… Of the SWL?
a) 200%✔️
b) 100%
c) 300%
d) 50%
9. Which information should be mentioned on Tag with wire rope Sling ?.
a) Diameter
b) Serial #
a) SWL
b) All above ✔️
Pro Safety By : YASIR IQBAL 3
10. What are the different sling angles acceptable in Aramco ?
a) Maximum 90°✔️
b) Preferred 60°✔️
c) Minimum 30°✔️
d) 360°
11. What’s GI number for Lifting gears ?
a) 7.028
b) 7.030
c) 7.029✔️
d) 7.025
12. What is GI number for Lifting?
a) 7.028✔️
b) 7.030
c) 7.029
d) 7.025
13. Which lifting equipment protects(spreads force) load from crushing force? .
a) Slings
b) Spreader beam ✔️
c) Shackles
d) Tag line
14. Spreader beam’s important information ?
a) SWL
b) It’s own weight
c) Third party inspection
d) All Above ✔️
15. While lifting a load we should also include the weight of……..to the total load
?.

Pro Safety By : YASIR IQBAL 4


a) Weight of the hook/Block ✔️
b) All Lifting gears ✔️
c) Rope between hook and boom tip
d) All above
16. Which Equipment are called lifting equipments? Select all that apply.
a) Cranes ✔️
b) Boom trucks ✔️
c) Excavator
d) Loader
17. While lifting, cranes outriggers must be …….and ……?
a) 2/3 extended, on pads
b) Fully extended ,on ground
c) Fully extended, on pads ✔️
d) Fully extended, on concrete
18. While inspecting the carrier/Deck of the mobile crane, we should inspect
following things? Select all that apply.
a) Outriggers ✔️

b) Any leakage ✔️
c) Lights ✔️

d) Mirrors✔️
e) Grounding ✔️
f) Fire extinguisher✔️

g) Ladders/access to cabin✔️
h) Counter weight✔️
i) Bucket
j) Tires ✔️

Pro Safety By : YASIR IQBAL 5


19. While inspecting the boom of mobile crane, we’ll check ?

Select all that apply.

a) Rope ✔️

b) Auxiliary hook/block ✔️
c) Main hook/block ✔️
d) Seat belt
e) Safety Devices✔️
20. Which device is used to measure wind speed in crane?
a) Anti two block
b) Anemometer ✔️
c) Tension meter
d) Inclinometer
e) Load cell
21. Which device is used to measure Load on rope in crane?
a) Anti two block
b) Anemometer
c) Tension meter(Dynamo Meter)✔️
d) Inclinometer
22. Which device is used to measure Load on hook?
a) Anti two block
b) Anemometer
c) Tension meter
d) Load cell✔️
23. Which device prevents hook block to hit boom?
a) Anti two block ✔️
b) Anemometer
c) Tension meter
Pro Safety By : YASIR IQBAL 6
d) Load cell
24. Which device measures the angle of the boom.
a) Anti two block
b) Anemometer
c) Tension meter
d) Inclinometer✔️
25. Which device is used to measure the length of the boom?
a) Anto two block
b) Anemometer
c) boom length sensor ✔️
d) Tension meter
26. What should be mentioned on both hook blocks?
a) Crane name
b) Crane company
c) SWL✔️
d) Operator’s name
27. Both hooks can be used at a time (simultaneously)
a) Yes
b) No ✔️
28. Which section of the boom is 1st telescopic section of the boom?
a) Mother boom
b) Main boom
c) Section Inside(after) Mother boom.✔️
d) Head of the boom
29. Maximum safe limit of wind speed for crane/Boom Truck operation?
a) 23 kph/20 mph/ 12 ms
b) 32Kph/20 mph/9ms✔️
c) 32 Kph/ 25 mph/ 5 Ms
Pro Safety By : YASIR IQBAL 7
d) 23 kph/ 40 mph/ 15 Ms
30. Maximum safe limit of wind speed for man basket/man lift operation?
a) 15 mph/25 Kph/7ms✔️
b) 20 mph/ 32 Kph
c) 18 mph/ 35 kph
d) All above
31. SLI stands for?
a) Safe load intension
b) Safe load indicator(Screen)✔️
c) Standard load inspection
d) All above
32. All safety devices show the results on……..?
a) Operator’s screen✔️
b) Mobile phone
c) Mirrors
d) Both A and B are correct
33. Which Document helps us to know the exact boom length/angle for specific
load?
a) Crane’s insurance
b) Third party sticker
c) Load Chart✔️
d) Operator’s license
34. What should be there in operator’s cabin? Select all that apply.
a) 360° view✔️

