Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Ethiopia 3

Download as pdf or txt
Download as pdf or txt
You are on page 1of 94

Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

ASSESSMENT OF CAUSES AND COST IMPACT OF


CHANGE ORDERS ON ROAD PROJECTS
IN ETHIOPIA

BY
MEKONNEN BESHAH

A THESIS SUBMITTED TO THE SCHOOL OF GRADUATE STUDIES OF ADDIS ABABA UNIVERSITY


IN PARTIAL FULFILMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTERS OF
SCIENCE IN CONSTRUCTION TECHNOLOGY AND MANAGEMENT

SEPTEMBER 2015

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 1
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

ADDIS ABABA UNIVERSITY


SCHOOL OF GRADUATE STUDIES

ASSESSMENT OF CAUSES AND COST IMPACT OF CHANGE ORDER

ON

ROAD PROJECTS IN EHTIOPIA

BY

MEKONNEN BEHSAH

APPROVED BY THE BOARD OF EXAMINERS

Name Signature Date

________________________ _____________________ _____________________


ADVISOR

________________________ _____________________ _____________________


EXAMINER (INTERNAL)

________________________ _____________________ _____________________


EXAMINER (EXTERNAL)

________________________ _____________________ _____________________


CHAIR PERSON
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 2
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

TABLE OF CONTENT

TABLE OF CONTENT ................................................................................................................ i


LIST OF TABLES........................................................................................................................ iii
ABBREVIATIONS ..................................................................................................................... iv
ACKNOWLEDGEMENTS........................................................................................................ v
ABSTRACT...................................................................................................................................vi

1. INTRODUCTION……………………..……………………………………………….……1
1.1 Significance of the Study …………………………..…………………………………..2
1.2 Research Outline ………………………………………………………………………..3
1.3 Statement of the Problem …………………………….………………………………..4
1.4 Objective of the Study ……………………………..…………………………………...4
1.5 Scope and Limitations ………………………..………………………………………...4
2. LITERATURE REVIEW …………………………………………………………………….6
2.1 Construction Changes and Change Orders ………………………………………….6
2.1.1 Construction Changes …………………..….……………..………………….…6
2.1.2 Construction Change Orders ………………...………………..……………….9
2.2 Causes of Change Order ………………………...……………………………………10
2.2.1 Change Orders Caused by Project Owners ……….………………………..10
2.2.2 Change Orders Caused By Consultant …………………………………….. 11
2.2.3 Change orders Caused by Contractors …………………..………………… 14
2.2.4 Other Causes of Changes ……………………………………………………..17
2.3 Impacts of Change Orders …………………………………………………………....18
2.3.1 Direct Cost Impact ……….……………………………………………………19
2.3.2 Direct Schedule Impact ……………………………………………………….22
2.3.3 Consequential Impacts ………………………………..………………………23
2.4 Legal Aspect of Change Orders ………………….....……………………………..…25
2.4.1 Types of Construction contracts ……………..………………………………25

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 3
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

2.4.2 Change Orders and Contract forms …………………………………………28


2.5 Change Order Management................………………………………………………..29
2.5.1 Contract Requirement Identification ………………………………………..30
2.5.2 Potential Changes Identification ……………………………………………..33
2.5.3 Measuring the Effect of Change Order ……………………………………..41
2.5.4 Negotiation and Execution of Change Order ………………………………42
2.5.5 Recording the Executed Changes ……………………………………………43
3. RESEARCH DESIGN AND METHODOLOGY………………...………………………44
3.1 The Study Approach and Research Type ………………………….……………….44
3.2 Data Source and Collection ………………….………………………………………44
3.3 The Research Population …………………….………………………………………46
3.4 Method of Analysis ………………………………..………………………………….46
4. DATA ANALYSIS AND DISCUSSION ………………………………………………...48
4.1 Questionnaire Response Rate ………………………….……….……..…………….49
4.2 The Existence and Extent of Change Orders ……….…………….………………..49
4.3 Assessment of Major Causes of Change Order Categories …….………………...59
4.4 Assessment of Cost Impact of Change Orders …………………….………………73
4.5 Test for Agreement ………………………………………………….………………..76
5. CONCLUSIONS AND RECOMMENDATIONS ………………………………………80
5.1 Conclusion ………………………….…………………………………………………80
5.2 Recommendations ……………………………………………………………………82

REFERENCE …………………………………………………………………………………...83

APPENDIX – A (Questionnaire) ……………………………………………………………..86

APPENDIX – B (Spearman rank correlation coefficient) .………..…………………….....89

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 4
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

LIST OF TABLES

Table-1:- Summary of Respondents‟ Response Rate

Table – 2:- Projects included in the desk study and their Project Cost

Table – 3:- Summary of Reason of Change Orders and their change order amount

Table – 4:- Major categories of Change Order and Reasons of change

Table – 5(a):- Change orders due to Design Errors and Omissions

Table – 5(b):- Change orders due Change of Scope

Table – 5(c):- Change Orders due to Unforeseen Condition

Table – 5(d):- Change orders due to Value Engineering

Table – 5(e):- Change Orders due to Force majeure

Table – 5(f):- Change orders due to other causes

Table – 6:- Summary of Major Causes of Change order category by percent

Table – 7:- Frequency of occurrence of Change order categories based on the responses of

clients, consultants and contractors;

Table – 8:- Percentage of Accountability for the cause of change order

Table – 9:- Cost impacts of change orders and their total change order amount percentile

Table – 10:- Mean Score (MS) of Cost Impact of Major Categories of Change Order causes

Table – 11:- Summary of correlation test on the ranking of variables of causes of change

order based on chance of occurrence.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 5
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

ABBREVIATIONS
 FIDIC - Federation Internationale Des Ingenieurs-Conseils
 PCO - Potential Change Order
 RFI – Request for Information
 RFP - Request for Proposal
 CCD - Construction Change Directive
 CII – Construction Industry Institute
 MS – Mean Score

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 6
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

ACKNOWLEDGEMENT
I am very grateful for the almighty Lord for granting me this opportunity to undertake
this research work. TO HIM ALONE BE THE GLORY!
I am thankful for Ethiopian Roads Authority (ERA), for the sponsorship of my post
graduate study at Addis Ababa University institute of Technology and all regional
contract administration directorates of ERA and staffs for their appreciated assistance
during my desk study.
My special thanks solely forwarded to my advisor, Prof. Dr. Ing. Abebe Dinku; first of
all for his iconic, ethical and professional personality he boldly wrote on my heart
alongside his lectures, it is much more than any material equivalent. And second, for
his willingness to be my advisor in this research, his responses, guiding comments and
most of all for sharing his precious time.
Finally, I wish to express my sincere gratitude to my family and all my friends who
encourage me to accomplish this research. God richly bless you all!

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 7
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

ABSTRACT
This research makes assessment on the causes and cost impacts of change orders on
road projects in Ethiopia. Emphasis is given to the identification of the root causes of
change order categories from seventeen road project with a total of 123 reasons of
causes of change order. As a result the most common reasons of causes of change order
are categorized as: design errors and omissions, scope change, unforeseen conditions, value
engineering, force majeure and others. Of the total reasons of causes of changes orders
included in the study, 40.8% were caused by design errors and omissions, 29.3% by
change of scope by owner, 15.8% resulted from other causes, 7.5% were caused by
unforeseen conditions, 5.8% by value engineering and 0.8% due to force majeure.

In addition to identifying the major categories of change orders, the consequential cost
impacts of these change orders were analyzed. As a result, those reasons of change
order categorized under value engineering have a decrement cost impact which saves an
amount of birr 23,861,361.94. The reasons of change orders in this category have
positive cost impact on the total project cost as they are a saving to the project owner.
However, the rest categories of causes of change order have increment or negative cost
impacts with a total change order amount of birr 410,596,232.76. From this total cost
increment 52.4% is caused by change of scope; 38.6% by design errors and omissions, and
7.6% contributed other causes. Though they are minor, 1.2% and 0.2%, the rest are
contributed by unforeseen conditions and force majeure respectively in descending manner
of their contribution.

Spearman rank order correlation analysis was used to evaluate whether consensus of
opinions exists between groups of respondents. From the analysis of the results it can be
concluded that the correlation between the attitudes of the respondents in all the three

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 8
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

groups is relatively weak. This is so, because two third of the groups assure the absence
of significant consensus.

Key words: change, change order, change order categories, cost impacts of change order.

1. INTRODUCTION
Many times, change is necessary for the success of a project. “change, defined as any
event that results in a modification of the original scope, execution time, or cost of work,
happens on most projects due to the uniqueness of each project and the limited
resources of time and money available for planning” (Hanna, 2002). While change
orders are necessary to address unforeseen conditions and other unavoidable or
unanticipated occurrences, they tend to negatively affect the progress of a construction
project. In most public works, change orders are the main reason for construction delays
and cost overruns (Wu, 2005). Change orders also lead to a decline in labor efficiency,
loss of man hours, and costly disputes (Moselhi, 2005).

It is important to understand the impact change orders have on project performance,


but it is also important to understand the causes of change orders. Since change orders
affect the relationship between contracting parties, those parties participated in
construction must be aware of the reason behind the change orders so that any change
order that could arise during the life of a project can be handled properly. Due to the
fact that construction contract is signed under the principle of good faith, which means
that the parties trust each other to perform according to the contract and that the
contract is fair with no intention of taking advantage of the parties during the life of the
contract. However, as soon as the contract needs to be modified by generating a change
order, the behavior of the parties could changes in relation to the initial good faith
environment for this change orders are accompanied by consequential impacts on
construction time and/or budget.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 9
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

This research aims to study change orders on road construction projects in Ethiopia
which occur most frequently and analyze their causes and the cost impact they impose
on the projects.

1.1 Significance of the study


Over the last two decades, the construction industry of Ethiopia has boom more than
any time in the history of the county‟s construction industry. As compared to other
economic sectors, the construction sector has invested huge capital investment for the
construction of different infrastructures such as dams, railroads, roads of different
category, building complexes, water supply facilities, etc. However, of this capital
investment, relatively considerable amount was allocated to the road sector for the
development of road networks throughout the country. An assessment of fifteen years
(July 1997 to June 2012) performance of road sector development program (RSDP) made
by Ethiopian Roads Authority depicts that over the fifteen years of the RSDP physical
works have been undertaken on a total of 81,363km of roads. The total budget invested
during this period amounted to Birr 107.8 billion.

However, relatively several road projects in Ethiopia have encountered construction


changes due to various causes during the course of their implementation. Some of the
most common causes of changes in the construction sector are change of scope of work
due to infinite needs of the owner, market conditions may impose changes to the
parameters of the project, and technological developments may alter the design and the
choice of the engineer. The engineer‟s review of the design may bring about changes to
improve or optimize the design and hence the operation of the project. Further, errors
and omissions in construction contract coupled with poor contract administration skills
and inability to predict changes may force a change. All these factors and many others
necessitate changes that are costly and generally un-welcomed by all parties.

Despite the fact that changes are inevitable phenomena in the construction projects,
emphases must be given to accommodate changes in construction contracts. A change

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 10
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

clause has to be incorporated to define the way how owner, consultant and contractor
handle changes. Therefore, change clauses and procedures must be set to process a
change from the conceptual development until it is realized to its material equivalent in
the field.

Hence, this research aims to assess causes of change orders and their cost impact on
road construction projects in Ethiopia and lay the foundation for future research so that
problems related to changes and change orders can be properly addressed.

1.2 Research Outline


This thesis comprises of three major chapters. Chapter one is an introduction explaining
the importance of this research study, defines the problem of the statement, specifies the
objectives, scope and limitations.
Chapter two is the review of literature on the subject of change in general and change
orders in particular. The chapter is divided into five sections: construction change and
change order, causes of change of change order, impacts of change order, legal aspects
of change order and change order management. Construction change and change
orders explains construction changes in general and change orders in particular. The
legal aspect of change focuses on types of construction contracts and the way how
change orders threated in those contract forms. As the name indicate, the cause and
effect section deals with causes and effects of change order of change orders in
construction. Change order management is about identifying contract requirements,
identifying potential changes, determining entitlement, negotiation and recording the
executed changes.
Chapter three, which is the research design and methodology, consists of four sections, the
study approach and research type, data source and collection, the research population
and finally method of analysis.
Chapter four, the data analysis and discussion, includes the questionnaire response rate,
the existence and extent of change orders, assessment of major causes of change order

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 11
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

categories, assessment of cost impact of change orders and test for agreement. The fifth
and the last chapter, conclusion and recommendation, explicitly put the conclusions of the
research and make a recommendation on how to minimize changes and change orders
in road construction projects in Ethiopia.

1.3 Statement of the Problem


Delivering the project to scope, budget and schedule is the number one challenge in
dealing with change order (The Economist, 2012). Most of the time, this is due to lack of
adequate knowledge to predict and manage changes which may be encountered during
the life of a project. Though changes in construction projects are very common and
likely to occur from different sources at any stage of a project, they may have
considerable impacts on the cost of the projects.
Owing to this fact, what are the causes for most contract changes in Ethiopian road
construction projects? And what kind of cost impact do these causes impart on total
project cost? This thesis is therefore, an attempt to make assessment on causes and cost
impacts of change orders on selected road projects in Ethiopia.

1.4 Objective of the study


The following are the specific objectives of the research.
To undertake thorough discussion on types of construction change and change
orders their causes and impacts in general.
To make assessment on the causes of change orders and their cost impact in road
construction projects in Ethiopia.

To formulate conclusions and recommendations.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 12
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

1.5 The Study Scope and Limitation


Change order in road construction projects are caused by many factors. Each cause of
changes has different rate of occurrence and cost impact. Therefore, this research work
is designed to make assessment of the causes and cost impacts of change orders based
on the categories of causes of change orders. To accomplish this, the research is limited
to those change orders arise in selected road projects constructed between years 2003 to
2013 by Ethiopian Roads Authority. Hence, the epicenter of the research shall spin
about the causes and cost impact of construction change orders.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 13
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

2. LITERATURE REVIEW
2.1 Construction Changes and Change Orders
In a perfect world changes will be confined to the planning stages. However, late
changes often occur during construction, and frequently cause serious disruption to the
project (Oracle, 2009). In these circumstances, decisions are being made under pressure
and cost and time invariably dominate the decision making process (O‟Brien, 1998;
Arain, 2005). Most forms of contract for construction projects allow a process for
changes. Even though there may be a process in place to deal with these late changes,
cost and time invariably dominate the decision making process. If the change affects the
design, it will impact on the construction process and, quite possibly, operation and
maintenance as well (Oracle, 2009).
To overcome the problems associated with changes to a project, the project team must
be able to effectively analyze the change and its immediate and downstream effects
(CII, 1990). An effective analysis of change and change orders requires a comprehensive
understanding of the root causes of changes and their potential downstream effects. To
manage a change means being able to anticipate its effects and to control, or at least
monitor the associated cost and schedule impact (Hester, 1991).

2.1.1 Construction Changes


A change is defined in literature as any deviation from an agreed upon well-defined
scope and schedule. Stated differently, a change is typically understood as the
difference between the contract requirements as set forth in the original agreement
between the parties and the requirements imposed subsequent to this agreement (Fisk,
1988). Construction contracts are assumed to be complete before they are implemented.
However, changes can be initiated by all parties in the construction process. All

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 14
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

changes, however, must be approved by Owner before implementation. CII Publication


6-10 (1990) summarizes initiation of change orders as follows:

1. Owner may request/order a change, usually a scope change.


2. Engineer may originate a change because of differing site conditions or new
governmental regulations etc.
3. Project management firm/person may originate a change, usually in schedule.
4. Contractor may initiate a change due to design errors, value engineering, or field
requirement.
In addition, construction changes could occur at any of the three stages of construction.
This is to mean that such changes may occur during specification preparation, ether by the
owner‟s over ambition or the consultants‟ impracticable material and design
specifications; at the design stage by the designer or consultant impractical design which
may not consider the actual site condition; and finally during the construction stage by
contractors‟ lack of special skills and frequent change demands of the owners.
Though the contract defines what constitutes a change, literatures categorize changes as
directed changes, constructive changes and cardinal changes (CII Publication 6-10 (1990), Fisk
1988, Cox 1997). Hence, each of these changes will be discussed as follow:

2.1.1.1 Directed changes


Directed changes are changes that are directed by the owner and understood by the
owner to be changes to the contract. Subject always to the specific requirements of the
contract and examples of such changes include:
Addition or deletion of work
Revision to material specifications
Revision to project phasing
Change to site access or hours of operation
Change to contract duration

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 15
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

2.1.1.2 Constructive Changes


Constructive changes typically resulted from a failure to do or not do on part of the
owner or owner‟s representative. This type is not initially documented as a change and
hence becomes a potential source of dispute. The failure of the owner or owner‟s
representative may take the form of error in design or drawings, wrong Engineer‟s
interpretation of contract documents, change in construction sequence imposed by a
construction requirement etc. Depending on the specific requirements of the contract,
constructive changes include the following:

Failure to disclose material information


Impossibility or impracticality of performing the work as designed
Imposition of joint occupancy or use of the project before completion
Slow turnaround of submittals and requests for information
Untimely inspections
Constructive changes are usually more difficult to recognize than directed changes and,
therefore, often become the basis for a dispute, or in the worst case, a formal claim.

