Integrated management in

engineering, construction and assembly for the oil and


gas sector
UTC INTERNACIONAL

Founded in 1974 as one of the leading Brazilian integrated


management system companies in the area of industrial
assembly services focused on O&G.

Our achievements over time are directly connected to


Brazil´s development in various segments:

ENERGY UNITS
Construction of 8 of the country's Built in EPC regime
largest hydropower plants (19,651 • several complete units
MW or 14% of national (Propeno, UHDT Diesel, Coque,
production), in addition to the UGH, UHD, UDEA, UDS, UDDTI,
Angra 2 - 1400 MW nuclear power Gas Drying, Co-generation, etc)
plant. • Co-generation CENPEN and
RECAP,
BASES AND TERMINALS • Piperack and
EPC Construction of bases of fuel • the entire utility system of
BASUL and TEPON, plus floating Comperj.
bases, pipelines and oil pipelines

Besides that, we bring a extensive expertise and portfolio from services in


other segments as Steel and Metallurgy, Mining, Paper and Celluloses,
Terminals Tanks, Energy, Oil & Gas On and Offshore, Chemistry and
Petrochemicals.
Integrated management for
O&G and Petrochemical segment
Projects EPCs Engineering Inovation
Project conception Integrated services of Engineering, Basic and detail Research and development of
and management Procurement, Construction and engineering technology suitable for
Assembly industrial companies

Civil & Industrial Industrial Plants, Platforms & Electromechanical Assembly Supply Chain
Construction Probes Construction and Assembly of Supply of goods and
Integrated construction Modularization and Processing units application materials
for large projects integration of process units
Since 2018, UTC is focused on the O&G
and Petrochemical segment.

Construction of FPSO Construction of Fuel Processing Construction of Chemical


platforms Refineries and Terminals and Petrochemical Plants
Strategically located on the
coast of the Brazilian territory
MACAÉ YARD
Rio de Janeiro State
Strategic location in the northern region of
Rio de Janeiro, has an area of 21 000 m² with
aimed at supporting the construction of oil
platforms.

NITEROI YARD
Rio de Janeiro State
Area with 96.000 m² located on the
northeast bank of Guanabara Bay - Niterói, RJ
(15km from Rio de Janeiro - Centro) with sea
and highway access aiming at assembly
Modules.

EQUIPMENTS DIVISION – SP
Mogi das Cruzes, São Paulo State
Area with 100.000 m² located in the city of
Mogi das Cruzes, State of São Paulo,
for easy transportation Equipment Department.
that ensure the arrival on time
We are committed to deliver quality and the best
experience because UTC has

46 YEARS EXPERIENCE TOP TEAM MODULES


Mais de 46 anos de atuação em Professionals with more than 30 Construction and assembly of
gerenciamento de projetos, years of experience in the Oil & more than 50 modules, having
engenharia, suprimentos, Gas segment; built 14 modules simultaneously in
construção e montagem de 2012;
empreendimentos industriais. PARTNERSHIP
Solid knowledge of the market, PLATFORMS
+ 1000 PROJETOS with active partnership with the Services performed on more than
More than 1,000 contracts main suppliers and manufacturers 70% of all platforms installed in
executed in the most diverse of machinery and equipment in Brazil, from construction and pre-
contracting modalities: EPC, LS/TK, Brazil and abroad; operation assembly and
unit prices, global price and maintenance in offhore plants;
alliance, alone or in consortia. UNIQUE INDUSTRIAL PLANT
Unique industrial plant in South MODULES IN PLATFORMS
America, with facilities comparable Integration of process modules in
to the world's largest ship repair more than 10 oil platforms;
players.
Projects concluded in the last 20 years

Metallic Structure Electrical Equipment Pipelines Cabling


564,157 tons 27,412 tons 17,306 tons 11,891,751 m

Mechanical Equipment Pipe Racks Instruments Painting


252,784 tons 75,892 tons 50,639 units 2,438,820 m2
EPC Contracts in Offshore Platforms
Here are some of our contracts

Carapeba III, 1993 (SS) P-25, 1996 (FPSO) P-47, 2005 FPU P-53, 2008
Fixed platform, including Conversion of Conversion of Floating, Supply of 8 modules, flare,
jacket e deck-box, assembly, Semi-Submersible Drilling Storage & Offloading (FSO) pipe rack topsides for the FPU
integration, commissioning, Unit into a Semi-Submersible P-47 into Floating Production, P-53, in Rio Grande-RS,
all tests and pre-operation. Production Unit, with a Storage and Offloading (FPSO) (Related Company).
process plant of 100,000 P-47,for the installation of an
bopd and 115 mmcf/d of oil and water treatment unit to
natural gas. export treated oil from the
Marlim to the Campos Basin.
EPC Contracts in Offshore Platforms
Here are some of our contracts

FPU P-55, 2011 P-59 & P-60, 2015 FPSO P-63, 2013
Full supply, including deckbox, Complete construction of each one BOT - Supply of Engineering,
assembly, integration, comprises a jack-up drilling unit Materials and Construction Services
commissioning, all tests and weighing around 11,000 tons with for Floating Production and Storage
pre-operation (Related three independent retractable legs. Unit P-63 (Related Company).
Company). The rig is capable of operating at
sites with a water depth up to 106
meters and drilling wells up to
9,144 meters (in Consortium).
Modules Construction in Offshore Platforms
More than 40 modules constructed, having built 14 simultaneously, in addition to jumpers and manifolds

