Generation Connection Guide
Generation Connection Guide
Generation
Connection Guide
Including commissioning, registering,
dispatch and payment
© TRANSPOWER NEW ZEALAND LIMITED ALL RIGHTS RESERVED 2021
This document is produced for external release. Its conclusions are based on the information currently available to Transpower and
may change as further information becomes available either internally or externally
Table of Contents
Glossary .................................................................................................................... 4
Generation connection guide .................................................................................. 5
INTRODUCTION ...................................................................................................................................... 5
GENERATION CONNECTION PROCESS ...................................................................................................... 6
Timeline Process Timeline.............................................................................................................. 8
WORKSTREAM A - TRANSMISSION CONNECTION ...................................................................................... 9
Phase A1. Concept ...................................................................................................................... 9
Phase A2. Feasibility ................................................................................................................. 11
Phase A3. Approval ................................................................................................................... 12
Phase A4. Design and construction........................................................................................... 13
WORKSTREAM B : GENERATION COMMISSIONING................................................................................... 15
Phase B1. Planning ................................................................................................................... 15
Phase B2. Pre-commissioning ................................................................................................... 20
Phase B3. Commissioning ......................................................................................................... 25
Phase B4. Post-commissioning ................................................................................................. 26
C – MARKET REGISTRATION ................................................................................................................. 27
D – DISPATCH ..................................................................................................................................... 29
E – PAYMENT ...................................................................................................................................... 33
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .3
Glossary
ACS Asset Capability Statement
Grid The system of transmission lines, substations and other works, including the
HVDC link used to connect grid injection points and grid exit points
NZX NZX Energy (currently the Clearing Manager, Pricing Manager, WITS Manager
and Reconciliation Manager)
1 See www.ea.govt.nz/code-and-compliance/the-code/
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .4
Generation connection guide
Introduction
The document provides a guide to connecting, commissioning, registration, offering and
dispatching of new generation plant onto New Zealand’s electricity system, plus a summary of
transmission charges.
Transpower’s purpose is ’empowering the energy future for New Zealand’, through its two
roles as Grid Owner and System Operator:
As Grid Owner, maintaining a reliable transmission network while undertaking efficient
investment to achieve a less constrained and more resilient grid.
As System Operator, providing an integrated operations service facilitating a reliable
efficient and competitive wholesale electricity market.
Transpower’s commitment is to deliver this safely and efficiently to meet customer
requirements and shareholder 2 expectations. This is accomplished while complying with the
regulatory obligations and fulfilling its responsibilities to future generations of New
Zealanders.
Generation connection, commissioning and dispatch are complex processes, requiring the
coordination of activities between several parties. This document provides a guide on the
processes required for new generation to be successfully connected, commissioned,
registered, offered and dispatched, plus a summary of transmission charges.
The latest version of this document, plus associated documentation and information, is
available on Transpower’s ’Connect your generation’ page:
https://www.transpower.co.nz/keeping-you-connected/getting-you-connected/connect-your-
generation
Transpower also provides information on its future plans and on market conditions through its
website www.transpower.co.nz, including its Transmission Planning Report and System
Security Forecast.
2Transpower is 100% owned by the New Zealand Government and operates under the State Owned Enterprises
Act
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .5
Generation connection process
The complexity and duration of each phase will vary from project to project but typically
follows a standard sequence from concept development through to operation.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .6
The generation connection process is further broken down into discrete phases that occur
across five concurrent workstreams.
A description of each of the workstreams is provided below.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .7
Phasing by workstream
The diagram below shows the typical sequencing of the connection, commissioning and registration.
Workstream
Commissioned
A A5
A1 A2 A3 A4
Transmission Concept Investigation Approval Design
Construction &
connection Commissioning
B B3 B5
B1 B2 B4
Generation Concept Planning
Pre-
Commissioning
Post-
commissioning commissioning commissioning
C C1
Market Market
registration registration
D D1
Dispatch Dispatch
E4
E E1 E3
E2 Ongoing TPM charges
Services Transpower
Transmission agreement +
Investigation
works E5
charges SOW
concept SOW agreement Ongoing electricity
industry levy
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .8
Workstream A - Transmission connection
This section provides an overview of the process for generators who require connection to
Transpower’s assets. This workstream does not apply to generators who are
connecting to a local network, but other workstreams do. (Note; for significant new
distributor connected generation, the company you are connecting to may need to
undertake some activities with Transpower under this workstream)
Transmission connection comprises five phases:
• Concept
• Investigation
• Approval
• Design
• Construction and Commissioning
Each phase consists of a number of actions that generally need to be completed before
moving to the next phase.
