Ethiopia 3
Ethiopia 3
Ethiopia 3
BY
MEKONNEN BESHAH
SEPTEMBER 2015
ON
BY
MEKONNEN BEHSAH
TABLE OF CONTENT
1. INTRODUCTION……………………..……………………………………………….……1
1.1 Significance of the Study …………………………..…………………………………..2
1.2 Research Outline ………………………………………………………………………..3
1.3 Statement of the Problem …………………………….………………………………..4
1.4 Objective of the Study ……………………………..…………………………………...4
1.5 Scope and Limitations ………………………..………………………………………...4
2. LITERATURE REVIEW …………………………………………………………………….6
2.1 Construction Changes and Change Orders ………………………………………….6
2.1.1 Construction Changes …………………..….……………..………………….…6
2.1.2 Construction Change Orders ………………...………………..……………….9
2.2 Causes of Change Order ………………………...……………………………………10
2.2.1 Change Orders Caused by Project Owners ……….………………………..10
2.2.2 Change Orders Caused By Consultant …………………………………….. 11
2.2.3 Change orders Caused by Contractors …………………..………………… 14
2.2.4 Other Causes of Changes ……………………………………………………..17
2.3 Impacts of Change Orders …………………………………………………………....18
2.3.1 Direct Cost Impact ……….……………………………………………………19
2.3.2 Direct Schedule Impact ……………………………………………………….22
2.3.3 Consequential Impacts ………………………………..………………………23
2.4 Legal Aspect of Change Orders ………………….....……………………………..…25
2.4.1 Types of Construction contracts ……………..………………………………25
REFERENCE …………………………………………………………………………………...83
LIST OF TABLES
Table – 2:- Projects included in the desk study and their Project Cost
Table – 3:- Summary of Reason of Change Orders and their change order amount
Table – 7:- Frequency of occurrence of Change order categories based on the responses of
Table – 9:- Cost impacts of change orders and their total change order amount percentile
Table – 10:- Mean Score (MS) of Cost Impact of Major Categories of Change Order causes
Table – 11:- Summary of correlation test on the ranking of variables of causes of change
ABBREVIATIONS
FIDIC - Federation Internationale Des Ingenieurs-Conseils
PCO - Potential Change Order
RFI – Request for Information
RFP - Request for Proposal
CCD - Construction Change Directive
CII – Construction Industry Institute
MS – Mean Score
ACKNOWLEDGEMENT
I am very grateful for the almighty Lord for granting me this opportunity to undertake
this research work. TO HIM ALONE BE THE GLORY!
I am thankful for Ethiopian Roads Authority (ERA), for the sponsorship of my post
graduate study at Addis Ababa University institute of Technology and all regional
contract administration directorates of ERA and staffs for their appreciated assistance
during my desk study.
My special thanks solely forwarded to my advisor, Prof. Dr. Ing. Abebe Dinku; first of
all for his iconic, ethical and professional personality he boldly wrote on my heart
alongside his lectures, it is much more than any material equivalent. And second, for
his willingness to be my advisor in this research, his responses, guiding comments and
most of all for sharing his precious time.
Finally, I wish to express my sincere gratitude to my family and all my friends who
encourage me to accomplish this research. God richly bless you all!
ABSTRACT
This research makes assessment on the causes and cost impacts of change orders on
road projects in Ethiopia. Emphasis is given to the identification of the root causes of
change order categories from seventeen road project with a total of 123 reasons of
causes of change order. As a result the most common reasons of causes of change order
are categorized as: design errors and omissions, scope change, unforeseen conditions, value
engineering, force majeure and others. Of the total reasons of causes of changes orders
included in the study, 40.8% were caused by design errors and omissions, 29.3% by
change of scope by owner, 15.8% resulted from other causes, 7.5% were caused by
unforeseen conditions, 5.8% by value engineering and 0.8% due to force majeure.
In addition to identifying the major categories of change orders, the consequential cost
impacts of these change orders were analyzed. As a result, those reasons of change
order categorized under value engineering have a decrement cost impact which saves an
amount of birr 23,861,361.94. The reasons of change orders in this category have
positive cost impact on the total project cost as they are a saving to the project owner.
However, the rest categories of causes of change order have increment or negative cost
impacts with a total change order amount of birr 410,596,232.76. From this total cost
increment 52.4% is caused by change of scope; 38.6% by design errors and omissions, and
7.6% contributed other causes. Though they are minor, 1.2% and 0.2%, the rest are
contributed by unforeseen conditions and force majeure respectively in descending manner
of their contribution.
Spearman rank order correlation analysis was used to evaluate whether consensus of
opinions exists between groups of respondents. From the analysis of the results it can be
concluded that the correlation between the attitudes of the respondents in all the three
groups is relatively weak. This is so, because two third of the groups assure the absence
of significant consensus.
Key words: change, change order, change order categories, cost impacts of change order.
1. INTRODUCTION
Many times, change is necessary for the success of a project. “change, defined as any
event that results in a modification of the original scope, execution time, or cost of work,
happens on most projects due to the uniqueness of each project and the limited
resources of time and money available for planning” (Hanna, 2002). While change
orders are necessary to address unforeseen conditions and other unavoidable or
unanticipated occurrences, they tend to negatively affect the progress of a construction
project. In most public works, change orders are the main reason for construction delays
and cost overruns (Wu, 2005). Change orders also lead to a decline in labor efficiency,
loss of man hours, and costly disputes (Moselhi, 2005).
This research aims to study change orders on road construction projects in Ethiopia
which occur most frequently and analyze their causes and the cost impact they impose
on the projects.
Despite the fact that changes are inevitable phenomena in the construction projects,
emphases must be given to accommodate changes in construction contracts. A change
clause has to be incorporated to define the way how owner, consultant and contractor
handle changes. Therefore, change clauses and procedures must be set to process a
change from the conceptual development until it is realized to its material equivalent in
the field.
Hence, this research aims to assess causes of change orders and their cost impact on
road construction projects in Ethiopia and lay the foundation for future research so that
problems related to changes and change orders can be properly addressed.
categories, assessment of cost impact of change orders and test for agreement. The fifth
and the last chapter, conclusion and recommendation, explicitly put the conclusions of the
research and make a recommendation on how to minimize changes and change orders
in road construction projects in Ethiopia.
2. LITERATURE REVIEW
2.1 Construction Changes and Change Orders
In a perfect world changes will be confined to the planning stages. However, late
changes often occur during construction, and frequently cause serious disruption to the
project (Oracle, 2009). In these circumstances, decisions are being made under pressure
and cost and time invariably dominate the decision making process (O‟Brien, 1998;
Arain, 2005). Most forms of contract for construction projects allow a process for
changes. Even though there may be a process in place to deal with these late changes,
cost and time invariably dominate the decision making process. If the change affects the
design, it will impact on the construction process and, quite possibly, operation and
maintenance as well (Oracle, 2009).
To overcome the problems associated with changes to a project, the project team must
be able to effectively analyze the change and its immediate and downstream effects
(CII, 1990). An effective analysis of change and change orders requires a comprehensive
understanding of the root causes of changes and their potential downstream effects. To
manage a change means being able to anticipate its effects and to control, or at least
monitor the associated cost and schedule impact (Hester, 1991).
construction phase. The replacement of materials affects the project contract amount
(Chappell and Willis, 1996). Therefore, an adjustment to the original contract value is
required if there is a change in materials. Prompt decision making is an important factor
for project success (Sanvido , 1992; Gray and Hughes, 2001). A delay in decision making
may hinder subsequent construction activities that may eventually delay the project
progress.
before the design is finalized (Fisk, 1997). Most of the time this practice happens when
the consultant believes improvement is vital for successful completion of the project.
