Rickson: Engineering Limited
Rickson: Engineering Limited
Rickson: Engineering Limited
Remark:
a) For temperature rise test, we can carry out one test loop per day only; we need 1 day before the
test for preparation and 1 day after the test to allow for cool down, dismantling of setup and
setup for next test loop. Therefore, the above “Test Day 1, 2 & 3”are not continuous.
Rickson Engineering Limited 利信機電有限公司
Replacement of Switchboard in North District Hospital
Routine Tests Procedure (Phase 2) (Rev. 0)
5. The tightness and secureness of all fixing screws, connecting bolts and nuts.
9. Cleanliness of equipment.
1. Remove links and fuses in all tripping, control and alarm circuits.
3. Test and record the insulation resistance between all circuits and earth and between
all circuits by means of a megger.
Remark
1. Any reading of less than 1 mega ohm at 1000V d.c. should be investigated.
2. Any measuring instrument of protective device, e.g. static relay, which may be
damaged by application of such a voltage shall be disconnected at one or all
terminals.
Rickson Engineering Limited 利信機電有限公司
Replacement of Switchboard in North District Hospital
Routine Tests Procedure (Phase 2) (Rev. 0)
2. each live circuit and all other circuits interconnected to earth (e.g. L1 to L2+L3+N+E)
1. Remove links and fuses in all tripping, control and alarm circuits.
3. Apply a voltage of 2500V a.c. at power frequency by means of an a.c. H.V. tester
between all live circuits and between each live circuit and all other circuits
interconnected to earth for 1 minute.
Primary injection test involves the passing of heavy currents through the current
transformers to check:-
L1
L1
L2
L3
L1
Rickson Engineering Limited 利信機電有限公司
Replacement of Switchboard in North District Hospital
Routine Tests Procedure (Phase 2) (Rev. 0)
Remark
1. The tolerance of the secondary current measured is ± 1% and spill current within
100mA
2. If the polarity of any P.C.T. is incorrect, the sum of the currents in the secondary
windings will pass through to earth and significant spill current will be recorded.
Remark
The tolerance of the operating time (at 10 times setting) is ± 5%.
ACB
1. Rack in and out the ACB
Temperature rise measurement test is performed by injection of primary current into the L.V.
Switchboard and recorded the temperature to verify the temperature rise of each incoming & outgoing
terminals, panel cover, operating handle, etc. are not exceed the corresponding limit as defined in
Table 6 of IEC 61439-1:2011 & BS EN 61439-1:2011.
Test Arrangement
The L.V. Switchboards under test are connected in accordance with below drawing no.:
Test Procedure
1. Connect the three phase heavy current supply transformer to the input ends of the Test Loop No. 1. Any
openings will be covered by cardboards (which are poor conductor of heat) throughout the test.
2. Paste thermocouples onto various testing points according to the above drawings (e.g. busbar terminals,
panel covers, operating handles, etc.). Thermocouples for measurement of ambient temperature (2 nos.)
will be positioned at 1m from the switchboard ends and 1m above the floor level.
3. Inject full load test current into the switchboard. Monitor and adjust the current where necessary.
(Remark: (i) in order to accelerate the heating effect, the initial current injected into the SWB/MCC may
be more than the rated current in the first quarter of the test, (ii) only the test current in the last quarter
of the test is material and should be kept constant within ±1%).
4. Measure & record temperature of all testing points per hour and then calculate the individual temperature
rise (i.e. measured temperature – average of ambient temperature).
[Remark: the temperature data under the first quarter period may not be captured.]
5. Continue the test (normally not exceeding 8 hours) until the temperature rise of every testing point does
not exceed 1K/hr.
6. Repeat all the above procedures for Test Loop No. 2 & 3
[Remark: allow adequate time for busbar cooling, normally 4-6 hours, before disconnect the measuring
equipment and busbar setup from Test Loop No. 1.]
Test Equipment
• Voltage Regulator
• Three Phase Heavy Current Supply Transformer
• Fluke 52-II K type Thermometer
• K Type Thermocouples
• Accuenergy Acuvim CL Digital Meter
Rickson Engineering Limited 利信機電有限公司
Replacement of Switchboard in North District Hospital
Routine Tests Procedure (Phase 2) (Rev. 0)
1. Place the test probes (2 nos.) of the ductor tester across the L1 phase of each
busbar joint/connection being measured. The position of the test probes should be as
close to the joint/connection as possible in order to get accurate value. For details,
see Fig.1
4. Repeat the test according to attached schedule (drawing: 800689-DD-01, 02 & 03).
Remark: