MPD Libra Project: Advance Training Seccion
MPD Libra Project: Advance Training Seccion
MPD Libra Project: Advance Training Seccion
Purpose
A pre-job Tool Box Talk will be conducted with all parties involved before start of Rig
up operations. The installation of the LV 4 choke skid will be done by third party
slinging company and will be focal point for the installation. For all piping Seadrill
will be responsible for the cutting welding and certification of are hard lines. The
MPD team will be present and required to help with the installation. All personnel
involved have STOP work authority.
The sensors on the buffer manifold will be installed on the blocks u/s of valves BFM-V1
and BFM-V2
Purpose:
This procedure provides requirements and guidance for fingerprinting in both cased
hole and open hole. Fingerprinting will take place before drilling of the casing shoe
set above the phase that will use MPD technology.
The results from these tests shall be properly documented and all data recorded to
the Geobalance database. So that this information can be used for reference
throughout the MPD operations.
The Geobalance MPD system is mainly self calibrated so to maximize efficiency majority of the
fingerprinting and calibration can be done while the MPD practical training is performed.
The drilling BHA should have been tested and fully functional, the bit should be above the shoe and
the drilling fluid switched over to the expected drilling system. The PWD tool needs to be programed
to read at the lowest possible pump rate (technical) and readings every 60 seconds max.( the closest
reading the better) and the recorded that pump rate.
Mud Weight and properties have to be homogeneous in the hole and surface.
RCD is installed.
GBA sensors and panels (operator, driller and remotes) are connected and working correctly.
Instrumentation Synchronization: All pressure gauges and pit volume instrumentation shall be
calibrated and crosschecked by the respective owners, and the data presented in a tabulated format.
This table should display Drillers, Mudloggers, GBA, MWD and Cementers instrumentation for cross
referencing. This calibration shall be conducted offline or during the kick detection equipment test.
Failure to obtain the required data for later use in the well.
5. GBSetpoint Fingerprinting
8. Effect of pipe movement on flow and pressures – using different block speeds and
rotation
Purpose
Circulate with the Rigs pumps and compare Flow in vs Coriolis flow out to
calculate the efficiency of all pumps available at rig site.
Flow Path
The following flow paths are to be considered while conducting this exercise:
See Figure 1.
Calculate the Pump Efficiency and input Efficiency into Iris Insite System
Repeat the process for 100% of Drilling Rates and for the others pumps.
Return to Activities /
Flow Paths
FOR INTERNAL USE ONLY 11
2 - Choke Controllability and Upper and Lower Bumper Setting
Purpose
The controllability of the choke is a function of Flow Rates, Density, Pressure, and Trim size, for
each trim there is controllable range base on the backpressure created by the choke position. This
not a linear function optimize choke controllability Halliburton utilizes it’s real time controllability
software. This provides the operator a real time chart displaying the optimal control range for each
trim size so the operator may change trim sizes when the choke falls out of its controllable range.
While circulating at 100% drilling rate record flow rate, SBP @ buffer manifold and SPP.
Select Chokes on the Menu, and select Choke A as active choke. Ensure choke B is fully closed.
Start closing the choke manually on the HMI until SBP has increased by 10 psi
Read and record choke position into Table below as High End Bumper Set point.
Set the Lower End Bumper to Zero, set Wellhead Pressure Target to the anticipated WHP for
Connection, and bring down Rig Pumps to Zero, allowing the Choke to trap the pressure, recorded
trap pressure in the chart below.
Manually open the Choke until pressure drops by 10 psi and record Choke position to set the Low
End Bumper position.
Purpose
The aim of PID Tuning is to determine the optimal speed at the choke work at different pump rates and
Mud Properties. These calibrations should be carried out as close as possible to actual operating
conditions when steady state normal operating conditions is achieved. GBA PID setting can be derived
from the PID Excel Guidance Sheet.
Sequence
• While applying and removing back-pressure, establish the best values for P & I (Proportional &
Integral Values from the PID – Proportional, Integral and Derivative Algorithm).
• From the PID Excel Guidance Sheet, introduce the information required in order to select the
optimal PID setting and introduce the same in the HMI PID Choke configuration.
• Run rig pumps at 100% drilling rate with Choke 100% open.
• Select Choke A as the Active Choke in the HMI and set the expected drilling WHP as Manual set
point.
• Adjust manually the WHP Set point to the Connection WHP and record result in the chart below.
• Wait for steady parameters and adjust if necessary using the PID Excel Guidance Sheet
• Repeat the process for Choke B and Choke C.
Purpose
Note: Please, ensure that MWD Company and Petrobras are both happy with the readings showed
by PWD and there is no reason to doubt this. The GBA GBSetpoint RT Hydraulic Model has the
ability to self-calibrate based on PWD readings in Real Time.
Note: Since the GeoBalance model calibrates itself in Real time, this calibration will have been
completed in previous tasks and will always be calibrating as long as PWD is updating.
Note: Mud properties required to be updated in the GBSetpoint at least every 12 hr. or when there is
a new fluid in the wellbore.
There are several steps to commissioning the MPD system before start
drilling. The aim of this test is to acquire quantitative data for the dynamic
response of the controlled variable (CV, e.g. backpressure or flow through
Choke A, B, C). This information will be used for tuning the controllers in the
GBSetpoint system. These tests should be carried out as close as possible to
actual operating conditions when steady state normal operating conditions
have been achieved. The choke will move to different positions and the
dynamic responses recorded.
NOTE: all Fingerprint Tests must capture the information in a screenshot and presented
in the Final Report.
6. Driller - Line-up drilling mud flow from the auxiliary pump (booster Pump) through Riser.
Commence flow from auxiliary pump through MPD manifold.
7. MPD Operator - Begin the disabled pump at a rate higher than the flow difference in the kick
detection configuration page.
8. MPD Operator - Confirm message indicating Influx Detected to alert the driller.
9. Driller/ MPD Operator -Repeat the above steps with the ActEV software enabled.
10. MPD Operator - Confirm message indicating Influx Detected to alert the driller and that the
choke has been removed from pressure control mode and placed into position control.
11. MPD Engineer put the choke into pressure control mode and increase Surface Back-Pressure
(SBP) by 100 psi and evaluates flow In/Out and PWDCF trends.