Errors and omissions in design cause of project delays (Arain ., 2004) and may lead to loss
of productivity and delay in project schedule (Assaf, 1995).
Conflict between contract documents can result in misinterpretation of the actual
requirement of a project (CII, 1986a). To convey complete project scope for participants,
the contract documents must be clear and concise.
In a multi-party player environment, like construction, the scope of work for all the
players must be clear and unambiguous for successful project completion (Fisk, 1997;
Arain, 2004). Technology change is related to technological advancements which can
accelerate the project‟s completion time. This could be a potential cause of changes in a
project. Therefore, project planning should be flexible for accommodating new
beneficial changes (CII, 1994b). This is because the new technology can be beneficial in
the project life cycle, for instance, reducing maintenance cost of the project. Value
engineering is related to those changes resulted due to economic condition and material
changes. Such changes should ideally be carried out during the design phase (Dell‟Isola,
1982). During the construction phase, value engineering can be a costly exercise, as
change in any design element would initiate down-stream changes to other relevant
design components (Mokhtar, 2000). Complex designs require unique skills and
construction methods (Arain, 2004). Complexity affects the flow of construction
activities, whereas simple and linear construction works are relatively easy to handle
(Fisk, 1997).
To convey a complete concept of the project design, the working drawings must be
clear and concise (Geok, 2002). Insufficient working drawing details can result in
misinterpretation of the actual requirement of a project (Arain, 2004). Professional
experience and judgment is an important factor for successful completion of a building
project (Clough and Sears, 1994; O‟Brien, 1998). The lack of professional experience
increases the risk of errors in design as well as during construction. Eventually, this
may affect the project quality and delay the project completion. A lack of required data
can result in misinterpretation of the actual requirements of a project (Assaf, 1995;
Arain, 2002). Where there is insufficient data, consultants are compelled to develop
designs based on their own perceptions, which may not be what the client wants. A
clearer design tends to be comprehended more readily (O‟Brien, 1998). Ambiguity in
design is a potential cause of changes in a project. This is because ambiguity in design
can be misinterpreted by project participants, leading to rework and delay in the project
completion. Inadequate design can be a frequent cause of variations in construction
projects (CII, 1990; Fisk, 1997). Design discrepancies affect the project functionality and
quality. Eventually, this can affect a project adversely depending on the timing of the
occurrence of the changes. Noncompliance of design with government regulations would
render the project difficult to execute (Clough and Sears, 1994). This may affect the
project safety and progress adversely, leading to serious accidents and delays in the
project completion. A comprehensive design is one that accommodates the owner‟s
requirements (Cox and Hamilton, 1995). A noncompliance design with the owner’s
requirements is considered an inadequate design (Fisk, 1997). Eventually, this may cause
changes to accommodate the owner‟s requirements which may affect the project
adversely during the construction phase. Changes in specifications are frequent in
construction projects with inadequate project objectives (O‟Brien, 1998). As mentioned
earlier with respect to changes in specifications by the owner, this is also a potential
cause of changes in a project, leading to reworks and delays in the project completion.
Unavailability of equipment
Financial difficulties
Desired profitability
Differing site conditions
Defective workmanship
Poor procurement process
Lack of communication
Lack of judgment and experience
Complex design and technology
Lack of strategic planning
Lack of required data
Involvement of the contractor in the design may assist in developing better designs by
accommodating his creative and practical ideas (Arain, 2004). Lack of contractor’s
involvement in design may eventually cause changes. Practical ideas which are not
accommodated during the design phase will eventually affect the project adversely.
Unavailability of equipment is a procurement problem that can affect the project
completion (O‟Brien, 1998). Occasionally, the lack of equipment may cause major design
changes or adjustments to project scheduling to accommodate the replacement. Skilled
manpower is one of the major resources required for complex technological projects
(Arain, 2004).
Construction is a labor intensive industry. Whether the contractor has been paid or not,
the wages of the worker must still be paid (Thomas and Napolitan, 1994). Contractor‟s
financial difficulties may cause major changes during a project, affecting its quality and
progress. Contractor’s desired profitability can be a potential cause of change in
construction projects. This is because changes are considered a common source of
additional works for the contractor (O‟Brien, 1998). The contractor may eventually
strive to convince the project owner to allow certain changes, leading to additional
financial benefits for him. Differing site condition can be an important cause of delays in
large building projects (Assaf, 1995). The contractor may face different soil conditions
than those indicated in the tender documents. Eventually this may affect his cost
estimates and schedule adversely.
Defective workmanship may lead to demolition and rework in construction projects (Fisk,
1997; O‟Brien, 1998). Defective workmanship results in poor quality of work in
construction projects (Arain, 2004). Eventually, this cause may affect the project
adversely, leading to rework and delay in the project completion. The construction
manager carries out the construction phase in an organized way to eliminate the risks of
delays and other problems. Procurement delays have various adverse effects on other
processes in the construction cycle (Fisk, 1997). Occasionally, the procurement delay
may cause an entire change or replacement for originally specified materials or
equipment for the project (Arain, 2004). This may therefore cause a need for project
activities to be reworked. A lack of communication between parties may cause major
changes that could eventually impact the project adversely (Arain, 2004). Detrimental
changes, which affect the projects adversely, can usually be managed at an early stage
with strong and continuous communication.
Complex design and technology require detailed interpretations by the designer to make it
comprehensible for the contractor (Arain, 2002). A complex design may be experienced
for the first time by the contractor. Eventually, the complexity may affect the flow of
construction activities, leading to delays in the project completion.
Proper strategic planning is an important factor for successful completion of a building
project (Clough and Sears, 1994; CII, 1994a). The lack of strategic planning is a common
cause of changes in projects where construction starts before the design is finalized, for
instance, in concurrent design and construction contracts (O‟Brien, 1998). A lack of
required data may affect the contractor‟s strategic planning for successful project
completion, leading to frequent disruptions during the construction process. This is
because a lack of data can result in misinterpretation of the actual requirements of a
project (Assaf, 1995; Arain, 2004).
The impacts of a change are classified in the literature as follows: (CII publication 6-
10,1990)
1. Direct cost impact
2. Direct schedule impact
3. Indirect or Consequential impact
Let us examine each of these impacts and its attributes making reference to published
literature on the subject.
2.3.1 Direct Cost Impact
The direct impacts are those limited to the work package in which a change is
introduced. The cost impact could be positive (savings) to the owner or negative (more
expenditure). The contractor‟s view of a change being positive or negative will be the
opposite of the owner. A change may also have a positive cost impact to both owner
and contractor. Further, a change may have zero cost impact to both parties. There are
two components to the cost of a change: labor cost and material cost. Material cost is
easy to estimate and predict to certain accuracy. However it is difficult to estimate labor
cost due to:
♦ The effect of changes on the productivity rate itself.
♦ The uncertainty about the scope of a change (exact engineering, procurement,
and construction activities that form a change work).
The discussion here about labor cost impact will use the situation where change is
issued after construction as the setting. Labor cost of changes can be broken into three
attributes (CII publication 6-10, 1990):
a) Productivity Degradation
b) Delays
c) Demolition and Rework
Of the direct cost impact attributes, productivity is the most difficult to estimate,
measure and control.
a. Productivity Degradation
Interruption, delays and redirection of work, associated with change work have a
negative impact on labor productivity which in turn translates into labor cost or dollar
value. Many studies were conducted to evaluate this aspect of change (CII publication 6-
10 (1990), Thomas 1994 &1995, Hester 1991). Two studies cited in CII publication 6-10
(1990) examined work by single craft crewmen and effects of changes on their
productivity. “The setting of the first study was a major chemical facility and the
craftsmen involved were union insulators”. “Study 2 was undertaken on a revamp
project at a refinery where changes were being generated at a rate that often exceeds 20
per week”. Comparing the productivity index against the frequency of change, the
studies concluded:
Productivity drops rapidly with increased frequency of interruptions.