2.1.1.3 Cardinal Changes


Cardinal change is a change outside the scope of the contract. This kind of change has the
effect of making the work to be performed fundamentally different from the work the
parties agreed to when the contract was bid and awarded. And it is executed only after
complete redefinition of the scope and re-negotiation of the contract.
This type of change may not necessarily be a single change but can be the result of a
number of changes that have the net effect of modifying the original scope. Cardinal
changes are typically viewed as a breach of contract by the owner and a contractor is
not obligated to proceed with a cardinal change if directed to do so by the owner. Such
kinds of changes include the following:
Unanticipated requirements imposed by third parties such as permitting
agencies, utility companies etc.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 16
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Unforeseen environmental issues.

2.1.2 Construction Change Orders


Change order is a written order to the contractor, signed by the owner, and issued after
execution of the contract, authorizing a change in the work or an adjustment in the
contract sum or the contract time (Hester, 1991). Whenever a change is encountered
during the construction stage it must be notified either orally or in written form to the
consultant. Then it will be subsided by a written change order from the consultant to
the contractor if that change is a real deviation from what is agreed up on. These
changes however occur after the award of the initial contract or after work might have
commenced at the construction sites. Change orders can be classified in to formal
change orders and informal change orders (O‟Brien, 1998).

2.1.2.1 Formal Change order


Formal change order is issued in writing by an authorized representative of the owner
or by the contractor to a sub-contractor. Formal change order rarely causes problems
because they are generally identified before they are incorporated. They are based on a
planned and deliberate choice of the contracting parties. Most often formal change
orders include two types of change orders, unilateral and bilateral change orders as briefly
discussed below:

i. Unilateral Change Order:


A unilateral change order is issued when an agreement is reached in negotiations or
when a contractor fails to submit his proposals in time. It is based on the owner‟s
estimate of cost and time for work. Most of the time such kind of change order is not
considered desirable due to the fact that it requires owner‟s decision which may
generate appeals. Hence, a unilateral change order should only be issued when
reasonable efforts have been exhausted to reach an agreement.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 17
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

ii. Bilateral Change Order:


It is a supplementary agreement whereby the owner‟s directives are issued to the
contractor with a bilateral agreement as to price or time. The supplemental agreements
are understood as being mutual agreements for the parties to increase or decrease the
work agreed upon.
It is essentially a new negotiated contract which must be founded upon a bilateral
agreement of the parties, and it is considered to be the proper medium for making
changes that are outside the general scope of a contract.

2.1.2.2 Informal Change Order


Informal change order is the result of constructive changes, which arise from the
informal acts and conduct of the owner or his representatives and it may increases the
contractor‟s cost of performance. Informal change order has same effects like that of
formal change order.

2.2 Causes of Change Order


Due to the fact that construction industry being a multi-party industry where the client
played his role as a promoter of the project, the consultant act as a professional to assist
the client in technical matters and assumed to be rational, and the contractor who
constructs as per the drawing and specification. In such kind of working environment,
change can be initiated by all parties in the construction process. An effective analysis of
change and change orders requires a comprehensive understanding of the root causes
of changes (Hester, 1991).
The causes of change orders have been identified in various literatures as client initiated
causes, consultant initiated causes, and contractor initiated causes. Apart from these three,
there are also other causes which can be considered as the fourth cause of change as
discussed below.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 18
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

2.2.1 Change Orders Caused by Project Owners


The most common change orders caused by project owners are initiated due to the
following reasons:
Change of scope or plan
Change of schedule
Financial difficulties
Poor project objectives
Change in specifications
Change of material
Late decision
One of the most significant causes of change in construction projects is change of scope or
plan (CII, 1990b). And this is usually resulted due to insufficient planning at the project
definition stage, or because of lack of involvement of the owner in the design phase
(Arain, 2004). This cause of change affects the project severely during the later phases.
Besides, during the construction phase of a project owners could change the project’s
schedule which may result in major resource reallocation (Fisk, 1997; O‟Brien, 1998).
Since time has an equivalent money value, a change in schedule means that the
contractor will either provide additional resources, or keep some resources idle. In both
cases additional cost is incurred. Whenever project owners face financial difficulties which
obliges them to make changes in an attempt to reduce cost, the project progress and
quality may be affected (Clough and Sears, 1994; O‟Brien, 1998). Proper planning and
review of project cash flow would be effective in eliminating this problem.
Poor project objectives are also the other important causes of changes in construction
projects (Ibbs and Allen, 1995). As a result various change orders may arise during the
project construction phase. One of the direct consequences of poor project objectives is
change in specification (O‟Brien, 1998). Change in specifications by the owner during the
construction phase may require major changes and adjustments in project planning and
procurement activities. Change of materials cause major change orders during the

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 19
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

construction phase. The replacement of materials affects the project contract amount
(Chappell and Willis, 1996). Therefore, an adjustment to the original contract value is
required if there is a change in materials. Prompt decision making is an important factor
for project success (Sanvido , 1992; Gray and Hughes, 2001). A delay in decision making
may hinder subsequent construction activities that may eventually delay the project
progress.

2.2.2 Change Orders Caused By Consultant


This section discusses the causes of changes that were initiated by the consultant. In
some cases, the consultant directly initiates changes or the changes are required because
the consultant fails to fulfill certain requirements for carrying out the project. The
following are some of the reasons of changes initiated by consultants.
Change in design
Errors and omissions in design
Conflicts between contract documents
Inadequate scope of work for contractor
Technology change
Value engineering
Design complexity
Inadequate working drawing details
Lack of judgment and experience
Lack of required data
Ambiguous design details
Inadequate design
Noncompliance of design with government regulations
Noncompliance of design with owner‟s requirements
Change in specifications by consultant
In contemporary professional practice it became a norm to make change in design
(Arain, 2004). The changes in design are frequent in projects where construction starts
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 20
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

before the design is finalized (Fisk, 1997). Most of the time this practice happens when
the consultant believes improvement is vital for successful completion of the project.
Errors and omissions in design cause of project delays (Arain ., 2004) and may lead to loss
of productivity and delay in project schedule (Assaf, 1995).
Conflict between contract documents can result in misinterpretation of the actual
requirement of a project (CII, 1986a). To convey complete project scope for participants,
the contract documents must be clear and concise.
In a multi-party player environment, like construction, the scope of work for all the
players must be clear and unambiguous for successful project completion (Fisk, 1997;
Arain, 2004). Technology change is related to technological advancements which can
accelerate the project‟s completion time. This could be a potential cause of changes in a
project. Therefore, project planning should be flexible for accommodating new
beneficial changes (CII, 1994b). This is because the new technology can be beneficial in
the project life cycle, for instance, reducing maintenance cost of the project. Value
engineering is related to those changes resulted due to economic condition and material
changes. Such changes should ideally be carried out during the design phase (Dell‟Isola,
1982). During the construction phase, value engineering can be a costly exercise, as
change in any design element would initiate down-stream changes to other relevant
design components (Mokhtar, 2000). Complex designs require unique skills and
construction methods (Arain, 2004). Complexity affects the flow of construction
activities, whereas simple and linear construction works are relatively easy to handle
(Fisk, 1997).
To convey a complete concept of the project design, the working drawings must be
clear and concise (Geok, 2002). Insufficient working drawing details can result in
misinterpretation of the actual requirement of a project (Arain, 2004). Professional
experience and judgment is an important factor for successful completion of a building
project (Clough and Sears, 1994; O‟Brien, 1998). The lack of professional experience
increases the risk of errors in design as well as during construction. Eventually, this

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 21
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

may affect the project quality and delay the project completion. A lack of required data
can result in misinterpretation of the actual requirements of a project (Assaf, 1995;
Arain, 2002). Where there is insufficient data, consultants are compelled to develop
designs based on their own perceptions, which may not be what the client wants. A
clearer design tends to be comprehended more readily (O‟Brien, 1998). Ambiguity in
design is a potential cause of changes in a project. This is because ambiguity in design
can be misinterpreted by project participants, leading to rework and delay in the project
completion. Inadequate design can be a frequent cause of variations in construction
projects (CII, 1990; Fisk, 1997). Design discrepancies affect the project functionality and
quality. Eventually, this can affect a project adversely depending on the timing of the
occurrence of the changes. Noncompliance of design with government regulations would
render the project difficult to execute (Clough and Sears, 1994). This may affect the
project safety and progress adversely, leading to serious accidents and delays in the
project completion. A comprehensive design is one that accommodates the owner‟s
requirements (Cox and Hamilton, 1995). A noncompliance design with the owner’s
requirements is considered an inadequate design (Fisk, 1997). Eventually, this may cause
changes to accommodate the owner‟s requirements which may affect the project
adversely during the construction phase. Changes in specifications are frequent in
construction projects with inadequate project objectives (O‟Brien, 1998). As mentioned
earlier with respect to changes in specifications by the owner, this is also a potential
cause of changes in a project, leading to reworks and delays in the project completion.

2.2.3 Change orders Caused by Contractors


As an active participant of the construction, contractors may suggest valuable changes
to the project. Changes may also be required because the contractor fails to fulfill certain
requirements for carrying out the project. Therefore, the most common reasons of
changes caused by contractors will be discussed as follow:
Lack of involvement in design

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 22
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Unavailability of equipment
Financial difficulties
Desired profitability
Differing site conditions
Defective workmanship
Poor procurement process
Lack of communication
Lack of judgment and experience
Complex design and technology
Lack of strategic planning
Lack of required data
Involvement of the contractor in the design may assist in developing better designs by
accommodating his creative and practical ideas (Arain, 2004). Lack of contractor’s
involvement in design may eventually cause changes. Practical ideas which are not
accommodated during the design phase will eventually affect the project adversely.
Unavailability of equipment is a procurement problem that can affect the project
completion (O‟Brien, 1998). Occasionally, the lack of equipment may cause major design
changes or adjustments to project scheduling to accommodate the replacement. Skilled
manpower is one of the major resources required for complex technological projects
(Arain, 2004).
Construction is a labor intensive industry. Whether the contractor has been paid or not,
the wages of the worker must still be paid (Thomas and Napolitan, 1994). Contractor‟s
financial difficulties may cause major changes during a project, affecting its quality and
progress. Contractor’s desired profitability can be a potential cause of change in
construction projects. This is because changes are considered a common source of
additional works for the contractor (O‟Brien, 1998). The contractor may eventually
strive to convince the project owner to allow certain changes, leading to additional
financial benefits for him. Differing site condition can be an important cause of delays in

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 23
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

large building projects (Assaf, 1995). The contractor may face different soil conditions
than those indicated in the tender documents. Eventually this may affect his cost
estimates and schedule adversely.
Defective workmanship may lead to demolition and rework in construction projects (Fisk,
1997; O‟Brien, 1998). Defective workmanship results in poor quality of work in
construction projects (Arain, 2004). Eventually, this cause may affect the project
adversely, leading to rework and delay in the project completion. The construction
manager carries out the construction phase in an organized way to eliminate the risks of
delays and other problems. Procurement delays have various adverse effects on other
processes in the construction cycle (Fisk, 1997). Occasionally, the procurement delay
may cause an entire change or replacement for originally specified materials or
equipment for the project (Arain, 2004). This may therefore cause a need for project
activities to be reworked. A lack of communication between parties may cause major
changes that could eventually impact the project adversely (Arain, 2004). Detrimental
changes, which affect the projects adversely, can usually be managed at an early stage
with strong and continuous communication.
Complex design and technology require detailed interpretations by the designer to make it
comprehensible for the contractor (Arain, 2002). A complex design may be experienced
for the first time by the contractor. Eventually, the complexity may affect the flow of
construction activities, leading to delays in the project completion.
Proper strategic planning is an important factor for successful completion of a building
project (Clough and Sears, 1994; CII, 1994a). The lack of strategic planning is a common
cause of changes in projects where construction starts before the design is finalized, for
instance, in concurrent design and construction contracts (O‟Brien, 1998). A lack of
required data may affect the contractor‟s strategic planning for successful project
completion, leading to frequent disruptions during the construction process. This is
because a lack of data can result in misinterpretation of the actual requirements of a
project (Assaf, 1995; Arain, 2004).

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 24
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

2.2.4 Other Causes of Changes


The under listed causes of changes are those that are not directly related to the
contracting parties. These causes affect progress of a construction project adversely by
causing considerable changes.
Weather conditions
Safety considerations
Change in government regulations
Change in economic conditions
Socio-cultural factors
Unforeseen problems
Adverse weather conditions can affect outside activities in construction projects (Fisk,
1997; O‟Brien, 1998). When weather conditions vary, the contractor needs to adjust the
construction schedule accordingly. Occasionally, this may affect the project progress
adversely, leading to delays in construction. Safety is an important factor for the
successful completion of a project (Clough and Sears, 1994). Noncompliance with safety
requirements may cause major changes in design. Lack of safety considerations may
affect the project progress adversely, leading to serious accidents and delays in the
project completion.
Local authorities may have specific codes and regulations that need to be
accommodated in the design (Arain, 2004). Change in government regulations during
the project construction phase may cause major changes in design and construction.
This can affect a project adversely depending on the timing of the occurrence of the
changes. Economic condition is one of the influential factors that may affect a
construction project (Fisk, 1997). The economic situation of a country can affect the
whole construction industry and its participants.
Professionals with different socio-cultural backgrounds may encounter problems due to
different perceptions, and this may affect the working environment of the construction

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 25
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

project (Arain, 2004). Lack of coordination is common between professionals with


different socio-cultural backgrounds (O‟Brien, 1998). Eventually, project delays may
occur that end up with vital changes in the entire project team. Unforeseen conditions are
usually faced by professionals in the construction industry (Clough and Sears, 1994;
O‟Brien, 1998). If these conditions are not solved spontaneously, they may cause major
changes in the construction projects. Eventually, this may affect the project adversely,
leading to reworks and delays in the project completion.