Purpose This test is to determine the magnitude of pressures that may be 'trapped'
after stopping circulation. The results of this test may have implications for the shut-in
method to be employed and gives an indication of pressures that may be trapped
during actual well control situations.
Sequence:
1. Driller - Circulate at 50% of drilling flow rate and wait for stable flow.
2. GBSetpoint must be set to Pressure control mode
3. Driller - Turn off the pumps.
4. MPD Operator – Observe MPD Choke Response.
5. MPD Operator - Record trapped surface pressures 3 minutes after the well is
closed-in.
6. Driller/ MPD Operator - Repeat test for 80 % and 100 % Drilling Flow rate.
Purpose This drill is to familiarize the rig and MPD crews to a connection. The
connection is the most regular activity that both crews will be doing together, so they
must be familiar with each other, since the Surface Back Pressure (SBP) will be
increased while the pumps are ramped down.
Sequence:
1. Driller - Circulate at 100% of drilling flow rate and wait for stable flow.
2. GBSetpoint must be set to pressure control mode
3. Driller – Ramp down the pumps following the MPD operator instructions.
4. MPD Operator – Observe MPD Choke Response.
5. MPD Operator – Inform driller when he can ramp up the pumps.
6. Driller – Ramp up the pumps following the MPD operator instructions to 100%
drilling rate.
7. Driller/ MPD Operator - Repeat test as required.
Sequence:
1. Bring pumps online at 50% flow rate normal drilling rate.
2. Set the SPL on the C choke to 200 psi and the PRV to 250 psi.
Note: If PRV adjustable planned for the well is not available during
fingerprinting. Only work with High Limit value
Note: If finger printing is planned in open hole be aware of maximum allow
surface pressure
3. Once it is determined the High Pressure limit is working on the Geobalance system,
increase the SBP closing the choke manually until reach the high limit. Hit the high limit,
which will automatically open the SPL.
4. Set the high limit again on the SPL to 400 psi to apply back pressure using control
variable to make the PRV test.
Note: If PRV adjustable planned for the well is not available during
Fingerprinting. Only work with High Limit value
5. Once confirmed that the PRV has been activated fully open, relieve the back pressure of
MPD choke.
6. Stop the pump, test complete. Re-set the PRV if necessary.
• Driller - Post slow pump data with all rig pumps on, both drill pipe friction loss and both
C&K Line Friction Pressures (CLFP- KLFP) at 3 different flow rates (e.g. 10/20/30 spm).
• Driller - Take pressures on two gauges reading from separate sources to guard against
gauge failure. (Mud Logging and RIG)
• Note the pressure required to break circulation the first time, and record this value for
use in kick detection and circulation procedures.
• If Dynamic Well Control is planned the slow circulating tests shall include circulating
through the MPD Stack, surface lines, and MPD Choke Manifold, using the rig
pumps at 3 different flow rates (e.g. 10/20/30 spm).
Driller - Circulate at 50 % of drilling flow rate and wait for stable flow.
Driller - Turn off the pumps.
Driller - Immediately shut-in the well using SSBOP. Do not wait for the flow to stop.
Driller- Record the time in seconds from 'pumps off' until the well is closed-in.
Driller -Record trapped surface pressures in KL/CL 3 minutes after the well is closed-in.
Driller Repeat test for 80 % and 100 % Drilling Flow rate.
5. Survey Fingerprinting
With the drilling BHA on bottom make exercise to take survey using Drilling Rate and
apply SBP on the MPD choke and record any change in Stand Pipe pressure and
BHP if receiving signal from PWD.
Purpose:
This procedure describes how a connection is made when drilling and make connection using
MPD Back Pressure Pump (Booster Pump), GBSetpoint and Auto choke are used to
control/adjust the annular pressured down hole.
Auto Mode:
The GBSetpoint system adjusts the applied surface back pressure automatically based on the
calculated bottom hole pressure from the transient hydraulics model. It requires a target ECD
(Bottom hole pressure) and the control depth at which this pressure will be maintained constant.
Model uses rig’s data in real time including pump flow rate, if there is a change in rig’s pump rate,
an automatic adjustment in the surface back pressure will be produced to maintain a constant
bottom hole pressure.
In Auto Mode connection, pump rate is gradually slow until zero, MPD Back pressure pump
(Riser Booster Pump) will supply the flow rate to MPD Choke to support the Target WHP required
for maintain constant BHP. This is the way that a connection with dynamic back pressure is
carried out.
1. Clear access to the rigs standpipe manifold to bleed off the drill pipe pressure.
2. The FOSV is on the drill floor in the open position. The handle to pick it up is in place, the
key to close the valve is at hand.
3. Confirm that FOSV thread or crossover is installed to make up onto the drill pipe.
4. The MPD backpressure pump (Booster pump) is on line and aligned through GBA Choke.
5. GBA Operator double check the Target WHP in GBSetpoint to maintain constant BHP at
Control Depth while connection.
6. The Driller should not make any connections before GBA Supervisor/Operator have been
informed in advance.
7. If there is PRV with a setting point lower or equal to target WHP on connection along the
MPD returns circuit, GBA operator request to RIG to change PRV set point if necessary to
make the connection.
8. GBA Operator will confirm that correct valves alignment.
9. Status Valve Alignment Update. (See Figure 1 for MPD Drilling Alignment).
Potential Hazards
1. BHA float valves failure with top drive not connected to the string.
2. Bringing the mud pumps on and off too quickly.
3. RCD failure / leak during the connection.
4. Lack of communication between relevant parties (especially Driller and GBA Operator),
resulting in a well control issue, with asset or environmental damage
3. When ready, slow down rpm to 10-20rpm. Adjust Booster Pump to 300 gpm before starting
shutting down rig pumps. The flow from Booster pump will allow building SBP at the MPD choke.
(See Figure 2. MPD Booster connection / Flow Path).
• Driller – Will then notify to GBA Supervisor/Operator that he is ready to start decreasing mud
pumps.
• GBA Operator - will notify the driller to slowly decrease mud pumps. GBSetpoint will apply
surface back pressure to compensate for loss in equivalent circulating density pressure.
• Driller – decrease the pump speed to zero.
