Estimate
Estimate
Estimate
(GR.+1ST) OF MR. AMAR DEY ,S/O LATE KHUDIRAM DEY AND MRS
KAKALI DHARA(DEY),W/O- MR AMAR DEY ,ON MOUZA- JOTERAGHAB, J.L
NO -046, PLOT NO -463, KH.NO- , P.O. & P.S. - JAMALPUR ,UNDER
JAMALPUR -I GRAM PANCHATAT DIST - PURBA BARDHAMAN.
GROUND FLOOR = 916.00 SQ.FT GROUND FLOOR =474.00 SQ.FT
Rates taken from PUBLIC WORKS DEPARTMENT [GOVERNMENT OF WEST BENGAL] BUILDING WORKS (VOLUME – I) [Incorporation of
GST Act, 2017 & All addenda & Corrigenda of SOR, 01.12.2015] Effective From 1 st November 2017
SL
DESCRIPTION OF ITEMS QUANTITY UNIT RATE UNIT AMOUNT
NO
Earth work in excavation of foundation trenches or drains, in all sorts
of soil (including mixed soil but excluding laterite or sandstone)
including removing, spreading or stacking the spoils within a lead of
1 75 m. as directed. The item includes necessary trimming the sides of 70.12 %Cum 11927.00 %Cum 8363.21
trenches, levelling, dressing and ramming the bottom, bailing out
water as required complete. a) Depth of excavation not exceeding
1,500 mm. [ P-1; It-2(a)]
8 Hire and labour charges for shuttering with centering and necessary
staging upto 4 m using approved stout props and thick hard wood
planks of approved thickness with required bracing for concrete
slabs, beams and columns, lintels curved or straight including fitting,
fixing and striking out after completion of works (upto roof of ground
floor) [ P- 42; It-36]
Page 1
ABSTRACT COST ESTIMATE FOR TWO STOIRED RESIDENTIAL BUILDING
(GR.+1ST) OF MR. AMAR DEY ,S/O LATE KHUDIRAM DEY AND MRS
KAKALI DHARA(DEY),W/O- MR AMAR DEY ,ON MOUZA- JOTERAGHAB, J.L
NO -046, PLOT NO -463, KH.NO- , P.O. & P.S. - JAMALPUR ,UNDER
JAMALPUR -I GRAM PANCHATAT DIST - PURBA BARDHAMAN.
GROUND FLOOR = 916.00 SQ.FT GROUND FLOOR =474.00 SQ.FT
Rates taken from PUBLIC WORKS DEPARTMENT [GOVERNMENT OF WEST BENGAL] BUILDING WORKS (VOLUME – I) [Incorporation of
GST Act, 2017 & All addenda & Corrigenda of SOR, 01.12.2015] Effective From 1 st November 2017
SL
DESCRIPTION OF ITEMS QUANTITY UNIT RATE UNIT AMOUNT
NO
14 Plaster (to wall, floor, ceiling etc.) with sand and cement mortar
including rounding off or chamfering corners as directed and raking
out joints including throating, nosing and drip course,
scaffolding/staging where necessary (Ground floor).[Excluding cost
of chipping over concrete surface] [P-189, It-1] (B)
(ii) With 1:4 cement mortar (c) 10 mm thick plaster for ground floor
320.00 Sqm 123.00 Sqm 39360.00
15 (i) With 1:6 cement mortar (c) 15 mm thick plaster for ground floor
360.00 Sqm 134.00 Sqm 48240.00
16 (i) With 1:6 cement mortar (b) 20 mm thick plaster for ground floor
450.00 Sqm 155.00 Sqm 69750.00
20 Collapsible gate with 40mm x 40mm x 6mm Tee as top and bottom
guide rail, 20mm x 10mm x 2mm vertical channels 100mm apart in
fully stretched position 20mm x 5mm M.S. flats as collapsible
bracings properly rivetted and washered including 38mm steel rollers
including locking arrangements, fitted and fixed in position with lugs 6.75 Sqm 3402.00 Sqm 22963.50
set in cement concrete and including cutting necessary holes, chasing
etc. in walls, floors etc. and making good damages complete. In
ground floor. [P-106; It-18]
Page 2
ABSTRACT COST ESTIMATE FOR TWO STOIRED RESIDENTIAL BUILDING
(GR.+1ST) OF MR. AMAR DEY ,S/O LATE KHUDIRAM DEY AND MRS
KAKALI DHARA(DEY),W/O- MR AMAR DEY ,ON MOUZA- JOTERAGHAB, J.L
NO -046, PLOT NO -463, KH.NO- , P.O. & P.S. - JAMALPUR ,UNDER
JAMALPUR -I GRAM PANCHATAT DIST - PURBA BARDHAMAN.