b) Proper Housekeeping✔️
c) Seat belt✔️
d) Cigarettes
35. Which documents will prove that operator is competent? Select all that apply.
Pro Safety By : YASIR IQBAL 8
a) Saudi Government driving License. ✔️
b) Saudi Aramco license✔️
c) Indian/Pakistani License
d) Medical fitness Certificate✔️
36. Which Documents prove that crane is ready to use.
a) Third party inspection sticker✔️
b) Third party certificate✔️

c) Internal inspection sticker✔️

d) Crane’s registration✔️

e) PUC✔️
f) Insurance✔️
37. How can we know that operator can perform lift with boom attachments?
a) He needs extra license
b) It’s mentioned on the back side of the Aramco license✔️
c) Driving license
d) Normal Aramco license is enough
38. How Can we know that an operator can operate specific model of the crane?
a) Only Aramco license .
b) It must be mentioned on the back Side of the Aramco license.✔️
c) Needs government approval
d) Only Saudi driving License
39. Who can operate cranes at Saudi Aramco premises?
a) All Contractors
b) Trainees under direct supervision of a qualified trainer✔️
c) Trainees under direct supervision of an operator
d) Saudi Aramco certified operators ✔️
40. Rigger level 3 can lift maximum…… Tons?
Pro Safety By : YASIR IQBAL 9
a) 15
b) 20
c) 10.✔️
d) 12
41. Rigger level 2 can lift a load between… ..Tons.?
a) 15- 40
b) 10-40✔️
c) 20-40
d) 10- 50
42. Only Rigger level 1 Can lift loads?
a) 30 Tons
b) 40 tons and more✔️
c) 39.9 Tons
43. Which load is critical lift
a) 20 tons
b) 40 tons ✔️
c) 39.9 tons
d) 41 tons ✔️
44. Which percentage of the rated load capacity of the load chart is critical lift ?
a) 84%
b) 85%
c) 86%✔️
d) 50%
e) 85.1%✔️
45. Which is important for lifting activity?
a) Work permit✔️

b) JSA✔️

Pro Safety By : YASIR IQBAL 10


c) Barricades✔️
d) Signages✔️
e) Fire watch✔️

f) Flagman ✔️

g) Emergency response plan✔️


46. What’s the minimum safe distance of the crane from 2 meters deep B/C type
soil excavation?
a) 2
b) 4✔️
c) 3
d) 1
47. What’s the minimum safe distance of the crane from 2 meters deep Rocks/A
type soil excavation?
a) 1 meter
b) 2 meters✔️
c) 3 meters
d) 6 meters
48. Crane should stay minimum………..feet away from power line if voltage is
under 50 kV.
a) 10 ✔️
b) 15
c) 20
d) 25
49. Crane should stay minimum………..feet away from power line if voltage is
between 50 kV-200 kV?
a) 10
b) 15✔️

Pro Safety By : YASIR IQBAL 11


c) 20
d) D. 25
50. Crane should stay minimum………..feet away from power line if voltage is
between 200kV- 350 kV?
a) 10
b) 15
c) 20✔️
d) 25
51. Crane should stay minimum………..feet away from power line if voltage is
Over 350 kV?
a) 10
b) 15
c) 20
d) 25✔️
52. We must install White flashing lights on the top of the boom if it reaches……
Meters height?
a) 20
b) 40
c) 50
d) 60✔️
53. Crane’s minimum tail clearance should be…. Feet?
a) 5
b) 2 ✔️
c) 4
d) 10
54. Which height from ground level is better option to measure wind speed?
a) 20 feet
b) 30 feet

