Untitled
Untitled
Untitled
4 18000 F4 417‐‐‐‐REV00
1.0 Introduction
All large generators require auxiliary systems to operate/run smoothly. Auxiliary systems such as
sealing oil for sealing hydrogen gas in the generator casing, Hydrogen gas for hydrogen cooled
rotors, demineralized water for stator winding cooling etc ensure efficient, reliable and safe
operation of the generator. Not all generators require all these systems & the requirement depends
on the size & nature of the machine. The auxiliary systems which are applicable for 660 MW
THDF generators are:-
Besides the auxiliary systems DC starter panels are also critical controls required in operation
during pump motor or power supply failure. The panels are
The rotor shaft ends of hydrogen cooled generators are supplied with pressurized seal oil to
prevent hydrogen losses via the seals and the ingress of air into the generator. This seal oil is fed
to the shaft seal on both the exciter (EE) and the turbine end (TE).The supplied seal oil is then
drained in approx. equal quantities to the hydrogen side and the air side through the annular gaps
between the shaft and the seal rings.
Three seal oil pumps (two pumps: MKW11AP001 & MKW12AP001 with three phase AC
motors and typically one pump, MKW13AP001 with a DC motor) are provided for the seal oil
system. These pumps draw oil from the vacuum tank and the seal oil storage tank. Downstream
of each AC pump pressure transmitter MKW11CP001/ MKW12CP001 and downstream of DC
pump three pressure transmitters MKW13CP001/002/003 are installed for measuring the actual
pressure signal. These transmitters generate the signal for the changeover between the two AC
pumps when seal oil pressure drops below a certain minimum value and for emergency start-up
of DC pump when neither of the two AC pumps builds up the desired pressure in the system.
Both the AC pumps are connected to different busbars to achieve successful changeover to the
pump connected to healthy busbar during under-voltage condition.
The DC operated emergency pump can only be switched off manually. A warning is generated as
soon as the DC pump is activated. After a continuous operation of DC pump for 30 minutes the
generator is depressurized by opening the fire protection valves and the turbine trip is activated to
protect the turbine-generator set.
All of the above controls are realized in BHEL DCS located in the control equipment room.
The primary water system is designed to supply primary water to the hollow stainless steel (660
MW) conductors with the primary water coolant.
For the circulation of primary water through the stainless nonmagnetic steel alloy stator
conductors two 100% AC three phase driven water pumps: MKF11AP001 &MKF12AP001 are
provided. Downstream of each AC pump pressure transmitter MKF11CP001/ MKF12CP001 are
installed for measuring the actual pressure signal and generate the signals for the changeover
between the two AC pumps when pump discharge pressure drops below a certain minimum value.
Level in the primary water tank is measured using level transmitter and an alarm is initiated when
the level falls below a minimum set value.
The small amount of hydrogen leak in the primary water system is vented by the expansion and
storage tank with degassing arrangements (water filled U loop).
A conductivity transmitter MKF29CQ011 installed after the primary water pumps trigger alarm
when the conductivity limit is above a certain minimum value.
A pressure transmitter (MKF41CP001) located in the upstream of stator winding initiates alarm
when the pressure is more than a maximum tolerable value. In order to ensure smooth flow of
water through the hollow stator bars, differential pressure transmitter (MKA20CP021) is installed
across the inlet and the outlet of the stator bars. A warning is generated when the differential
pressure is more than a certain set value.
The primary water filters are monitored for choking and warning is generated. Transmitter
MKF27CP021/ MKF28CP021 is mounted on each PW filter for differential pressure
measurement.
The generator is filled with hydrogen (H2) gas used as coolant and for purging the generator with
inert gas (CO2) during hydrogen charging. The hydrogen pressure at the manifold and in the
generator is measured by explosion proof transmitters (MKG10CP001 & MKG18CP001/2/3). An
alarm is initiated when the pressure at the manifold drops below a certain minimum value. The
pressure transmitters MKG18CP001/2/3 measuring the generator casing pressure are also
connected in a differential pressure configuration to the seal oil pressure and this differential
pressure signal is used in the protection circuit.
Purity of Hydrogen is measured by gas analyzers. A three range gas analyser is used to measure
H2 or CO2 purity. Alarm is initiated when purity falls below 95% Hydrogen in Air.
During carbon dioxide (CO2) filling, the CO2 is passed through parallel arrangements of CO2
flash evaporators. A warning is generated for high CO2 evaporator heater temperature.
In order to maintain the dew point within the threshold limit it is important to keep the
hydrogen gas dry. Refrigeration type gas driers MKG69BT001 and MKG69BT011 are used.
Most Hydrogen from the generator is first passed through a gas to gas heat exchanger. The
hot moist gas on the primary side is cooled in advance through the dried and cold gas on the
secondary side. This heat exchanger is shell and tube type with cold gas passing through the
tubes.
After the pre-cooling the H2 gas passes through the evaporator, which is Freon to gas heat
exchanger. In this way cooling takes place at constant pressure dew point up to 2-3 °C. The
evaporator is again a shell and tube type heat exchanger in which refrigerant from condenser
passes through copper tubes and pre-cooled H2 gas surrounding the tubes. This way heat
from H2 gas is taken away by liquid circulating through tubes. The H2 gas sheds excess
moisture, which is collected in the condensate chamber.