Description The owner of the proposed new generation plant will contact
Transpower’s Customer Solutions Team. A meeting will be arranged
with the prospective Generator to discuss their proposal. Transpower
provides guidance and information on the process required for
generation connection. Transpower will appoint a point of contact
person for the connection process.
Responsible party Generator, Transpower’s Customer Solutions Team
Timeframe Dependent on Generator
Resources Customer.solutions@transpower.co.nz or +64 4 495 7000.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .9
A1.3 Provide preliminary information
Description Following the initial meeting, the Generator submits a formal request for
a Concept Assessment workshop or a Concept Assessment completed
by desk top study.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .10
Phase A2. Investigation
The Generator reviews the Concept Assessment and decides whether to proceed. This
process may involve several further discussions with Transpower before the Generator is
ready to commit to more detailed studies.
Description Transpower and the Generator agree and sign a Detailed Solution
Development (DSD) statement of work under a Transpower Services
Agreement (TSA) . The DSD documents the scope and cost of work to
produce a Solution Study Report (SSR) .
Transpower will agree the exact scope with the Generator.
Depending on the complexity of the project and the Generator’s internal
decision points, this may be staged with a series of agreed scopes of
work..
Responsible party Generator / Transpower
Timeframe About 1 month
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .11
A2.4 Solution Study Report (SSR)
Description Following on from the results of the SSR, the Generator decides
whether to proceed, and advises Transpower accordingly.
Responsible party Generator
Timeframe About 2 to 3 months for Transpower approval
Description Transpower and the generator agree and sign a Transpower Works
Agreement (TWA). The TWA is Transpower’s standard contract
covering the terms and conditions for Transpower’s provision of new
infrastructure to enable customer projects, and the recovery of costs.
Responsible party Generator / Transpower
Timeframe About 2 months
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .12
Phase A4. Design
Transpower undertakes the design of the new connection on behalf of the Generator.
Description Transpower prepares the detailed design for the construction and
commissioning of the new connection.
The design work will typically be undertaken concurrently with the
consenting process (Phase A4.2).
Responsible party Transpower
Timeframe Varies depending on the complexity of the project
Description The party or parties designated in Phase A2.2 secures the necessary
environmental approvals to enable the construction, operation,
maintenance and upgrade of the new connection.
Gaining approvals will likely be staged. Some may be obtained based
on SSR level engineering detail. Others will require detailed design and
civil design aspects (Phase A4.1).
Responsible party Generator or Transpower (dependant on Phase A2.2).
Timeframe Varies depending on the complexity of the project
A4.3 Metering
Description The Generator must arrange a metering installation that complies with
the Code. Grid connected Generators must provide Transpower with a
copy of their metering installation design for review and comment.
Generators should note that the Code contains other obligations on
collecting and providing data to the market, noted below. (Noted also in
section B2.8).
Responsible party Generator / Transpower
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .13
Phase A5. Construction & commissioning
Transpower undertakes the construction and commissioning of the new grid connection on
behalf of the Generator.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .14
Workstream B : Generation commissioning
This section outlines the process for Generators who want to commission new generation
plant onto the grid or a local or embedded network. It applies to all generators. However,
not all of the phases may be applicable to smaller Generators. Transpower in its role as
System Operator will advise what is required.
Generation commissioning comprises four phases:
• Concept
• Planning
• Pre-commissioning
• Commissioning
• Post-commissioning
Each phase consists of a number of actions that need to be completed before moving to the
next phase. Each of the actions has an associated commissioning lead-time, which is the
minimum period of time between completing the action and beginning the commissioning and
testing in order to avoid delays to the planned commissioning date. The actions within each
phase can be carried out in any order, so long as they are all completed by their ‘lead-time’.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .15
B1.2 Education pre Investigation
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .16
B2.2 Identify protection coordination requirements
Description The Generator should have an awareness of ancillary services that may
be offered to the electricity market, that could be required to be
demonstrated during commissioning. Examples may include, but not be
limited to:
• Fast and/or sustained instantaneous reserves
• Over-frequency reserves
• Single frequency keeping
• Multiple frequency keeping
• Black start
Responsible Generator
party
Lead-time 6 months pre commissioning
Compliance No
Show- No
stopper
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .17
B2.4 Submit Planning Asset Capability Statement (ACS)
Description Generators are required under the Code to submit an Asset Capability
Statement (ACS) to the System Operator. The ACS contains the
technical details of the new generation plant to be connected. This is
the first stage of an iterative process, with more detail added to the ACS
as the project progresses toward commissioning. Transpower will
provide access to their on-line Asset Capability Database upon
request.