2.3 Impacts of Change Orders


This type of literature studies changes in construction from a cost point of view. The
literature published can be classified as either qualitative or quantitative. Qualitative
studies discuss the various attributes of cost and schedule impacts without quantifying
them. Quantitative studies on the other hand attempt to quantify the various attributes
of cost and schedule impacts. Most of the quantitative studies were done on the
productivity factor in change. CII has great contributions to this type of studies.
Quantitative assessments of change impacts can be done for different purposes:
♦ To predict the impacts of change before construction (by owner or contractor)
♦ To calculate cost of change during construction (for accounting corrective actions)
♦ To calculate cost of change after project close out or for claim purposes
Attempts to quantify impacts of change usually confronted two major problems
(Zeitoun and Oberlender, 1993):
♦ Difficulty in collection and accuracy of data
♦ Difficulty in assessing indirect impacts of changes
The cost impact of a change is greatly affected by the timing of the change (CII
publications 5-1(1986) & 6-10 (1990)). A change issued before construction has limited
effects as compared to a change issued after construction has already started and
materials have been procured. Also successive changes cost more than a single change.
Changes after construction or completion of design must provide high cost saving to be
justified.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 26
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

The impacts of a change are classified in the literature as follows: (CII publication 6-
10,1990)
1. Direct cost impact
2. Direct schedule impact
3. Indirect or Consequential impact
Let us examine each of these impacts and its attributes making reference to published
literature on the subject.
2.3.1 Direct Cost Impact
The direct impacts are those limited to the work package in which a change is
introduced. The cost impact could be positive (savings) to the owner or negative (more
expenditure). The contractor‟s view of a change being positive or negative will be the
opposite of the owner. A change may also have a positive cost impact to both owner
and contractor. Further, a change may have zero cost impact to both parties. There are
two components to the cost of a change: labor cost and material cost. Material cost is
easy to estimate and predict to certain accuracy. However it is difficult to estimate labor
cost due to:
♦ The effect of changes on the productivity rate itself.
♦ The uncertainty about the scope of a change (exact engineering, procurement,
and construction activities that form a change work).
The discussion here about labor cost impact will use the situation where change is
issued after construction as the setting. Labor cost of changes can be broken into three
attributes (CII publication 6-10, 1990):
a) Productivity Degradation
b) Delays
c) Demolition and Rework
Of the direct cost impact attributes, productivity is the most difficult to estimate,
measure and control.
a. Productivity Degradation

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 27
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Interruption, delays and redirection of work, associated with change work have a
negative impact on labor productivity which in turn translates into labor cost or dollar
value. Many studies were conducted to evaluate this aspect of change (CII publication 6-
10 (1990), Thomas 1994 &1995, Hester 1991). Two studies cited in CII publication 6-10
(1990) examined work by single craft crewmen and effects of changes on their
productivity. “The setting of the first study was a major chemical facility and the
craftsmen involved were union insulators”. “Study 2 was undertaken on a revamp
project at a refinery where changes were being generated at a rate that often exceeds 20
per week”. Comparing the productivity index against the frequency of change, the
studies concluded:
Productivity drops rapidly with increased frequency of interruptions.
♦ As the rate of disturbances to the normal flow of work increases, the extent of
productivity degradation becomes compounded.
♦ More than 40% reduction in productivity was noticed with an extreme number of
disturbances.
Productivity degradation is not the same for all tasks and settings. The following factors
are noted:
1. Concentration required to accomplish the task
2. Machine intensive tasks vs. labor intensive tasks
3. Frequency of interruptions and duration of time between them
4. Worker expectation of the change and his opinion about it
We can also expect productivity of workers to be greatly affected in cases where
workers were required to work overtime for prolonged periods to compensate for
schedule delays. In a study by Thomas and Napolitan (1995) productivity values from
three industrial projects constructed between 1989 and 1992 were used in the analysis.
The study concluded that on average there was 30% loss of efficiency due to changes
(25-50% was the actual range). It is worth noting that Thomas and Napolitan concluded
that changes do not lead to productivity degradation or efficiency loss in them. Instead,

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 28
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

a construction change causes other disruptive influences to be activated. In fact, Thomas


and Napolitan concluded that it is possible to perform changes without negatively
impacting labor efficiency. However, it is difficult to qualify this statement. Changes are
disruptive in nature and to think of eliminating some of these disruptions is impossible
before the change is introduced.
Thomas and Napolitan show the same results in their Construction Industry Institute
report (1994). The report indicated that earlier research done by the United Nations in
1965 identified two major factors affecting labor productivity, namely the nature of
work being done (Organizational Continuity) and the management and the
environment of the work (Executional Continuity). The United Nation‟s report has led
to the development of a model called the Factor Model that tries to explain factors
affecting labor productivity.
The CII report concluded again that changes normally lead to disruptions and these
disruptions are responsible for labor productivity degradation: “The most significant
types of disruptions are the lack of materials and information and having to perform
the work out of sequence”. Lack of material is reported as being the most serious
disruption. The report emphasized that to manage changes one needs to manage these
disruptions. However the disruptive effects “cannot be avoided in many instances”.

b. Cost of Delay
To make a change and process takes time. This usually results in placing a hold on the
work and waiting for new instructions to come. In addition, equipment, tools and
materials may not be the same after the change is introduced. To procure or rent new
material, tools and equipment will cause delay and cost of resources may be substantial.
Furthermore, if delays are prolonged demobilization/remobilization may become quite
costly. The cost of delay may apply to engineering and procurement activities if
impacted by change (CII publication 6-10, 1990).
c. Demolition and Rework

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 29
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Changes, which are introduced when the construction is underway or even complete
involve several direct cost items (CII publication 6-10,1990) which can be summarized
as follows:
i. Labor cost to demolish existing facility
ii. Equipment cost to demolish existing facility
iii. Materials wasted by removal of existing work
iv. Associated cost of engineering/shipping and handling of waste materials

2.3.2 Direct Schedule Impact


It is easy to document a schedule impact of a change after change work is done, because
all data is available regardless of its accuracy. However, it is difficult to predict impact
of change on schedule before making a change because of the many uncertainties
related to labor productivity, material availability or job interference. The cost of
schedule slippage becomes very high if the contract includes a penalty clause.
Most projects are planned using a critical path method, CPM, (CII publication 6-10, 1990).
This method of scheduling shows the activities included and their dependencies. CPM
provides the basis against which impact of changes on schedule can be evaluated. Floats
both total and free play an important role in schedule impact evaluation for they
represent the flexibility available to handle the unforeseen conditions such as changes.
The magnitude of schedule slippage due to changes is reported by Zeitoun and
Oberlender (1993) as 9% of the original schedule on average for 71 fixed price projects
studied. In a study by Ibbs, Lee & Li (1998) on the effects of schedule acceleration on
project changes, researchers concluded that “a high level of fast tracking generally does
not result in any more changes than non-fast tracking projects”. This study used data
from an earlier study (Ibbs & Allen) sponsored by the Construction Industry Institute in
which 108 projects were analyzed for change data. The study found that fast track
projects, however, tend to generate more changes toward the end of the project,

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 30
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

resulting in increased labor intensity and a more hectic finishing and close out
operation.

2.3.3 Consequential Impacts


There are always indirect impacts to changes that are overlooked or underestimated
(CII publication 6-10, 1990). Consequential effects can occur later in other work packages
and thus on the total project. Therefore, it is essential to acknowledge this possibility
and establish the mechanism to evaluate its consequences. The contract change clause
should fully consider both direct and indirect (consequential) effects.
The following are among the possible consequential effects (CII publication 6-10, 1990).
1. Effects on the methods or procedures used in other work packages due to a
change in a previous task or package.
2. Degradation of productivity in subsequent packages or activity: Productivity
studies cited earlier confirmed that a degradation of productivity in the change
package is followed by productivity degradation in subsequent packages. A
degradation of productivity was also noted in concurrent activities due to a
change.
3. Increase in overhead cost – Obviously if the change has an impact on schedule,
material or administration level, the project overhead increases proportionally.
4. Impacts on subcontractors: Normally subcontractors have their own plan and
schedule assuming that the main contractor will maintain the original conditions
that allow start and end of work as scheduled. When a change takes a place, the
subcontractor may need to adjust his plans and schedule accordingly. The
subcontractor in turn may seek price and or schedule adjustments.
5. Miscellaneous: The following are some potential cost items that may be
overlooked:
Time value of capital tied due to a change
Shifting of work to a less favorable period.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 31
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Additional bonding and insurance.


Engineering work for correcting drawings and documents.
Procurement activities effects
In summary, changes in construction generate effects that far exceed the working
package or activity in which changes occur. This situation is called a “Ripple Effect”.
Thomas and Napolitan (1994) indicated that “While much has been said about the
ripple effect, there have been no quantitative studies showing the magnitude of these
effects”.
An attempt to measure ripple effects quantitatively was done by Zeitoun and
Oberlender (1993). The attempt was not successful, because of the relative respondent
interpretation of the term „ripple effect‟. The researchers then proposed a method called
„ripple tree‟. Again results obtained applying the ripple tree method came out to be
inconsistent with the actual situation. Zeitoun and Oberlender (1993) attributed the
unexpected results to erroneous historical data and suggested the use of the method
during construction.
Nevertheless, managers of construction projects must develop the means to evaluate
and estimate the consequential impacts of a change. An effective tool in consequential
impact evaluation is the use of Work Breakdown Structure (WBS). A contractor should
consider using the Work Breakdown Structure (WBS) as an evaluation tool especially
on large projects. In this method, the whole project is broken into hierarchical fashion.
Resources are allocated to each element in the WBS. “The WBS is a vital tool in change
management. If a change involves work not previously included on the WBS, it can be
logically added to the WBS and its relationship to the WBS element seen”
(CII publication 6-6, 1988). Ripple effects can be traced by the use of WBS. The discussion
of the details and applications of the WBS is beyond the scope of this paper and the
reader is referred to the above CII publication. Other evaluation tools cited in literature
include market factor (MF), forensic scheduling, and current control schedule. The
details of these tools are covered in CII publication 6-6 and Hester et al (1991).

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 32
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

2.4 Legal Aspects of Change Orders


In this regard, literatures discussing legal aspects such as contract change, clause
interpretation, substantiation and management of claims are referred. In this approach
changes are looked as a major source of construction claims and disputes. The major
legal aspects are (CII publication 5-10 (1986), Cox 1997).
♦ Selecting the best delivery system (contract format)
♦ Drafting and interpreting change clauses
♦ Documenting change orders to be ready in case of litigation
Most of these issues can be found in literature discussing claims and disputes and deal
with after the fact approach. However, there are few points that affect how a project will
cope with changes and problems foreseen. An owner‟s management of change orders
and claims must also anticipate and provide for dispute prevention and dispute
resolution processes from the outset.

2.4.1 Types of Construction Contracts


Whenever legal issues of change orders are raised, the contract format used could be the
subject of concern. The actual form of agreement is often a very brief document which
describes the contracting parties, authority, scope of the work, the consideration to be
paid, penalties or bonuses, and the time for performance. This document is seldom the
issue of concern whenever a dispute occurs between the contracting parties. Primarily,
these documents for a construction project comprises of the Agreement form, Bill of
quantities, General conditions, Special conditions, Technical specification, Plans and Addenda
(Alan T., Gordon R. 2004).
There are numerous contract types used in construction and depending on the project
requirements contracts can be identified as either fixed price or cost reimbursable [Ibbs,
W., Neguyen, L., Lee, S. 2007].

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 33
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

i) Fixed price contract


This category includes all contract types in which financial terms require the contractor
to establish a stipulated sum for the completion or execution of a defined quantity of
work. Under this category the following two most common types of contracts are
referred:
a) Lump Sum: The contractor, in this type of contract, is required to construct the project
in accordance with plans and specification for a fixed sum. Hence, the contractor is
solely responsible for any cost exceeding the agreed amount.
The term lump sum is often used to indicate a lump sum contract including design
procurement and construction. Sometimes it is referred to as simply turnkey contract.
b) Unit Price: This contract type contains a detailed list of estimated work quantities of
different types of work units. Actual price paid (fixed) is determined by actual units
done as constructed. In such kind of contract, the owner is required to take the risk of
variation in quantity. However, unit price contract allows the owner the freedom to
make changes in the volume of work and permit more control.
c) Guaranteed Maximum: In this type of contracts the owner is guaranteed a maximum
price for executing the work as defined in the contract. Normally the contract contains
incentive clauses for cost under-runs and penalty clauses for cost overruns. Ashly and
Workman (1986) discussed the effects of incentives in the contract and concluded that
they promote an attitude of motivation on the contractual relationship and take the
form of inducements, encouragement and threats. The study also indicates that
incentives are a tool used by owners to adjust the contractor‟s fee. The study includes
full details of finding on contractual motivation which is beyond our scope of this
review.
ii) Cost reimbursable contracts
This category includes all contract types, in which financial terms allows the contractor
price adjustment relative to project costs. Ibbs et al (1986) summaries the type of
contracts which fall under this category as:

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 34
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

a. Cost plus Fixed Fee


The contractor in this type of contract is paid whatever cost associated with the
project plus a lump sum fee for corporate overhead and profit.
b. Cost plus Percentage
In this type of contract the contractor is paid all costs associated with the project
plus a percentage of these costs rather than a fixed sum or fee.
c. Target Price plus a Fee
In this type of contract, a target price is first established for the cost of the project
based on contract documents or unit prices. “The contractor‟s fee will be based
on this sum. Typically financial arrangements make provision for the contractor
to share any savings below the target price or participate in the liability of cost
overruns”.

The following block diagram depicts the contract format division:

Contract Forms

Fixed Price Cost Reimbursable

Lump Sum Cost plus Fixed Fee

Unit Price Cost plus Percentage

Guaranteed Maximum Target price plus a Fee

Reimbursable contracts allow for contract adjustments relative to project scope as


determined by the cost and do not, generally, address a final fixed price. Fixed price
contracts allocate more risk to the contractor and thus require more effort, money, and
time on design documentation before construction is initiated. Cost reimbursable
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 35
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

contracts require greater risk sharing between the owner and contractor and require
more owners‟ personnel for contract administration during the construction phase to
enforce cost and schedule. They are more easily used for fast tracking of design and
construction. Reimbursable contracts are also very flexible for changing design or scope
of work and establish the basis for a less adversarial relationship between the owner
and contractor.
Ibbs et al (1986) indicated that “the choice of the type of contract (fixed cost versus cost
reimbursable) should be heavily influenced by four circumstances:
1. The extent to which the work is defined
2. The desired allocation of risk between owner and contractor
3. The availability of owner expertise and effort on the project
4. The need to accommodate fast-tracking of design and construction
Often both forms of contracts exist on a project simultaneously. Prime contractors will
often have cost reimbursable contracts with the owner and fixed price contracts with
their subcontractors. In the Ethiopian construction industry fixed price contract is
widely practiced.

2.4.2 Change orders and Contract Forms


Certainly not all types of contracts are equally sensitive to changes. If contracts are
classified as either cost reimbursable or fixed cost, the latter will be the most sensitive to
changes. Fixed price contracts are selected for projects in which the scope is well
defined and the risk is low. Cost reimbursable contracts on the other hand are selected
for vaguely defined projects for schedule acceleration. In cost reimbursable projects,
there is a direct transfer of cost and schedule effects to the owner. Owners should
consider changes when considering the type of contract for their project in terms of the
ability of the contract to contain and minimize changes. In this regard, change clauses
are an important element of the contract because they provide mechanism for contract
modification (either to react to unexpected events or because the owner desires change)

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 36
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

and for appropriate compensation. The change clause establishes the right of the owner
to make changes within certain limitations and through a defined mechanism.
However, it was found that change clause is one of the most troublesome contract
clauses. Problems most often encountered with construction change clauses involved
definition and negotiation of costs, dispute resolution and time required for approval.
Legal disputes over changes often focus on whether or not a compensatory change
exists, the appropriate level of compensation, and the relative responsibility for a
change.

2.5 Change Order Management


Construction contracts are unique in that they typically provide the owner the right to
make changes to the contract documents without avoiding the contract. However, as
the number of change orders on a project increase, so does the possibility of
misunderstanding among the contracting parties. Such a misunderstanding may occur
because one or more of the parties lack full knowledge of the change order process
itself, the cost involved in implementing the change, or the delays, conflicts, and
interruption of the construction sequence and schedule which can adversely impact the
project coordination.
The discussion so far has concentrated on the legal and cost aspects of a change. Equally
important is the need to have a well-developed program for the management of
changes. This includes a change control program and change order administration
during initiation, evaluation, approval and implementation. Most of what is written
deals with the control part. The Changes Impact Task Force of the Construction
Industry Institute (CII) prepared a checklist of the most common parameters to consider
when considering a change. These parameters were classified under different
categories. According to Thomas and Napolitan (1994), the major categories are:
Size and scope
Nature of the scope

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 37
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Timing
Managing Impact
Who does the change
Site conditions (environment)
In its special publication (Oracle, 2009), change management best practices for the
engineering and construction industry recognized five valuable steps for effective
change management:
Identifying contract requirements.
Identifying potential changes.
Determination of Entitlement and Effect of Change
Negotiation and execution of change order.
Recording the executed change.

2.5.1 Contract requirements Identification


The contract documents identify the requirements for the project in terms of its scope,
schedule, and budget. The contract requirements must first be identified so that any
deviation (that is, a change) can be recognized, because a change is essentially a
requirement that deviates from the requirements set forth in the contract documents.

The contract documents typically include the following components:


Contract. Addenda, agreement, special provisions, and all similar or related
provisions and references.
Specifications. General provisions, technical specifications, supplemental
provisions or specifications, and other referenced standards.
Plans. Project plans include standard plans, standard details, boring logs, or other
information that depicts the work to be constructed or site conditions prior to the
start of construction.
When reviewing the contract documents it is important to apply general rules of
contract interpretation. This means reading the contract as a whole and following the
order of precedence clause when interpreting the component contract documents.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 38
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

The owner and contractor should also pay particular attention to the contract clauses
related to notice and changes, because these clauses are the logical starting points for
the identification and administration of changes.

2.5.1.1 Changes Clause


The changes clause could be the most important clause in a construction contract because
it specifies that the owner can make changes in quantities or other alterations it deems
necessary to complete the work (scope), which can affect the contract time (schedule) or
cost (budget). The contractor, on the other hand, is obligated by the changes clause to
execute changes to the work according to the owner‟s instructions, provided that a
mechanism exists for the contractor to be compensated in terms of cost and time.