♦ As the rate of disturbances to the normal flow of work increases, the extent of
productivity degradation becomes compounded.
♦ More than 40% reduction in productivity was noticed with an extreme number of
disturbances.
Productivity degradation is not the same for all tasks and settings. The following factors
are noted:
1. Concentration required to accomplish the task
2. Machine intensive tasks vs. labor intensive tasks
3. Frequency of interruptions and duration of time between them
4. Worker expectation of the change and his opinion about it
We can also expect productivity of workers to be greatly affected in cases where
workers were required to work overtime for prolonged periods to compensate for
schedule delays. In a study by Thomas and Napolitan (1995) productivity values from
three industrial projects constructed between 1989 and 1992 were used in the analysis.
The study concluded that on average there was 30% loss of efficiency due to changes
(25-50% was the actual range). It is worth noting that Thomas and Napolitan concluded
that changes do not lead to productivity degradation or efficiency loss in them. Instead,
b. Cost of Delay
To make a change and process takes time. This usually results in placing a hold on the
work and waiting for new instructions to come. In addition, equipment, tools and
materials may not be the same after the change is introduced. To procure or rent new
material, tools and equipment will cause delay and cost of resources may be substantial.
Furthermore, if delays are prolonged demobilization/remobilization may become quite
costly. The cost of delay may apply to engineering and procurement activities if
impacted by change (CII publication 6-10, 1990).
c. Demolition and Rework
Changes, which are introduced when the construction is underway or even complete
involve several direct cost items (CII publication 6-10,1990) which can be summarized
as follows:
i. Labor cost to demolish existing facility
ii. Equipment cost to demolish existing facility
iii. Materials wasted by removal of existing work
iv. Associated cost of engineering/shipping and handling of waste materials
resulting in increased labor intensity and a more hectic finishing and close out
operation.
Contract Forms
contracts require greater risk sharing between the owner and contractor and require
more owners‟ personnel for contract administration during the construction phase to
enforce cost and schedule. They are more easily used for fast tracking of design and
construction. Reimbursable contracts are also very flexible for changing design or scope
of work and establish the basis for a less adversarial relationship between the owner
and contractor.
Ibbs et al (1986) indicated that “the choice of the type of contract (fixed cost versus cost
reimbursable) should be heavily influenced by four circumstances:
1. The extent to which the work is defined
2. The desired allocation of risk between owner and contractor
3. The availability of owner expertise and effort on the project
4. The need to accommodate fast-tracking of design and construction
Often both forms of contracts exist on a project simultaneously. Prime contractors will
often have cost reimbursable contracts with the owner and fixed price contracts with
their subcontractors. In the Ethiopian construction industry fixed price contract is
widely practiced.
and for appropriate compensation. The change clause establishes the right of the owner
to make changes within certain limitations and through a defined mechanism.
However, it was found that change clause is one of the most troublesome contract
clauses. Problems most often encountered with construction change clauses involved
definition and negotiation of costs, dispute resolution and time required for approval.
Legal disputes over changes often focus on whether or not a compensatory change
exists, the appropriate level of compensation, and the relative responsibility for a
change.
Timing
Managing Impact
Who does the change
Site conditions (environment)
In its special publication (Oracle, 2009), change management best practices for the
engineering and construction industry recognized five valuable steps for effective
change management:
Identifying contract requirements.
Identifying potential changes.
Determination of Entitlement and Effect of Change
Negotiation and execution of change order.
Recording the executed change.
The owner and contractor should also pay particular attention to the contract clauses
related to notice and changes, because these clauses are the logical starting points for
the identification and administration of changes.
Changes include changing the quantities of work or the conditions under which it is to
be performed, and suspending, adding, or eliminating work that is within the scope of
the contract. Therefore,
• During the course of the contract, the owner through its agent has the right to
make written changes in the quantities or other alterations as necessary to
complete the work [FIDIC 1987, Clause51 (a to f)].
• Contract time will be adjusted [FIDIC 1987, Clause 44.1 (a to e)] for changes that
require additional time to complete.
The changes clause, illustrated above, first addresses the potential scope, schedule, and
budget effects of the change, then direct to the appropriate contract provisions
governing payment and time extensions.
As to how this might work in practice, changes that affect the project‟s “critical path”
might require the issuance of a time extension.
Likewise, the provisions that govern the payment requirements for the changed work
are referenced by the changes clause. For contract changes that affect unit price work
items, the preferred solution is typically to use the existing contract unit prices to price
the changed work. If contract unit prices for the changed work do not exist, suitable
rates or prices can be negotiated between the contracting parties. In the event of
disagreement, the consultant, as per clause 52.1 of the FIDIC condition of contract, can fix
such rates or prices which are, in his opinion, appropriate and notify the contractor
accordingly, with a copy to the owner. However, the consultant can also determine
provisional rates or prices to enable on-account payments to be included in certificates
issued in accordance with Clause 60.
If the Owner responds unacceptably, or not at all, the contractor must provide a written
notice within five working days of the first notice. The written notice has to include the
following:
Construction contracts are often thorough in identifying the different kinds of changes
that might be encountered during construction and defining the procedures that must
be followed upon their identification. The common types of change provisions defined
in construction contracts are:
Suspension of work,
Extra work, or
Elimination of work.
FIDIC 1987, condition contract Clause 51.1 grants the Engineer (Owner‟s representative)
to make any variation of the form, quality or quantity of the works that may, in his
opinion, be necessary. The type of variation this clause commands include “increase or
decrease the quantity of any work included in the contract” and “change the character or quality
or kind of any such work.
If the changes in quantities significantly change the character of the work under the
contract, whether or not changed by any such different quantities or alterations, an
adjustment, excluding loss of anticipated profits, will be made to the contract. The basis
for the adjustment shall be agreed upon prior to the performance of the work. If a basis
cannot be agreed upon, then an adjustment will be made either for or against the
contractor in such amount as the Engineer may determine to be fair and equitable.
If the alterations or changes in quantities do not significantly change the character of the
work to be performed under the contract, the altered work will be paid for as provided
in Sub Clause 52.1 of FIDIC 1987, condition contract as follow:
All variations referred to in Clause 51 and any additions to the Contract Price which are
required to be determined in accordance with Clause 52 (for the purposes of this Clause referred
to as “varied work”), shall be valued at the rates and prices set out in the Contract if, in the
opinion of the Engineer, the same shall be applicable. If the Contract does not contain any rates
or prices applicable to the varied work, the rates and prices in the Contract shall be used as the
basis for valuation so far as may be reasonable, failing which, after due consultation by the
Engineer with the Employer and the Contractor, suitable rates or prices shall be agreed upon
between the Engineer and the Contractor. In the event of disagreement the Engineer shall fix
such rates or prices as are, in his opinion, appropriate and shall notify the Contractor
accordingly, with a copy to the Employer.
physical conditions and other physical obstructions and pollutants, which the
contractor encounters at the site when executing the works, including sub-surface and
hydrological conditions but excluding climatic conditions.