Responsible party Generator
Lead-time 6 months pre commissioning
Compliance Clause 8.25(4) of Part 8 (Common Quality) of the Code
Clause 2(5) of Schedule 8.3 (Tech Code A) of Part 8 (Common Quality)
of the Code
Show-stopper No
Resources Information on Asset Capability Statements is available via
Transpower’s Generation Connection & Dispatch page 3. For further
information contact the System Operator
Description Based upon the submitted ACS the generator the System Operator
should agree which Asset Owner Performance Obligations (AOPOs)
and Technical Codes apply to the unit being commissioned and any
changes to obligations of the station it is a part of.
Any residual non-compliances should be noted and managed
appropriately as they are identified.
Responsible party Generator / System Operator
Lead-time 6 months pre commissioning
Compliance Part 8 (Common Quality) sub-part 2 of the Code
Show-stopper No
3 www.transpower.co.nz/industry/generation-connection/generation-connection-dispatch.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .18
B2.6 Consider establishing a Memorandum of Understanding (MoU)
Description Where generators are uncertain of all the Code obligations Transpower
may be able to give guidance in specific areas to assist, which could
include establishing the need for dispatch facilities. If a new dispatch
connection is required this could take several months to arrange
depending on the type of facility.
Responsible party Generator
Lead-time 6 months pre commissioning
Compliance Yes
Show-stopper No
4 https://www.transpower.co.nz/system-operator/resources-asset-owners/generation-connection-dispatch
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .19
B2.8 Metering Installation Design
Description The Generator must arrange a metering installation that complies with
the Code. Grid connected Generators must provide Transpower with a
copy of their metering installation design for review and comment.
Generators should note that the Code contains other obligations on
collecting and providing data to the market, noted below. (Noted also in
section A2.6).
Responsible party Generator / Transpower
Lead-time 6 months pre commissioning
Compliance Part 10 (Metering arrangements) of the Code includes metering
installation requirements
Part 13 (Trading arrangements) of the Code includes requirements for
embedded generators subject to dispatch or intermittent generation
connected to the Grid
Part 15 (Reconciliation) of the Code includes requirements for collection
and provision of metered data to the market
Show-stopper Yes
Description As more data comes to hand, the Generator provides further technical
details of their new plant via an updated ACS.
Responsible party Generator
Lead-time 4 months pre commissioning
Compliance Clause 8.25(4) of Part 8 (Common Quality) of the Code
Clause 2(5) of Schedule 8.3 (Technical Code A) of Part 8 (Common
Quality) of the Code
Show-stopper No
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .20
B3.2 Submission of draft plans for review
Description All outage requests must be lodged in the Transpower outage planning
system for primary grid equipment and protection systems.
Responsible party Generator
Lead-time 4 months pre commissioning
Compliance No
Show-stopper Yes
Description Final drafts must be submitted the System Operator for review and
agreement with sufficient time for a review to be carried out and
changes, if identified, made to the documents.
Responsible party Generator
Lead-time 3 months pre commissioning
Compliance Clause 2 of Technical Code A of Part 8 (Common Quality) of the Code.
Show-stopper Yes
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .21
B3.5 Indications and measurements
Description The System Operator reviews and signs off the commissioning and test
plans.
Responsible party System Operator
Lead-time 6 weeks pre commissioning
Compliance Clause 2(7) of Technical Code A (Assets) of Schedule 8.3 (Technical
codes) of Part 8 (Common quality)
Show-stopper Yes
Description The Generator liaises with Transpower to ensure that the protection
settings and design at the Grid interface meet Code requirements.
Transpower will provide the Generator with the Transpower document
‘Generation Protection at the Interface’.