Changes include changing the quantities of work or the conditions under which it is to
be performed, and suspending, adding, or eliminating work that is within the scope of
the contract. Therefore,

• During the course of the contract, the owner through its agent has the right to
make written changes in the quantities or other alterations as necessary to
complete the work [FIDIC 1987, Clause51 (a to f)].

• Such changes in quantities or alterations neither invalidate the contract nor


release the surety.

• Contract time will be adjusted [FIDIC 1987, Clause 44.1 (a to e)] for changes that
require additional time to complete.

The changes clause, illustrated above, first addresses the potential scope, schedule, and
budget effects of the change, then direct to the appropriate contract provisions
governing payment and time extensions.

As to how this might work in practice, changes that affect the project‟s “critical path”
might require the issuance of a time extension.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 39
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Likewise, the provisions that govern the payment requirements for the changed work
are referenced by the changes clause. For contract changes that affect unit price work
items, the preferred solution is typically to use the existing contract unit prices to price
the changed work. If contract unit prices for the changed work do not exist, suitable
rates or prices can be negotiated between the contracting parties. In the event of
disagreement, the consultant, as per clause 52.1 of the FIDIC condition of contract, can fix
such rates or prices which are, in his opinion, appropriate and notify the contractor
accordingly, with a copy to the owner. However, the consultant can also determine
provisional rates or prices to enable on-account payments to be included in certificates
issued in accordance with Clause 60.

2.5.1.2 Contractor Notice Clause


The contractor typically has the responsibility of informing the owner of any condition
that is potentially a change before proceeding with the affected work. Notice must
typically be provided in written form, but some contracts might also allow oral notice.
Contracts typically define notice as written notice that is provided within a certain time
frame (typically, not longer than a week or so) of identifying a change. The notice clause
is important because it prevents the contractor from prejudicing the owner‟s rights to
investigate, mitigate, and document the change while the opportunity exists. In other
words, the notice clause provides the owner with an opportunity to decide on the
appropriate course of action before any work is performed or additional cost incurred
and to document the changed work as it is performed. Notice clauses are often
enforceable, and the contractor‟s failure to notify the owner within the specified time
frame could result in the forfeiture of all rights for additional compensation or time.
Notice provisions not only encourage or force the parties to communicate effectively,
but they also instigate the collaborative process necessary for the project participants to
resolve the change.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 40
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

If the Owner responds unacceptably, or not at all, the contractor must provide a written
notice within five working days of the first notice. The written notice has to include the
following:

A description of the situation;


The time and date the situation was first identified;
A clear explanation of why the situation represents a change to the contract,
including accurate references to the pertinent portions of the contract;
A statement of the amendments deemed necessary in the contract price(s),
delivery schedule(s), phasing, time, and so on. Because of its preliminary nature,
the Owner recognizes that this information may rely on estimates;
An estimate of the time by which the Owner must respond to minimize cost,
delay, or disruption; and
Anything else that will help achieves a timely resolution.
As it was explained in the above paragraphs, the initial contract notice can be provided
orally instead of in writing, which can save time - a benefit to both the owner and the
contractor. The contractor is still required to provide written notice within five days if
the owner responds differently than anticipated, or fails to respond to the oral
notification. Conversely, if the owner agrees with the contractor that a change has
occurred, then steps can be taken to document and administer the change. In summary,
the notice clause should be part of a fair and workable change management process that
serves the needs of the owner, the contractor, and the project in general.

2.5.2 Potential Changes Identification


When a potential change is identified, it is important to correctly classify it and follow
the correct procedures. In this step of the process, a potential change is classified among
the different types of change provisions that are defined by the contract.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 41
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Construction contracts are often thorough in identifying the different kinds of changes
that might be encountered during construction and defining the procedures that must
be followed upon their identification. The common types of change provisions defined
in construction contracts are:

Change in the character of work,

Unforeseeable Site Conditions,

Suspension of work,

Extra work, or

Elimination of work.

2.5.2.1 Change in the character of work

A change in the character of work is defined as a significant variation in quantity or


change in the conditions under which the work is to be performed. Most of the time this
happens due to the owner‟s contractual right to make change in quantities and
alterations in the works that are necessary for the proper completion of the project. Such
changes in quantities and alterations shall not invalidate the contract nor release the
surety, and the contractor shall abide himself to the contractual obligations to perform
the work as altered.

FIDIC 1987, condition contract Clause 51.1 grants the Engineer (Owner‟s representative)
to make any variation of the form, quality or quantity of the works that may, in his
opinion, be necessary. The type of variation this clause commands include “increase or
decrease the quantity of any work included in the contract” and “change the character or quality
or kind of any such work.
If the changes in quantities significantly change the character of the work under the
contract, whether or not changed by any such different quantities or alterations, an
adjustment, excluding loss of anticipated profits, will be made to the contract. The basis
for the adjustment shall be agreed upon prior to the performance of the work. If a basis

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 42
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

cannot be agreed upon, then an adjustment will be made either for or against the
contractor in such amount as the Engineer may determine to be fair and equitable.
If the alterations or changes in quantities do not significantly change the character of the
work to be performed under the contract, the altered work will be paid for as provided
in Sub Clause 52.1 of FIDIC 1987, condition contract as follow:

All variations referred to in Clause 51 and any additions to the Contract Price which are
required to be determined in accordance with Clause 52 (for the purposes of this Clause referred
to as “varied work”), shall be valued at the rates and prices set out in the Contract if, in the
opinion of the Engineer, the same shall be applicable. If the Contract does not contain any rates
or prices applicable to the varied work, the rates and prices in the Contract shall be used as the
basis for valuation so far as may be reasonable, failing which, after due consultation by the
Engineer with the Employer and the Contractor, suitable rates or prices shall be agreed upon
between the Engineer and the Contractor. In the event of disagreement the Engineer shall fix
such rates or prices as are, in his opinion, appropriate and shall notify the Contractor
accordingly, with a copy to the Employer.

2.5.2.2 Unforeseeable Site Conditions

Unforeseeable means not reasonably foreseeable by an experienced contractor [FIDIC,


MDB Harmonized 2010 edition]. Such site conditions include natural and manmade

physical conditions and other physical obstructions and pollutants, which the
contractor encounters at the site when executing the works, including sub-surface and
hydrological conditions but excluding climatic conditions.
Whenever such site conditions happen while executing, Sub clause 4.12 of FIDIC, MDB
Harmonized 2010 edition treats the case as follow:
If the Contractor encounters adverse physical conditions which he considers to have been
Unforeseeable, the Contractor shall give notice to the Engineer as soon as practicable. This notice
shall describe the physical conditions, so that they can be inspected by the Engineer, and shall set
out the reasons why the Contractor considers them to be Unforeseeable. The Contractor shall
continue executing the Works, using such proper and reasonable measures as are appropriate for

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 43
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

the physical conditions, and shall comply with any instructions which the Engineer may give. If
an instruction constitutes a Variation, Clause 13 [Variations and Adjustments] shall apply.
If and to the extent that the Contractor encounters physical conditions which are Unforeseeable,
gives such a notice, and suffers delay and/or incurs Cost due to these conditions, the Contractor
shall be entitled subject to notice under Sub-Clause 20.1 [Contractor’s Claims] to:
(a) An extension of time for any such delay, if completion is or will be delayed, under Sub-
Clause 8.4 [Extension of Time for Completion], and
(b) Payment of any such Cost, which shall be included in the Contract Price.
Upon receiving such notice and inspecting and/or investigating these physical conditions, the
Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or
determine (i) whether and (if so) to what extent these physical conditions were Unforeseeable,
and (ii) the matters described in subparagraphs (a) and (b) above related to this extent.
However, before additional Cost is finally agreed or determined under sub-paragraph (ii), the
Engineer may also review whether other physical conditions in similar parts of the Works
(if any) were more favorable than could reasonably have been foreseen when the Contractor
submitted the Tender. If and to the extent that these more favorable conditions were encountered,
the Engineer may proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or
determine the reductions in Cost which were due to these conditions, which may be included (as
deductions) in the Contract Price and Payment Certificates. However, the net effect of all
adjustments under sub-paragraph (b) and all these reductions, for all the physical conditions
encountered in similar parts of the Works, shall not result in a net reduction in the Contract
Price.
The Engineer shall take account of any evidence of the physical conditions foreseen by the
Contractor when submitting the Tender, which shall be made available by the Contractor, but
shall not be bound by the Contractor’s interpretation of any such evidence.

2.5.2.3 Suspension of work

A suspension of work is defined as an order by the owner/or owner‟s representative to


stop the work, or elements of the work, for a period of time. Work suspensions are
changes of particular importance because they impede the contractor from performing
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 44
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

the work in the sequence or manner that the contractor intended. Suspension could be
instigated by either of the contractual parties depending on their contractual right.
Suspension by the Employer/Engineer
Sub clause 40.1 of FIDIC Conditions of Contract recommends suspension of work where
such suspension is necessary by reason of: breach of contract by the contractor or climatic
conditions on the site, or for the proper execution of the works or for the safety of the Works or
any part thereof.
Sub-Clause 40.1:
The Contractor shall, on the instructions of the Engineer, suspend the progress of the Works or
any part thereof for such time and in such manner as the Engineer may consider necessary and
shall, during such suspension, properly protect and secure the Works or such part thereof so far
as is necessary in the opinion of the Engineer. Unless such suspension is:
(a) Otherwise provided for in the Contract,
(b) Necessary by reason of some default of or breach of contract by the Contractor or for
which he is responsible,
(c) Necessary by reason of climatic conditions on the Site, or
(d) Necessary for the proper execution of the Works or for the safety of the Works or any
part thereof,
If the performance of all or any portion of the work is suspended or delayed by the
owner or owner‟s representative in writing for an unreasonable period of time (i.e.
suspension lasting more than 84 days) and if permission to resume work is not given by
the engineer, the contractor may submit in writing to the engineer requiring permission
within 28 days to proceed with the suspended works pursuant to Clause 40.3.

Clause 40.3:

If the progress of the Works or any part thereof is suspended on the instructions of the Engineer
and if permission to resume work is not given by the Engineer within a period of 84 days from
the date of suspension then, unless such suspension is within paragraph (a), (b), (c) or (d) of
Sub-Clause 40.1, the Contractor may give notice to the Engineer requiring permission, within
28 days from the receipt thereof, to proceed with the Works or that part thereof in regard to
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 45
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

which progress is suspended. If, within the said time, such permission is not granted, the
Contractor may, but is not bound to, elect to treat the suspension, where it affects part only of
the Works, as an omission of such part under Clause 51 by giving a further notice to the
Engineer to that effect, or, where it affects the whole of the Works, treat the suspension as an
event of default by the Employer and terminate his employment under the Contract in
accordance with the provisions of Sub-Clause 69.1, whereupon the provisions of Sub-Clauses
69.2 and 69.3 shall apply.

Moreover, suspensions of work that delay critical path activities can extend the overall
duration of the project, potentially resulting in both added costs and delaying the
scheduled project completion date.

In the event of any delay, impediment or prevention by the Employer, or other special
circumstances which may occur, other than through a default of or breach of contract by
the Contractor or for which he is responsible, the contractor has to notify the Engineer
within 28 days after such event has first arisen with a copy to the Employer pursuant to
Sub-Clause 44.2 [Contractor to Provide Notification and Detailed Particulars]. No contract
adjustment will be allowed unless the contractor has submitted the request for
adjustment within the time prescribed.
Clause 40.2

Where, pursuant to Sub-Clause 40.1, this Sub-Clause applies the Engineer shall after due
consultation with the Employer and the Contractor, determine

(a) Any extension of time to which the Contractor is entitled under Clause 44, and

(b) the amount, which shall be added to the Contract Price, in respect of the cost incurred by
the Contractor by reason of such suspension, and shall notify the Contractor accordingly,
with a copy to the Employer.

Upon receipt, the Owner will evaluate the contractor‟s request. If the Owner agrees that
the cost and/or time required for the performance of the contract has increased as a
result of such suspension and the suspension was caused by conditions beyond the

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 46
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

control of and not the fault of the contractor, its suppliers, or subcontractors at any
approved stage, and not caused by weather, the Owner will make an adjustment.
No contract adjustment will be allowed under this clause to the extent that performance
would have been suspended or delayed by any other cause, or for which an adjustment
is provided for or excluded under any other term or condition of this contract.
Suspension by the Contractor
Contrary to sub-clause 40.1, sub clause 69.4 depicts that the contractor too has a
contractual right of suspending the work or reduce the rate of work if employer fails to
pay the contractor the amount certified under any payment certificate approved by the
engineer within the time stated on the contract. However, this contractual privilege
should be accompanied by a notice written to the employer and the engineer prior to
suspending or reduce the rate of work.
Sub-clause 69.4 :
Without prejudice to the Contractor’s entitlement to interest under Sub-Clause 60.10 and to
terminate under Sub-Clause 69.1, the Contractor may, if the Employer fails to pay the
Contractor the amount due under any certificate of the Engineer within 28 days after the expiry
of the time stated in Sub-Clause 60.10 within which payment is to be made, subject to any
deduction that the Employer is entitled to make under the Contract, after giving 28 days’ prior
notice to the Employer, with a copy to the Engineer, suspend work or reduce the rate of work….

If the Contractor suspends work or reduces the rate of work in accordance with the provisions of
this Sub-Clause and thereby suffers delay or incurs costs the Engineer shall, after due
consultation with the Employer and the Contractor, determine:
(a) any extension of time to which the Contractor is entitled under Clause 44, and
(b) the amount of such costs, which shall be added to the Contract Price, and shall notify the
Contractor accordingly, with a copy to the Employer.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 47
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

2.5.2.4 Extra Work

Extra work is defined as added work not provided in the original contract, but found to
be essential for the satisfactory completion of the project within its intended scope.
Extra work can be added to the project‟s scope due to a design consultant‟s error or
omission, or through changes requested by the owner or demanded by a third party.
The extra work clause is particularly important because it provides a mechanism for the
owner to introduce additional elements of work. Whenever a need for extra work arise,
sub-clause 51.1(e) of FIDIC condition of contract gives power to the Engineer to instruct
the contractor to “ execute additional work of any kind necessary for the completion of the
Works” and the contractor shall do the work in accordance with the instruction.

2.5.2.5 Eliminated work

Eliminated work is defined as original contract items that are no longer desired or
necessary to complete the work and are, thus, removed from the project‟s scope by the
owner through a deductive change order. Eliminated work items can become the basis
for disputes, however, if the contractor has already incurred cost for those items, for
example, purchased materials. In such cases, it is customary for the contractor to
request reimbursement for actual costs incurred. Whenever needs to omit works arise
by the owner, sub-clause 51.1(b) of FIDIC condition of contract gives power to the
Engineer to instruct the contractor to “omit any such work (but not if the omitted work is to
be carried out by the Employer or by another contractor)”.
As indicated previously, after a contractor, owner, or third party has determined the
type of change, appropriate change provision has to be identified as indicated
previously, and it should then demonstrate that it has met all requirements set forth in
that provision including notice requirements if the change was identified by the
contractor. All contract documents, contemporary project records, and correspondence
used to support the position that the potential change is a legitimate contract change
should then be filed for further analysis. The following crucial steps are advised to be
followed while keeping a record for a potential change.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 48
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

2.5.3 Measuring the Effect of Change Order


As previously stated, the changes clause indicates that changes to the contract might be
necessary for the satisfactory completion of the project or project conditions can differ
from the conditions originally shown in the contract. The first step in determining the
contractor‟s entitlement to additional costs or time related to an alleged change is
establishing that a change, according to the contract, has in fact occurred, and then
determining whether the contract provides the contractor with remedies for the change.

To establish that a change has occurred, the contractor should identify the specific
change-related contract language associated with the alleged change. Then, referencing
the specific change provision, the contractor should demonstrate that the alleged
change is in fact a change by comparing it to the baseline requirements set forth in the
contract. After establishing that a change has occurred according to the contract, the
contractor must show that the relevant contract provision enables the recovery of
additional time or costs that result from the allowable change.

Only after a contractor has established entitlement to a change can the effect of the
change begin to be measured. Typically, a change will consist of either the addition or
elimination of work. If a change requires the addition of work, the contractor should
use the contract‟s time extension provision to determine how the delay associated with
the change should be measured and the appropriate extension of time determined.

However, if the contract‟s time extension provision does not provide direction to the
contractor on how to request additional contract time for the delay that might result
from the additional contract work, then the contractor should use an appropriate
schedule analysis technique to measure the delay to the project and the duration of the
appropriate time extension.