Whenever such site conditions happen while executing, Sub clause 4.12 of FIDIC, MDB
Harmonized 2010 edition treats the case as follow:
If the Contractor encounters adverse physical conditions which he considers to have been
Unforeseeable, the Contractor shall give notice to the Engineer as soon as practicable. This notice
shall describe the physical conditions, so that they can be inspected by the Engineer, and shall set
out the reasons why the Contractor considers them to be Unforeseeable. The Contractor shall
continue executing the Works, using such proper and reasonable measures as are appropriate for
the physical conditions, and shall comply with any instructions which the Engineer may give. If
an instruction constitutes a Variation, Clause 13 [Variations and Adjustments] shall apply.
If and to the extent that the Contractor encounters physical conditions which are Unforeseeable,
gives such a notice, and suffers delay and/or incurs Cost due to these conditions, the Contractor
shall be entitled subject to notice under Sub-Clause 20.1 [Contractor’s Claims] to:
(a) An extension of time for any such delay, if completion is or will be delayed, under Sub-
Clause 8.4 [Extension of Time for Completion], and
(b) Payment of any such Cost, which shall be included in the Contract Price.
Upon receiving such notice and inspecting and/or investigating these physical conditions, the
Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or
determine (i) whether and (if so) to what extent these physical conditions were Unforeseeable,
and (ii) the matters described in subparagraphs (a) and (b) above related to this extent.
However, before additional Cost is finally agreed or determined under sub-paragraph (ii), the
Engineer may also review whether other physical conditions in similar parts of the Works
(if any) were more favorable than could reasonably have been foreseen when the Contractor
submitted the Tender. If and to the extent that these more favorable conditions were encountered,
the Engineer may proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or
determine the reductions in Cost which were due to these conditions, which may be included (as
deductions) in the Contract Price and Payment Certificates. However, the net effect of all
adjustments under sub-paragraph (b) and all these reductions, for all the physical conditions
encountered in similar parts of the Works, shall not result in a net reduction in the Contract
Price.
The Engineer shall take account of any evidence of the physical conditions foreseen by the
Contractor when submitting the Tender, which shall be made available by the Contractor, but
shall not be bound by the Contractor’s interpretation of any such evidence.
the work in the sequence or manner that the contractor intended. Suspension could be
instigated by either of the contractual parties depending on their contractual right.
Suspension by the Employer/Engineer
Sub clause 40.1 of FIDIC Conditions of Contract recommends suspension of work where
such suspension is necessary by reason of: breach of contract by the contractor or climatic
conditions on the site, or for the proper execution of the works or for the safety of the Works or
any part thereof.
Sub-Clause 40.1:
The Contractor shall, on the instructions of the Engineer, suspend the progress of the Works or
any part thereof for such time and in such manner as the Engineer may consider necessary and
shall, during such suspension, properly protect and secure the Works or such part thereof so far
as is necessary in the opinion of the Engineer. Unless such suspension is:
(a) Otherwise provided for in the Contract,
(b) Necessary by reason of some default of or breach of contract by the Contractor or for
which he is responsible,
(c) Necessary by reason of climatic conditions on the Site, or
(d) Necessary for the proper execution of the Works or for the safety of the Works or any
part thereof,
If the performance of all or any portion of the work is suspended or delayed by the
owner or owner‟s representative in writing for an unreasonable period of time (i.e.
suspension lasting more than 84 days) and if permission to resume work is not given by
the engineer, the contractor may submit in writing to the engineer requiring permission
within 28 days to proceed with the suspended works pursuant to Clause 40.3.
Clause 40.3:
If the progress of the Works or any part thereof is suspended on the instructions of the Engineer
and if permission to resume work is not given by the Engineer within a period of 84 days from
the date of suspension then, unless such suspension is within paragraph (a), (b), (c) or (d) of
Sub-Clause 40.1, the Contractor may give notice to the Engineer requiring permission, within
28 days from the receipt thereof, to proceed with the Works or that part thereof in regard to
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 45
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
which progress is suspended. If, within the said time, such permission is not granted, the
Contractor may, but is not bound to, elect to treat the suspension, where it affects part only of
the Works, as an omission of such part under Clause 51 by giving a further notice to the
Engineer to that effect, or, where it affects the whole of the Works, treat the suspension as an
event of default by the Employer and terminate his employment under the Contract in
accordance with the provisions of Sub-Clause 69.1, whereupon the provisions of Sub-Clauses
69.2 and 69.3 shall apply.
Moreover, suspensions of work that delay critical path activities can extend the overall
duration of the project, potentially resulting in both added costs and delaying the
scheduled project completion date.
In the event of any delay, impediment or prevention by the Employer, or other special
circumstances which may occur, other than through a default of or breach of contract by
the Contractor or for which he is responsible, the contractor has to notify the Engineer
within 28 days after such event has first arisen with a copy to the Employer pursuant to
Sub-Clause 44.2 [Contractor to Provide Notification and Detailed Particulars]. No contract
adjustment will be allowed unless the contractor has submitted the request for
adjustment within the time prescribed.
Clause 40.2
Where, pursuant to Sub-Clause 40.1, this Sub-Clause applies the Engineer shall after due
consultation with the Employer and the Contractor, determine
(a) Any extension of time to which the Contractor is entitled under Clause 44, and
(b) the amount, which shall be added to the Contract Price, in respect of the cost incurred by
the Contractor by reason of such suspension, and shall notify the Contractor accordingly,
with a copy to the Employer.
Upon receipt, the Owner will evaluate the contractor‟s request. If the Owner agrees that
the cost and/or time required for the performance of the contract has increased as a
result of such suspension and the suspension was caused by conditions beyond the
control of and not the fault of the contractor, its suppliers, or subcontractors at any
approved stage, and not caused by weather, the Owner will make an adjustment.
No contract adjustment will be allowed under this clause to the extent that performance
would have been suspended or delayed by any other cause, or for which an adjustment
is provided for or excluded under any other term or condition of this contract.
Suspension by the Contractor
Contrary to sub-clause 40.1, sub clause 69.4 depicts that the contractor too has a
contractual right of suspending the work or reduce the rate of work if employer fails to
pay the contractor the amount certified under any payment certificate approved by the
engineer within the time stated on the contract. However, this contractual privilege
should be accompanied by a notice written to the employer and the engineer prior to
suspending or reduce the rate of work.
Sub-clause 69.4 :
Without prejudice to the Contractor’s entitlement to interest under Sub-Clause 60.10 and to
terminate under Sub-Clause 69.1, the Contractor may, if the Employer fails to pay the
Contractor the amount due under any certificate of the Engineer within 28 days after the expiry
of the time stated in Sub-Clause 60.10 within which payment is to be made, subject to any
deduction that the Employer is entitled to make under the Contract, after giving 28 days’ prior
notice to the Employer, with a copy to the Engineer, suspend work or reduce the rate of work….
If the Contractor suspends work or reduces the rate of work in accordance with the provisions of
this Sub-Clause and thereby suffers delay or incurs costs the Engineer shall, after due
consultation with the Employer and the Contractor, determine:
(a) any extension of time to which the Contractor is entitled under Clause 44, and
(b) the amount of such costs, which shall be added to the Contract Price, and shall notify the
Contractor accordingly, with a copy to the Employer.
Extra work is defined as added work not provided in the original contract, but found to
be essential for the satisfactory completion of the project within its intended scope.
Extra work can be added to the project‟s scope due to a design consultant‟s error or
omission, or through changes requested by the owner or demanded by a third party.
The extra work clause is particularly important because it provides a mechanism for the
owner to introduce additional elements of work. Whenever a need for extra work arise,
sub-clause 51.1(e) of FIDIC condition of contract gives power to the Engineer to instruct
the contractor to “ execute additional work of any kind necessary for the completion of the
Works” and the contractor shall do the work in accordance with the instruction.