P-43 & P-48 P-53 P-57 P-58 & P-62


2001 to 2003 2005 to 2007 2008 to 2010 2010 to 2012
client: PNBV client: QUIP client: SBM client: PNBV
6 units 4 units 5 units 14 units
8.590 t 1.934 t 3.171 t 12.416 t
`
P58 - M07 Manifold
The Largest and Heaviest
Topside Module made by UTC
20m (W) x 30m (L) x 18m (H)
1.530 t

P-47 P-56 P-55 14 units constructed


2002 to 2004 2007 to 2010 2008 to 2010 simultaneously at UTC Niteroi
client: PNBV client: PNBV client: PNBV Yard (photo shows the
6 units 2 units 2 units construction peak)
1.700 t 2.400 t 1.180 t
Experience and Track Record - Offshore Hook-up and Maintenance

PETROBRAS International Companies

1 VERMELHO-I M 16 P-08 M 33 P-40 M H 1 ESPIRITO SANTO

2 VERMELHO-II M 17 P-09 M 34 P-43 M H 2 FRADE

3 VERMELHO-III M 18 P-18 M 35 P-47 M H 3 FLUMINENSE

4 PARGO-1A M 19 P-19 M 36 P-48 M 4 CIDADE DE NITEROI

5 PARGO-1B M 20 P-20 M 37 P-50 M H 5 CIDADE DO RJ

6 CARAPEBA-I M 21 P-23 M 38 P-51 6 RIO DAS OSTRAS

7 CARAPEBA-II M 22 P-24 39 P-52 M 7 POLVO A

8 CARAPEBA-III M H 23 P-25 M H 40 P-53 M H 8 OSX-3

9 GAROUPA M 24 P-26 M 41 P-54 M 9 PEREGRINO A M H

10 ENCHOVA M 25 P-31 M H 42 P-55 M H 10 PEREGRINO B M H

11 PAMPO-1 M 26 P-32 M H 43 P-56 M 11 CIDADE DE ANCHIETA

12 NAMORADO-1 M H 27 P-33 M H 44 P-57 12 CAPIXABA

13 NAMORADO-2 M 28 P-34 M H 45 P-58 M 13 ESPADARTE M

14 CHERNE-1 M H 29 P-35 M 48 P-61 14 BRASIL

15 CHERNE-2 M H 30 P-36 M H 49 P-62 M H


UTC scope of work
31 P-37 M H 50 P-63 H
M 64% - Modification and Maintenance(M&M)
32 P-38 M 51 P-65 M
H 28% - Hook-up
Refineries and Petrochemicals

Petrobras – REFAP S.A. , RS - 2014 Petrobras – REPAR , PR - 2010 Petrobras – REPLAN, SP - 2009 PETROQUÍMICA UNIÃO, SP -2009 Petrobras – REVAP, SP -2008

UHDT e UGH PLANTS COKE AND GASOLINE PLANTS PROPYLENE PRODUCTION UNIT GAS TRATAMENT UNIT PROPYLENE PRODUCTION UNIT

INNOVA, RS -2008 Petrobras – REFAP, RS -2006 Petrobras – REPLAN, SP - 2004 Petrobras – REPAR, PR -2004 Petrobras – REVAP, SP -2003 Petrobras – REFAP, SP - 2001
ETILBENZENO UNIT DELAYED COKING UNIT INTERCONNECTION WITH NEW UNITS HDT, HYDROGEN and DEA CYCLONS FOR FCC UNIT SOLVENTS PLANT
Terminals and Distribution Bases

Petrobras Distribuidora, AC - 2013 Petrobras Distribuidora, TO - 2013 Petrobras Distribuidora, RR e AM, 2012 Petrobras Distribuidora, RJ -2012

DISTRIBUTION BASE - BASUL DISTRIBUTION BASE - BAPON FLOATING RAFTS DIESEL OIL TANKING

Transpetro, RS -2009 Petrobras – OSCAN, RS - 2009 Transpetro – Terminal, SP -2005 MSGÁS, MS -2003
SOUTH TANK PIPELINE – OSÓRIO-CANOAS FIRE AND DRAINAGE SYSTEMS CITY GATES
Energy

PETROBRAS - CENPES, RJ - 2009 PETROBRAS - Seropédica, RJ - 2008 VOITH SIEMENS POWER -2005 ITAIPU BINACIONAL-2005
CO-GENERATION PLANT CONVERTION TO DUAL COMBUSTIBLE AYMORÉS POWER PLANT ITAIPU POWER PLANT

VOITH SIEMENS POWER -2003 VOITH SIEMENS POWER -2003 CONSÓRCIO AHE -2003 TERMONORTE-2003
QUEBRA QUEIXO POWER PLANT JAURU POWER PLANT FUNIL POWER PLANT PORTO VELHO THERMAL PLANT
Mr. Marcelo Povoas
Commercial Offshore Director
marcelo.povoas@utc.com.br
Bcc: getec@utc.com.br
Mobile: +55 21 99979-5220
www.utc.com.br

UTC is continuously available in case of any


clarification or additional information need.
Please do not hesitate to be in touch.

You might also like