Note: If two pumps are being used for drilling, repeat the same procedure to reduce
the second pump to zero SPM.
• GBA Operator should monitor the response of the GBA Choke to ensure it is responding in
accordance and is holding proper target WHP for connection.
• Mud logger – To reset the stroke counter to zero, to have control of bottom up.
• GBA Operator - Once pressure stabilizes, will notify the driller to slowly increase mud pump
from reduced SPM/gpm to full drilling rate.
Note: While rig pumps are being brought online, GBA Operator to ensure the ramp down is
being followed on the MPD choke to ensure WHP is adjusting to achieve the current target
WHP.
Note: If two pumps are being used for drilling, repeat the same procedure to bring the
second pump online to full drilling rate.
• Driller - Once drilling rate is achieved the rotary can be increased according to DD instructions.
(NOTE: Wait for MWD operator instructions if survey is desired before rotate the string)
• Driller – Reduce booster pump flow rate in a controlled manner to the flow rate dictated by
GBA Supervisor.
• Driller – Confirm when mud pumps are back to original SPM.
Purpose
This procedure describes how a connection is made with trapping WHP during connections; MPD
pump (booster Pump) is not available.
Trapping Pressure:
The GBSetpoint system adjusts the applied surface back pressure automatically based on the
calculated bottom hole pressure from the transient hydraulics model. It requires a target ECD
(Bottom hole pressure) and the control depth at which this pressure will be maintained constant.
Model uses rig’s data in real time including pump flow rate, if there is a change in rig’s pump rate,
an automatic adjustment in the surface back pressure will be produced to maintain a constant
bottom hole pressure.
In a Trapping Pressure connection, pump rate is gradually reduced in previous accorded steps to
slow pump rate, Target WHP for connection will be required to be input manually and wait for the
MPD choke to achieve this Target WHP, once the WHP reading is equal to the Target WHP for
connection is equal, mud pumps are shut down to continue with the Trapping Connection Process.
This is the way that a Trapping Pressure Connection is carried out.
1. Clear access to the rigs standpipe manifold to bleed of the drill pipe pressure.
2. The FOSV is on the drill floor in the open position. The handle to pick it up is in place, the
key to close the valve is at hand.
3. The FOSV valve is the correct thread to make up onto the drill pipe.
4. GBA Operator double check the Target WHP in GBSetpoint to maintain constant BHP at
Control Depth while connection.
5. The Driller should not make any connections before GBA Supervisor/Operator have been
informed in advance.
6. If there is PRV with a setting point lower or equal to target WHP on connection along the
MPD returns circuit, GBA operator request to RIG to change PRV set point if necessary to
make the connection.
7. GBA and Driller to agree on the number of step to reduce pump rate to slow pump rate and
vice versa.
8. GBA Operator will confirm that correct valves alignment.
9. Status Valve Alignment Update. (See Figure 1 for MPD Drilling Alignment).
Potential Hazards
1. BHA float failure with top drive not connected to the string.
2. Bringing the mud pumps on and off too quickly. (Problems to adjust Target WHP).
3. RCD failure / leak during the connection.
4. Lack of communication between relevant parties, resulting in a well control issue, with asset
or environmental damage
Note: If two mud pumps are being used for drilling, the driller can reduce the first pump at a controlled
rate until shut down. Then can follow the shutdown procedure for the final pump
Note: GBSetpoint will compensate automatically the Target WHP based on pump rate. Driller should
take around 20 seconds to make the transition between steps.
• Once the target pump speed has been reached, and the Target WHP is been achieved the
GBA Operator – Communicate to Driller mud pump can be shut off. MPD Choke will close
along with pump rate reduction in Auto Mode. (See Figure 2 for MPD Trapped connection).
FOR INTERNAL USE ONLY 5
If target pressure was not trapped MPD operator will put the choke in manual mode and the driller can
slowly turn his pump on against the closed choke adding the additional SBP required with the drilling
pump.
• GBA Operator should monitor the response of the GBA Choke to ensure it is responding in
accordance and is holding proper target WHP for connection.
7. When drilling parameters are achieved, the driller is then ready to resume drilling operations.
8. Driller– Let pressures stabilize if returns match previous fingerprint (confirmed via the Coriolis
meter), go to bottom and resume drilling.
9. The Mud logger, MPD supervisor and Driller should now all continue to monitor the well to see
if connection gas has been taken.
Purpose
This procedure describes how a Dynamic Flow Check can be undertaken if required. Its use would
be for instances where volume changes are needed to be confirmed against flow rate changes.
The word dynamic here means that the flow check will be performed while some circulation is
maintained on surface.
There may be instances where a flow check is required while holding back pressure on the well. A
dynamic flow check in a closed loop is required through the MPD choke and Coriolis flow meters
returning into a slug tank (less volume, more easy to identify volume variations using other PVT
monitoring systems).
If the situation that a Dynamic Flow Check arises, the system needs to be lined up as shown on
Figure 1. The selected slug tank (#1 or #2) will be in a closed loop low volume system and use the
Level Sensor of the slug tank which is more sensitive to volume variations due to the nature of the
slug tank (it holds low volumes).
The dynamic flow check should only be conducted if deemed necessary since it will delay the
actions required to tackle the possible influx.
The main instance when a Dynamic Flow Check would be used is when a statically underbalanced
fluid is being circulated and WHP is required along with the ECD to remain overbalanced and a
situation arises where the well requires to be monitored.
1. Dynamic flow check will be performed using the rigs riser booster pump.
2. The selected slug tank must remain clean and free of cuttings to avoid any plugging of the
filter on the suction of rig pumps.
3. The rig should maintain ¾ of the slug tank filled with drilling mud all times.
4. Ensure those involved in the procedure have fully charged radios.
5. The MPD system should be lined up as per normal MPD operations with flow being received
through the GBA choke manifold and return to flow divider.
6. The Coriolis flow meter and the slug tank Level Sensor will be used to evaluate if there are
losses or gains.
7. Ensure flow is directed to selected slug tank as show in the Figure 1, Failure in divert the
total flow to slug tank may lead to false interpretation.
8. Space out the drill string to be ready to shut the well in on the SSBOP’s. If inside casing DO
NOT rotate, if in open hole continue to rotate.