Eliminated work is defined as original contract items that are no longer desired or
necessary to complete the work and are, thus, removed from the project‟s scope by the
owner through a deductive change order. Eliminated work items can become the basis
for disputes, however, if the contractor has already incurred cost for those items, for
example, purchased materials. In such cases, it is customary for the contractor to
request reimbursement for actual costs incurred. Whenever needs to omit works arise
by the owner, sub-clause 51.1(b) of FIDIC condition of contract gives power to the
Engineer to instruct the contractor to “omit any such work (but not if the omitted work is to
be carried out by the Employer or by another contractor)”.
As indicated previously, after a contractor, owner, or third party has determined the
type of change, appropriate change provision has to be identified as indicated
previously, and it should then demonstrate that it has met all requirements set forth in
that provision including notice requirements if the change was identified by the
contractor. All contract documents, contemporary project records, and correspondence
used to support the position that the potential change is a legitimate contract change
should then be filed for further analysis. The following crucial steps are advised to be
followed while keeping a record for a potential change.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 48
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
To establish that a change has occurred, the contractor should identify the specific
change-related contract language associated with the alleged change. Then, referencing
the specific change provision, the contractor should demonstrate that the alleged
change is in fact a change by comparing it to the baseline requirements set forth in the
contract. After establishing that a change has occurred according to the contract, the
contractor must show that the relevant contract provision enables the recovery of
additional time or costs that result from the allowable change.
Only after a contractor has established entitlement to a change can the effect of the
change begin to be measured. Typically, a change will consist of either the addition or
elimination of work. If a change requires the addition of work, the contractor should
use the contract‟s time extension provision to determine how the delay associated with
the change should be measured and the appropriate extension of time determined.
However, if the contract‟s time extension provision does not provide direction to the
contractor on how to request additional contract time for the delay that might result
from the additional contract work, then the contractor should use an appropriate
schedule analysis technique to measure the delay to the project and the duration of the
appropriate time extension.
disseminate the information included with an owner‟s Request for Proposal (RFP) to all
affected parties, including subcontractors, and then assemble the detailed responses to
support the estimated cost or the delay resulting from the change within this specified
period.
Upon receipt of a contractor‟s response to a RFP, the owner will review the information
as described in the third activity of the change management process and respond to it
within the period of time specified by the contract. At this time, the owner will either
accept the contractor‟s proposal as submitted and generate a change order for signature
or reject the proposal, noting the basis for the rejection. As a standard practice, both of
these actions should be performed in writing for record-keeping purposes. If the
contractor‟s proposal is rejected by the owner, the contractor could then respond in
writing to the owner‟s decision or set up a meeting with the owner to negotiate the
matter until an acceptable cost and time extension are agreed upon.
If it appears that the change order process is too lengthy and impact the progress of the
work and cause further delays, the owner could choose to address the change through
means other than a bilaterally executed change order. A construction change directive
(CCD) could be issued to the contractor directing that the work be performed on a time-
and-materials basis, invoking the force account provision in the contract, with or
without a not-to-exceed amount. A unilateral change order issued by the owner to the
contractor allows the work to be performed in accordance with the changes clause of
the contract without the cost and a time extension being agreed upon by the two parties
in advance.
It is advisable for the contractor and owner to work together as diligently as possible to
agree upon the cost and time adjustment for the change. If the parties have been
working together throughout the course of the project, then their collaboration might
allow them to find a middle ground during the negotiation process based on effective
communication and trust. However, it is always possible that the two parties will not
come to an agreement. If the parties are unable to negotiate a mutually agreed upon
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 50
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
cost or time extension for the change, and if the contractor disagrees with performing
the work included in a CCD after a final decision has been made by the owner, then the
contractor‟s only remedy might be to continue its dispute through the channels
identified by the contract.
Most of the time, the contract documents log begin with the bid documents and include
the most recent drawings or sketches that might be issued as part of an RFI or
supplemental specifications by the owner or the consultants.
The creation of the contract documents log aids in establishing the baseline
requirements of the contract. As documents are revised and incorporated into the
contract, they should be available to all project personnel so that the most recent
information will be used in evaluating changes or aid in generating the as-built set of
documents as the project progresses and work is being performed.
project engineers at the beginning of the data collection as per the command given by
deputy director of Ethiopian Road Authority.
The questionnaire was carefully designed in light of getting high response rate from
respondents. The responses for the structured part of the questionnaire are based on
Likert’s-scale, ordinal data commonly used to measure attitude, providing a range of
responses to a given question or statement.
The variables of major causes of change order categories in road construction projects in
Ethiopia were identified from the desk study by clustering each reason of change order
in to major categories of change. Then, respondents are asked about their agreement on
these variables whether they can be the causes of change order or not, so that the
respondents are required to choose one of the above categories as per their attitude
toward the causes.
Depending on the response given on the causes of change order, the respondents are
once again inquired to give their response on the chance of occurrence of such variables
based on the following choices:
Not at all = 0, Unlikely = 1, Likely = 2, Almost certain = 3, and Certain = 4.
The probability to happen of each of the variables based on their chance of occurrence is
defined in percentile as follow: Not at all= 0%, Unlikely= 0% - 25%, Likely =26% - 50%,
Almost certain =51% - 99%, Certain = 100%.
At last the respondents were inquired to give their response on the type of
consequential cost impact the causes of change orders have based on their responses on
the frequency of occurrence alleged causes of change order. The responses on the
consequential cost impacts were expected to be given as: Decrement (Positive) or
Increment (Negative).
The identification of the responsible party for the causes of change order and their cost
impact was done after the required data regarding the causes and cost impacts of
change order is gathered. The questionnaires are prepared in such a way that detailed
information can be gathered in a systematically prepared matrix table.
∑( f x S )
MS = 3.10
N
Where:-
MS – Mean Score
f – Frequency of responses for each score
S – Scores given to each factor (from 0 to 4)
N – Total number of responses concerning each factor
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 54
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
The difference in ranking of two groups of respondents for several factors (such as
client Vs. consultant, client Vs. contractor, and consultant Vs. contractor) is measured
The Spearman rank correlation coefficient, ρ, for any two groups of ranking is given by
6 ×( ∑ di2 )
ρ ═ 1— 3.20
N × (N2 – 1)
The procedure used in analyzing the results was aimed at establishing the relative
importance of the various factors responsible for change orders and their cost impact.
The questionnaire gives each respondent an opportunity to express their agreement or
disagreement on whether that change order is the cause of dispute among the
contracting parties or not. As a result respondents were expected to give their response
as per the following alternatives: strongly disagree, disagree, agree and strongly agree;
frequency of occurrence of the variables of causes of change order; and the cost impacts
of each change order variables on the final cost of the project. For each variables of
change order, the percentages of respondents‟ response were ranked for analysis
purpose. On the basis of the ranking of the variables by the various groups, it was
possible to identify the most important factors that influenced change order on road
construction projects in Ethiopia.
In the desk study seventeen road construction projects constructed in almost the four
corners of Ethiopia were surveyed and 123 total reasons of change orders and their
corresponding costs were taken onto consideration. During the desk study, documents
such as project completion status reports of each project were thoroughly investigated.
This helps to understand the reasons behind each project‟s change orders, and the
change order amounts accompanied by each cause of change order. Collecting these
data helped to analyze and draw the relationship between rate of causes of change
order and the corresponding associated cost and hence the gross cost impact of the
change orders.
Other relevant documents of the projects, a total of 123 contract change orders were
found and examined as shown in table-3.