Responsible party Generator / Transpower
Lead-time 3 months pre commissioning for the final draft
Compliance Clause 4(4a) of Technical Code A (Assets) of Schedule 8.3 (Technical
codes) of Part 8 (Common quality) of the Code
Show-stopper Yes
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .22
B3.8 Notices of intention to Connect and Offer
Description If the generating units are greater than 1MW, the Generator submits a
'Notice of Intention to Connect' and a “Notice of Initial Offer” as
appropriate to the System Operator.
Responsible party Generator
Lead-time 4 weeks pre commissioning
Compliance Clause 8.21(2) of Technical Code A (Assets) of of Part 8 (Common
quality) of the Code
Show-stopper Yes
Resources These forms are available via Transpower’s Generation Connection &
Dispatch page 5.
5 https://www.transpower.co.nz/system-operator/resources-asset-owners/generation-connection-dispatch
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .23
B3.11 Market confirmation
Description This requires setting a minimum confirmation period to the market for
system ride through and other significant system tests when required.
Responsible party Generator
Lead-time 2 days
Compliance No
Show-stopper Yes
Description The Generator must comply with all the relevant Electricity Market
Trading Arrangements including:
• Complying with offer and dispatch provisions unless agreed
otherwise in an approved Operational Test Plan
• Managing the offer of the commissioning assets in order to
ensure they are dispatched to the loads necessary for
commissioning. At the discretion of the Generator this may
include bidding into the must run dispatch auction 7 or offering
the unit at $0.01/MWh.
Responsible party Generator
Show-stopper No
Resources See D3 for more information on offering and dispatch
6 https://www.transpower.co.nz/system-operator/resources-asset-owners/generation-connection-dispatch
7The must run dispatch auction enables generators to offer generation at $0/MWh, giving the generator the
greatest likelihood of dispatch but it does not confer a guarantee of actually being dispatched. See D6.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .24
Phase B4. Commissioning
The Generator commissions and performs the required tests - adhering to the timeline in the
agreed commissioning and test plan.
Description The Generator commissions the new plant, then performs the tests
according to the timetable in the Commissioning Plan unless agreed
otherwise with the System Operator.
Responsible party Generator
Compliance Clauses 3(7-9) of Technical Code A (Assets) of Schedule 8.3
(Technical codes) of Part 8 (Common quality) of the Code
Description The System Operator may request to witness AOPO tests as required.
Responsible party System Operator
Compliance Clause 8(4) of Technical Code A (Assets) of Schedule 8.3 (Technical
codes) of Part 8 (Common quality) of the Code
Description The Generator provides test results and data to the System Operator
to demonstrate compliance with AOPOs and Technical Codes.
Responsible party Generator
Compliance Clause 8 of Technical Code A (Assets) of Schedule 8.3 (Technical
codes) of Part 8 (Common quality) of the Code
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .25
Phase B5. Post-commissioning
Following commissioning and testing, the Generator provides updated test data to
Transpower, who reviews and provides a final assessment of compliance. The Generator is
required to adhere to all of the ongoing obligations as set out in the Code.
Description The Generator submits test reports and data from commissioning
(including unencrypted verified models) to Transpower for analysis.
Responsible party Generator
Compliance Clause 2(5b) of Technical Code A (Assets) of Schedule 8.3 (Technical
codes) of Part 8 (Common quality) of the Code
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .26
C – Market Registration
This section provides an overview of the process for Generators who will be offering electricity
to the market after the new generation has been commissioned. Registration comprises six
actions that must be completed prior to starting commissioning, so is typically conducted in
parallel with the early phases of the commissioning workstream.
The Generator registers with the Electricity Authority and NZX Energy as the appointed
Clearing Manager. The generator will also require a contract with NZX Energy as the
appointed Clearing Manager in order to take or inject electricity from or to the Grid.
8 An exemption to registering as a participant for small generation (<100kw) has been drafted by the Authority but
is yet to be enacted at the time of publication
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .27
C4 Register for WITS
Description The Generator registers for WITS (the wholesale information and trading
system) with the Clearing Manager (NZX Energy) if it has not already
done so. cadmin@nzx.com
Description The Generator advises the Clearing Manager (NZX Energy) of the
upcoming generation connection in order that they are setup in the
Clearing Manager’s system in order to be cleared in the market each
month. cmanager@nzx.com
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .28
D – Dispatch
This section provides a high-level description of the dispatch process. This guide is not
intended to relieve asset owners from identifying and meeting their obligations set out in the
Electricity Industry Participation Code 2010 (Code). Where there is conflict between this guide
and the Code, the Code takes precedence.