Pro Safety By : YASIR IQBAL 12


c) 50 feet✔️
d) 40 feet
55. Who can give signal to operator?
a) Foreman
b) Supervisor
c) Only Aramco Certified rigger✔️
d) Safety officer
56. Which signals are acceptable?
a) Only universal hand signals✔️
b) Any singles
c) Explain with loud voice
57. Load floating should be minimum
a) 5 seconds
b) 3 seconds✔️
c) 10 seconds
d) 8 seconds
58. What must b done before actual man basket lift?
a) An empty man basket trial lift
b) A trial lift with intended load (Without persons)✔️
59. To prevent load from swing, we should use.
a) Backhoe
b) Man lift
c) Taglines✔️
a) Push it manually
60. When load is suspended for some time, operator can…?
b) Go to toilet
c) pray
d) Not come out of the cabin✔️
Pro Safety By : YASIR IQBAL 13
e) Sleep
61. The writer of critical lifting plan is called originator.

Who can write critical Lift plan?

a) Rigger level 3
b) Rigger level 1✔️
c) Rigger level 2✔️
62. Who can finally approve a critical lifting plan?
a) Rigger level 2
b) Only rigger level 1✔️
c) Rigger level 2
d) Supervisor
63. What should be written on man basket.?
a) Third party sticker✔️

b) SWL✔️

c) Maximum number of riders✔️


d) Crane Operator’s ID
e) Empty Weight✔️

f) Manufacturing date✔️

g) ID✔️
64. What documents required to perform a man basket lifting?
a) Work permit✔️

b) Man basket permit ✔️

c) JSA/Risk Assessment ✔️
d) Method of statement ✔️

e) Critical lift plan ✔️


f) Emergency response plan ✔️
Pro Safety By : YASIR IQBAL 14
g) Excavation plan
h) Pre-lift safety meeting ✔️
i) Man basket 3rd party Certificates✔️
j) Man basket Manufacturer’s certificate ✔️
65. Who can write man basket permit?
a) Rigger level 1✔️
b) Rigger level 2✔️
c) Rigger level 3
66. Who will Finally approve man basket permit?
a) Operator
b) Aramco representative
c) Rigger level 2
d) Rigger level 1✔️
67. During man basket lifting crane’s load chart will be de reted.
a) 60%
b) 25%
c) 50%✔️
a) 80%
68. New man basket lift can’t be started if operator has been working
continuously for last…… Hours.
b) 12
c) 10 ✔️
d) 8
e) 15
69. An operator has been continuously lifting man basket, 10 hours have passed
and man basket is still in the air. How many hours more this operator can
continue this lift.?

Pro Safety By : YASIR IQBAL 15


a) 6 hours
b) 2 maximum✔️
c) 4 maximum
d) 3 maximum
70. Who must stay at site during man basket lifting?
a) Rigger level 1
b) Rigger level 2
c) Rigger level 1 or 2✔️
71. Minimum sling angle for man basket lifting ?
a) 60°
b) 30°
c) 45°✔️
d) 50°
72. Man basket’s slings can’t be used for any other lifting?
a) True✔️
b) False
73. Critical lift is that lift which needs a special document.
a) Work permit
b) JSA
c) Critical lift plan✔️
d) Method of statement
74. Which of the following is critical lifting? Select all that apply.
a) Inside 10 meters of live pipeline ✔️

b) Inside 10 meters of Traffic/populated areas.✔️

c) Inside 10 meters of railway line.✔️

d) Inside 10 meters of power lines ✔️


e) Any attachment to main boom ✔️

Pro Safety By : YASIR IQBAL 16


f) 40 tons and more ✔️
g) On Rubber/Pick and Carry lift ✔️
h) More than 85% of the load chart ✔️
i) 30 tons load
j) Presence of fire/explosion/high heat hazards ✔️
k) Attaching fly jib ✔️

l) tandem(multiple)/turning/tailing.✔️

m) Night lift ✔️
75. During tandem/turning/tailing lifts, we’ll de-rate Crane’s Capacity.
a) 85%
b) 25%✔️
c) 50%
d) D. 20%
76. During tandem/Tailing/turning lifts, We’ll use cranes of.
a) Same Model✔️

b) Same Company✔️

c) Same Size✔️
d) Same Color
77. For tandem lifting, how many critical lifting plans do we need?
a) Only one plan for all cranes
b) 2 Plans
c) Sperate plan for each crane✔️
78. We’re going to Turn the position of a load from horizontal to vertical using
two cranes. It’s….. Lift?
a) Tandem
b) Tailing
c) Turning✔️
Pro Safety By : YASIR IQBAL 17
d) Normal
79. We’re going to Turn the position of a load from vertical to horizontal using
two cranes. It’s….. Lift?
a) Tandem
b) Tailing✔️
c) Turning
d) Normal
80. We’re going to move one load using two cranes without changing it’s position.