Potential Hazards
1. Over flow the slug tank by drawing fluid from the suction pit and not the slug tank.
2. Mud pumps cavitation’s.
3. Gas break out at the slug tank that may have poisonous gas entrained in it.
4. Deadheading against closed valves.
5. Misinterpretation due valves leaking.
6. The dynamic flow check should only be conducted if deemed necessary since it will delay
the actions required to tackle the possible influx
The well is circulating using the rig pumps and a dynamic flow check is required, use the following
steps:
Note: It is advised that any time an influx is suspected the dynamic flow test be conducted without
flow down the drill pipe only using the riser booster pump to avoid unnecessary circulation of gas in
the annulus.
GBA Supervisor: Inform the Driller and Company Man that the well is losing fluid.
GBA Supervisor: Inform the GBA Operator to reduce the back pressure applied to the well in 25 psi
increments (up to the lower limit). Remain lined up on the Slug tank and monitor for a reduction in
losses. If high losses are observed, may be necessary to line up flow from the active system.
If losses do not decrease, ensure that Company Man knows that you are attempting to reduce
losses, and that he may need to prepare for pumping LCM.
This procedure describes how the MPD System can be used to reduce the BHP until it equalizes
with the formation pressure. The objective is to understand the real pore pressure and subsequently
use the most appropriate bottom hole pressure to continue drilling.
The DPPT can be performed with or without rotation, pumping down the drill string, using the active
system, with returns through the MPD primary flow line using GBA equipment. The WHP is reduced
in decrements to a pressure where flow out deviates from flow in. This pressure is measured by the
PWD. MPD pump (booster pump) must also be running.
To conduct this procedure the mud weight in the well should be static under balanced. In the event
that friction losses do not allow detect pore pressure, a lower flow rate could be selected, but
always starting DPPT from the overbalanced condition. This procedure could be also adapted to
control BHP only circulating on surface. In this case the PWD reading will not be available.
Note: PETROBRAS may apply this procedure to define or confirm the operational window.
Potential Hazards
1. Circulating for too long in the same depth position may cause washout.
2. The PWD may have failed prior to this stage resulting in the inability to read real time BHP.
This will require tighter control of the actual mud weight in the well.
3. Flow against closed valves.
FOR INTERNAL USE ONLY 3
Procedure Dynamic Pore Pressure Test (DPPT)
1. MPD/PMCD Supervisor/Driller: Ensure valves are lined up as per normal MPD drilling
operations. See Figure 1. Drilling MPD Flow Path.
At this time the GBSP is in pressure control.
2. Driller: Circulate well clean a minimum of 1.5 BU to remove all connection gas and cuttings from
the well. Record SPP at circulating rate.
3. Driller: Rotate at 20 rpm while circulating down the drill string using the rig mud pumps.
4. Driller: Space out at tool joint. Continue circulation at drilling rates and rotation at 20 rpm.
5. GBA Operator: With Booster Pump running, set system to SBP mode with the set point as drilling
conditions.
6. GBA Operator: Begin to decrease Target ECD in 0.20 ppg decrements. Confirm the choke is
moving accordingly.
Note: The maximum Influx size allowed during the test is 1 bbl.
Purpose:
This procedure to determine a pre-determined BHP, describes two (2)
options to perform a Formation Integrity Test (FIT):
This Dynamic FIT uses the main pump, against the well and
RCD. Suction and return is from Active system.
1. Over flow the pits by drawing fluid from the suction pit
and returning different pit.
2. Flow against closed valves.
3. Misinterpretation due valves leaking.
4. Over pressuring the formation causing losses.
5. Leak in the Rotating Head.
6. The EMW will be greater at shallower depths than at
TD. Use caution to prevent over pressuring a weak
formation and causing fracturing.
1) Driller - Reduce surface rotation to 20 rpm and circulate well clean. Record SPP
at circulating rate.
Note: Circulate a minimum of 1.5 BU to remove all connection gas and cutting
from the well.
2) Booster pump is aligned and running at 300 gpm.
3) GBA Operator - Confirm system is ready and running in Auto Mode.
4) Driller – Slowly reduce the rig pump flow rate to 0 gpm.
Note: D-FIT will be done with the drilling pump(s).
Note: If loss is detected, slowly reduce the Target ECD to last setting
recorded without loss and report WHP and ECD/BHP (loss conditions.)
13)Driller - If loss was detected, circulate at least 1 BU and monitor gas trends
and SPP behavior. Deviate to MGS if required. If losses were not detected, it
is not necessary to circulate BU. Resume drilling operation.
14)GBA Operator - Wait for parameters stabilization (SPP, BHP, Flow In = Flow
Out) and after that inform Driller to drill ahead.
2000
4000
100
6000
230
290
8000 500
600
700
10000
1200
14000
16000
18000
Purpose:
This procedure applies exclusively to well control situations on the RIG SEADRILL
when using the GeoBalance MPD System to detect and control formation fluid
influxes into the well bore.
The Driller will monitor the well at all times, USING RIG WELL CONTROL POLICY.
RIG IS RESPONSIBLE FOR WELL CONTROL AND WELL MONITORING AT
ALL TIMES. The MPD system provides enhanced well control event detection, and
allows rapid and accurate control of BHP, but does not replace standard RIG or
Petrobras well control procedures.
Any variations to the established trend should be investigated and resolved at the
very earliest occurrence before any situation is allowed to escalate.
Once detected and stabilized, the circulation of the kick could be done
conventionally through Rig Conventional Well Control System, if the influx is
bigger than 2 bbl. or dynamically through MPD system, if the influx is less
than 2 bbl. depending on the specific planned limit at MPD or DPPT limit
defined for the location as per Petrobras Simulation.
The Driller, Tool Pusher, Company man and MPD crew must have reviewed this procedure and
understand the actions to be taken and lines of communication.
The MPD Operators must have an accurate valve numbering diagram in place all the time.
The rigs MGS must have an effective liquid seal. This should have been recently circulated to
ensure the fluid is mobile.
Radios must be fully charged and all operating on the same channel.
SONDA will prepare and coordinate kill sheets in accordance with Petrobras and assisted by mud
loggers. All responsible parties should have kill sheets prepared and ready.
Booster pump must be working all the time during drilling the section.