2.5.4 Negotiation and Execution of Change Order


Many contracts dictate the process, including the duration of time that each party must
follow to address any potential changes to the contract work. The contractor must

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 49
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

disseminate the information included with an owner‟s Request for Proposal (RFP) to all
affected parties, including subcontractors, and then assemble the detailed responses to
support the estimated cost or the delay resulting from the change within this specified
period.

Upon receipt of a contractor‟s response to a RFP, the owner will review the information
as described in the third activity of the change management process and respond to it
within the period of time specified by the contract. At this time, the owner will either
accept the contractor‟s proposal as submitted and generate a change order for signature
or reject the proposal, noting the basis for the rejection. As a standard practice, both of
these actions should be performed in writing for record-keeping purposes. If the
contractor‟s proposal is rejected by the owner, the contractor could then respond in
writing to the owner‟s decision or set up a meeting with the owner to negotiate the
matter until an acceptable cost and time extension are agreed upon.

If it appears that the change order process is too lengthy and impact the progress of the
work and cause further delays, the owner could choose to address the change through
means other than a bilaterally executed change order. A construction change directive
(CCD) could be issued to the contractor directing that the work be performed on a time-
and-materials basis, invoking the force account provision in the contract, with or
without a not-to-exceed amount. A unilateral change order issued by the owner to the
contractor allows the work to be performed in accordance with the changes clause of
the contract without the cost and a time extension being agreed upon by the two parties
in advance.

It is advisable for the contractor and owner to work together as diligently as possible to
agree upon the cost and time adjustment for the change. If the parties have been
working together throughout the course of the project, then their collaboration might
allow them to find a middle ground during the negotiation process based on effective
communication and trust. However, it is always possible that the two parties will not
come to an agreement. If the parties are unable to negotiate a mutually agreed upon
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 50
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

cost or time extension for the change, and if the contractor disagrees with performing
the work included in a CCD after a final decision has been made by the owner, then the
contractor‟s only remedy might be to continue its dispute through the channels
identified by the contract.

2.5.5 Recording the executed changes


Documentation of changes is a key responsibility of all parties of the construction
project, especially the contractor‟s and the employer representative‟s personnel. At the
beginning of a project, the staff should create standardized forms, procedures, contract
document log, an issues log, request for information (RFI) log, and potential change
orders (PCO) log so that detail project information will be maintained.

Most of the time, the contract documents log begin with the bid documents and include
the most recent drawings or sketches that might be issued as part of an RFI or
supplemental specifications by the owner or the consultants.
The creation of the contract documents log aids in establishing the baseline
requirements of the contract. As documents are revised and incorporated into the
contract, they should be available to all project personnel so that the most recent
information will be used in evaluating changes or aid in generating the as-built set of
documents as the project progresses and work is being performed.

3. RESEARCH DESIGN AND METHODOLOGY


3.1 The Study Approach and Research Type
Research is described as a process of collecting, analyzing and interpreting information
to provide solutions to questions. For the purpose of this thesis, research is defined as a
practical investigation or exploration to find out new facts or assemble old facts by
scientific ways for the purpose of developing existing theory or its application for real
problems.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 51
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

3.1.1 The Research Type


This research can be categorized as applied research, because the research was initiated
from practical problems to make assessment on the causes of change order and their
cost impact on road projects in Ethiopia. To get data necessary for the research, three
methods are available: questionnaire surveys, review of project records, and case
studies. Most researchers found through their research that questionnaire surveys are
best when used to collect opinions from a large sample of people in a specific industry.
The only drawback is that opinions can be biased based on their position within the
industry. To counteract this perceived bias, in this research review of project record
data of different road construction projects is used as a primary data source.

3.2 Data Source and Collection


The study has employed data sources to produce respondents‟ documents and archival
documents. The respondents‟ documents were collected using questionnaires from
professionals in the construction industry such as clients, consultants and contractors.
Archival documents were mostly from reports of completed projects and those on
progress, in which the project history was recorded and investigated thoroughly which
were very important in identifying the recurrent problems related to change orders on
road construction projects in Ethiopia. In addition, they helped to find out how change
orders arise and being handled and managed.
During data collection, the most tiresome and challenging aspect was the unpunctuality
and negligence of respondents. This so because, most of the time, the respondents‟ were
not enthusiastic enough to give their response as per the schedule they agreed to return
the questionnaire. Contrary to this, archival documents from Ethiopian Roads
Authority were voluntarily provided by the project engineers, who were assigned to
administer the contracts of each project under consideration, whenever they are asked
their cooperation. The projects used as a data source were randomly selected by those

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 52
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

project engineers at the beginning of the data collection as per the command given by
deputy director of Ethiopian Road Authority.
The questionnaire was carefully designed in light of getting high response rate from
respondents. The responses for the structured part of the questionnaire are based on
Likert’s-scale, ordinal data commonly used to measure attitude, providing a range of
responses to a given question or statement.
The variables of major causes of change order categories in road construction projects in
Ethiopia were identified from the desk study by clustering each reason of change order
in to major categories of change. Then, respondents are asked about their agreement on
these variables whether they can be the causes of change order or not, so that the
respondents are required to choose one of the above categories as per their attitude
toward the causes.
Depending on the response given on the causes of change order, the respondents are
once again inquired to give their response on the chance of occurrence of such variables
based on the following choices:
Not at all = 0, Unlikely = 1, Likely = 2, Almost certain = 3, and Certain = 4.
The probability to happen of each of the variables based on their chance of occurrence is
defined in percentile as follow: Not at all= 0%, Unlikely= 0% - 25%, Likely =26% - 50%,
Almost certain =51% - 99%, Certain = 100%.
At last the respondents were inquired to give their response on the type of
consequential cost impact the causes of change orders have based on their responses on
the frequency of occurrence alleged causes of change order. The responses on the
consequential cost impacts were expected to be given as: Decrement (Positive) or
Increment (Negative).
The identification of the responsible party for the causes of change order and their cost
impact was done after the required data regarding the causes and cost impacts of
change order is gathered. The questionnaires are prepared in such a way that detailed
information can be gathered in a systematically prepared matrix table.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 53
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

3.3 The Research Population


The research samples are taken from stakeholders in road construction industry such as
clients, contractors and consultants. Ethiopian Roads Authority, ERA, is the only and
sole owner (employer) of the road projects used as a sample in the research. Whereas,
there are considerable number of consultants and contractors in the road sector; of
which few are used as a sample of the study, selected randomly based on their
experience in the road construction projects.
Though the parties involved in the construction industry are not equally liable for the
occurrence of changes, the samples were restricted to be fifteen from each party so that
the questionnaires are fairly distributed among the respondents. This would avoid
biasedness and miss conclusion due to uneven number of population size when the
responses are analyzed.

3.4 Method of Analysis


In the analysis the Mean Score method is adopted to establish the relative importance of
the causes of change order on the road construction projects in Ethiopia. In addition to
this, Likert‟s scale of five ordinal measures of agreement towards each statement (0, 1, 2,
3 and 4) is used to calculate the mean score for each factor that is used to determine the
relative ranking.
The mean score (MS) for each variables of cause of change order is computed by using
the following formula:

∑( f x S )
MS = 3.10
N
Where:-
MS – Mean Score
f – Frequency of responses for each score
S – Scores given to each factor (from 0 to 4)
N – Total number of responses concerning each factor
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 54
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

The difference in ranking of two groups of respondents for several factors (such as
client Vs. consultant, client Vs. contractor, and consultant Vs. contractor) is measured

using the Spearman rank correlation coefficient, ρ (Rho).

The Spearman rank correlation coefficient, ρ, for any two groups of ranking is given by

the following formula.

6 ×( ∑ di2 )
ρ ═ 1— 3.20
N × (N2 – 1)

Where: ρ – Spearman rank correlation coefficient


di – The difference in ranking between each pair of factors
N – Number of factors (variables)
Procedure for hypothesis testing:
1. Define the null hypothesis (H0) and the alternative hypothesis (HA)
2. Choose a value for ρ. (i.e. choose the significance level)
3. Calculate the value of the test statistic, ρ.
4. Compare the calculated value with a table of the critical values of the test statistic.
5. If the calculated value of the test statistic is less than the critical value from the table,
accept the null hypothesis (H0). If the absolute (calculated) value of the test statistic is
greater than or equal to the critical value from the table, reject the null hypothesis
(H0) and accept the alternative hypothesis (HA).

4. DATA ANALYSIS AND DISCUSSION


This part of the research deals with the analysis and discussion of the data gathered
from the desk study and questionnaire survey. It includes the identification of the major
causes of change order in road construction projects, rate of occurrences of variables of
change orders, the relationship between: change orders and project contract amount,
project type(new and upgrading) and change orders, the cost impact of the variables of
change orders on road projects.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 55
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

The procedure used in analyzing the results was aimed at establishing the relative
importance of the various factors responsible for change orders and their cost impact.
The questionnaire gives each respondent an opportunity to express their agreement or
disagreement on whether that change order is the cause of dispute among the
contracting parties or not. As a result respondents were expected to give their response
as per the following alternatives: strongly disagree, disagree, agree and strongly agree;
frequency of occurrence of the variables of causes of change order; and the cost impacts
of each change order variables on the final cost of the project. For each variables of
change order, the percentages of respondents‟ response were ranked for analysis
purpose. On the basis of the ranking of the variables by the various groups, it was
possible to identify the most important factors that influenced change order on road
construction projects in Ethiopia.
In the desk study seventeen road construction projects constructed in almost the four
corners of Ethiopia were surveyed and 123 total reasons of change orders and their
corresponding costs were taken onto consideration. During the desk study, documents
such as project completion status reports of each project were thoroughly investigated.
This helps to understand the reasons behind each project‟s change orders, and the
change order amounts accompanied by each cause of change order. Collecting these
data helped to analyze and draw the relationship between rate of causes of change
order and the corresponding associated cost and hence the gross cost impact of the
change orders.

4.1 Questionnaire Response Rate


Detailed questionnaires were designed and distributed for the assessment of causes and
cost impact of change order on road construction projects in Ethiopia. For this purpose,
a total of 45 questionnaires were distributed equally among professional employees of
contractors, consultants and employer (ERA). As a result, 38 of the questionnaires were
returned back with completed answers for each question inquired.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 56
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Though 45 questionnaires were distributed, only 38 of them (84.44 percent) are


returned.
Table – 1 below shows the number of questionnaires distributed to clients, consultants
and contractors and the number of questionnaires returned from these stakeholders
including their percentage response rate.
Table-1 Summary of Respondents’ Response Rate
Questionnaire Questionnaire Response
Professional Distributed Returned Rate
No. Respondents No. % No. % %
1 Employer 15 33.33 14 36.84 93.33
2 Consultant 15 33.33 13 34.21 86.67
3 Contractor 15 33.33 11 28.95 73.33
Total / Average 45 100 38 100 84.44

4.2 The Existence and Extent of Change Orders


In the desk study, the data were collected from seventeen road projects constructed
across Ethiopia with a total project cost of 8,143,451,307.55 (See Table – 2). The projects
range in value from birr 138,601,822.00 to birr 817,570,809.78 and were constructed
between the years of 2005 and 2014. Sixteen different contractors completed these
projects and participated in supplying the change order data used in this research.
Moreover, a total of sixteen different local and international consulting firms
participated in design and supervision of these projects. From the progress reports and

Other relevant documents of the projects, a total of 123 contract change orders were
found and examined as shown in table-3.

Table – 2 projects included in the desk study and their Project Cost

Percentage
Project Net Amount of
Name of Road Initial Project Final Project Of Change
Code Change
Projects Cost Order Cost order

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 57
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

(%)
P1 Arerti - Gobesa 444,696,050.03 (46,307,004.54)
398,389,045.49 90
P2 Sembo - Sholagebeya 613,072,806.85 (64,266,499.62)
548,806,307.23 90
P3 Gindeber - Gobesa 755,411,059.74 (68,718,699.35)
686,692,360.39 91
P4 Mojo-Ejere-Arerti 407,320,609.16 5,161,076.68
412,481,685.84 101
P5 Wolkite - Hosaina 618,998,415.32 28,279,611.75
647,278,027.07 105
P6 Wukro - Zalambessa 530,187,942.00 170,216,010.63
700,403,952.63 132
P7 Gonder - Debark 690,779,965.13 83,306,143.32
774,086,108.45 112
P8 Gondar - Dansha 369,149,638.91 (14,214,407.57)
354,935,231.34 96
Nazaret-Assela-
P9 Dodola 398,988,518.00 1,426,821.67
409,276,701.61 100
P10 Aposto - Irba Moda 660,938,029.10 109,663,504.10
770,601,533.20 117
P11 Irba Moda - Wadera 185,447,955.09 (4,342,346.28)
191,105,608.82 98
P12 Nekemte - Mekenajo 300,723,746.00 10,444,650.27
311,168,396.27 103
P13 Nekemte - Nejo 138,601,822.00 50,119,176.31
198,720,998.31 136
P14 Gore-Gambela 817,570,809.78 6,260,110.81
823,830,920.59 101
P15 Ginir - Beredimtu 541,718,515.05 30,420,788.38
572,139,303.43 106
P16 Irebti - Afdera 436,758,578.38 (2,483,53825)
434,275,040.13 99
P17 Yalo-Abala 233,086,874.01 91,769,472.51
324,856,346.52 139

TOTAL PROJECT COST 8,143,451,307.55 386,734,870.82 8,530,186,178.37


105
N.B: Negative net change order amount means a decrement of cost and the positive one is
increment of cost.

During the desk study, the reasons for the change orders associated with each project
name are tabulated as shown in Table-3 with their corresponding change order
amounts.

Table – 3 Summary of Reason of Change Orders and their change order amount

S/No Reasons of Change Order Change order Project’s

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 58
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Amount Name
1 Change of two types of type A houses to type B houses. (463,937.62) P1
2 Re-alignment from km 83+008.922 to km 85+345.057
Back/88+003.497 Ahead. (24,135,269.04) ―
3 Re-grading from km 79+060 to 79+600. 75,990.40 ―
4 Realignment from km 88+541.107 to km 89+216.98
Back/89+280.899 Ahead. (3,274,904.04) ―
5 Re-alignment from km 94+065.923 to km 96+409.492
Back/96+393.625 Ahead. (3,612,475.03) ―
6 Re-grading of the vertical alignment from km 100+100 to
100+860 (end of the project). (734,936.32) ―
7 Re-alignment from km 94+390 to km 95+209.4 Back/95+200
Ahead. 1,672,315.14 ―
8 Re-alignment from km 96+000 to km 98+446.216
Back/98+500 Ahead. (14,069,024.63) ―
9 Omission of the modified vertical alignment on V.O No.7
and to follow the original contract design. 734,936.32 ―
10 Re-alignment from km 94+765 to km 95+043 Back/95+033
Ahead. (1,738,203.17) ―
11 Re-alignment from km 91+499.641 to km 91+662
Back/91+679 Ahead. (761,496.55) ―

Net Amount of Change Order of Project - P1 (46,307,004.54)

12 Overall design revision in relation to the requirements of (71,181,738.38)


geometric design and re-alignment from 0+000 to 59+833.05 P2
13 Re-alignment from km 36+900 to km 38+433.06 to provide
better access to Sholagebeya town 1,239,542.26 ―
14 Mitigation works for the landslide prone and back slope
eroded road sections. 5,675,696.50 ―

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 59
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Net Amount of Change Order of Project – P2 (64,266,499.62)


15 Overall design revision in relation to the requirements of
geometric design. (69,953,131.09) P3
16 Re-alignment as a result of the height of the retaining wall
constructed around station 100+859 of contract-2, Arerti-
Gobensa road project. 1,234,431.74 ―

Net Amount of Change Order of Project – P3 (68,718,699.35)


17 Alignment change from station 33+960 to 34+415.66 of the
bridge to get a better foundation and to minimize the
scouring effect in the long run. 5,163,196.98 P4
18 Pavement design changes from station 58+000 to 59+000
and 59+500 to 64+500. 2,743,189.14 ―
19 Design change of longitudinal drainage structure to
accommodate expected surface water that may flow to the
project road from station 0+000 to 1+300 4,258,520.87 ―
20 Replacement of type "A" houses and some of type "B"
houses to type "C" houses. (6,731,876.47) ―
21 Longitudinal drainage structure design change. (280,740.70) ―

Net Amount of Change Order of Project – P4 5,161,076.68


22 Design change of kilometer posts 8,786.86 ―
23 Additional type B houses for the Engineers facility 3,536,250.00 P5
24 Extension of town section (Hosaina Town) 22,950,435.75 ―
25 Design Modification of Woredas‟ town (457,380.00) ―
26 Additional cross drainage structures 2,250,306.00 ―