The condensate chamber is provided with a sight glass. The water from the condensate
chamber shall be manually drained.
The two pairs of valves MKG19AA025 & 035 and MAG19AA026 & 36 are connected to
separate 24VDC power supplies. These valves are open when de-energised (to make system
fail safe). Power supply for these Solenoid valves MKG19AA025 & 035 must be routed
separately from power supply of MAK19AA026 & 036 to ensure power supply for two
parallel fire protection valves in the event of malfunction
1) Control during operation with DC seal oil pump:- If AC pumps are not available
and DCSOP is operating. After 30 minutes these valves are operated to bring
generator in safe state.
2) Both Generator Exhaust Fans failed:- If both exhaust fans failed and one seal oil
pump is working, a alarm is issued with a delay of 40 seconds. Command issued to
valves if same criterion stays for 60 minutes.
Pushbuttons are provided in the control room for opening the fire protection valves.
Note:- These valves should not be used to reduce the casing H2 gas pressure in normal
operation
Operation of Fire protection valves is realized in Siemens SPPA T3000 located in the control
equipment room.
During the generator frame filling and emptying procedures, the existing air, inert gas and
hydrogen (H2), as well as mixtures of these gases, must also be discharged via a defined path.
These gases are removed in a defined process through waste gas lines. These waste gas lines
exhaust above the roof in order to ensure safe discharge of the gas mixtures to atmosphere.
The waste gas system also includes two redundant extraction fans which generate a slight partial
vacuum. The generator bearing spaces (TE&EE), the sealing oil supply tank, the primary water
tank and gas dryer are connected to the extraction fan/bearing exhaust fan. Three number
pressure transmitters are provided before the exhaust fan. When the active exhauster is no longer
able to maintain the required vacuum (MKQ81CP001/2/3), the standby exhauster starts
automatically. The other exhauster is shut down when the vacuum is back.
All of the above controls are realized in BHEL DCS (except Fire protection valves) located in the
control equipment room.
The Generator instrumentation provides measurements at various generator points such as the
generator stator slot, generator stator core, hot gas temperature measurement etc. Resistance
temperature detectors (MKA20CT*) & (MKA35*) are provided to obtain data on the stator slot
temperature and stator core temperature during operation. Impermissible deviations from the
normal values indicate a fault in the core laminations. Inside the generator’s hot gas chambers are
the temperature sensors which measure the hot gas temperature, while the cold gas temperature is
measured downstream of the coolers. If the measured temperature values are outside the
tolerance bands, alarm is generated, indicating a fault in the cooling system.
All of the above measurements are realized in Siemens BHEL DCS located in the control
equipment room.
The trip signals from various protection criteria as listed below are gated in OR logic and the trip
over the turbine trip system is initiated. Warnings and a group alarm from the generator are read
in and displayed. The trip signal is read in by two channels in order to trip the turbine.
All the protection controls as given below are realized in BHEL DCS/ Siemens SPPA T3000
located in the control equipment room.
Command is issued to trip the generator when the oil level in the generator terminal box is
above the set limit value. Three numbers of level switch MKA16CL111, 112, and 113 are used
for signal measurement in 2V3 configuration.
Command is issued to trip the generator when the cold gas temperature generator terminal box is
above the set limit value. Three numbers of temperature measurements after each cooler set:
MKA71CT011/12/13 after coolers A/B & MKA71CT031/32/33 after cooler C/D are used for
signal measurement in 2V3 configuration.
Considerable importance is attached to vibration monitoring and protection measures for the
steam turbine generator unit. The vibration data supply important information regarding the
mechanical condition of the operating turbine unit. This protection is realized in two out of two
configurations. The signal generated by the vibration probes (MKD11/MKD12/MKD15CY021
& CY022) are displayed at the operator station of the control system for operator information and
recorded for long term storage. Pre-trip alarm is initiated to inform the operator in and Trip is
initiated automatically when the vibration exceeds the very high critical limit.
Temperature downstream of primary water cooler is measured using three numbers of RTDs
MKF29CT011/12/13.The protection circuit is realized in 2V3 configuration. When the
temperature exceeds the limit value pre-trip alarm is initiated to inform the operator and Trip is
initiated automatically when the value exceeds the very high critical limit.
This protection is realized in 2V3 configurations. The flow is measured using three numbers of
flow transducers MKF41CF011A, MKF41CF011B and MKF1141CF012. Pre-trip alarm is
This protection is realized in 2V3 configurations. The flow is measured using three numbers of
flow transducers MKF51CF011/12/13, MKF51CF21/22/23 and MKF51CF031/32/33 in each
bushing. Pre-trip alarm is initiated to inform the operator and Trip is initiated automatically when
the value exceeds the very high critical limit.
The generator casing pressure protection is realized in two out of three failsafe configuration.
The three explosion proof pressure transmitters MKG18CP001/002/003 generates continuous
signal of pressure value. When the pressure exceeds the low limit value pre-trip alarm is initiated
to inform the operator and Trip is initiated automatically when the value exceeds the very low
critical limit.
This generator seal oil and casing pressure differential is generated in the DCS. The transmitters
MKW31CP051/52/53 and MKG18CP001/002/003 are used to derive the signal
MKW31CP901/902/ 903. When the differential pressure exceeds the low limit value pre-trip
alarm is initiated to inform the operator and Trip is initiated automatically when the value
exceeds the very low critical limit.