Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

B Checking, Inspection and Loading Test at Site

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 7

Previous Week This Week Next Week December

October November
No. Work item 11 - 16 - 26 - Notes
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 - 10
15 25 30
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

A PREPARATION OF MACHINES AND EQUIPMENT OK

B CHECKING, INSPECTION AND LOADING TEST AT SITE

1 Loading Test Work

1.1 L1 (P13-P17) and L2 (P17-P21)

1.1.1 L1 (P13-P17)

Equipment installation

Test Load (Trucks) Arrangement

Stress measurement

Measurement of deflection due to static and dynamic loads

Measurement of superstructure vibration

Measurement of displacement vibration of abutments & piers

1.1.2 L2 (P17-P21)

Equipment installation

Test Load (Trucks) Arrangement

Stress measurement

Measurement of deflection due to static and dynamic loads

Measurement of superstructure vibration

Measurement of displacement vibration of abutments & piers

1.2 L4 (P44-P47), L5 (P54-P57) & RAMP L6 (R1M0-R1P4)

1.2.1 L4 (P44-P47)

Equipment installation

Test Load (Trucks) Arrangement

Stress measurement

Measurement of deflection due to static and dynamic loads

Measurement of superstructure vibration

Measurement of displacement vibration of abutments & piers

1.2.2 Thử tải xác định khả năng chịu lực liên L5 (P54-P57)

Equipment installation

Test Load (Trucks) Arrangement

Stress measurement

Measurement of deflection due to static and dynamic loads


Previous Week This Week Next Week December

October November
No. Work item 11 - 16 - 26 - Notes
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 - 10
15 25 30
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

Measurement of superstructure vibration

Measurement of displacement vibration of abutments & piers

1.2.3 RAMP L6 (R1M0-R1P4)

Equipment installation

Test Load (Trucks) Arrangement

Stress measurement

Measurement of deflection due to static and dynamic loads

Measurement of superstructure vibration

Measurement of displacement vibration of abutments & piers

1.3 Cantilever bridge L3 (P60-P63)

Equipment installation

Test Load (Trucks) Arrangement

Stress measurement

Measurement of deflection due to static and dynamic loads

Measurement of superstructure vibration

Measurement of displacement vibration of abutments & piers

2 Check joints of struts and beams

2.1 Visual inspection of struts and beams at test beam locations

Check of eccentricity through strain results under load test (check


2.2
struts at load test sections and adjacent to load test section)

3 Inspect cracks and advise on crack treatment (if any)


INSPECTION OF THE QUALITY OF GIRDERS,
C
ABUTMENTS AND PIERS
1 Quality inspection

1.1 Quality inspection of box girder construction

L1 (P13-P17)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

Measurement of main girder static deflection

L2 (P17-P21)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine
Previous Week This Week Next Week December

October November
No. Work item 11 - 16 - 26 - Notes
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 - 10
15 25 30
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

Measurement of main girder static deflection

Cantilever bridge L3 (P60-P63)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

L4 (P44-P47)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

Measurement of main girder static deflection

L5 (P54-P57)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

Measurement of main girder static deflection

RAMP L6 (R1M0-R1P4)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

Measurement of main girder static deflection

1.2 Quality inspection of abutment construction

L1 (P13-P17)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

L2 (P17-P21)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete
Previous Week This Week Next Week December

October November
No. Work item 11 - 16 - 26 - Notes
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 - 10
15 25 30
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

L3 (P60-P63)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

L4 (P44-P47)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

L5 (P54-P57)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

RAMP L6 (R1M0-R1P4)

Determination of concrete homogeneity on structure by non-


destructive method using ultrasonic machine

Electromagnetic method to determine the thickness of the protective


concrete layer, the position of reinforcement in the concrete

D Data analysis, reporting of test results


Tiến độ chi tiết thực hiện kiểm định

Previous Week This Week Next Week December

October November
No. Work item 11 - 16 - 26 - Notes
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 - 10
15 25 30
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

Thử L1 (P13-P17) và L2 Thử L5 (P54-P57) và L6 (R1M0-


Thử L3 (P60-P63) Thử L4 (P44-P47)
(P17-P21) R1P4)

1 CHUẨN BỊ MÁY MÓC VÀ THIẾT BỊ OK

KHẢO SÁT, KIỂM ĐỊNH, THỬ TẢI L1 (P13-P17), L2 (P17-


Lấn 1 P21)
(Từ ngày 02/11/2022 ÷ 06/11/2022)

Xác định độ đồng nhất bê tông trên kết cấu bằng phương pháp
không phá hoại sử dụng máy siêu âm (90 cấu kiện):
- N14; N15, N16, N18, N19, N20: 6 nhịp x 3 mặt cắt x 3 vị trí =
1.1
54 cấu kiện
- Trụ P13, P14, P15, P16, P17, P18, P19, P20, P21: 9 trụ x 4 vị trí
= 36 cấu kiện