While drilling ahead in MPD mode, the MPD system will be set in Pressure control mode to keep
BHP constant. Both DetectEV and ActEV will be enabled at all times
Note: Ensure MPD system is set as per MPD commissioning procedures according to
maximum SBP.
1. Driller: Establish stable MPD circulating conditions within predefined MPD operational
window for the hole section.
2. MPD Operator: Maintain all alarms and keep model updated for pressure control mode.
3. Driller/MPD operator: Perform all connections as per Fingerprinting Connection Drill (if
applicable).
4. MPD Operator/Mud Engineer: To ensure hydraulics model is calibrated and PWCD is within .2
of one at all times. If PWCF is outside of that tolerance verify model and mud parameters.
5. MPD Operator informs Driller & Company Man that influx or loss is taken.
If influx size is bigger than specific planned limit or DPPT limit defined, circulate the
influx through Rig Conventional Well Control System following the next procedure.
1. MPD Operator: to inform the Driller an influx has been detected and this is bigger
than 2 bls. MPD automatically start to increase SBP to maintain SPP constant or to
MDODP (Max Dynamic Operating Pressure)
2. Driller: Stop drilling, pick up off bottom space out (to ensure Tool Joints are not
placed in SSBOP and Surface Annular BOP).
3. Driller: simultaneously, monitor rig’s kick detection system to confirm any gain. Mud
logger must also monitor Pit gain on his system.
Due to system’s PRV (pressure rating = 2000 psi) that will be installed at the beginning of the operation, MASBP is
limited to 1600 psi
6. MPD Operator: Notify the Driller to be ready to start decreasing the first mud pump (if
using 2 mud pumps for drilling) and wait confirmation from Driller.
7. Driller: Immediately decrease the first mud pump to 5-7 SPM in a ramp down
progression, as trained during the fingerprinting, and hold at that rate.
8. If two pumps are being used for drilling, repeat the same procedure to reduce the 2nd
pump to completely stop in a ramp down progression. (Maintain booster pump
running).
9. Driller: Inform the MPD operator and stop the first mud pump from 5-7 SPM to zero.
10. MPD Operator: Meanwhile Mud Pumps are stopped as per steps 6, 7, 8 and 9,
monitors that MPD response accordingly.
Ensure SBP are within the 80% of maximum allowable Surface Back Pressure.
12. Driller: Open upper choke line valve and monitor casing pressure on the rig
choke panel.
14. Driller: maintain pumping with Booster pump to verify if there is gas in the Riser
with the MPD system. See Figure 2 flow path. If there is Gas in Riser, follow
step A,
if not, release pressure in MPD choke and between MPD annular and RCD
through 2-1/16” valve of RCD V1 to MPD choke, and continue with
conventional well control procedure.
As MPD will be operated in automatic mode, there should not be any gas entering the
riser undetected. This means that the system will automatically detect if a kick is taken
and will close the choke to increase the bottom hole circulating pressure and control the
well.
In the event of gas in the riser, MPD should be aligned to the MGS of the rig to be used
to circulate out the gas. Next steps to be followed:
1. Assistant Driller: Confirm Surface Annular BOP is close. (Don’t reciprocate pipe
during this operation. Release pressure trapped between Surface Annular BOP and
RCD through 2 1/16 “ valve V1/V2 to rig choke, and monitoring pressure above MPD
annular with RCD pressure gauge. See Figure 3.
4. MPD Supervisor/Driller: Once gas has been displaced from riser, open
Surface Annular BOP and line up 2-1/16” RCD outlet (V1/V2) through the
Buffer manifold, choke manifold and MGS to evacuate any possible gas
trapped into the Surface Annular BOP chamber and Flow spool.
5. Driller: Circulate with Booster Pump across 2-1/16” RCD outlet and Flow line
to evacuate any gas maybe trapped below MPD annular.
Note: The flow rate to circulate through 2-1/16” line will depend on
Fingerprinting for this flow path.
6. Driller: Once all gas confirmed out of the riser, stop booster pump and line up
to performed a flow check. See Figure 4.
1.7.1.2 Dynamically Well Control through MPD system and Riser: For
Influx Size less then specific planned limit at MPD matrix or MDDP limit
defined
This procedure only will be followed after SONDA and Petrobras agree that the kick size is
sufficiently small to guarantee that the higher surface pressure is within limit of Surface
equipment (RCD-Riser, Surface annular BOP).
1. If micro influx size is less than specific planned limit or DPPT limit defined, circulate the
micro influx dynamically through the riser and MPD system following the next procedure.
a) MPD Operator: To inform the driller an influx has been detected and this is less than
2 bls. MPD Operator to maintain a stable SPP by adjusting SBP accordingly.
b) Driller/Assistant Driller: Stop rotation and Close Surface Annular BOP and monitor
pressure above MPD annular with RCD pressure gauge.
c) MPD Operator/Driller – Monitor SBP value, choke position and flow in/flow out trends
while micro influx is circulated.
d) Driller/MPD Operator: Before micro influx reach the surface, line up the returns to
MGS via MPD system.
e) Release pressure trapped between Surface Annular BOP and RCD through 2 1/16
“valves V1/V2, buffer manifold to rig choke.
3. Driller: Circulate across 2-1/16” RCD outlet to evacuate any gas maybe trapped below
RCD and MPD annular. Reduce flow to 200-300 gpm to flow through 2” line to MPD and
maintain BHP with MPD System.
Note: If is not possible circulate through 2 1/16” valves V1/V2 and maintain the
BHP. (Low flow and high friction loss through 2” Line) Stop the pump and close
SSBOP and circulate with the Booster line following the same flow path. Be aware
that during process to stop the pump the MPD system must maintain constant the
BHP.
6. Driller: Once all gas confirmed out of the riser, line up to primary flow lines again. Increase
Booster pump flow rate according with MPD operator instructions.
• Volume of mud pumped to replace metal displacement is less than theoretical volume when
tripping out.
• Fluid displaced by string when tripping in is higher than theoretical or expected
displacement.
a. If the Trip out is without Back pressure, make a Flow Check using the Trip Tank, circulating
through RCD and MPD System in a close loop.
b. If the trip out is with back pressure (Booster Pump is used) made a Dynamically Flow
Check as per “WM-BRA-HAL-MPD-OP-005 Dynamic Downhole Flow Check”.