It’s…. Lift?

a) Tailing
b) Tandem✔️
c) Turning
d) Normal
81. Which information will be written on critical lift plan?
a) SA inspection sticker /Expiry date ✔️
b) Work permit
c) Date✔️

d) Load type✔️
e) Crane Model/Type/Capacity ✔️
f) JSA
g) Counterweight ✔️

h) Lifting gears type/size/length/Capacity ✔️

i) Hook Block weight✔️

j) Boom Angle/Length/Radius ✔️

k) Hitch Arrangement ✔️
l) Rigger Level One’s age

Pro Safety By : YASIR IQBAL 18


m) Total Load✔️
n) Name of the company✔️
82. How can Rigger level 1 leave the site while critical lifting is in progress?
a) He’ll only inform Project manager
b) He’ll dedicate lift plan to Rigger 2/3 by writing their names/license
numbers and his own name/ License number on lift plan.✔️
c) He can never leave site during any critical lift
83. Fall Arrest equipment Will be approved by Saudi Aramco to use them with
man basket.
a) True✔️
b) False.
84. Upon which condition rigger level 1 handover site to rigger level 2 or 3 after
dedicating them critical lift plan?
a) After conducting initial lift He’ll supervise them for minimum 2 subsequent
lifts to verify their capabilities to make sure that they can also perform the
same critical lift under the same lift plan during his absence from site with
all same conditions(Without any changes)✔️
b) He’ll supervise them for minimum 5 consecutive lifts and make sure that
they can perform more lifts with same critical lift plan, with all same
Situations.
c) He can never leave site
d) All above
85. During which critical lift , level 1 can leave site?
a) Within 10 meters of live pipeline✔️
b) Within 10 meters of power lines
c) Man basket lift✔️
d) Tandem lift.
e) Pick and Carry lift
Pro Safety By : YASIR IQBAL 19
86. What are the main duties of rigger level 3?
a) Giving signal to operator✔️
b) Holding taglines
c) Rigging loads✔️

d) Selecting Correct hardware for specific load✔️


e) Installing barricades and signages himself
f) Daily Inspection of rigging hardware.✔️
87. During a blind lift, We need 3 persons to pass signals to the operator. Who
are these 3 persons?
a) 2 certified rigger and Supervisor
b) 1 certified rigger and 2 foreman
c) All 3 Aramco certified riggers✔️
d) 2 helpers, 1 rigger
88. Before starting a lift, we must know the exact…?
a) Weight of the load✔️

b) Weight/Capacity of the rigging hardwares/equipments✔️


c) Weight of the Operator
d) Capacity of the crane✔️
89. Select all correct names of possible Hitch arrangements.
a) Choker hitch✔️
b) Basket hitch✔️
c) Vertical/bridle hitch✔️
d) All wrong
90. According to Aramco, We don’t need any rigger with side boom if it only just
holding/carrying the load (Not lift)
a) True✔️
b) False
Pro Safety By : YASIR IQBAL 20
91. All persons present on the site allowing operator to start a lift but operator
rejects the lift, saying that it’s not safe. Who can make final decision in this
situation? The final authority?
a) Rigger level 1
b) Crane operator✔️
c) Rigger level 3
d) Foreman
e) Safety officer
92. During Which critical liftings, rigger level 1 can not leave the site?
a) Around Power lines✔️

b) Tandem/Tailing/Turning lifts✔️
c) 40 Tons or more ✔️

d) More than 85% of the rated load capacity✔️

e) On Rubber/Pick and Carry ✔️


f) Night lift
93. If crane boom contacts with live power lines what should be done by the
crane operator ?
a) He should jump out of the crane immediately and run away
b) He should swing the boom into the clear and stay in the crane without
touching its body and wait for the emergency response team.✔️
c) If it is necessary to leave the equipment, he should jump entirely clear
of the unit. Keep your feet close together and jump so that both feet hit
the ground at the same time✔️
94. Which type of work permit do we need for lifting using crane at Saudi
Aramco projects.
a) Cold work
b) Hot work✔️