Net Amount of Change Order of Project – P5 28,279,611.75


27 Additional Engineer's house construction 3,247,952.29 P6

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 60
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

28 Change of 600mm pipe to 900mm 804,788.40 ―


29 Fireweyni town section modification 15,444,484.92 ―
30 Edagahamus town section modification 5,781,128.60 ―
31 Change of Radio to Mobile (606,468.61) ―
32 Adigrat town section modification 43,045,254.11 ―
33 Pavement design change 3,103,281.43 ―
34 Modification of drainage structures 4,850,908.74 ―
35 Modification of drainage structures (97,632.92) ―
36 Fatse town section modification 10,584,428.36 ―
37 Provision of approach road at Zalambessa town 78,001,430.49 ―
38 Additional two bridge works 4,211,241.60 ―
39 Fireweyni town additional works 4,166,246.57 ―
40 Fatse town concrete cover for ditch 1,769,792.11 ―
41 HIV/AIDS and Alleviation works 2,393,105.57 ―
42 Concreting shoulder in Fatse town 1,137,252.96 ―
43 Slab culvert construction from 64+995 1,449,123.34 ―
44 Roundabout construction in Adigrat town 1,137,252.96 ―
45 Omission of the last 226 m in Zalambessa town (2,126,216.44) ―
46 Omission of grassing and landscaping (8,081,343.85) ―

Net Amount of Change Order of Project – P6 170,216,010.63


47 Design modification of town section at Amba-ghiorgis,
Dabat and Debark towns. 50,658,919.37 P7
48 Re-alignment of km 25 3,173,128.95 ―
49 Provision of median at Ambaghiogis & Dabat towns 1,358,250.00 ―
50 Design modification of Gondar town section 28,115,845.00 ―

Net Amount of Change Order of Project – P7 83,306,143.32


51 Deletion of stretch from km (-)2+000 to km 0+000 from
scope of the contract (1,176,158.00) P8

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 61
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

52 Change in Specification for providing Asphalt concrete in


lieu of DBST 1,234,431.74 ―
53 Due to missing item of power door lock and electrical (263,925.00)
winch in type "A" vehicle ―
54 Re-construction of pipe culvert at km 64+610 92,250.00 ―
55 Reduction in thickness of capping layer (2,404,610.76) ―
56 Increase in BOQ quantities of bridge over Sanja river at
km 66+927 887,971.81 ―
57 Re-construction of pipe culvert at km 57+127 47,912.52 ―

58 Reduction in quantity of Crushed stone base course (12,632,279.88) ―

Net Amount of Change Order of Project – P8 (14,214,407.57)


59 Reduction in quantity of primer coat MC-30 cut back
bitumen at 1.1 liter per square meter (1,384,600.00) P9
60 Additional pipe culvert at km 105+510
27,010.74 ―
61 Reconstruction of existing pipe culvert at km 79+823
62,292.52 ―
62 Deletion of pipe culvert at km 43+772 (7,543.79) ―
63 Deletion of new pipe culvert at km 75+200 (33,322.81) ―
64 Deletion of new pipe culvert at km 33+280 (45,872.65) ―
65 25% increase in BOQ quantity for Bill No. 2.04 (Pay item
No. 42.03 (cut and borrow to fill) 7,194,457.50 ―
66 Change in quantity for Elastomeric bearings for bridges
item No. 5.13 61,456.37 ―
67 Drainage system and side walk/foot path in urban sections
of Tikil Dingay, Sanja and Saroka (5,119,648.91) ―
68 Re-construction of pipe culvert at km 34+435 45,136.66 ―
69 Re-construction of pipe culvert at km 34+714 85,762.42 ―
70 Re-construction of pipe culvert at km 81+240 31,174.04 ―

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 62
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

71 Providing and placing of Tack Coat RC-70 cut back


bitumen complying with AASHTO M81 or M82 and
application as per ERA STS division 6200 and 6700
complete. 47,930.47 ―
72 Construction of new pipe culvert at km 4+389 35,672.10 ―

Net Amount of Change Order of Project – P9 1,426,821.67


73 Widening of Bekoji town section 2,888,957.72 P10
74 Provision of walkways in urban sections 5,711,383.08 ―
75 Change of wearing course from Double Bitumen Surface
Treatment( DBST ) to Asphalt Concrete (AC) 66,019,090.00 ―
76 Provision of additional slab culverts 1,737,552.20 ―
77 Design modification of Assasa town section 1,452,000.66 ―
78 Construction of safe structures in flood prone areas of
Kubsa and Assasa Town 5,426,806.64 ―
79 Removing and relaying of existing pipes 742,153.50 ―
80 Provision of Vehicular access 14,635,196.30 ―
81 Change of Single Surface Treatment(SST) to AC at towns
for parking lanes 11,050,364.00 ―

Net Amount of Change Order of Project – P10 109,663,504.10


82 Change of drainage type from 900mm pipe culvert to slab
culvert 37,216.00 P11
83 Change in design alignment of the road section from km
8+500 to km 10+578.709 and also construction of retaining
walls along the project route; redesign of Kola River Bridge. (16,005,353.40) ―
84 Change in design alignment of the road section from km
25+300 to km 27+150 and from km 31+100 to km
32+625.213 96,141.85 ―
85 Provision of medians in Aletawondo town section (84,975.92) ―

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 63
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

86 Change in alignment of the road section from km 69+680 to


km 70+240 491,785.62 ―
87 Replacement of natural gravel sub-base material by crushed
stone material for sub-base layer construction in Bore town 1,855,500.00 ―
88 Change in alignment of the road section from km 30+640 to
km 32+520 (335,193.33) ―
89 Change in alignment of the road section from km 18+660 to
km 19+512 (79,557.00) ―
90 Blending of capping material with crushed aggregate for
sub-base layer construction from km 0+000 to km 17+000 2,722,569.90 ―
91 Provision of center median curbstone 6,959,520.00 ―

Net Amount of Change Order of Project – P11 (4,342,346.28)


92 Horizontal & vertical alignment to improve the sharp curve
and steep gradient from km 155+820 to km 156+940 175,233.26 P12
93 Replacement of 15 existing corroded steel pipes and one
new pipe culvert at 16 different locations. 1,890,391.68 ―
94 Horizontal & vertical alignment to improve the sharp
hairpin bends and steep gradient from km 134+400 to km
138+600 6,183,363.26 ―

95 Demolition of existing slab culvert and re-construction of


new slab culvert at station 138+587 239,996.59 ―
96 Construction of lined ditch type II in undercut section
having a highly expansive soil and < 5% gradient from
121+000 to 160+000 806,520.00 ―

97 Construction of stairway at high cut back slope location for


local villagers at 35 different locations 1,110,148.07 ―
98 Replacement of existing damaged steel pipe culvert by a
new concrete pipe culvert at km 112+346.15 38,997.41 ―

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 64
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Net Amount of Change Order of Project – P12 10,444,650.27


99 Provision of curbed median at Kibremengist town from km
144+160 to 151+160 595,971.74 P13
100 Change of Vehicles & House Type "A" by Type "B" (2,702,989.12) ―
101 Additional Vehicles & House Type "B" 1,416,730.31 ―
102 Provision of retaining wall from km 42+440 to 42+720 (1,789,927.70) ―
103 Provision of retaining wall from km 42+020 to 42+240 (6,499,430.54) ―
104 Review of design at Bridges km 25+345 & 26+784 (690,346.85) ―
105 Provision of retaining wall from km 41+156 to 41+440 to
42+240 (566,882.37) ―
106 Review of design at Logita Bridge km 36+470 5,379,507.05 ―
107 Review of design at Gelana Bridge km 33+904 692,836.24 ―
108 Review of design at Bonewa Bridge km 49+672 5,049,614.37 ―
109 Provision of retaining wall from km 38+640 to 38+760 to
38+800 & 49+520 to 49+600 811,240.25 ―
110 Provision of hand laid rock embankment unit rate 1,441,176.26 ―
111 Provision of retaining wall for back holding at Gelana
Bridge approach & other protection works 5,358,877.64 ―
112 Change of Road standard from DBST to AC 41,622,799.03 ―

Net Amount of Change Order of Project – P13 50,119,176.31


113 Additional covered U-ditch & Parking lane at Gimbi town 5,624,602.97 P14

114 Change in culvert type and sub-base thickness 635,507.84 ―

Net Amount of Change Order of Project – P14 6,260,110.81


115 (1)Change of type D drain to trapezoid precast concrete, (2)
change of type A drain (3) tack coat variation 5,420,788.38 P15
116 Design change of Aleltu and Agar Bridges 25,000,000.00 ―

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 65
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Net Amount of Change Order of Project – P15 30,420,788.38


117 Change of type A Vehicles and Engineers office type A to
type B (3,001,763.21) P16
118 For foundation investigation 518,224.96 ―

Net Amount of Change Order of Project – P16 (2,483,538.25)


119 Change of type A Vehicles and Engineers office type A to
type B (5,234,678.00) P17
120 Additional 13 bridges 43,597,330.27 ―

121 Additional 5 bridges, 32 slab/box culverts and 121 pipe


culverts 49,265,792.24 ―
122 Additional Engineer‟s Housing Accommodations 1,439,028.00 ―

123 Additional Engineer‟s Housing Accommodations 2,702,000.00 ―

Net Amount of Change Order of Project – P7 91,769,472.51

TOTAL AMOUNT OF CHANGE ORDER 410,596,232.76

From table-3, it can be easily seen that a substantial amount change order occurs in those
road construction project under the study. As it is depicted in table – 2, the total project
cost of those projects under consideration was 8,143,451,307.55. However, as a result of
the total amount of change order, the total project cost increased by an amount of
410,596,232.76 birr. This amount is around five percent (5%) of the total sum of project
cost of the projects under consideration.

Hence, the desk study has proved the existence of change order in the road
construction project in Ethiopia to the extent that the causes and cost impact of change

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 66
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

orders on road construction projects in Ethiopia must be studied so that the stake
holders in the construction industry be aware of the causes of change orders and their
cost impact while managing the construction contracts.

4.3 Assessment of Major Causes of Change Order Categories


Though causes of change order are identified by the different researchers, as shown in
the literature review, all of the stated causes might not represent the causes of change
order in the case of road construction in Ethiopia. In this research, after careful review
of the available literature, six major categories of causes of change order are selected to
reduce redundancy of similar causes and to look for one which would reduce overlap
when sorting data. One of the objectives of this research is to identify the causes which
were resulting in change orders. Therefore, the following is a list of the major categories
of causes of change order used in this research:
1. Design Errors and Omissions
2. Scope Change
3. Unforeseen Conditions
4. Value Engineering
5. Force Majeure
6. Others
Design Errors and Omissions - This cause relates to items that were omitted, improperly
drawn or improperly coordinated by the design team. Scope Change - An owner directed
scope change can occur due to unexpected needs, change of business, purpose of
project, acquisition of more capital, or the depletion of expected available funds.
Unforeseen Conditions - Unforeseen conditions are defined as conditions in the field that
do not match the expected conditions. Value Engineering - substitution as a result of
improved function or a reduced cost. Force Majeure -Time delays due to forces beyond
the control of the contractor. Others – Other causes of change order includes those
causes with indirect effect on the project.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 67
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Table – 4, Major categories of Change Order and Reasons of change


No Major Categories of Change
Order Reasons of causes of change order
1 Design errors & Omission Replacement of materials or procedures
Change in specifications
Change in design
Design discrepancies
Conflicts between contract documents
Design complexity
Ambiguous design details
Inadequate working drawing detail

2 Change of scope Noncompliance of design with owner‟s requirements


Inadequate project objectives
Inadequate scope of work

3 Unforeseen conditions Unforeseen problems


Differing site condition
Increase /decrease in quantities
Right of way problems

4 Value Engineering Replacement of material and equipment


Change in economic conditions
Inflation

5 Force majeure Harsh weather Conditions


Natural disaster , etc.

6 Others Health and safety condition


Change in government regulations
Defective workmanship
Lack of skilled man power
Technology changes, etc.

Those reasons of change order depicted in table – 3, are grouped in to major categories
of causes of change order along with their corresponding change order amount as
shown in the tables 5 (a) – (f).
Table – 5 (a) Change orders due to Design Errors and Omissions
S/No Reasons of Change Order Change order Project
Amount

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 68
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

1 Re-alignment from km 83+008.922 to km 85+345.057


Back/88+003.497 Ahead. (24,135,269.04) P1
2 Re-grading from km 79+060 to 79+600. 75,990.40 “
3 Realignment from km 88+541.107 to km 89+216.98
Back/89+280.899 Ahead. (3,274,904.04) “

4 Re-alignment from km 94+065.923 to km 96+409.492


Back/96+393.625 Ahead. (3,612,475.03) “
5 Re-grading of the vertical alignment from km 100+100
to 100+860 (end of the project). (734,936.32) “
6 Re-alignment from km 94+390 to km 95+209.4
Back/95+200 Ahead. 1,672,315.14 “
7 Re-alignment from km 96+000 to km 98+446.216
Back/98+500 Ahead. (14,069,024.63) “
8 Omission of the modified vertical alignment on V.O
No.7 and to follow the original contract design. 734,936.32 “
9 Re-alignment from km 94+765 to km 95+043
Back/95+033 Ahead. (1,738,203.17) “
10 Re-alignment from km 91+499.641 to km 91+662
Back/91+679 Ahead. (761,496.55) “
11 Overall design revision in relation to the requirements
of geometric design and re-alignment from 0+000 to
59+833.05 (71,181,738.38) P2
12 Re-alignment from km 36+900 to km 38+433.06 to
provide better access to Shola-gebeya town 1,239,542.26 “
13 Overall design revision in relation to the requirements
of geometric design. (69,953,131.09) P3
14 Re-alignment as a result of the height of the retaining
wall constructed around station 100+859 of contract-2, 1,234,431.74
Arerti - Gobensa road project. “

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 69
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

15 Alignment change from station 33+960 to 34+415.66 of


the bridge to get a better foundation and to minimize
the scouring effect in the long run. 163,196.98 P4
16 Pavement design changes from station 58+000 to
59+000 and 59+500 to 64+500. 2,743,189.14 “
17 Design change of longitudinal drainage structure to
accommodate expected surface water that may flow to
the project road from station 0+000 to 1+300 4,258,520.87 “
18 Longitudinal drainage structure design change. (280,740.70) “
19 Design change of kilometer posts 8,786.86 “
20 Design Modification of Woredas‟ town (457,380.00) P5
21 Change of 600mm pipe to 900mm 804,788.40 P6
22 Fireweyni town section modification 15,444,484.92 “
23 Edagahamus town section modification 15,781,128.60 “
24 Adigrat town section modification 43,045,254.11 “
25 Pavement design change 3,103,281.43 “
26 Modification of drainage structures 4,850,908.74 “
27 Modification of drainage structures (97,632.92) “
28 Fatse town section modification 10,584,428.36 “
29 Provision of approach road at Zalambessa town 78,001,430.49 “
30 Omission of the last 226 m in Zalambessa town (2,126,216.44) “
31 Omission of grassing and landscaping (8,081,343.85) “
32 Design modification of town section at Amba-ghiorgis,
Dabat and Debark towns. 50,658,919.37 P7
33 Re-alignment of km 25 3,173,128.95 “
34 Design modification of Gondar town section 28,115,845.00 “
35 Deletion of stretch from km (-)2+000 to km 0+000 from
scope of the contract (1,176,158.00) P8
36 Reduction in thickness of capping layer (2,404,610.76) “
37 Widening of Bekoji town section 2,888,957.72 P9

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 70
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

38 Change of wearing course from Double Bitumen


Surface Treatment( DBST ) to Asphalt Concrete (AC) 66,019,090.00 “
39 Design modification of Assasa town section 1,452,000.66 “
40 Change of Single Surface Treatment(SST) to AC at
towns for parking lanes 11,050,364.00 “
41 Change of drainage type from 900mm pipe culvert to
slab culvert 37,216.00 P10
42 Change in design alignment of the road section from
km 8+500 to km 10+578.709 and also construction of
retaining walls along the project route; redesign of Kola
River Bridge. (16,005,353.40) “
43 Change in design alignment of the road section from
km 25+300 to km 27+150 and from km 31+100 to km
32+625.213 96,141.85 “
44 Change in alignment of the road section from km
69+680 to km 70+240 491,785.62 “
45 Change in alignment of the road section from km
30+640 to km 32+520 (335,193.33) “
46 Change in alignment of the road section from km
18+660 to km 19+512 (79,557.00) “
47 Horizontal & vertical alignment to improve the sharp
curve and steep gradient from km 155+820 to km
156+940 175,233.26 P11
48 Horizontal & vertical alignment to improve the sharp
hairpin bends and steep gradient from km 134+400 to
km 138+600 6,183,363.26 “
49 Design change of Aleltu and Agar Bridges 25,000,000.00 14
NET AMOUNT DUE TO DESIGN ERRORS AND
OMISSION 158,583,295.80