Xác định chiều dày lớp bê tông bảo vệ, vị trí cốt thép trong bê tông
bằng phương pháp điện từ (90 cấu kiện):
- N14; N15, N16, N18, N19, N20: 6 nhịp x 3 mặt cắt x 3 vị trí = 54
1.2
cấu kiện
- Trụ P13, P14, P15, P16, P17, P18, P19, P20, P21: 9 trụ x 4 vị trí
= 36 cấu kiện

1.3 Khảo sát vết nứt tại nhịp N14, N15, N18, N19

Khảo sát liên kết thanh chống tại vị trí thử tải:
1.4 - Mặt cắt 1/2 các nhịp N14; N15, N18, N19: 4 vị trí thử tải x 2
bên x 2 thanh = 16 thanh chống

Lắp cảm biến đo biến dạng (dán lá điện trở, đi dây): 4 mặt cắt x 42
1.5
điểm = 168 điểm
Dán, thả dây thép để lắp thiết bị đo võng tĩnh, võng động khi thử tải:
1.6
4 mặt cắt x 4 điểm = 16 điểm
Thử tải: đo biến dạng, võng tĩnh, võng động tại các mặt cắt 1/2 các
1.7
nhịp N14; N15; N18; N19
Đo dao động kết cấu nhịp, mố, trụ:
1.8 - Nhịp N14, N15, N18, N19;
- Trụ: P13; P14; P17; P18

1.9 Đo độ vồng tĩnh kết cấu nhịp: nhịp N14, N15, N18, N19

Thực hiện các công tác khảo sát còn lại (các công tác siêu âm bê
1.10 tông, dò cốt thép, khảo sát vết nứt chưa thực hiện trong thời gian từ
02/11-06/11)

KHẢO SÁT, KIỂM ĐỊNH, THỬ TẢI L3 (P60-P63)


Lần 2
(Từ ngày 07/11/2022 đến 12/11/2022)

Xác định độ đồng nhất bê tông trên kết cấu bằng phương pháp
không phá hoại sử dụng máy siêu âm (31 cấu kiện):
2.1 - N61; N62, N63: (2 khối K0 + 3 khối K của 3 nhịp) x 3 vị trí = 15
cấu kiện
- Trụ P60, P61, P62, P63: 4 trụ x 4 vị trí = 16 cấu kiện

Xác định chiều dày lớp bê tông bảo vệ, vị trí cốt thép trong bê tông
bằng phương pháp điện từ (43 cấu kiện):
2.2 - N61; N62, N63: (2 khối K0 + 3 khối K của 3 nhịp) x 3 vị trí =
15 cấu kiện
- Trụ P60, P61, P62, P63: 4 trụ x 4 vị trí = 16 cấu kiện

2.3 Khảo sát vết nứt tại nhịp N61, N62

Khảo sát liên kết thanh chống tại vị trí thử tải:
2.4 - Mặt cắt 1/2 các nhịp N61; N62: 2 vị trí thử tải x 2 bên x 2 thanh
= 8 thanh chống

Lắp cảm biến đo biến dạng (dán lá điện trở, đi dây): 2 M/C giữa
2.5
nhịp x 42 điểm + 1 M/C trụ P61 x 48 điểm= 132 điểm
Dán, thả dây thép để lắp thiết bị đo võng tĩnh, võng động khi thử tải:
2.6
2 mặt cắt x 4 điểm = 8 điểm
Previous Week This Week Next Week December

October November
No. Work item 11 - 16 - 26 - Notes
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 - 10
15 25 30
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

Thử tải: đo biến dạng, võng tĩnh, võng động tại các mặt cắt 1/2 các
2.7
nhịp N61; N62; đo biến dạng tại M/C trụ P61
Đo dao động kết cấu nhịp, mố, trụ:
2.8 - Nhịp N61, N62
- Trụ: P60, P61
Thực hiện các công tác khảo sát còn lại (các công tác siêu âm bê
2.9 tông, dò cốt thép, khảo sát vết nứt chưa thực hiện trong thời gian từ
07/11-12/11)

KHẢO SÁT, KIỂM ĐỊNH, THỬ TẢI L4 (P44-P47)


Lần 3
(Từ ngày 14/11/2022 ÷ 18/11/2022)

Xác định độ đồng nhất bê tông trên kết cấu bằng phương pháp
không phá hoại sử dụng máy siêu âm (43 cấu kiện):
3.1
- N45; N46, N47: 3 nhịp x 3 mặt cắt x 3 vị trí = 27 cấu kiện
- Trụ P44, P45, P46, P47: 4 trụ x 4 vị trí = 16 cấu kiện
Xác định chiều dày lớp bê tông bảo vệ, vị trí cốt thép trong bê tông
bằng phương pháp điện từ (43 cấu kiện):
3.2
- N45; N46, N47: 3 nhịp x 3 mặt cắt x 3 vị trí = 27 cấu kiện
- Trụ P44, P45, P46, P47: 4 trụ x 4 vị trí = 16 cấu kiện

3.3 Khảo sát vết nứt tại nhịp N45, N46

Khảo sát liên kết thanh chống tại vị trí thử tải:
3.4 - Mặt cắt 1/2 các nhịp N45; N46: 2 vị trí thử tải x 2 bên x 2 thanh
= 8 thanh chống

Lắp cảm biến đo biến dạng (dán lá điện trở, đi dây): 2 mặt cắt x 42
3.5
điểm = 84 điểm
Dán, thả dây thép để lắp thiết bị đo võng tĩnh, võng động khi thử tải:
3.6
2 mặt cắt x 4 điểm = 8 điểm
Thử tải: đo biến dạng, võng tĩnh, võng động tại các mặt cắt 1/2 các
3.7
nhịp N45, N46
Đo dao động kết cấu nhịp, mố, trụ:
3.8 - Nhịp N45, N46
- Trụ: P44, P45

3.9 Đo độ vồng tĩnh kết cấu nhịp: nhịp N45, N46

Thực hiện các công tác khảo sát còn lại (các công tác siêu âm bê
3.10 tông, dò cốt thép, khảo sát vết nứt chưa thực hiện trong thời gian từ
14/11-18/11)
KHẢO SÁT, KIỂM ĐỊNH, THỬ TẢI L5 (P54-P67); L6 (R1M0-
Lần 4 R1P4)
(Từ ngày 25/11/2022 ÷ 30/11/2022)

Xác định độ đồng nhất bê tông trên kết cấu bằng phương pháp
không phá hoại sử dụng máy siêu âm (93 cấu kiện):
- N55, N56, N57: 3 nhịp x 3 mặt cắt x 3 vị trí = 27 cấu kiện
- tuyến nhánh N1, N2, N3: 3 nhịp x 3 mặt cắt x 3 vị trí = 27 cấu
4.1
kiện
- Trụ P54, P55, P56, P57, P58, R1P1, R1P2, R1P3, R1P4: 9 trụ x
4 vị trí = 36 cấu kiện
- Mố R1M0: 1 mố x 3 vị trí = 3 cấu kiện

Xác định chiều dày lớp bê tông bảo vệ, vị trí cốt thép trong bê tông
bằng phương pháp điện từ (93 cấu kiện):
- N55, N56, N57: 3 nhịp x 3 mặt cắt x 3 vị trí = 27 cấu kiện
- tuyến nhánh N1, N2, N3: 3 nhịp x 3 mặt cắt x 3 vị trí = 27 cấu
4.2
kiện
- Trụ P54, P55, P56, P57, P58, R1P1, R1P2, R1P3, R1P4: 9 trụ x
4 vị trí = 36 cấu kiện
- Mố R1M0: 1 mố x 3 vị trí = 3 cấu kiện

4.3 Khảo sát vết nứt tại nhịp N55, N56, N1, N2

Khảo sát liên kết thanh chống tại vị trí thử tải:
4.4 - Mặt cắt 1/2 các nhịp N55; N56: 2 vị trí thử tải x 2 bên x 2 thanh
= 8 thanh chống

Lắp cảm biến đo biến dạng (dán lá điện trở, đi dây): 129 điểm
4.5 + 2 mặt cắt nhịp chính x 42 điểm = 84 điểm
+ 3 mặt cắt nhịp nhánh x 15 điểm = 45 điểm
Previous Week This Week Next Week December

October November
No. Work item 11 - 16 - 26 - Notes
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 - 10
15 25 30
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed

Dán, thả dây thép để lắp thiết bị đo võng tĩnh, võng động khi thử tải:
4.6
4 mặt cắt x 4 điểm = 16 điểm
Thử tải: đo biến dạng, võng tĩnh, võng động tại các mặt cắt 1/2 các
4.7
nhịp N55, N56, N1, N2
Đo dao động kết cấu nhịp, mố, trụ: 24 điểm đo
4.8 - Nhịp N55, N56, N1, N2: 4 nhịp x 3 điểm = 12 điểm
- Trụ: P54, P55, R1M0, R1P1: 4 điểm x 3 mố trụ = 12 điểm

4.9 Đo độ vồng tĩnh kết cấu nhịp: nhịp N55, N56, N1, N2
Thực hiện các công tác khảo sát còn lại (các công tác siêu âm bê
4.10 tông, dò cốt thép, khảo sát vết nứt chưa thực hiện trong thời gian từ
25/11-30/11)

XỬ LÝ SỐ LIỆU, LẬP BÁO CÁO


5
(Từ ngày 1/12/2022 ÷ 10/12/2022)

Ghi chú: Tiến độ trên là dự kiến.

You might also like