This procedure describes how to RIH, with well closed on SSBOP and MW statically
underbalanced. This procedure also assumes that the well has been monitored on surface
through the rig choke pressure sensor and GBA system and observed stable.
Preparation
This procedure assumes the well is balanced with the MW and pressure trapped on surface at the
rig choke and transmitted down through choke line. It also recognizes that will be necessary to
equalize the SSBOP before opening.
From surface to SSBOP, bit can be run conventionally and continue stripping from SSBOP to
bottom.
1. Make up BHA and run into the riser, taking returns through Rig Flow Line to the trip tank.
• Ensure to fill the pipe every five (5) stands while tripping in. Check if NRV's are holding
pressure (no returns through DP).
• Mud logger to confirm the string displacement (trip tank volume change).
2. Directional Engineer: Shallow Test as per BHA requirements.
3. Continue RIH to 60 m above the SSBOP.
4. Install RCD bearing. WM-BRA-HAL-RCD-OP-002 Installation and Removal Bearing Assembly.
5. Equalize SSBOP
• Line up the riser to the MPD choke and tanks to draw and return to the slug tank, as for
dynamic flow check. See Figure 1.
RCD Stack
Close: RCD V1, RCD V2.
Flow Spool
Close: FLS V4, FLS V3.
Open: FLS V1, FLS V2.
Buffer Manifold
Closed: BFM V9, BFM V8, BFM V7, BFM V6, BFM V5, BFM V4, BFM2.
Open: BFM V1, BFM V3
Junk Catcher
Closed: MV007, JUNK V.2
Open: JUNK V1, JUNK V3.
Note:
o Be aware additional drag over bearing seal element.
o Ensure to fill the pipe every 5 (five) stands while tripping in. Ensure NRV's are holding.
o Mud logger to confirm the string displacement (slug tank volume change).
END
FOR INTERNAL USE ONLY 8
Tripping Out– POOH
When MPD mud weight is planned to be statically underbalanced, the preferred method to trip out of
hole will be to circulate the hole clean, perform a Dynamic MPD Flow Check, and then pull the string
out of the hole to SSBOP doing stripping through RCD, while circulating on surface through the MPD
system to maintain the BHP constant. If the trip is to run casing instead of a liner, the well needs to be
balanced and POOH is done conventionally; or a barrier plug/fluid is placed in the hole. However if the
option is to run a liner, the trip may be done as planned for BHA change.
Preparation
1. The drill string should not be tripped out of the hole unless it is safe to do so.
2. It is important that all relevant parties, including the Company Man, MPD Engineer, Tool Pusher,
Driller, Derrickman/Shaker Hand, Mud Loggers, Mud Engineers, MWD/LWD Engineers and other
service personnel, are informed about the planned tripping operations and procedures to follow.
4. Expected swab and surge pressures must be calculated by two independent parties, i.e.
the Mud Loggers and/or Mud Company Engineer. Determine the maximum pipe speed,
taking into account swab/surge pressures recorded in the fingerprinting.
6. The Driller and Mud Logger shall maintain independent trip sheets to verify that the well
is displacing the correct amount of fluid and that gains/losses are not occurring. A trip
sheet from the previous trip should be available and intervals where overpulls and
resistance were encountered should be recorded on the trip sheets for reference.
7. The Driller must ensure that the rig floor is fully prepared to shut-in the well at any time,
that the FOSV and crossovers (if required) are operational, accessible and ready for
use.
8. Always install a FOSV on the string if the trip is interrupted for any reason, such as a
mechanical failure, flow check, etc. The valve should be left open to monitor the well, but
ready for immediate closing-in of the well if required.
9. The Tool Pusher and Company Man shall be on the floor at all times when tripping out/in
open hole.
FOR INTERNAL USE ONLY 3
10. The MPD Supervisor should inform the Mud Engineer of the static pressure being
applied to the well and the pressure friction lost estimated. This will allow the parties to
decide about the tripping option. APWD readings are also advised to be observed to
ensure tripping option.
Note: The last dynamic FIT or LOT must be used like reference to calculate the
maximum ECD allowed before trip.
11. The rig should prepare the preferred Slug Tank for dynamic flow check. After which the
tank should be prepared for POOH.
12. Mud bucket lined up for POOH with the correct seals installed.
13. Clear access to the rig’s standpipe manifold to bleed of the drill pipe pressure.
14. Have ready minimum 50-80 bbl. of viscous sweep pill having same density of drilling
fluid.
15. Ensure that fluid inside Choke and Kill lines has the same density of fluid in the well.
This procedure describes how to pull out of hole with a statically underbalanced drilling fluid.
Pump 50-80 bbl Hi-Vis pill and circulate hole clean using drilling
circulation rate. Reciprocate pipe per the Company
1
Man. Observe SPP, torque and drag when working pipe, and slow Mud Engineer/Driller
reciprocation of tool joints through RCD Element.
2 Maintain BHP as for drilling. Monitor SBP, BHP, SPP, Flow Rates for
any trend changes. Note any background gas and compare trends with GBA Operator
the mud loggers.
4.3 Set GBA system with the Swab & Surge option engaged. GBA Operator
Monitor the well and maintain BHP constant with GBA system.
GBA Operator
5.4
Apply additional SBP while POOH to compensate for swab.
7.7 Ensure that pressure (SBP) on the rig choke remains constant. Driller
• Above [Mud Sustainability] & below [Hole Cleaning Criteria] – Continue with MPD Fluid System
• Above [BHA Requirements] – Switch to PMCD with Intermittent Flush Cycle Injection
• Above [BHA Requirements + Bullhead Gas Migration Rates] – Continue with PMCD with Flush Cycle Injection
Injectivity Test
• Pump drilling fluid down the drillstring, slowly
raising the flowrate at 50 gpm steps.
• Pump 3 min for each step.
• Stop the test if SBP approaches 80 % of
MAASP. (Failed test)
– In case of negative test check fluid loss level at the
Action Plan chart.
– Proceed operations accordingly.
Injectivity Test
• Approved test:
– SBP and SPP stay constant after reaching drilling
injection rate.
– Repeat the procedure pumping SAC. If the same
results are found, the test is successful.