Table – 2 projects included in the desk study and their Project Cost
Percentage
Project Net Amount of
Name of Road Initial Project Final Project Of Change
Code Change
Projects Cost Order Cost order
(%)
P1 Arerti - Gobesa 444,696,050.03 (46,307,004.54)
398,389,045.49 90
P2 Sembo - Sholagebeya 613,072,806.85 (64,266,499.62)
548,806,307.23 90
P3 Gindeber - Gobesa 755,411,059.74 (68,718,699.35)
686,692,360.39 91
P4 Mojo-Ejere-Arerti 407,320,609.16 5,161,076.68
412,481,685.84 101
P5 Wolkite - Hosaina 618,998,415.32 28,279,611.75
647,278,027.07 105
P6 Wukro - Zalambessa 530,187,942.00 170,216,010.63
700,403,952.63 132
P7 Gonder - Debark 690,779,965.13 83,306,143.32
774,086,108.45 112
P8 Gondar - Dansha 369,149,638.91 (14,214,407.57)
354,935,231.34 96
Nazaret-Assela-
P9 Dodola 398,988,518.00 1,426,821.67
409,276,701.61 100
P10 Aposto - Irba Moda 660,938,029.10 109,663,504.10
770,601,533.20 117
P11 Irba Moda - Wadera 185,447,955.09 (4,342,346.28)
191,105,608.82 98
P12 Nekemte - Mekenajo 300,723,746.00 10,444,650.27
311,168,396.27 103
P13 Nekemte - Nejo 138,601,822.00 50,119,176.31
198,720,998.31 136
P14 Gore-Gambela 817,570,809.78 6,260,110.81
823,830,920.59 101
P15 Ginir - Beredimtu 541,718,515.05 30,420,788.38
572,139,303.43 106
P16 Irebti - Afdera 436,758,578.38 (2,483,53825)
434,275,040.13 99
P17 Yalo-Abala 233,086,874.01 91,769,472.51
324,856,346.52 139
During the desk study, the reasons for the change orders associated with each project
name are tabulated as shown in Table-3 with their corresponding change order
amounts.
Table – 3 Summary of Reason of Change Orders and their change order amount
Amount Name
1 Change of two types of type A houses to type B houses. (463,937.62) P1
2 Re-alignment from km 83+008.922 to km 85+345.057
Back/88+003.497 Ahead. (24,135,269.04) ―
3 Re-grading from km 79+060 to 79+600. 75,990.40 ―
4 Realignment from km 88+541.107 to km 89+216.98
Back/89+280.899 Ahead. (3,274,904.04) ―
5 Re-alignment from km 94+065.923 to km 96+409.492
Back/96+393.625 Ahead. (3,612,475.03) ―
6 Re-grading of the vertical alignment from km 100+100 to
100+860 (end of the project). (734,936.32) ―
7 Re-alignment from km 94+390 to km 95+209.4 Back/95+200
Ahead. 1,672,315.14 ―
8 Re-alignment from km 96+000 to km 98+446.216
Back/98+500 Ahead. (14,069,024.63) ―
9 Omission of the modified vertical alignment on V.O No.7
and to follow the original contract design. 734,936.32 ―
10 Re-alignment from km 94+765 to km 95+043 Back/95+033
Ahead. (1,738,203.17) ―
11 Re-alignment from km 91+499.641 to km 91+662
Back/91+679 Ahead. (761,496.55) ―
From table-3, it can be easily seen that a substantial amount change order occurs in those
road construction project under the study. As it is depicted in table – 2, the total project
cost of those projects under consideration was 8,143,451,307.55. However, as a result of
the total amount of change order, the total project cost increased by an amount of
410,596,232.76 birr. This amount is around five percent (5%) of the total sum of project
cost of the projects under consideration.
Hence, the desk study has proved the existence of change order in the road
construction project in Ethiopia to the extent that the causes and cost impact of change
orders on road construction projects in Ethiopia must be studied so that the stake
holders in the construction industry be aware of the causes of change orders and their
cost impact while managing the construction contracts.
Those reasons of change order depicted in table – 3, are grouped in to major categories
of causes of change order along with their corresponding change order amount as
shown in the tables 5 (a) – (f).
Table – 5 (a) Change orders due to Design Errors and Omissions
S/No Reasons of Change Order Change order Project
Amount
Change order
S/No Reasons of Change Order Amount Project
1 Increase in BOQ quantities of bridge over Sanja river at P8
km 66+927 887,971.81
2 Reduction in quantity of Crushed stone base course (12,632,279.88) “
3 Reduction in quantity of primer coat MC-30 cut back
bitumen at 1.1 liter per square meter (1,384,600.00) “
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 73
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
4 25% increase in BOQ quantity for Bill No. 2.04 (Pay item
No. 42.03 (cut and borrow to fill) 7,194,457.50 “
5 Change in quantity for Elastomeric bearings for bridges
item No. 5.13 61,456.37 “
6 Review of design at Bridges km 25+345 & 26+784 (690,346.85) P12
7 Review of design at Logita Bridge km 36+470 5,379,507.05 “
8 Review of design at Gelana Bridge km 33+904 692,836.24 “
9 Review of design at Bonewa Bridge km 49+672 5,049,614.37 “
One of the key questions presented at the beginning of this research was, “What are the
causes of most contract changes in Ethiopian road construction projects?” And as it
was mentioned above, form seventeen projects about 123 change order records were
analyzed to answer this question. Of the changes included in the study a review of the
project record data showed that 40.8% were caused by design errors and omissions,
29% were change of scope by owner, 15.8% resulted from other causes, 7.5% were
caused by unforeseen conditions. The rest were caused by value engineering and force
majeure (see table-6 below).
Number Total
No Major Categories of Causes of of Change order
Change order Change order (In %)
1 Design errors and omissions 49 40.8
2 Change of scope 35 29.3
3 Unforeseen conditions 9 7.5
4 Value Engineering 7 5.8
5 Force majeure 1 0.8
6 Others 19 15.8
TOTAL 123 100
The causes of change order from the questionnaire survey are identified based on
respondents‟ response on each change order category by the frequency of their
occurrence during the construction period. The factors which are chosen by the
respondents as causes of change order on road construction projects in Ethiopia are
identified from the returned questionnaires based on the mean scores (MS) of the three
groups of respondents, clients, consultants and contractors for each variables of change
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 76
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
order. In this research variables of change order which have a mean score of greater
than 2 are taken as causes of change order; since a mean score of less than 2 means the
respondents do not agree that the variable could be considered as a cause of change
order.
Table - 7, Frequency of occurrence of Change order categories based on the responses of
clients, consultants and contractors;
Major Categories of Causes of Mean Score (MS) Weighted
No. Change Order Employer Consultant Contractor Average
As we can observe from the weighted average column of table – 7, the major categories
of causes of change order, in their descending order, are design errors and omissions,
change of scope, unforeseen conditions, value engineering, others (like administrative
issues and the interests of third parties) and force majeure. Due to the fact that, the reasons
behind the occurrence of each change order are the results of some unfulfilled interests
or needs of either of the contracting parties, during the implementation of the project
ideas in to the ground, identifying the responsible party for each category of change
order will give meaning to the research. Hence, the respondents once again asked to
identify the contracting party which could be responsible in relation to each cause of
change order category. The identification of responsible party is useful to understand
who causes change order so that the liable party shall be accountable contractually.
The data gathered during the desk study regarding the reasons of change order proves
that most of the change orders were the results of poor design and contract
administration, which can be minimized before the implementation of project. As a
result, employers believe that if designs, specifications and contract documents were
prepared correctly from the start, the rate of occurrence of change orders would have
been minimal.
However, consultants on the other extreme blame that it is the employer that initiate
changes orders due to their rarely satisfying demands. To make the research free of any
biases, responsibility of each contracting party in causing the change orders was rated
during the questionnaire survey and the accountable party was selected based on the
maximum percentile on each change order category. The identification of the
accountable party for causes of change orders is depicted in Table – 8 below.