GROUND FLOOR = 916.00 SQ.FT GROUND FLOOR =474.00 SQ.FT
Rates taken from PUBLIC WORKS DEPARTMENT [GOVERNMENT OF WEST BENGAL] BUILDING WORKS (VOLUME – I) [Incorporation of
GST Act, 2017 & All addenda & Corrigenda of SOR, 01.12.2015] Effective From 1 st November 2017
SL
DESCRIPTION OF ITEMS QUANTITY UNIT RATE UNIT AMOUNT
NO
22 Supplying best Indian sheet glass panes set in putty and fitted and
fixed with nails and putty complete. (In all floors for internal wall &
1.08 Sqm 536.00 Sqm 578.88
upto 6 m height for external wall) (ii) 4 mm thick In ground floor. [P-
205; It-1]
23 Supplying, Fitting & Fixing 30 mm thick Factory made solid Panel
PVC Door Shutter consisting of outer frame made out of M.S. tubes
of 19 gauge thickness and size 19 mmx19 mm for styles, top and
bottom rails, M.S. frame shall have cost of steel primers of approved
make and manufacture, M.S. frame covered with 5 mm th. heat
moulded PVC “C” channel of size 30 mm th, 70 mm width out of
which 50 mm shall be flat and 20 mm shall be tapered in 45 degree
angle on either sides forming styles; and 5 mm th. 95 mm wide PVC
sheet out of which 75 mm shall be flat and 20 mm tapered in 45
degree on the inner side to form top & bottom rail and 115 mm wide
PVC sheet out of which 75mm shall be flat and 20 mm shall be 6.30 Sqm 1943.00 Sqm 12240.90
tapered on both sides to form lock rail. Top, bottom and lock rails
shall be provided either side of the panel with 10 mm (5 mm x 2)
th.,20 mm wide cross PVC sheet as gap insert for top rail and bottom
rail. Paneling of 5 mm th. both side PVC sheet to be fitted in the M.S.
frame welded/sealed to the styles &rails with 7 mm (5 mm+2 mm)
th.x15 mm wide PVC sheet beading on inner side and joined together
with solvent cement adhesive. An additional 5 mm th. PVC strip of
20 mm In ground floor. [P-125; It-15]
25 Supplying, fitting & fixing 1st quality Ceramic tiles in walls and
floors to match with the existing work & 4 nos. of key stones (10mm)
fixed with araldite at the back of each tile & finishing the joints with
white cement mixed with colouring oxide if required to match the
colour of tiles including roughening of concrete surface, if necessary
or by synthetic adhesive & grout materials etc. (B) Wall With Sand 112.00 Sqm 1091.00 Sqm 122192.00
Cement Mortar (1:3) 15 mm thick & 2 mm thick cement slurry at
back side of tiles using cement @ 2.91 Kg/Sq.m & joint filling using
white cement slurry @ 0.20kg/Sq.m. (b) Area of each tile above 0.09
Sq.m (i) Coloured decorative In ground floor. [P-64; It-
35](b)-b]
26 Priming one coat on steel or other metal surface with synthetic oil
bound primer of approved quality including smoothening surfaces by 62.36 Sqm 29.00 Sqm 1808.44
sand papering etc. In Ground floor: [P- 200; It- 1(a)]
Page 3
ABSTRACT COST ESTIMATE FOR TWO STOIRED RESIDENTIAL BUILDING
(GR.+1ST) OF MR. AMAR DEY ,S/O LATE KHUDIRAM DEY AND MRS
KAKALI DHARA(DEY),W/O- MR AMAR DEY ,ON MOUZA- JOTERAGHAB, J.L
NO -046, PLOT NO -463, KH.NO- , P.O. & P.S. - JAMALPUR ,UNDER
JAMALPUR -I GRAM PANCHATAT DIST - PURBA BARDHAMAN.
GROUND FLOOR = 916.00 SQ.FT GROUND FLOOR =474.00 SQ.FT
Rates taken from PUBLIC WORKS DEPARTMENT [GOVERNMENT OF WEST BENGAL] BUILDING WORKS (VOLUME – I) [Incorporation of
GST Act, 2017 & All addenda & Corrigenda of SOR, 01.12.2015] Effective From 1 st November 2017
SL
DESCRIPTION OF ITEMS QUANTITY UNIT RATE UNIT AMOUNT
NO
27 (A) Painting with best quality synthetic enamel paint of approved
make and brand including smoothening surface by sand papering etc.
including using of approved putty etc. on the surface, if necessary
(b) On steel or other metal surface : With super gloss (hi-gloss) - (iv) 62.36 Sqm 79.00 Sqm 4926.44
Two coats (with any shade except white)
[P-200; It- 2(A)-(b)-iv]
30 c) Bend 87.5 degree (ii) 110 mm. Dia. 15.00 nos 140.00 nos 2100.00
Total Amount:= 1839909.10
ADD 3% FOR PLUMBING WORK:= 55197.27
ADD 5% FOR ELC.WORK:= 110394.55
Grand Total Amount:= 2005500.92
SAY AMOUNT:= 2005500.00
Total Estimated Cost comes to Rupees Twenty Lakh Five Thousaand Five Hundred only.
Page 4