Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Slab Culvert Estimate 5M

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

Rural Reconstruction & Rehabilitation Sector Development Programme - 2

District Project Office, Chitwan

DETAILED QUANTITY ESTIMATE

Name of Works: 5 m Slab Culvert

Item
Description of works No. Length Breadth Height Quantity Unit
No.
(m) (m) (m)

1 Earthwork in excavation in foundation


Abutment Wall 2 5.10 3.00 1.50 45.90 cu.m.
Wing Walls 4 3.69 1.78 1.50 39.41 cu.m.
Bedding in between Abutments 1 5.10 3.10 1.50 23.72 cu.m.
U/S & D/S Apron 2 2.60 6.27 0.50 16.30 cu.m.
Cut off Walls (U/S & D/S) 2 8.27 0.50 1.00 8.27 cu.m.
Total = 133.60 cu.m.

2 P.C.C work in 1:2:4 in foundation bed & floors :


Abutments 2 5.10 2.90 0.20 5.92 cu.m
Wing Walls 4 3.59 1.68 0.10 2.41 cu.m
Total = 8.33 cu.m.

3 Gabion work
Bed Block 1 5.10 4.56 0.50 11.63 cu.m
Apron 2 2.50 6.27 0.50 15.68 cu.m.
Cut off Walls (U/S & D/S) 2 8.27 1.00 1.00 16.54 cu.m.
Total = 43.84 cu.m.

4 Stone masonry work in 1:4 c/s mortar


Abutments 2 5.10 1.040 2.50 26.52 cu.m
Abutment First Footing 2 5.10 2.50 0.50 12.75 cu.m
Abutment Second Footing 2 5.10 2.00 0.50 10.20 cu.m
Wing Walls 4 3.54 0.99 2.95 41.35 cu.m
Total = 90.82 cu.m.

5 PCC work for RCC in 1:1.5:3


Deck Slab 1 5.85 5.10 0.44 13.13
Kerb 2 5.85 area= 0.13 1.52
Abutment cap 2 5.10 0.725 0.30 2.22
Dirt wall 2 5.10 0.250 0.44 1.12
Total = 17.99 cu.m.

6 Reinforcement Work Area Wt


Slab along Span bottom 1 5.75 0.011 496.51 Kg
Slab along Span top 1 5.75 0.002 90.28 Kg
Slab across Span bottom 1 5.00 0.0039 153.08 Kg
Slab across Span top 1 5.00 0.00196 76.93 Kg
Abutment Cap Longitudinal bars (top+bottom) 2 5.00 0.001 78.50 Kg
Abutment Cap Stirrups 2 1.750 0.004 109.90 Kg
Dirt wall Longitudinal bars 2 5.00 0.00030 23.55 Kg
Dirt wall Stirrups 2 1.68 0.004 105.50 Kg
Total = 1134.25 Kg
Rural Reconstruction & Rehabilitation Sector Development Programme - 2
District Project Office, Chitwan

DETAILED QUANTITY ESTIMATE

Name of Works: 5 m Slab Culvert

Item
Description of works No. Length Breadth Height Quantity Unit
No.
(m) (m) (m)

7 Formwork
Slab Bottom 1 4.90 5.100 24.99 sq.m
Slab Edge 2 5.85 0.44 5.15 sq.m
Kerb Outer side 2 5.85 0.5 5.85 sq.m
Kerb inner side inclined portion 2 5.85 0.29 3.39 sq.m
Kerb inner side vertical portion 2 5.85 0.25 2.93 sq.m
Abutment Cap outer side 2 5.10 0.74 7.55 sq.m
Abutment Cap inner side 2 5.10 0.74 7.55 sq.m
Abutment Cap side Horizontal 4 0.30 0.3 0.36 sq.m
Abutment Cap side vertical 4 0.25 0.44 0.44 sq.m
Total = 58.20 sq.m

8 100mm Dia. HDPE Pipe Weep Holes Nos.


Abutments 2 1.01 9.000 18.18 rm.
Wing walls 4 0.95 14.000 53.20 rm.
Total = 71.38 rm.

9 Bearing (Tar Paper) 2 5.10 0.425 4.34 sq.m.


Unit Total
Number quantity

Culvert Details
Clear Span 6
Overall Depth 0.5
Overall Length 6.85
H 1.5
width of Culvert 5.1
Apron length 1
0

496.5125

spacing dia(m)
0.12 0.02

12mm bar 12 nos.


2 LS 8mm dia @150mm C/C
8mm dia. Bar @ 150mm C/C
2 LS 12mm dia @150mm C/C
0
Unit Total
Number quantity

Culvert Details

150

1 0.750
0.666667
0
53.2
0

You might also like