For the question that inquired to identify which contracting party is accountable for the
occurrence of each category of change order causes, the respondents give their
responses to ascertain the liability of the contracting party relative to each category of
change order cause. As a result, 76.38 percent of the respondents make consultants to be
liable for the occurrence of most design errors and omissions. Regarding change of scope,
the second category of causes of change order, 65.79 percent of the respondents agree
that employers are accountable for the occurrence of most scope changes. The other
three change order categories, unforeseen conditions, value engineering and force majeure are
also caused by consultants, contractors and other causes with accountability percentage
of 57.89, 52.63 and 68.48 respectively. In a nut shell, when change order categories
analyzed together, respondents assure that 36 percent of the changes are caused by
consultants, 26 percent caused by employers, 21 percent by other causes and 17 percent
by contractors.
Percentage of Accountability
Employers
Others
21%
26%
17%
36%
Contractors
Consultants
The respondents were also asked to explain their reasons why they make each specific
contracting party being accountable for the cause of each category of change order. And
from the feedback given by the respondents, it is due to consultants‟ lack of required
data, ambiguous design details, design discrepancies, conflict between contract
documents; inadequate working drawing details etc. make consultants liable for the
occurrence of change orders.
Employers are also blamed for having inadequate scope of work, inadequate project
objective, frequent change of ideas, being delayed in resolving right-of-way issues.
Regarding to the contribution of contractors to change orders is expressed in relation to
financial shortages, lack of skilled man power, lack of knowledge of contract
management, etc.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 79
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
Apart from those parties mentioned above, other causes such as third parties, like
utility agencies and governmental bodies are blamed for not cooperating with
contracting parties when their cooperation is needed. In addition to these, inflation or
increase in the cost of construction materials, change in foreign exchange rate are found
to be caused by government related actions.
As shown in the above table-9, those causes of change included in value engineering
have total change order amount of birr 23,861,361.94. This amount is a decrement of
change order amount, the impact of those reasons of causes of change order categorized
under value engineering would be considered as positive impact since they are savings
to the employer. Whereas, except value engineering all other major categories of change
orders have a total change order amount of birr 410,596,232.76; which is an incremental
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 80
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
cost impacts which are considered as expenses to the project owners. However, the
combined impacts of all categories of change order shows an incremented (negative)
impact of birr 386,734,870.82.
Therefore, when we look at the cost impact of value engineering from the desk study,
we can conclude that, in this specific study, value engineering has a reduction cost
impact in those road construction projects under consideration. However, the rest
categories of causes of change order have incremental cost impacts.
This implies that the total project cost of those projects under consideration, which was
birr 8,143,451,307.55, now increased by 5 percent to 8,530,186,178.37 birr. 52.4 percent of
this increment is caused by change of scope; design errors and omissions share 38.6 percent,
and other causes have 7.6 percent contribution. Though they are minor, 1.2 and 0.2
percent, the rest are contributed by unforeseen conditions and force majeure respectively in
descending manner of their contribution.
Consequently, from the analysis of those categories of change order with respect to their
accompanied change order amount we can observe that change of scope contribute
huge share to the cost increment. The next greater cost increment was resulted due to
design errors and omissions and the rest by other causes, unforeseen conditions and
force measure in their descending order of contribution on the total cost increment.
In addition to the data gathered during the desk study about the consequential cost
impacts due to change orders, questionnaire survey was also conducted to assess the
cost impact of change orders from the respondents‟ perspective. During cost impact
analysis, respondents were asked if change orders are one of the causes of dispute
among the contracting parties. If so, they were also requested whether it is due to
consequential cost impact. As a result, 82 percent of the respondents agreed that change
orders, most of the time, are causes of dispute among contracting parties due to their
accompanied cost impact.
From the respondents‟ response the mean score (MS) of the frequency of occurrence of
cost impact due to each major category of causes of change order is analyzed as shown
in the table – 10 below.
Table – 10, Mean Score (MS) of Cost Impact of Major Categories of Change Order causes
No. Major Categories of Causes Mean Score (MS) Weighted
Change Order Employer Consultant Contractor Average
1 Design errors and omissions 2.70 2.23 3.45 2.80
2 Change of scope 2.07 2.15 2.91 2.38
3 Unforeseen conditions 2.36 2.00 2.36 2.24
4 Value Engineering 2.36 2.54 3.09 2.66
5 Force majeure 2.86 2.46 3.45 2.92
6 Others - - - -
As depicted on Table – 10 above, the weighted average of the mean scores of the
respondents show that force majeure was ranked first for its consequential incremental
cost impact. This is so, because, respondents may understand the question from point of
view of the catastrophic effects of force majeure. Design errors and omissions became the
next category of causes of change order which can be accompanied by considerable cost
impact. Value engineering is the third category of cause of change order for its cost
impact when exists during the construction. The rest categories of causes of change
order having undeniable cost impact are change of scope and unforeseen conditions in their
descending order. Other causes did not be ranked by the respondents as a potential cost
incurring causes of change order.
This questionnaire response regarding the cost impact contradicts the results obtained
during the desk study, because during the desk study it was found that the change of
scope contributes much to the total cost increment (52.4 percent) and other causes had
considerable shares (7.6 percent) of the cost increment during the desk study. However,
in the questionnaire survey, the design errors and omission being ranked higher for its
consequential cost impacts and other causes were not considered as potential cost
incurring categories of change order.
However, both the desk study and the responses analyzed from the questionnaire
survey show that design errors and omissions are major causes of change order
categories having considerable amount of incremental cost impact.
sources of change orders due to their improper designs and inefficient contract
management. This leads employers to unexpected additional project costs and project
delays.
In a nut shell, cost impacts due to change order in Ethiopian road construction projects
incurs extra budget, which is expected to be financed from the country‟s limited
economy, which lead to budget deficits for construction projects. As a result, new
projects that the government planned to promote and implement could either be
extended other fiscal years‟ plan or canceled totally.
In order to decide whether to accept or reject the null hypothesis the level of
significance, 95% (P=0.05) is used. This allows to state whether or not there is agreement
between respondents‟ opinion.
If the calculated value of ρ is greater than the critical value, Ho is rejected; i.e there is
evidence of a statistically significant agreement between the groups. If the calculated
value of ρ is less than the critical value, Ho is accepted; i.e there is no evidence of a
statistically significant agreement between the groups.
Table – 11, Summary of correlation test on the ranking of variables of causes of change order
based on chance of occurrence.
Significance Accept/Reject
Groups
Non-
1 Consultant Vs. Contractor 0.819 0.886 Significant Accept
In this case, with a significant level of 95% (P=0.05) the calculated values of the
Spearman‟s correlation coefficient, ρ, for group-1 (i.e. Consultant Vs. Contractor) and
group-3 (i.e. Contractor Vs. Employer) are less than the critical value. As a result, for these
two groups the null hypothesis becomes accepted. This is due to the fact that there is no
significant agreement between the two groups. However, the calculated values of ρ for
group-2 (i.e. Consultant Vs. Employer) is greater than the critical value. Therefore, the
null hypothesis is rejected; and hence we can conclude that there is agreement between
the respondents.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 85
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
From table-11 it is observed that the average calculated values of Spearman‟s correlation
coefficient, rho (ρ) is 0.845 which is less than the critical value of 0.886. This shows the
absence of significant agreement between the attitudes of the respondents in all the
three groups. In other words the correlation between the respondents attitude is
relatively weak. This implies that most of the respondents have different perception on
the frequency of occurrence of causes of change order.
causes of change orders and their consequential cost impact. A desk study and questionnaire
surveys were used to identify the existence and extent of causes and cost impacts of
change order on road construction projects in Ethiopia.
