Developing The Schedule
Developing The Schedule
This chapter deals with estimating the resources and durations for all the specific activities, and
developing a detailed project schedule that determines when each activity should start and
finish.
• Calculating the latest times by which each activity must start and finish to com-
plete the project by its required completion time
• Determining the amount of positive or negative slack between the time each
activity can start or finish and the time it must start or finish
• Identifying the critical (longest) path of activities
• Performing the steps in the project control process
• Determining the effects of actual schedule performance on the project schedule
• Incorporating changes into the schedule
• Developing an updated project schedule
• Determining approaches to controlling the project schedule
• Implementing agile project management
Estimate Activity Resources
● The estimated resources required for an activity will influence the estimated
duration to perform the activity and the estimated cost of the activity.
● When estimating resources for activities, the availability of each resource has
to be taken into account. It is important to know what types of resources are
available, in what quantities, and during what time periods to determine if the
right types of resources will be available in sufficient quantities during the time
periods that they are needed for specific activities.
● The estimated duration for each activity must be the total elapsed time
● The estimated duration for an activity must be based on the estimated quantity of
resources required to perform the activity.
● As the project progresses, the project team can progressively elaborate the estimated
durations as more information is known or becomes clear to allow for more accurate
estimated durations.
Establish Project Start and Completion Times
● it is necessary to select a project estimated start time for when the project is expected to
begin and a project required completion time
for when the project must be done .