Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

ANALYSIS OF RATE Bituminous Macadam 50mm To 75mm Thickness (Grading II)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ANALYSIS OF RATE Bituminous Macadam 50mm to 75mm thickness

(Grading II)
Sr. No. DESCRIPTION QUANTITY UNIT RATE AMOUNT
1/24.18 Providing and laying bituminous macadam 50mm
(a) to 75mm thick with batch type hot mix plant
using
crushed aggregates of specified grading premixed
with bituminous binder VG-30 @3.4%, laid over a
previously prepared surface with hydrostatic
paver finisher with sensor control to the required
grade, level and alignment and rolled to achieve
the desired compaction complete as per
technical
clause 504 of MORT&H specifications

BITUMEN VG-30 @ 3.4% PER MT =74.8 Kg


BASIC RATE 1 CUM 5254.05
0% PREMIUM 0
2 DIFF. OF COST FOR QUARRY & EXTRA CARRIAGE
OF 25 mm - 10mm STONE METAL @ 40%
BEYOND 5.0 Km 0.5667 CUM 258.32 146.39
3 DIFF. OF COST FOR QUARRY & EXTRA CARRIAGE
OF 10 mm - 5mm STONE METAL @ 40% BEYOND
5.0 Km 0.5667 CUM 322.46 182.74
4 DIFF. OF COST FOR QUARRY & EXTRA CARRIAGE
OF 5mm COARSE SAND & BELOW @ 20%
BEYOND 5.0 Km
0.2834 CUM 514.68 145.86
1.4168
5 EXTRA CARRIAGE OF MIXED MATERIAL FROM
PLANT TO SITE AVR. LEAD 5 Km 1 CUM 195.17 195.17
6
ADD 20% FOR BITUMEN MATERIAL 39.034

TOTAL 5963.24
7
LESS/ADD DIFFERENCE OF BITUMEN 0.0748 MT 27185.86 2033.50
NET TOTAL 7996.75
8 ADD 5.35% DIFF OF GST AS PER SLIP NO 5 427.8259
GRAND TOTAL 8424.57