PMCD Pore Pressure Determination
• Considering UB mud.
• If BHA is close to casing shoe, pull BHA to casing
shoe.
• Driller to turn off Booster and Standpipe pumps.
• Sut in the well: 1st option MPD, 2nd option
Annular BOP – cautin with readings below 50 psi.
• Pump LAM in the annulus to prevent migration.
The pumped volume must be at least the same
volume between the high pressure zone and the
fluid loss zone.
PMCD Pore Pressure Determination
• MPD operator to calculate PP.
• As the PMCD drilling begins, PWD must
confirm the readings.
• Annulus fluid must generate 100 psi back
pressure at surface, not to exceed
80% MAASP - Pf – ΔP
Pf: Annular friction loss for influx bullheading
ΔP: max allowed annulus pressure to gas
migration
PMCD Pore Pressure Determination
• Considering OB mud:
• Stop pumps.
• If BHA is close to casing shoe, pull BHA to casing
shoe.
• Shut in the well at MPD choke.
• Close BOP.
• Pump light fluid in the annulus at high flow rates
until return is observed (cautin with volume
control)
• Define PP and LAM weight. Change LAM in the
well.
VND
example:
To annulus
PMCD
• In case of drilling without buffer manifold (as
SS46) or problems with any of the required
buffer manifold lines to drill PMCD, booster
line may be an alternative for bullheading.
• When using booster line, it is recommended
to be conservative regarging gas migration.
Risks
• Exceed pressure limits of the Riser + MPD
systems;
• Wrong valve aligning causing wellbore
pressure drop;
• Delays on annulus gas migration control;
• Running out of LAM;
• Sticking due to poor wellbore cleaning.
Procedimento
• Garantir alinhamento correto das válvulas, sucção
dos tanques e adição dos componentes do SAC.
• Entrar com bombas lentamente para dar tempo
de reação em caso de perda de injetividade.
• Monitorar continuamente comportamento da
SBP, SPP e tempo de migração até o limite pré-
definido.
• Em caso de não detecção de migração se
recomenda o bombeio de 50 bbl a cada 6h.
• Fazer uso de tampões viscosos conforme
necessidade e tendência de torque e drag.
Bullheading
• Zerar contador de strokes e bombear LAM no
anular até a pressão do anular retornar para o
valor anterior a migração. Não exceder o
limite de 80 % MAASP durante o bombeio.
Cenários possíveis na perfuração
PMCD
PWD Annular Drill pipe Probable Cause Action
Reading Surface Surface
Pressure Pressure
Stays the Increases Stays the Gas Bubble migrating in Annulus Increase Annular
Same Same Injection Rate
Decreases Decreases Decreases High loss rate into formation or Continue drilling
lower bottom hole pressure ahead if other factors
formation associated with losses to are not a problem.
other formation – Impossible to
determine if cross flow is occurring.
Conexão em PMCD - 003
• Semelhante a conexão em MPD.
• Riscos:
– Pressão trapeada.
– Falha NRVs
– Prisão de coluna devido limpeza deficiente.
Procedure
• Recommended to pump vicous pill prior to
connections;
• In case of annulus pressure buildup, start
bullheading. It is not recommended to do both
this opeartions in parallel.
• Take not of T&D and remove bit from bottom.
• Bleed off tubing pressure.
• DO NOT BLEED OFF ANNULUS PRESSURE.
• Make up connection, monitoring annulus.
• Slowly bring the pumps on and be aware of
additional drag.
PMCD POOH - 004
• There are two conditions that demand POOH
to surface:
– Required BHA changes (MWD, bit, etc.);
– Once TD was reached and liner was run, or any
other completion technique that require
cementing.
Purpose:
• This procedure should be used when needing to install the RCD Bearing Assembly with sealing
elements rubber with drill pipe in the hole. It considers both a general deterioration of the
element that warrants a change, with Back Pressure. (Well is static underbalance or with Back
pressure).
When a RCD bearing and/or the sealing elements fail during drilling operations, it can be changed
out without pulling out to surface or killing the well. This is the procedural guideline is for safe
removal and instructions to carry out the exchange of RCD bearings.
• During the removal and installation of the RCD bearing, the MPD annular preventer is closed
and the Riser Booster Pump is used with GBA System to keep BHP constant with Back
pressure.
The RCD Operator will guide the Rig crew through this process with respect to tool orientation,
alignment of connections and the pick-up/set down weights.
• A good vertical alignment of the rig over the wellhead is of critical importance in avoiding
operational problems with the RCD. Sufficient time should be taken during rig-up to ensure good
vertical alignment is achieved.
Note: It is preferable to change the bearing in casing. Although it can be done in open hole, it
increases risk of getting stuck. If is mandatory change the Element in open hole, pull an additional
stand out of the well to provide working room to work the string.
Note: If a small leak is observed adjust Annular preventer pressure to minimize leak and continue
Stripping in and monitor. If is not possible continue stripping in (leaking) shut in Subsea Annular
preventer. See Initial stripping operational pressure for MPD annular.
Note: As the tool joint passes through the first Sealing Element, the Bearing Assembly
Running Tool will tend to suddenly gain momentum; the natural reaction is for the driller
to apply the brake and stop. Try to avoid this as it increases the weight that needs to be
applied to pass through the second Sealing Element. Instead, use the momentum to
pass through the Bearing Assembly to ease the process. Once through both Sealing
Elements, continue running through until the Bearing Assembly Running Tool is seated in
the Bearing Assembly.
5. The Bearing Assembly Running Tool is inserted into the Bearing and Sealing Element
Assembly. Pneumatic hoses are connected to the running tool and set in Lock
Position.
6. Pneumatic hoses are removed from the Bearing Assembly. The running tool and BA
are lifted from the mousehole.
7. The Starter Mandrel is removed and the running tool with BA is made up with drill
pipe.
8. The slips and bushings are removed to allow the running tool with BA pass through
the Rotary Table.
9. Pneumatic hoses are connected to the Bearing Assembly Running Tool.
10. Using the Control Console, the Bearing Latch is tested.
RCD Stack
Open: RCD V1, RCD V2.
Flow Spool
Close: FLS V4, FLS V3.
Open: FLS V1, FLS V2.