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 71
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Table – 5 (b) Change orders due Change of Scope

S/No Reasons of Change Order Change order


Amount Project
1 Additional type B houses for the Engineers facility 3,536,250.00 P5
2 Extension of town section (Hosaina Town) 22,950,435.75 “
3 Additional cross drainage structures 2,250,306.00
4 Additional cross drainage structures 2,250,306.00 “
5 Additional two bridge works 4,211,241.60 P6
6 Fireweyni town additional works 4,166,246.57 “
7 Fatse town concrete cover for ditch 1,769,792.11 “
8 Concreting shoulder in Fatse town 1,137,252.96 “
9 Slab culvert construction from 64+995 1,449,123.34 “
10 Roundabout construction in Adigrat town 1,137,252.96 “
11 Provision of median at Ambaghiogis & Dabat towns 1,358,250.00 P7
12 Change in Specification for providing Asphalt concrete in
lieu of DBST 1,234,431.74 “
13 Additional pipe culvert at km 105+510 27,010.74 P8
14 Construction of new pipe culvert at km 4+389 35,672.10 “
15 Provision of walkways in urban sections 5,711,383.08 “
16 Provision of additional slab culverts 1,737,552.20 “
17 Construction of safe structures in flood prone areas of
Kubsa and Assasa Town 5,426,806.64 P9
18 Removing and relaying of existing pipes 742,153.50 “
19 Provision of medians in Aletawondo town section (84,975.92) P10
20 Replacement of natural gravel sub-base material by
crushed stone material for sub-base layer construction in
Bore town 1,855,500.00 “
21 Provision of center median curbstone 6,959,520.00 “
22 Construction of stairway at high cut back slope location

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 72
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

for local villagers at 35 different locations 1,110,148.07 P11


23 Provision of curbed median at Kibremengist town from
km 144+160 to 151+160 595,971.74 “
24 Provision of retaining wall from km 42+440 to 42+720 (1,789,927.70) P12
25 Provision of retaining wall from km 42+020 to 42+240 (6,499,430.54) “
26 Provision of retaining wall from km 41+156 to 41+440 to
42+240 (566,882.37) “
27 Provision of retaining wall from km 38+640 to 38+760 to
38+800 & 49+520 to 49+600 811,240.25 “
28 Provision of hand laid rock embankment unit rate 1,441,176.26 “
29 Provision of retaining wall for back holding at Gelana
Bridge approach & other protection works 5,358,877.64 “
30 Change of Road standard from DBST to AC 41,622,799.03 “
31 Additional covered U-ditch & Parking lane at Gimbi town 5,624,602.97 P13
32 Change in culvert type and sub-base thickness 635,507.84 “
33 (1)Change of type D drain to trapezoid precast concrete,
(2) change of type A drain (3) tack coat variation 5,420,788.38 P14
34 Additional 13 bridges 43,597,330.27 P17
35 Additional 5 bridges, 32 slab/box culverts and 121 pipe
culverts 49,265,792.24 “

NET AMOUNT DUE TO CHANGE OF SCOPE 215,255,073.71

Table – 5 (c) Change Orders due to Unforeseen Condition

Change order
S/No Reasons of Change Order Amount Project
1 Increase in BOQ quantities of bridge over Sanja river at P8
km 66+927 887,971.81
2 Reduction in quantity of Crushed stone base course (12,632,279.88) “
3 Reduction in quantity of primer coat MC-30 cut back
bitumen at 1.1 liter per square meter (1,384,600.00) “
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 73
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

4 25% increase in BOQ quantity for Bill No. 2.04 (Pay item
No. 42.03 (cut and borrow to fill) 7,194,457.50 “
5 Change in quantity for Elastomeric bearings for bridges
item No. 5.13 61,456.37 “
6 Review of design at Bridges km 25+345 & 26+784 (690,346.85) P12
7 Review of design at Logita Bridge km 36+470 5,379,507.05 “
8 Review of design at Gelana Bridge km 33+904 692,836.24 “
9 Review of design at Bonewa Bridge km 49+672 5,049,614.37 “

NET AMOUNT DUE TO UNFORESEEN CONDITIONS 4,558,616.61

Table – 5(d) Change orders due to Value Engineering

S/No Reasons of Change Order Change order Project


Amount
1 Change of two type A houses to type B houses. (463,937.62) P1
2 Replacement of type "A" houses and some of type "B"
houses to type "C" houses. (6,731,876.47) P4
3 Change of Radio to Mobile
(606,468.61) “
4 Drainage system and side walk/foot path in urban
sections of Tikil Dingay, Sanja and Saroka (5,119,648.91) P8
5 Change of Vehicles & House Type "A" by Type "B" (2,702,989.12) P12
6 Change of type A Vehicles and Engineers office type A
to type B (3,001,763.21) P16
7 Change of type A Vehicles and Engineers office type A
to type B (5,234,678.00) P17

NET AMOUNT DUE TO VALUE ENGINEERING (23,861,361.94)


Table – 5 (e) Change Orders due to Force majeure

S/No Reasons of Change Order Change order


Amount Project
1 Construction of lined ditch type II in undercut section
having a highly expansive soil and < 5% gradient from 806,520.00
121+000 to 160+000 P11

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 74
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

NET AOUNT DUE TO FORCE MAJEUR 806,520.00

Table – 5 (f) Change orders due to other causes

S/No Reasons of Change Order Change order


Amount Project
1 Additional Engineer's house construction 3,247,952.29 P6
2 HIV/AIDS and Alleviation works 2,393,105.57 “
3 Due to missing item of power door lock and electrical
winch in type "A" vehicle (263,925.00) P8
4 Re-construction of pipe culvert at km 64+610 92,250.00 “
5 Re-construction of pipe culvert at km 57+127 47,912.52 “
6 Reconstruction of existing pipe culvert at km 79+823 62,292.52 “
7 Re-construction of pipe culvert at km 34+435 45,136.66 “
8 Re-construction of pipe culvert at km 34+714 85,762.42 “
9 Re-construction of pipe culvert at km 81+240 31,174.04 “
10 Providing and placing of Tack Coat RC-70 cut back
bitumen complying with AASHTO M81 or M82 and
application as per ERA STS division 6200 and 6700
complete. 47,930.47 “
11 Provision of Vehicular access 14,635,196.30 P9
12 Blending of capping material with crushed aggregate
for sub-base layer construction from km 0+000 to km
17+000 2,722,569.90 “
13 Replacement of 15 existing corroded steel pipes and
one new pipe culvert at 16 different locations. 1,890,391.68 P11
14 Demolition of existing slab culvert and re-construction
of new slab culvert at station 138+587 239,996.59 “
15 Replacement of existing damaged steel pipe culvert by
a new concrete pipe culvert at km 112+346.15 38,997.41 “
16 Additional Vehicles & House Type "B" 1,416,730.31 P12
17 For foundation investigation 518,224.96 P16
18 Additional Engineer‟s Housing Accommodations 1,439,028.00 P18

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 75
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

19 Additional Engineer‟s Housing Accommodations 2,702,000.00 P19

NET AMOUNT DUE TO OTHER CAUSES 31,392,726.64

One of the key questions presented at the beginning of this research was, “What are the
causes of most contract changes in Ethiopian road construction projects?” And as it
was mentioned above, form seventeen projects about 123 change order records were
analyzed to answer this question. Of the changes included in the study a review of the
project record data showed that 40.8% were caused by design errors and omissions,
29% were change of scope by owner, 15.8% resulted from other causes, 7.5% were
caused by unforeseen conditions. The rest were caused by value engineering and force
majeure (see table-6 below).

Table – 6, Summary of Major Causes of Change order category by percent

Number Total
No Major Categories of Causes of of Change order
Change order Change order (In %)
1 Design errors and omissions 49 40.8
2 Change of scope 35 29.3
3 Unforeseen conditions 9 7.5
4 Value Engineering 7 5.8
5 Force majeure 1 0.8
6 Others 19 15.8
TOTAL 123 100

The causes of change order from the questionnaire survey are identified based on
respondents‟ response on each change order category by the frequency of their
occurrence during the construction period. The factors which are chosen by the
respondents as causes of change order on road construction projects in Ethiopia are
identified from the returned questionnaires based on the mean scores (MS) of the three
groups of respondents, clients, consultants and contractors for each variables of change
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 76
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

order. In this research variables of change order which have a mean score of greater
than 2 are taken as causes of change order; since a mean score of less than 2 means the
respondents do not agree that the variable could be considered as a cause of change
order.
Table - 7, Frequency of occurrence of Change order categories based on the responses of
clients, consultants and contractors;
Major Categories of Causes of Mean Score (MS) Weighted
No. Change Order Employer Consultant Contractor Average

1 Design errors and omissions 3.00 4.00 2.00 3.00


2 Change of scope 1.80 3.23 3.64 2.91
3 Unforeseen conditions 2.00 2.00 4.00 2.67
4 Value Engineering 2.00 2.00 2.73 2.24
5 Force majeure 1.50 1.00 2.00 1.50
6 Others 2.29 2.00 2.36 2.22

As we can observe from the weighted average column of table – 7, the major categories
of causes of change order, in their descending order, are design errors and omissions,
change of scope, unforeseen conditions, value engineering, others (like administrative
issues and the interests of third parties) and force majeure. Due to the fact that, the reasons
behind the occurrence of each change order are the results of some unfulfilled interests
or needs of either of the contracting parties, during the implementation of the project
ideas in to the ground, identifying the responsible party for each category of change
order will give meaning to the research. Hence, the respondents once again asked to
identify the contracting party which could be responsible in relation to each cause of
change order category. The identification of responsible party is useful to understand
who causes change order so that the liable party shall be accountable contractually.

The data gathered during the desk study regarding the reasons of change order proves
that most of the change orders were the results of poor design and contract
administration, which can be minimized before the implementation of project. As a

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 77
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

result, employers believe that if designs, specifications and contract documents were
prepared correctly from the start, the rate of occurrence of change orders would have
been minimal.
However, consultants on the other extreme blame that it is the employer that initiate
changes orders due to their rarely satisfying demands. To make the research free of any
biases, responsibility of each contracting party in causing the change orders was rated
during the questionnaire survey and the accountable party was selected based on the
maximum percentile on each change order category. The identification of the
accountable party for causes of change orders is depicted in Table – 8 below.

Table – 8, Percentage of Accountability for the cause of change order


Categories of Change Order Percentage of Accountability (%)

No. Causes Employer Consultant Contractor Others


1 Design errors and omissions 18.42 76.38 5.26 -
2 Change of scope 65.79 18.42 10.53 5.26
3 Unforeseen conditions 5.26 57.89 13.16 23.68
4 Value Engineering 28.95 10.53 52.63 7.89
5 Force majeure 10.53 15.79 5.26 68.42

AVERAGE RESPONSIBILITY (%) 26 36 17 21

For the question that inquired to identify which contracting party is accountable for the
occurrence of each category of change order causes, the respondents give their
responses to ascertain the liability of the contracting party relative to each category of
change order cause. As a result, 76.38 percent of the respondents make consultants to be
liable for the occurrence of most design errors and omissions. Regarding change of scope,
the second category of causes of change order, 65.79 percent of the respondents agree
that employers are accountable for the occurrence of most scope changes. The other
three change order categories, unforeseen conditions, value engineering and force majeure are

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 78
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

also caused by consultants, contractors and other causes with accountability percentage
of 57.89, 52.63 and 68.48 respectively. In a nut shell, when change order categories
analyzed together, respondents assure that 36 percent of the changes are caused by
consultants, 26 percent caused by employers, 21 percent by other causes and 17 percent
by contractors.

Percentage of Accountability
Employers
Others

21%
26%

17%

36%

Contractors
Consultants

The respondents were also asked to explain their reasons why they make each specific
contracting party being accountable for the cause of each category of change order. And
from the feedback given by the respondents, it is due to consultants‟ lack of required
data, ambiguous design details, design discrepancies, conflict between contract
documents; inadequate working drawing details etc. make consultants liable for the
occurrence of change orders.
Employers are also blamed for having inadequate scope of work, inadequate project
objective, frequent change of ideas, being delayed in resolving right-of-way issues.
Regarding to the contribution of contractors to change orders is expressed in relation to
financial shortages, lack of skilled man power, lack of knowledge of contract
management, etc.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 79
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Apart from those parties mentioned above, other causes such as third parties, like
utility agencies and governmental bodies are blamed for not cooperating with
contracting parties when their cooperation is needed. In addition to these, inflation or
increase in the cost of construction materials, change in foreign exchange rate are found
to be caused by government related actions.

4.4 Assessment of Cost Impact of Change Orders


The second key question to be answered in this research was „what kind of cost
impact do the causes of change orders imply?’ To answer this question, the cost
implication of each reasons of change order collected during the desk study are
analyzed along with the questionnaire response given by respondents for questions
designed to assess the cost impact of causes of change order.
From the desk study, the net amount of each category of causes of change order is
analyzed as shown in table-9 below.
Table – 9 Cost impacts of change orders and their total change order amount percentile
Cost impacts of Change orders Total Change
No Categories of Causes of Change order Amount (In
order Positive Negative %)
(Decrement) (Increment)
1 Design errors and omissions 158,583,295.80 38.6
2 Change of scope 215,255,073.71 52.4
3 Unforeseen conditions 4,558,616.61 1.2
4 Value Engineering (23,861,361.94) -
5 Force majeure 806,520.00 0.2
6 Others 31,392,726.64 7.6

TOTAL AMOUNT OF CHANGE ORDER (23,861,361.94) 410,596,232.76 100


NET AMOUNT OF CHANGE ORDER 386, 734,870.82

As shown in the above table-9, those causes of change included in value engineering
have total change order amount of birr 23,861,361.94. This amount is a decrement of
change order amount, the impact of those reasons of causes of change order categorized
under value engineering would be considered as positive impact since they are savings
to the employer. Whereas, except value engineering all other major categories of change
orders have a total change order amount of birr 410,596,232.76; which is an incremental
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 80
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

cost impacts which are considered as expenses to the project owners. However, the
combined impacts of all categories of change order shows an incremented (negative)
impact of birr 386,734,870.82.

Therefore, when we look at the cost impact of value engineering from the desk study,
we can conclude that, in this specific study, value engineering has a reduction cost
impact in those road construction projects under consideration. However, the rest
categories of causes of change order have incremental cost impacts.

This implies that the total project cost of those projects under consideration, which was
birr 8,143,451,307.55, now increased by 5 percent to 8,530,186,178.37 birr. 52.4 percent of
this increment is caused by change of scope; design errors and omissions share 38.6 percent,
and other causes have 7.6 percent contribution. Though they are minor, 1.2 and 0.2
percent, the rest are contributed by unforeseen conditions and force majeure respectively in
descending manner of their contribution.

Consequently, from the analysis of those categories of change order with respect to their
accompanied change order amount we can observe that change of scope contribute
huge share to the cost increment. The next greater cost increment was resulted due to
design errors and omissions and the rest by other causes, unforeseen conditions and
force measure in their descending order of contribution on the total cost increment.

