1 8015-0151-00-AL-CD 1133-19-GF-OGF4-J-VD-9503-00001_00 - ITP

INSPECTION AND TEST PLAN Rev.: 00 Status IFA

COMPANY No.: 8015-0151-00-AL-CD 1133/19-GF-OGF4-J-VD-9503-00001 Page: 4

DOCUMENT REVISION HISTORY SHEET


DATE
REV STATUS ISSUED UPDATE / AMENDMENT DETAILS

00 IFA 05/02//2020 ISSUED FOR APPROVAL

Page No. : 4
Inspection & Test Plan Document. No. : 8015-0151-00-AL-CD 1133/19-GF-OGF4-J-
VD-9503-00001
Rev. No. / Date :00 / 05/02/2020

Supplier : Customer / End User : Project Name : PO NO : Issued Date 03/02/2020


EPCC OF OIL GATHERING FACILITIES
PHASE 4 CD 1133/19 Prepared Reviewed Reviewed Approved

H : Mandatory Hold Point, The Supplier cannot carry out the specified controls and tests without Inspector attendance.

Description : W : Witness Point, The manufacturer shall notify the client and TPI Inspector, but there is no hold on the production.
LP - GV IC
SW : Spot Witness, Vendor may proceed with the work with agreement of the Contractor and/or the Employer
Monolithic Insulating Joints
18" R : Review Point, Review document, which includes the review of quality control records, test reports, etc.
-

Reference Procedure (Job Inpection Involvement Point


Q'ty of Acceptance Criteria (only for Remarks (Doc. to
No. Work Process Work Process Activity spec. No. if any) or Approved
check reference) be Submitted)
Vendor Print ZUNT TPI PCIHBV

Technical and Quality Analisys of


1 Contract Review 100% Tender Offer H /
PO

2 Inspection Test Plan Test to be carry out & Delivery 100% As per delivery Date H R R ITP-519-19

3 Approval Of Documentation As per VDMR H R R

4 ACCEPTANCE OF PIPE MATERIAL


4.1 Pipe procurement
4.2 Sampling drawn out for tests
GF-OGF4-P-SP-1003 CMTR EN-10204 3.1
4.3 Transfer Marking
API 5L X65 PSL2 API 5L - B31.4 JOINTS
4.4 Chemical Composition Verification Check of Material Certification 100% ASTM A370 API 5L X65 PSL2 H R R MTC SUPPLIER
ASTM E92 KV -10°C 20/27J
4.5 Tensile & Impact Test
NACE MR0175/ ISO 15156 250 HV10
4.6 Hardness Test
4.7 Documentation
5 ACCEPTANCE OF FORGING MATERIAL
5.1 Pipe procurement
5.2 Sampling drawn out for tests CMTR EN-10204 3.1
GF-OGF4-P-SP-1003
ASTM A694 F65
5.3 Transfer Marking ASTM A694 F65
Ceq≤0,43% ; C≤0,23%; Mn≤1,40%;
Check of Material Certification 100% ASTM A370 H R R MTC SUPPLIER
5.4 Chemical Composition Verification P≤0,25%
ASTM E92
KV -10°C 20/27J
5.5 Tensile & Impact Test NACE MR0175/ ISO 15156
250 HV10
5.6 Hardness Test

ASTM D709 G10 and minimum Material Data sheets equivalent to EN Sub-Supplier Data
6 Acceptance of insulating material Check of Material Certification 100% H R R
Hardness 75 Shore D 10204 2.2 level Sheet

Cutting and Machining Of Forging 8015-0151-00-AL-CD 1133/19-GF-


7 100% Conformity to DWG 519/19 H R R
and Pipes OGF4-J-VD-9503-00001

GF-OGF4-P-SP-1003
NDE on all machined Forgings and ASME V Art. 7 & 25 ASME VIII Div.1 App.6
8 NDE H R R MT REPORT
Pipes (MPI) 8015-0151-00-AL-CD 1133/19-GF- Absence of defects
OGF4-J-VD-9508-00001

Weld Body Parts To Pipe Pups Butt 8015-0151-00-AL-CD 1133/19-GF- ASME IX


H R R
Welds N° [W1] & [W2] OGF4-J-VD-9505-00001 Approved WPS & PQR
9 Welding WB DATA
8015-0151-00-AL-CD 1133/19-GF- ASME IX
Welding connection Lugs H R R
OGF4-J-VD-9505-00001 Approved WPS & PQR

22 HRC- 248HV10-237 HB max


Hardness Check On Butt Welds N° GF-OGF4-P-SP-1003
10 Hardness on Base material, Weld metal and H R R HTC REPORT
[W1] & [W2] ASTM E92
H.A.Z.