Based on this finding of the desk study and questionnaire surveys, the following
conclusions are drawn:
1. The most common reasons of change order encountered during the construction of
road projects in Ethiopia are categorized into the following major causes of change
orders: Design Errors and Omissions, Change of Scope, Unforeseen Conditions, Value
Engineering, Force Majeure and Others.
2. From the total change orders encountered 40.8 percent of the change orders were
caused by design errors and omissions, 29 percent occurred due to change of scope by
owner, 15.8 percent resulted from other causes, 7.5 percent were caused by unforeseen
conditions. The rest were caused by value engineering and force majeure.
3. The frequency of occurrence of changes in Ethiopian road construction projects
shows that design errors and omissions are the most frequent cause of change order
followed by change of scope, unforeseen conditions, value engineering, others and force
majeure respectively in their descending order of occurrence.
4. Of the three parties involved in the construction, 36 percent of the changes orders
are caused by consultants, 26 percent caused by employers, 21 percent by other causes
(third parties such as regulatory bodies) and 17 percent by contractors.
5. Regarding consequential cost impacts occurred due to the change orders, the desk
study revealed that except value engineering, all other causes of change order
categories have incremental (negative) associated cost impacts. Of the total
incremental costs, 52.4 percent are caused by change of scope; 38.6 percent caused by
design errors and omissions, and 7.6 percent by other causes. Though they are minor, 1.2
and 0.2 percent respectively, the rest are contributed by unforeseen conditions and
force majeure.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 87
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia
5.2 Recommendations
Forwarding recommendations was one of the objectives of the research. Therefore,
based on the findings of the research, the following recommendations are made:
1. As a promoter of the projects, the employer (such as the Ethiopian Roads Authority
in the context of this research), should undertake thorough and comprehensive
project feasibility study before the implementation of the projects to their
material equivalent. This would avoid the time and again change of project ideas
by the employer. To help minimize such change of ideas, it is better if the
opinions of other stake holders are properly addressed. And once the project is
started, the employer should stick to the very first of its project ideas as much as
possible to avoid the scope changes that can be encountered at some point of the
project‟s life.
2. Consultants should play their role, as per the expected disciplinary requirements,
from the project inception to its implementation on the ground. This is so,
because it is the consultant‟s responsibility to coordinate all sorts of information
that can satisfy the employers‟ and other stake holders‟ interest. Hence, the
consultant should do the following before the commencement of the project:
Collect actual and genuine field data during site investigation.
Make proper and holistic feasibility study that can accommodate different
stake holders‟ interest.
Make a peer review on the feasibility study and collect professional
opinion as an input during design. This would minimize change orders
due to unforeseen conditions.
Make feasible design that can at least minimize future changes due to
design errors and omissions.
Prepare clear, concise and comprehensive contract document which can
accommodate changes and resolve disputes that can occur as a result of
change orders.
3. As a key practical player of the construction industry, contractors are
accustomed to different types of change orders. Therefore, contractors are
recommended to:
Foresee changes that can be encountered during project implementation
and make aware other parties on how they are going to be handled.
Avoid interests of extra profits that could be generated as a result of
changes.
REFERENCE
1. Alaa Zeitoum and Garold Oberlender: Early warning Signs of Project Changes,
Oklahoma State University/CII source document No.91, April 1993.
2. Alan T., Gordon R. (2004). Civil Engineering Project Management. Oxford: Elsevier
Butterworth.
3. Arain, F.M., Assaf, S.A. & Low, S.P. (2004) Causes of discrepancies between design
and construction. Architectural Science Review, 47(3), pp.237-249.
4. Assaf, S.A., Al-Khalil, M. & Al-Hazmi, M. (1995) Causes of delays in large building
5. Chappell, D. & Willis, A. (1996) The Architect in Practice. (8th edition) Blackwell
Science Ltd, USA.
6. Clough, R.H. & Sears, G.A. (1994) Construction Contracting. (6th edition) John Wiley
& Sons Inc., New York.
7. Construction Industry Institute (CII) Publication 5-1: Impact of Various Contract Type
and Clauses on Project Performance. The University of Texas at Austin, April 1986.
9. Construction Industry Institute (CII) Publication 6-6: Work Packaging for Project
Control. The University of Texas at Austin, April 1988.
10. Cox, S. & Hamilton, A. (1995) Architect’s Job Book. (6th Edition) RIBA Publications,
Royal Institute of British Architects, UK.
11. Dell‟Isola, A.J. (1982) Value Engineering in the Construction Industry. Van Nostrand
Reinhold, New York.
12. Edward R Fisk: Construction Project Administration, third edition. John Wiley & Sons
Inc. New York 1988.
13. Fisk, E. R. (1997) Construction Project Administration. (5th edition) Prentice Hall, New
Jersey.
14. Geok, O.S. (2002) Causes and Improvement for Quality Problems in Design & Build
Projects. Unpublished B.Sc. Thesis, National University of Singapore. Singapore.
15. H. Randolph Thomas and Carmen L. Napolitan: The Effects of Changes on Labor
Productivity: Why and How much, CII source document No.99, The Pennsylvania State
University, August 1994.
17. Ibbs, C.W. & Allen, W.E. (1995) Quantitative Impacts of Project Chang. Construction
Management Technical Report no.23, University of California at Berkeley, USA.
18. Ibbs, W., Nguyen,L., & Lee, S. (2007). Quantified Impacts of Project Change. Journal
of Professional Issues in Engineering Education and Practice, 45-52.
19. James L., Burati Jr., Jodi J. F., & William B. L.(1992). Causes of Quality Deviation in
20. Mokhtar, A., Bedard, C. & Fazio, P. (2000) Collaborative planning and scheduling of
interrelated design changes. Journal of Architectural Engineering, ASCE, 6(2), pp.66-75.
21. Moselli,O., Assem,I., & El-Rayes,K.(2005). Change Orders Impact on Labor
Productivity. Journal of Construction Engineering and Management, 354-359.
22. O‟Brien, J.J. (1998). Construction Change Orders: Impact, Avoidance, Documentation,
McGraw-Hill, New York.
23. Oracle Publication: Change Management Best Practices for the Engineering and
Construction Industry, Journal of Construction Technology and Management, Redwood
Shores, USA. April 2009.
24. Paul M., Timothy R.B. (2010). Change Orders and Lessons Learned, Report of
Kentucky Transportation Center, Kentucky USA.
25. Robert K. Cox: Managing Change Orders and Claims, Journal of Management in
engineering, January/February 1997.
26. Sanvido, V., Parfitt, K., Guvensia, M. & Coyle, M. (1992) Critical success factors for
construction projects. Journal of Construction Engineering and Management, ASCE,
118(1), pp. 94-111.
28. Thomas, H.R. and Napolitan, C.L. (1994) The Effects of Changes on Labor Productivity:
Why and How Much. CII Document 99, The Pennsylvania State University, USA.
29. Weston Hester, John A. Kuprenas, T.C. Chang: Construction Changes and Change
Orders: Their Magnitude and Impact, The University of California-Berkley/CII source
document No. 66, April 1991.
30. Wu, C., Hsieh,T., & Cheng, W.(2005). Statistical Analysis of Causes for Design change in
Highway Construction on Tiwan. International Journal of Project Management, 554-
563.
Appendix B
Table C Critical values of ρ (rho) at various levels of probability (Spearman rank correlation
coefficient)
For any N the observed value of ρ is significant at any level of significance if it is equal to or
larger than the critical values shown in the table
14
Note: when there is no exact number use the next lowest number.