D1 Electricity market
The System Operator schedules and dispatches generation on the basis of the bids
and offers made by purchasers and generators. Generators offer electricity into the
electricity market. Purchasers bid for electricity.
D2 Pricing
The New Zealand wholesale market design includes dispatch, based on bids and
offers with locational marginal pricing (nodal pricing) to arrive at the overall lowest
cost dispatch solution. The co-optimisation of the cost and quantity of reserve
needed to cover the loss of generation or HVDC transfer, along with the cost of
energy dispatch, is included in meeting the least cost objective.
The market settles on an ex-post basis with 30 minute trading periods and a price
for each of the over 200 nodes in the market model. Generators are paid for the
amount of output produced in a trading period, at the final price for the trading
period, at the node to which they are connected. Dispatch occurs every five
minutes through formal dispatch instructions sent electronically.
The Electricity Authority is currently developing enhancements to the spot market so
settlement prices will be available in real time.
D3 Generation offers
All generation offered under the trading rules in Part 13 of the Code is dispatched
through the offer process in real time. There is no provision for dispatch rights
based on any bilateral arrangement or hedge arrangements between generators
and retailers.
All generation over 10 MW - if directly grid connected - must offer. Embedded
generation above 10 MW can be required to offer if this will assist the System
Operator in meeting its principal performance objective (PPO). Embedded
generation below 10 MW can be required to provide intended output data if the
Authority agrees this will assist the System Operator in meeting its principal
performance objective (PPO).
Different dispatch rules exist for intermittent (wind and solar) generation and certain
types of co-generation plant, reflecting the characteristics of these generators.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .29
Participants can change their offer up to ‘gate closure’ 9. A number of schedules are
provided to participants up to a week in advance giving an indication of the likely
dispatch quantities and prices.
There is currently no binding ahead or unit commitment market as in some
overseas jurisdiction.
D4 No right of capacity
A connection to the Grid does not result in any capacity rights for that connected
party. Generators connecting to the Grid should be aware that existing, or future
congestion on the Grid may affect the ability of a generator to deliver its energy to
the market.
D5 No right of dispatch
Connection to the grid and participation in the electricity market does not guarantee
that a generator will be dispatched at all times by the System Operator. A generator
may not be dispatched where:
• there is sufficient lower priced generation to meet demand;
• there are constraints on the power system that limit the amount of electricity
that the generating unit can produce; or
• the generator is non-compliant with the AOPOs and Technical Codes.
Dispatch is based on offer price. Generating plant may not be dispatched if there is
sufficient lower priced generation offered to meet system demand.
At times, clearing prices may drop to close to zero if there is a surplus of generation
that wants to run irrespective of the clearing price. This typically happens at times
of low system demand; overnight in summer, and at other times when there is a
very high proportion of hydro generation relative to total system demand due to full
storage catchments and strong inflows.
Negative priced offers are not allowed; however, there is a Must Run Dispatch
Auction (MRDA) where generators can bid for rights to offer at $0.00 per MWh. The
quantity of generation that can be cleared in this auction is limited to 80% of the
minimum system demand. All other generation must offer at $0.01 per MWh or
above.
Rules for the dispatch of intermittent (wind and solar) generation and type B
cogeneration plant effectively see them dispatched to their current output. However
due to the offer price, system constraints or times of excess generation, intermittent
generation may need to “spill” in the same way that can happen with hydro
9Gate closure is the point at which changes to offers can no longer be made for commercial reasons. For most
generation this is currently 1 hour ahead of dispatch beginning for the applicable trading periods. Clause 13.17 of
Part 13 of the Code.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .30
generation at times.
Holding rights to offer at $0.00 per MWh from the MRDA does not guarantee
dispatch. Reserve co-optimisation or constraints, could result in dispatch being less
than the quantity offered at times, particularly during periods of low demand. In
some cases, this may put thermal generating units below minimum running limits,
requiring the plant operators to disconnect the generating unit.
Transmission constraints on the Grid may also affect generation dispatch. The
System Operator analyses generation schedule information to identify when and
where a constraint may have to be applied to ensure the power system remains
within capability. The market system will bring on higher cost generation within a
constrained region once a constraint limit is reached.
Details of the permanent transmission constraints applied by the System Operator
are available on this page of our website.
The New Zealand power system currently has single generating units of up to 380
MW output dispatched. Single generating units or multiple generators on a single
connection can be constrained back at times due to the co-optimisation of reserve
in the market model.