In addition to the data gathered during the desk study about the consequential cost
impacts due to change orders, questionnaire survey was also conducted to assess the
cost impact of change orders from the respondents‟ perspective. During cost impact
analysis, respondents were asked if change orders are one of the causes of dispute
among the contracting parties. If so, they were also requested whether it is due to
consequential cost impact. As a result, 82 percent of the respondents agreed that change
orders, most of the time, are causes of dispute among contracting parties due to their
accompanied cost impact.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 81
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

From the respondents‟ response the mean score (MS) of the frequency of occurrence of
cost impact due to each major category of causes of change order is analyzed as shown
in the table – 10 below.
Table – 10, Mean Score (MS) of Cost Impact of Major Categories of Change Order causes
No. Major Categories of Causes Mean Score (MS) Weighted
Change Order Employer Consultant Contractor Average
1 Design errors and omissions 2.70 2.23 3.45 2.80
2 Change of scope 2.07 2.15 2.91 2.38
3 Unforeseen conditions 2.36 2.00 2.36 2.24
4 Value Engineering 2.36 2.54 3.09 2.66
5 Force majeure 2.86 2.46 3.45 2.92
6 Others - - - -

As depicted on Table – 10 above, the weighted average of the mean scores of the
respondents show that force majeure was ranked first for its consequential incremental
cost impact. This is so, because, respondents may understand the question from point of
view of the catastrophic effects of force majeure. Design errors and omissions became the
next category of causes of change order which can be accompanied by considerable cost
impact. Value engineering is the third category of cause of change order for its cost
impact when exists during the construction. The rest categories of causes of change
order having undeniable cost impact are change of scope and unforeseen conditions in their
descending order. Other causes did not be ranked by the respondents as a potential cost
incurring causes of change order.
This questionnaire response regarding the cost impact contradicts the results obtained
during the desk study, because during the desk study it was found that the change of
scope contributes much to the total cost increment (52.4 percent) and other causes had
considerable shares (7.6 percent) of the cost increment during the desk study. However,
in the questionnaire survey, the design errors and omission being ranked higher for its

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 82
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

consequential cost impacts and other causes were not considered as potential cost
incurring categories of change order.

However, both the desk study and the responses analyzed from the questionnaire
survey show that design errors and omissions are major causes of change order
categories having considerable amount of incremental cost impact.

In response to the question forwarded to respondents to identify the type of


consequential cost impact occurred due to each cause of change order category, around
74 percent of the respondents confirmed that these causes of change order bring an
incremental or negative cost impacts.
At the end, a question that inquires “which contracting party is most of the time being victim
of the cost impacts and why?” was asked and 87 percent of the respondents gave their
response as employers were victims of the cost impact. Whereas 13 percent them
consider that contractors are being victim of the cost impacts. Those respondents who
assure that employers are victims of the cost impact justify their reason that employers
incur considerable amount of money due to change orders which can at least be
minimized if proper feasibility studies were prepared and actual site data are collected
and analyzed before the implementation of the project. However, those respondents
who chose contractors as being victim of the cost impact argue that when change orders
occur, they are accompanied by rework, which deteriorates the workers efficiency,
inflation, delayed procurement process and delayed payments etc.
Despite the above mentioned facts, cost impacts of change orders will be a source of
conflict between the employers and the consultants. This is mainly due to the fact that
employers are assumed as if they are non-professional and whose main responsibility is
to initiate the project ideas so that the consultants, who are the professional staff, are
expected to realize the employer‟s project ideas in to their material equivalent based on
scientific analysis of data collected from the sites where the project is going to be
implemented and manage the contract efficiently. However, the reality is not as
expected that consultants, despite the employer‟s frequent change of ideas, became
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 83
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

sources of change orders due to their improper designs and inefficient contract
management. This leads employers to unexpected additional project costs and project
delays.
In a nut shell, cost impacts due to change order in Ethiopian road construction projects
incurs extra budget, which is expected to be financed from the country‟s limited
economy, which lead to budget deficits for construction projects. As a result, new
projects that the government planned to promote and implement could either be
extended other fiscal years‟ plan or canceled totally.

4.5 Test for Agreement


In this section, the degree of agreement or disagreement between the stake holders (i.e.
consultants vs contractors, consultants vs employers, and contractors vs employers) on the
variables of causes of change orders and their cost impact on road construction projects
in Ethiopia is tested using Spearman rank correlation coefficient, ρ, rho. The analysis
here was done on the mean values for causes of change orders and the cost impacts. The
purpose of a hypothesis test is to avoid being deceived by chance of occurrences.
The tests also helped to evaluate whether consensus of opinions exist among
respondents.
The Null Hypothesis (Ho):
There is no agreement in the ranking of causes/cost impacts of change order between
two groups of respondents.
The Alternative Hypothesis (HA):
There is agreement in the ranking of causes/cost impacts of change order between two
groups of respondents.
The Spearman correlation coefficient (ρ) is calculated using equation 3.2 and tabulated
as shown in table 11.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 84
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

In order to decide whether to accept or reject the null hypothesis the level of
significance, 95% (P=0.05) is used. This allows to state whether or not there is agreement
between respondents‟ opinion.
If the calculated value of ρ is greater than the critical value, Ho is rejected; i.e there is
evidence of a statistically significant agreement between the groups. If the calculated
value of ρ is less than the critical value, Ho is accepted; i.e there is no evidence of a
statistically significant agreement between the groups.

Table – 11, Summary of correlation test on the ranking of variables of causes of change order
based on chance of occurrence.
Significance Accept/Reject
Groups

Critical for The Null


Respondents ρ value P<0.05 Hypothesis

Non-
1 Consultant Vs. Contractor 0.819 0.886 Significant Accept

2 Consultant Vs. Employer 0.903 0.886 Significant Reject


Non-
3 Contractor Vs. Employer 0.812 0.886 Significant Accept
Non-
Average 0.845 0.886 Significant Accepted

In this case, with a significant level of 95% (P=0.05) the calculated values of the
Spearman‟s correlation coefficient, ρ, for group-1 (i.e. Consultant Vs. Contractor) and
group-3 (i.e. Contractor Vs. Employer) are less than the critical value. As a result, for these
two groups the null hypothesis becomes accepted. This is due to the fact that there is no
significant agreement between the two groups. However, the calculated values of ρ for
group-2 (i.e. Consultant Vs. Employer) is greater than the critical value. Therefore, the
null hypothesis is rejected; and hence we can conclude that there is agreement between
the respondents.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 85
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

From table-11 it is observed that the average calculated values of Spearman‟s correlation
coefficient, rho (ρ) is 0.845 which is less than the critical value of 0.886. This shows the
absence of significant agreement between the attitudes of the respondents in all the
three groups. In other words the correlation between the respondents attitude is
relatively weak. This implies that most of the respondents have different perception on
the frequency of occurrence of causes of change order.

5. CONCLUSIONS AND RECOMMENDATIONS


5.1 Conclusions
The research set out to analyze the leading causes and cost impact of change orders on Road
construction Projects in Ethiopia, with the objectives to undertake thorough discussion on
types of construction change orders, their causes and effects in general, to identify the specific
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 86
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

causes of change orders and their consequential cost impact. A desk study and questionnaire
surveys were used to identify the existence and extent of causes and cost impacts of
change order on road construction projects in Ethiopia.

Based on this finding of the desk study and questionnaire surveys, the following
conclusions are drawn:

1. The most common reasons of change order encountered during the construction of
road projects in Ethiopia are categorized into the following major causes of change
orders: Design Errors and Omissions, Change of Scope, Unforeseen Conditions, Value
Engineering, Force Majeure and Others.
2. From the total change orders encountered 40.8 percent of the change orders were
caused by design errors and omissions, 29 percent occurred due to change of scope by
owner, 15.8 percent resulted from other causes, 7.5 percent were caused by unforeseen
conditions. The rest were caused by value engineering and force majeure.
3. The frequency of occurrence of changes in Ethiopian road construction projects
shows that design errors and omissions are the most frequent cause of change order
followed by change of scope, unforeseen conditions, value engineering, others and force
majeure respectively in their descending order of occurrence.
4. Of the three parties involved in the construction, 36 percent of the changes orders
are caused by consultants, 26 percent caused by employers, 21 percent by other causes
(third parties such as regulatory bodies) and 17 percent by contractors.

5. Regarding consequential cost impacts occurred due to the change orders, the desk
study revealed that except value engineering, all other causes of change order
categories have incremental (negative) associated cost impacts. Of the total
incremental costs, 52.4 percent are caused by change of scope; 38.6 percent caused by
design errors and omissions, and 7.6 percent by other causes. Though they are minor, 1.2
and 0.2 percent respectively, the rest are contributed by unforeseen conditions and
force majeure.
AAU, School of Civil and Environmental Engineering
Construction Technology and Management 87
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

However, the weighted averages of the mean scores of the questionnaire


respondents show that force majeure was ranked first for its consequential
incremental cost impact. Design errors and omissions became the next category of
causes of change order which can be accompanied by considerable incremental cost
impact. Value engineering is in the third level of category of cause of change order for
its cost impact. The rest categories of causes of change order having undeniable cost
impact are change of scope and unforeseen conditions in their descending order. Other
causes did not ranked by the respondents as a potential cost incurring causes of
change order.
This questionnaire response regarding the cost impact, except for design errors and
omission contradicts the results obtained during the desk study. This contradiction
could happen due the fact that the respondents may consider force majeure from its
catastrophic effect.
However, both the desk study and the responses analyzed from the questionnaire
survey show that design errors and omissions and change of scope are major causes of
change order categories having considerable amount of incremental cost impact.
From this fact, we can conclude that both project owners and consultants were
accountable for the occurrence of most of the change orders on road construction
projects in Ethiopia.

5.2 Recommendations
Forwarding recommendations was one of the objectives of the research. Therefore,
based on the findings of the research, the following recommendations are made:
1. As a promoter of the projects, the employer (such as the Ethiopian Roads Authority
in the context of this research), should undertake thorough and comprehensive
project feasibility study before the implementation of the projects to their
material equivalent. This would avoid the time and again change of project ideas
by the employer. To help minimize such change of ideas, it is better if the

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 88
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

opinions of other stake holders are properly addressed. And once the project is
started, the employer should stick to the very first of its project ideas as much as
possible to avoid the scope changes that can be encountered at some point of the
project‟s life.
2. Consultants should play their role, as per the expected disciplinary requirements,
from the project inception to its implementation on the ground. This is so,
because it is the consultant‟s responsibility to coordinate all sorts of information
that can satisfy the employers‟ and other stake holders‟ interest. Hence, the
consultant should do the following before the commencement of the project:
Collect actual and genuine field data during site investigation.
Make proper and holistic feasibility study that can accommodate different
stake holders‟ interest.
Make a peer review on the feasibility study and collect professional
opinion as an input during design. This would minimize change orders
due to unforeseen conditions.
Make feasible design that can at least minimize future changes due to
design errors and omissions.
Prepare clear, concise and comprehensive contract document which can
accommodate changes and resolve disputes that can occur as a result of
change orders.
3. As a key practical player of the construction industry, contractors are
accustomed to different types of change orders. Therefore, contractors are
recommended to:
Foresee changes that can be encountered during project implementation
and make aware other parties on how they are going to be handled.
Avoid interests of extra profits that could be generated as a result of
changes.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 89
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

Avoid adversarial relations, due to change orders, with contracting parties


and try to solve issues related to changes amicably based on change order
clauses on the contract document.

REFERENCE
1. Alaa Zeitoum and Garold Oberlender: Early warning Signs of Project Changes,
Oklahoma State University/CII source document No.91, April 1993.

2. Alan T., Gordon R. (2004). Civil Engineering Project Management. Oxford: Elsevier
Butterworth.

3. Arain, F.M., Assaf, S.A. & Low, S.P. (2004) Causes of discrepancies between design
and construction. Architectural Science Review, 47(3), pp.237-249.

4. Assaf, S.A., Al-Khalil, M. & Al-Hazmi, M. (1995) Causes of delays in large building

construction projects. Journal of Construction Engineering and Management, ASCE,


11(2), pp. 45-50.

5. Chappell, D. & Willis, A. (1996) The Architect in Practice. (8th edition) Blackwell
Science Ltd, USA.

6. Clough, R.H. & Sears, G.A. (1994) Construction Contracting. (6th edition) John Wiley
& Sons Inc., New York.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 90
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

7. Construction Industry Institute (CII) Publication 5-1: Impact of Various Contract Type
and Clauses on Project Performance. The University of Texas at Austin, April 1986.

8. Construction Industry Institute (CII) Publication 6-10: The Impact of Changes on


Construction Cost and Schedule. The University of Texas at Austin, April 1990.

9. Construction Industry Institute (CII) Publication 6-6: Work Packaging for Project
Control. The University of Texas at Austin, April 1988.

10. Cox, S. & Hamilton, A. (1995) Architect’s Job Book. (6th Edition) RIBA Publications,
Royal Institute of British Architects, UK.

11. Dell‟Isola, A.J. (1982) Value Engineering in the Construction Industry. Van Nostrand
Reinhold, New York.

12. Edward R Fisk: Construction Project Administration, third edition. John Wiley & Sons
Inc. New York 1988.

13. Fisk, E. R. (1997) Construction Project Administration. (5th edition) Prentice Hall, New
Jersey.

14. Geok, O.S. (2002) Causes and Improvement for Quality Problems in Design & Build
Projects. Unpublished B.Sc. Thesis, National University of Singapore. Singapore.

15. H. Randolph Thomas and Carmen L. Napolitan: The Effects of Changes on Labor
Productivity: Why and How much, CII source document No.99, The Pennsylvania State
University, August 1994.

16. Hanna,A., Camlic,R., Peterson,P., Nordeheim,E. (2002). Qualitative Definition of


Projects Impacted by Change orders. Journal of Construction Engineering and
Management, 57-64.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 91
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

17. Ibbs, C.W. & Allen, W.E. (1995) Quantitative Impacts of Project Chang. Construction
Management Technical Report no.23, University of California at Berkeley, USA.

18. Ibbs, W., Nguyen,L., & Lee, S. (2007). Quantified Impacts of Project Change. Journal
of Professional Issues in Engineering Education and Practice, 45-52.

19. James L., Burati Jr., Jodi J. F., & William B. L.(1992). Causes of Quality Deviation in

Design and Construction. Journal of Construction Engineering and Management, Vol.


118, No.1.

20. Mokhtar, A., Bedard, C. & Fazio, P. (2000) Collaborative planning and scheduling of
interrelated design changes. Journal of Architectural Engineering, ASCE, 6(2), pp.66-75.
21. Moselli,O., Assem,I., & El-Rayes,K.(2005). Change Orders Impact on Labor
Productivity. Journal of Construction Engineering and Management, 354-359.

22. O‟Brien, J.J. (1998). Construction Change Orders: Impact, Avoidance, Documentation,
McGraw-Hill, New York.

23. Oracle Publication: Change Management Best Practices for the Engineering and
Construction Industry, Journal of Construction Technology and Management, Redwood
Shores, USA. April 2009.

24. Paul M., Timothy R.B. (2010). Change Orders and Lessons Learned, Report of
Kentucky Transportation Center, Kentucky USA.

25. Robert K. Cox: Managing Change Orders and Claims, Journal of Management in
engineering, January/February 1997.

26. Sanvido, V., Parfitt, K., Guvensia, M. & Coyle, M. (1992) Critical success factors for
construction projects. Journal of Construction Engineering and Management, ASCE,
118(1), pp. 94-111.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 92
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

27. The Economist (2012). Building in change: Project Construction in Asset-intensive


Industries, A Report from the Economist Intelligence Unit. Pp.8-10.

28. Thomas, H.R. and Napolitan, C.L. (1994) The Effects of Changes on Labor Productivity:
Why and How Much. CII Document 99, The Pennsylvania State University, USA.

29. Weston Hester, John A. Kuprenas, T.C. Chang: Construction Changes and Change
Orders: Their Magnitude and Impact, The University of California-Berkley/CII source
document No. 66, April 1991.

30. Wu, C., Hsieh,T., & Cheng, W.(2005). Statistical Analysis of Causes for Design change in
Highway Construction on Tiwan. International Journal of Project Management, 554-
563.

Appendix B
Table C Critical values of ρ (rho) at various levels of probability (Spearman rank correlation
coefficient)

For any N the observed value of ρ is significant at any level of significance if it is equal to or
larger than the critical values shown in the table

Level of significance for one tailed test

0.05 0.025 0.01 0.005

Level of significance for two tailed test


N (number of
subjects) 0.10 0.05 0.02 0.01

5 0.900 1.000 1.000 -

6 0.829 0.886 0.943 1.000

7 0.714 0.786 0.893 0.920

8 0.643 0.738 0.833 0.881

9 0.600 0.683 0.783 0.833

10 0.564 0.648 0.746 0.794

12 0.506 0.591 0.712 0.777


0.456 0.544 0.645 0.715

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 93
Assessment of Causes and Cost Impact of Change Orders on Road Projects in Ethiopia

14

16 0.425 0.506 0.601 0.665

18 0.399 0.475 0.564 0.625

20 0.377 0.450 0.534 0.591

22 0.359 0.428 0.508 0.562

24 0.343 0.409 0.485 0.533

26 0.329 0.392 0.465 0.515

28 0.317 0.377 0.448 0.496

30 0.306 0.364 0.432 0.478

Note: when there is no exact number use the next lowest number.

AAU, School of Civil and Environmental Engineering


Construction Technology and Management 94

You might also like