Buffer Manifold
Closed: BFM V8, BFM V5, BFM V4, BFM2, BFM6
Open: BFM V1, BFM V3, BFM V9, BFM V7
Valves position Rig manifold: Line up by the rig crew to bleed off pressure.
Avoid surge Junk Catcher
Closed: MV007, JUNK V2.
Open: JUNK V1, JUNK V3.
12. Stripping in through MPD annular Preventer to lower running tool with Bearing
Assembly.
Note: Minimize stripping speed through the annular preventer. See Figure 7
“closing pressure for stripping operations T3 annular preventer”1
13. Land Bearing Ass. in the RCD Body, and then set down 6,000 lbs on the BA to
ensure that it seats properly
Note: The maximum OD of the Bearing Assembly is 19.4” and the minimum
diameter above the RCD is at the slip joint 19.5¨.
Note: The 2” valves RCD V1 & RCD V2 must keep open.
14. Using the Control Console, the Bearing Assembly is hydraulically latched to the
Body.
16. A slight upward pull of 2,700 - 3,600 kgs. (Approximately 6,000 – 8,000 lbs.) is
exerted on the drill string to confirm that the Bearing Assembly is latched.
21. The pneumatic hoses are disconnected from the Bearing Assembly Running Tool.
22. Break-out the connection and left running tool with drill pipe in rack as a stand or
place in the V-door or other appropriate location.
23. Make up new Drill Pipe stand.
24. Once bearing assembly to ready to go, equalize Pressure between MPD annular
and RCD. using BFM V5. Line up Figure 2.
Note: The RCD Pressure Gauge, gauge in Buffer manifold and Choke manifold gauge
will be monitored while pressure is equalized.
BTR-RCD
Close: 2 1/16” RCD V1 & RCD V2.
Buffer Manifold
Open: BFM7 (Bleed off valve) & BFMV9 (Already Open)
Buffer Manifold
Close: BFM7 & BFMV9.
27. Proceed to open the MPD Annular and Line up to continue normal rig
operations.
Purpose:
This procedure should be used when needing to remove the RCD element rubber with drill
pipe in the hole if Back pressure is used to Keep BHP constant. The procedure for removal of
the Bearing and Sealing Element Assembly is the reverse of the installation procedures.
Note: Caution: Removal of Bearing Assembly shall only occur when there is no
annulus pressure on the Rotating Control Device. In case there is an ongoing
operation, the annular preventer will isolate the well while the Bearing Assembly is
replaced.
1. Ensure Booster Pump at 200 gpm minimum. Slowly Stop Rig Pumps and control BHP
with GBA choke while continuing to flow through RCD V1, RCD V2, FLS V1 & FLS V2.
2. Open flow path for MPD Annular: (Overpressure the top of the MPD Annular while closing
the rubbers may lead to equipment failure), as show in Figure 4.
RCD Stack
Open: RCD V1, RCD V2.
Flow Spool
Close: FLS V4, FLS V3.
Open: FLS V1, FLS V2.
Buffer Manifold
Closed: BFM V8, BFM V4, BFM2, BFM6, BFM V7
Open: BFM V1, BFM V3, BFM V9 & BFM V5.
Junk Catcher
Closed: MV007, JUNK V2.
Open: JUNK V1, JUNK V3.
Flowline
a) Start circulation to surface to aid in flushing the components above RCD.
b) Cicle C-Latch open to close 4 times during circulation.
c) Stop pumping.
Scope
The surface system has different pressure relief devices, PRV’s in the Buffer manifold that will protect
the equipment in case any overpressure upstream the MPD Choke manifold, besides the MPD
manifold has a choke that will release pressure once reach the setting pressure.
The level 4 choke will be equipped with 2 x 3” drilling choke trims and a 2” connection choke trim. An
instance of plugging may require the pump rate to be dropped or shut down before the obstruction
can be isolated and removed.
• Ensure all necessary work permits must are in place prior to opening chokes/junk catcher/ Coriolis
for repair while circulating.
• Mud engineer to inform MPD when of any mud additives are changed that may cause choke
plugging.
• Be aware of risk from hot mud or H2S when opening any surface lines for maintenance and take
all required precautions.
Potential Hazards
• Miscommunication
• High pressure at surface may exceed surface equipment ratings
• Loss of Bottom hole pressure
• Spills
FOR INTERNAL USE ONLY 2
Notes
1. Upstream pressures trends must be monitored in the junk catcher, coriolis meter and GBA
MPD autochoke, to determine the plugged section.
2. While the system is built with redundancy and bypasses anytime the systems pressure
encroaches the designed safe operating pressure the rig team must;
PLUGGED CHOKE
The purpose of this procedure is to demonstrate the appropriate steps to take if there are
indications that the GeoBalance choke is plugged or plugging.
Halliburton’s automated choke system has the ability to isolate and complete maintenance on the
plugged choke without affecting drilling activities but the driller must be informed of the operation.
Purpose
This procedure addresses the required steps to be taken after a NVR or Drillstring failure has been
encountered.
Scope
• In event of a drill string failure all precautions should be made to prevent any contact with hot mud
or spill on the rig floor.
• All NRVs are to be pressure tested and redressed after each run.
• It must be assumed that there is trapped pressure under all NRVs. Breaking out an NRV with
pressure underneath can lead to serious injury.
• Ensure an FOSV, pre-made up with the correct crossover, is ready on the drill floor.
• If the string is sitting in the slips for an extended period of time, install an FOSV in the open
position.
• Monitor the string continuously while tripping and making connections in case conditions change.
• Inspect all tool joint sealing faces for damage as each joint is made up.
Potential Hazards
• Miscommunication
• Loss of Bottom hole pressure
• Spills
Washouts may be hard to detect and may be easily confused with an NRV failure. A washout
above the last NRV may allow back flow up the drill pipe during connections. A washout is usually
indicated by a slow decrease in standpipe pressure. So it is very important to keep the mud pump
rate constant where possible.
All precautions must be taken to prevent a drill string pack off. Ensure junk or
solids are not re-circulated down hole and drill pipe is drifted prior to RIH.
If the drill string becomes plugged during MPD operations the well will need to be
killed prior to tripping out of the hole. As circulation will not be possible the
bullhead method will be used.