Pro Safety By : YASIR IQBAL 21


c) Confined space entry
d) EOLB

Pro Safety By : YASIR IQBAL 22


Topic : Heavy Equipment
1) Backup alarm's noise should be minimum........ desibel louder than the
ambient noise of the equipment engine.
a) 20
b) 15
c) 10 ✓
d) 5
2) While reversing heavy equipment what is most important one thing?
a) Light
b) Engine noise
c) Tire pressure
d) Backup alarm ✓
3) ROPs stands for
a) Round over pressure
b) Rollover protections✓
c) Right order prevention
d) Right of path
4) What is GI # for heavy equipment operator testing and certification.
a) 7.250
b) 7.025✓
c) 7.026
d) 6.025
5) GI # for Crane and heavy equipment incident reporting and investigation.
a) 7.250
b) B. 7.025
c) C. 7.026 ✓
d) D. 6.025

Pro Safety By : YASIR IQBAL 23


6) We need to transfer a loader through a main highway. What is the best
option?
a) Drive this loader like a car
b) Load it over Lowbed trailer ✓
c) Pull it tying with another equipment
d) All above
7) Heavy equipment should stay away from stable rocks/A type soil while
passing close to an excavation minimum........ If depth is 3 meters?
a) 1 meter
b) 2 meters
c) 3 meters✓
d) 6 meters
8) What does FOPs stands for?
a) First option Pass
b) Founder of Pakistan
c) First of all park
d) Falling objects protections✓
9) Equipments(Backhoe/loader)involving in excavating/backfilling activities in
the same excavation should stay away from excavation edge .
a) 2 meters
b) Double to the depth
c) No limit✓
d) Equal to the depth
10) Which Documents show that heavy equipment is ready to use at Saudi
Aramco projects?
a) Insurance✓
b) Registration✓
c) Third party✓
Pro Safety By : YASIR IQBAL 24
d) Internal sticker✓
e) PUC
f) RFC
g) Daily Inspection checklist✓
h) Flagman's ID?
11) Which Documents show that a heavy equipment operator is competent
person ?
a) Aramco license✓

b) Saudi Government driving license ✓


c) Indian/Pakistani license
d) Saudi Aqama✓
12) How many cameras will show the perfect view to a loader operator?
a) A.2
b) B. 1
c) C. 3
d) 4✓
13) What does PWAS stands for
a) Possible warning alarm sound
b) Proximity warning alarm system✓
c) Probably warning alarm sound
d) Possibly warning alarm sound
14) What will you inspect "outside" the cabin of a Front wheel loader?
a) Tires✓
b) Hydraulic oil leakage✓
c) Diesel leakage✓

d) Pipe hoses connection/condition✓


e) Lights✓

Pro Safety By : YASIR IQBAL 25


f) Beacon light✓
g) Parts joints/pins✓
h) Seat belt
i) Cameras✓

j) PWAS sensor ✓
k) ROPs✓

l) FOPs✓

m) Backup alarm✓
n) Horn✔️
o) Access to the Operator's cabin ✓

p) Fire extinguisher ✓
15) What will you inspect "inside" the cabin of a Front wheel loader?
a) Housekeeping✓

b) Seat belt✓

c) 360° view✓

d) AC✓
e) PWAS ( speaker)✓

f) Screen (Cameras' result)✓


g) Tires
h) First Aid kit ✓
i) Fire extinguisher
16) When outriggers of a backhoe loader should be fully extended/tires
suspended.?
a) When it travels like a car
b) When it involves in excavation activity.✓

