An organization structure can be defined as the framework of a company that describes the entire
structure and functioning of the company. Organization structures are split into different levels and
each level is placed according to a hierarchy. These levels have direct or indirect relationship with
one another. The various levels in a standard organization are as follows −
Company
Company code
Plant
Storage location
Purchasing organization
Purchasing group
Create Company
Company is the topmost organizational unit after client, which incorporates individual financial
accounting statements of several company codes. A company can have many company codes. In
SAP, it is optional to create a company. The following steps will take you through the procedure of
creating company.
IMG ⇒ Enterprise Structure ⇒ Definition ⇒ Financial Accounting ⇒ Define Company
TCode: OX15
Create Plant
A Plant is an organizational unit within a company where activities take place. A plant will produce
goods and make goods available for the company. The following steps will take you through the
procedure of creating a plant −
Path to create Plant
IMG ⇒ Enterprise Structure ⇒ Definition ⇒ Logistic General ⇒ Define, Copy, Delete check plant
TCode: OX10
Create Storage Location
A Storage Location is an organizational unit, which actually differentiates between the different
material stocks in a Plant. Storage location is a place where stock is kept physically. A plant can
consist of multiple storage locations. All data is stored at a storage location level for a particular
storage location. Follow the steps given below to create a Storage Location −
Path to Create Storage Location
IMG ⇒ Enterprise Structure ⇒ Definition ⇒ Materials Management ⇒ Maintain Storage Location
TCode: OX09
Number Range
When we create a material master record, every material is recognized by a unique number that is
known as the material number. We can assign a number to a material through two ways −
External number assignment − While creating a material, you have to enter your own
number (containing alphabets or digits), and that should be unique.
Internal number assignment − While creating a material, you need not enter any number.
The system automatically generates a unique number to that material.
Define Number Range −
Internal number range can be defined by following the steps given below −
Path to Create Number Range
IMG ⇒ Logistic General ⇒ Material Master ⇒ Basic Settings ⇒ Material Types ⇒ Define Number
Range for Each material Type
TCode: MMNR
Vendor master has three characteristics, which we will discuss one by one in the following sections.
Vendor Account Group
Vendors are categorized according to their requirements. Some of the vendors having similar
characteristics are grouped together and placed in one category. For example, all local vendors can
be placed under one account group. Create a Vendor Account group by following the steps given
below.
Path to create Vendor Account Group
IMG ⇒ Logistic General ⇒ Business Partner ⇒ Vendors ⇒ Control ⇒ Define Account group and field
selection(vendor)
TCode: OBD3
Number Range
When we create a vendor master record, every vendor is recognized by a unique number known as
the vendor number. As in the case of material master, we have external as well as internal number
assignments for vendor master.
Define Number Range:
Number range can be defined by following the steps given below −
Path to create Number Range
IMG ⇒ Logistic General ⇒ Business Partner ⇒ Vendors ⇒ Control ⇒ Define Number Range for
Vendor master record
TCode: XDN1
Automatically
Manually
Determination of Requirement
Creating Purchase Order
Posting Goods Receipt
Posting Invoice
Determination of Requirement
This is the first step in a procurement cycle. It is the logical subdivision, where it is determined what
material or services are required by the company, and which supplier can fulfill the requirement. A
list of requirements is made and then it is approved by a senior authority within the organization.
After approval, a formal list is made that is known as the purchase order with one more level of
approval which is sent to the vendor.
Step 2 − Fill in all the necessary details such as name of the vendor, purchasing organization,
purchasing group, company code, and details of the material, for example, material number, price,
currency, and plant.
Step 3 − Fill in all the necessary details under Item, by selecting the tabs as shown in the following
screenshot −
Invoice/Delivery Tab (Provide the tax code, Payment terms and conditions, and incoterms)
Assignment Tab (Provide a valid G/L code, business area, and WBS element)
Click on Save. A new Purchase Order will be created.
Posting Goods Receipt
After processing the purchase order, the vendor delivers the material to the ordering party and this
process is called Goods Receipt. It is the phase where the material is received by the ordering party
and its condition and quality are verified. Once the material is verified against the predefined quality,
a goods receipt is posted. Goods receipt can be posted by following the steps given below.
Path to Post Goods Receipt
Logistics ⇒ Materials Management ⇒ Inventory management ⇒ Goods movement ⇒ Goods
movement
TCode: MIGO
Step 1 − On the SAP Menu screen, select Goods movement (MIGO) by following the above path.
Step 2 − Fill in all the necessary details such as movement type (101 for goods receipt), name of the
material, quantity received, details of storage location and the plant where the material will be
placed. Click on Save. Goods Receipt is now posted for the material.
Posting Invoice
Invoice is received from the vendor after goods receipt, and then the invoice is verified by the
ordering party. This is the phase where the vendor (seller) is paid from the company and
reconciliation of the invoice and PO is accomplished. An invoice can be posted by following the
steps given below −
Path to Post Invoice
Logistics ⇒ Materials Management ⇒ Logistic Invoice verification ⇒ Document Entry ⇒ Enter
Invoice
TCode: MIRO
Step 1 − On the SAP Menu screen, select Enter Invoice by following the above path.
Step 2 − Fill in all the necessary details such as invoice posting date, amount that is paid to the
vendor along with the quantity for which the amount is paid. Click on Save. Invoice is now posted for
the goods receipt.