In determining the least cost solution for each 30 minute trading period, the market
system co-optimises the cost and quantity of instantaneous reserve (reserve)
needed to cover the loss of the largest generating unit connected, group of
generators on a single connection or HVDC at risk transfer at that time. Where the
cost of the reserve to cover the loss of the largest generating unit, group of
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .31
generators on a single connection or at risk HVDC transfer is more than dispatching
energy from other generators, the market system will dispatch the largest
generating unit, group of generators on a single connection (or adjust the HVDC
transfer by re-dispatching generation in one island to the other) below where it
might otherwise clear based on its offer price alone.
Reserve is offered through the market in a similar way to energy offers. Reserve is
offered as generator response or interruptible load. There can be times where
reserve prices are as high as, or higher than, energy offers. There are also times
when there is insufficient reserve to cover the full output of the largest generating
unit or at risk HVDC transfer. In such situations, large generating units, at risk
HVDC transfer or a group of generators on a single connection, may be constrained
back.
Common situations where generation unit dispatch can be constrained by reserves
include:
• when reserve prices may be high relative to energy prices; and
• times where prices are low and close to zero.
In some situations (i.e. low load), reserve co-optimisation has resulted in large
generators being dispatched below minimum running levels and having to
disconnect.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .32
E – Transmission charges
A generation plant connecting to the Grid will be required to pay charges as follows.
In phase A2.3, Transpower and the Generator agree and sign a Detailed Solution
Development statement of work (SOW)). This defines the scope and cost of
investigation to produce the Solution Study Report (SSR).
Depending on the complexity of the project, the investigation may be staged, with a
series of SOWs.
Transpower’s business is subject to price and quality regulation under Part 5 of the
Commerce Act 1986. This regulation determines the amount of revenue
Transpower can recover, while the methodology by which Transpower allocates the
annual revenue requirement is regulated by the Electricity Authority under Schedule
12.4 of Part 12 (Transport) of the Code: this is known as the Transmission Pricing
Methodology (TPM)
There are three charge components to the TPM, plus LCE rebates.
Connection charges
A connection asset is any Grid asset that connects a customer to Transpower’s
interconnected transmission network. Connection charges recover the capital,
maintenance, operating and injection overhead component associated with
connection assets.
Interconnection charges
A demand based charge that recovers the remainder of Transpower’s HVAC
revenue requirement. The charge is based on each customer’s contribution to the
regional coincident peak demand (RCPD) in their region.
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .33
HVDC charges
An injection based charge levied on South Island generators, used to recover
Transpower’s revenue allowance associated with the operating the HVDC
interisland link. This charge was based on each customer’s historic anytime
maximum injection (HAMI), however from September 2015 Transpower began
transitioning in the South Island Mean Injection (SIMI) charge to replace HAMI. The
SIMI charge will first be charged in April 2017 and be used to allocate 25% of
Transpower’s HVDC revenue allowance, reaching 100% of Transpower’s revenue
allowance by April 2020. There will be no HAMI charges for generators connected
after 31 August 2015.
LCE credit
Under Part 14 (Clearing and settlement) of the Code, Transpower receives the loss
and constraint excess (LCE), a surplus generated in the wholesale electricity
market, net of that used for the Financial Transmission Rights (FTR) market. There
is currently no regulation around how Transpower should allocate the funds,
however the current methodology is to allocate the LCE back to the assets that
have created the LCE. For example, where an LCE amount has generated from the
HVDC link, this amount is apportioned back to those of Transpower’s customers
that contribute toward our HVDC revenue. In most cases, this can result in a credit
toward the cost of our customer’s transmission bill.
Information
For more information on the historical TPM rates levied on transmission customers,
see Transpower’s revenue and pricing page, which includes information on our
forecast transmission revenue for future years.
TPM review
At the time of writing, the TPM is under review by the Electricity Authority 10.A new
Transmission Pricing Methodology is under development, more information can be
found on this page of our website.
All registered market participants are required pay an electricity industry levy to
cover the cost of the Electricity Authority’s activities. The levy is payable in monthly
instalments to NZX Energy as the Clearing Manager .
10 See www.ea.govt.nz/development/work-programme/pricing-cost-allocation/transmission-pricing-review
Generation Connection Guide © Transpower New Zealand Limited 2021. All rights reserved .34