Pro Safety By : YASIR IQBAL 26


17) When equipments are resting in parking areas, their blades/Buckets should
be...........?
a) Up/High from the ground
b) Down/ On ground surface✓
18) How many persons can sit inside the cabin at a time?
a) 4
b) 2
c) 3
d) Only operator can sit.✓
19) While rock breaking using jack hammer, nearby workers and operator
should use ........ If noise is more than..........?
a) Gloves/40°
b) Ear plugs/ 85 desibels✓
c) Ear plugs/ 100 desibels
20) You want to talk to operater , what should you do?
a) Go directly near to the Operator's cabin and open the door
b) Stay at safe distance, make eye contact with operator and then go
nearer.✓
c) Go behind the machine so operator will see you in the camera.
21) Which work permit do we need for excavation using backhoe?
a) EOLB
b) Cold
c) Hot✓
d) Confined space
22) We need following persons for loader operation?
a) Fire watch✓
b) Flagman✓
c) Hole watch
Pro Safety By : YASIR IQBAL 27
d) A conductor
23) While operating heavy equipments operator can use mobile phone if.
a) He's an important call from his family
b) He's an important call from girlfriend
c) He has to check underground utilities while excavating
d) He can never use mobile phone while he's operating any machine.✓
24) While equipment is resting in parking areas, We can........... around them.
a) Take rest
b) Take lunch
c) We need to stay away.✓
d) Sleep under their shade
25) While refueling equipments, ......... should be done.?
a) Lights should be on
b) Engine should be off✓
c) Operator should be inside cabin
d) All above
26) A backhoe is going to pass under live power line. What's the minimum safe
distance for backhoe's heights part from power line? If voltage is 49 kV.
a) 6 feet✓
b) 10 feet
c) 12 feet
d) 16 feet
27) A loader is going to pass under live power line. What's the minimum safe
distance for loader's heights part from power line? If voltage is 51 kV.
a) 6 feet
b) 8 feet
c) 10feet✔️
d) 16 feet

Pro Safety By : YASIR IQBAL 28


28) A side boom is going to pass under live power line. What's the minimum safe
distance for side boom's heights part from power line? If voltage is 201 kV.
a) 6 feet
b) 10 feet✓
c) 12 feet
d) 16 feet
29) A manlift is going to pass under live power line. What's the minimum safe
distance for manlift's heights part from power line? If voltage is 499 kV.
a) 6 feet
b) 8 feet
c) 10 feet
d) 16 feet✓
30) A backhoe is going to work under/near live power line. What's the minimum
safe distance for backhoe's heights part from power line? If voltage is 49 kV.
a) 10 feet✓
b) 15feet
c) 20feet
d) 25 feet
31) A backhoe is going to work under/near live power line. What's the minimum
safe distance for backhoe's heights part from power line? If voltage is 51 kV
a) 10 feet
b) 15 feet✓
c) 20 feet
d) 25 feet
32) A backhoe is going to work under/near live power line. What's the minimum
safe distance for backhoe's heights part from power line? If voltage is 201 kV
a) 10 feet
b) 15 feet

Pro Safety By : YASIR IQBAL 29


c) 20 feet✓
d) 25 feet
33) A backhoe is going to work under/near live power line. What's the minimum
safe distance for backhoe's heights part from power line? If voltage is 351 kV
a) 10 feet
b) 15 feet
c) 20 feet
d) 25 feet✓
34) If we're using backhoe with internal work permit, we must stay away from
power lines minimum........... horizontally?
a) 15 meters ✓
b) 20 meters
c) 18 meters
d) 10 meters
35) When parking our equipments near highways for night time, we
should........?
a) Barricade the equipment ✓

b) Use reflectors/blinking lights ✓


c) Use candles
d) Just park it normally
36) Minimum distance of the goal posts from live power lines should be........?
a) 10 meters
b) 15 meters ✓
c) 20 meters
d) 18 meters
37) A loader is passing close to the excavation having 1 meter depth. What's the
minimum safe distance to be maintained?
a) 2 meters ✓
Pro Safety By : YASIR IQBAL 30
b) 3 meters
c) 1 meter
d) 1.5 meters
38) A loader is passing close to the excavation having 3 meter depth. What's the
minimum safe distance to be maintained?
a) 6 meters
b) 3 meters ✓
c) 4 meter
d) 4.5 meters

Pro Safety By : YASIR IQBAL 31