GF-OGF4-P-SP-1003
R
Radiographic Examination On Butt ASME V Art. 2 & 22 8015-
11 NDE ASME VIII Div.1 UW51 H (RT films R RT REPORT
Welds N° [W1] & [W2] 0151-00-AL-CD 1133/19-GF-OGF4-J-
review)
VD-9506-00001
8015-0151-00-AL-CD 1133/19-GF-
12 Assembling Insulating Joints Assembling Insulating Joints Conformity to DWG 519/19 H / /
OGF4-J-VD-9502-00001

8015-0151-00-AL-CD 1133/19-GF- ASME IX


13 Welding Closure Weld N°[F] H / / WB DATA
OGF4-J-VD-9505-00001 Approved WPS & PQR

GF-OGF4-P-SP-1003
ASME V Art. 7 & 25 ASME VIII Div.1 App.6
14 NDE MT On Closure Welds N°[F] H R R MT REPORT
8015-0151-00-AL-CD 1133/19-GF- Absence of defects
OGF4-J-VD-9508-00001

Check Calibration and Gauging Of


H R R Calibration certificate
Instrumentation For The Testing

No pressure increase over 5mbar VC REPORT


Vacuum Test: 5mbar for 5 min

a) Hydrostatic Test : 70,5 bar for 4h


holding time
b) Combined Hydrobending fatigue
16 Pressure Test Test: 1h plus 5 cycles from 0 bar to 100%
56,4 bar for 5 min each, with GF-OGF4-P-SP-1003
bending generating 75% pipe 8015-0151-00-AL-CD 1133/19-GF- H W R
SYSM total longitudinal stress OGF4-J-VD-9510-00001
No Leakage, No permanent Strain HT & HTB REPORT

b) Combined Hydrobendingt: 70,5


1 piece for
bar with bending generating 75%
size/
pipe SYSM total longitudinal stress
diameter
for 24h

d) Air Leak Test 51,7 bar for 10 min 100%

Torsional Test: apply a torsional 1 piece for GF-OGF4-P-SP-1003


No relative rotational movement of pup
17 Torsional Test stress of 5% SYMS in the adjoining size/ 8015-0151-00-AL-CD 1133/19-GF- H W R TT REPORT
piece at the completation of test
pup piece. diameter OGF4-J-VD-9511-00001

OUTSIDE: HEMPADUR 15560 50÷75


micron + HEMPADUR MASTIC 45880
150 micron + HEMPATHANE 55210
GF-OGF4-P-SP-1003 and GFDP-
Cleaning and Drying, Surface 50÷75 micron TOTAL DFT: 300
COM-52-PP-SP-GE-003
preparation, Coating and Lining 100% microns Final colour White RAL 9016 H R R
8015-0151-00-AL-CD 1133/19-GF-
Application INSIDE: HEMPADUR 85671 300
OGF4-J-VD-9512-00001
microns DFT in minimum three coats –
18 Coating and Lining activity suitable for sour service

Coating and Lining Inspection (DFT GF-OGF4-P-SP-1003 and GFDP-


OUTSIDE: TOTAL DFT: 300 microns
measure, Holiday Test at 60V, COM-52-PP-SP-GE-003
100% Final colour White RAL 9016 H W R PR REPORT
Adhesion Test on sample by Cross- 8015-0151-00-AL-CD 1133/19-GF-
INSIDE: 300 microns DFT
cut Method) OGF4-J-VD-9512-00001
GF-OGF4-P-SP-1003 and ASTM A
UT on Welding Ends 578 No lamination cracks, no
100% H R R UT REPORT
(50mm from each side of the joint) 8015-0151-00-AL-CD 1133/19-GF- discontinuities
OGF4-J-VD-9507-00001

19 NDE
GF-OGF4-P-SP-1003 and ASME V
Art. 7 & 25 No lamination cracks, no
MT On final bevels 100% H R R MT REPORT
8015-0151-00-AL-CD 1133/19-GF- discontinuities
OGF4-J-VD-9508-00001

2 joint (1st
Immersion Test before Electrical produced GF-OGF4-P-SP-1003
Check: and 1 8015-0151-00-AL-CD 1133/19-GF- R≥5MOhm @ 1000V DC H R R EI REPORT
12h immersion in 3% NaCl solution selected by OGF4-J-VD-9509-00001
PCIHBV)

20 Electrical Tests GF-OGF4-P-SP-1003


Electrical Test (In dry condition)
100% 8015-0151-00-AL-CD 1133/19-GF- R≥5MOhm @ 1000V DC H ET REPORT
R> 5 MOhm @1000V DC
OGF4-J-VD-9509-00001
W R
GF-OGF4-P-SP-1003
High Voltage Test (In dry condition)
100% 8015-0151-00-AL-CD 1133/19-GF- H
1,5 kV @50 Hz A.C. x 5 min.
OGF4-J-VD-9509-00001

Visual & Dimensional Inspection, 8015-0151-00-AL-CD 1133/19-GF-


100% Approved DWG H W R DR REPORT
Marking and Taggings OGF4-J-VD-9502-00001
Dimensional Inspection, Marking
21
and Taggings
8015-0151-00-AL-CD 1133/19-GF- Free passage of 97% Nominal ID
Gauging Pigging Check 100% H W R PG REPORT
OGF4-J-VD-9502-00001 Plate

22 Inspection Release Certificate Inspection Release Certificate H W R

23 Packing and Shipping Packaging And Shipping GF-OGF4-P-SP-1003 H / R PACKING LIST

24 Final Certification Manufacturer's Data/Record Book GF-OGF4-P-SP-1003 MRB H / R