Testing & Commissioning Plan - Jotun Project - Rev 00
Testing & Commissioning Plan - Jotun Project - Rev 00
Testing & Commissioning Plan - Jotun Project - Rev 00
Issue Date: 16 August 2022 T & C Plan For: DESCRIPTION OF ACTIVITY Rev.: 00
Ref.# HAC-TCP-JOTUN-22-00 Project JOTUN PROJECT – PHASE 2 Pages: Page 1 of 19
MASTER
: N\A
DEVELOPER
PMC : N/A
SUB-CONSULTANT : Sub-consultants
SUB-CONTRACTOR : PERFECT
TABLE OF CONTENTS
1. REVISION RECORD ...................................................................................................................................... 4
I. INTRODUCTION ............................................................................................................................................ 5
I.1. Overview of the commissioning process .............................................................................................. 5
I.2. Systems and assemblies included in commissioning authority’s scope of work ............................. 5
I.3. Commissioning team and its responsibilities ....................................................................................... 6
I.3.1. Owner (El Mohandes Jotun S.A.E) ......................................................................................................... 6
I.3.2. Commissioning Authority (Production Team “JOTUN” & Quality Team “HAC”) .............................. 6
I.3.3. Design / Technical Control Consultants (COSMOS) ............................................................................. 7
I.3.4. Contractor / Sub-contractor / Supplier (HAC)........................................................................................ 7
I.4. Description of management, Communication and Reporting of Commissioning Process ...... Error!
Bookmark not defined.
I.5. Commissioning Plan ............................................................................................................................... 8
I.6. Commissioning Process Milestone, Schedule...................................................................................... 8
I.7. Commissioning Check-Lists and Testing Procedures ....................................................................... 10
2. SCOPE ......................................................................................................................................................... 11
3. REFERENCES ............................................................................................................................................. 11
3.1. References / Code of Practices ............................................................................................................ 11
3.2. Contract documents .............................................................................................................................. 13
3.3. Contractors Submittal ........................................................................................................................... 13
4. DEFINITIONS / ABBREVIATIONS .............................................................................................................. 14
5. Completion Phase .........................................................................................Error! Bookmark not defined.
6. Commissionig Phase ...................................................................................Error! Bookmark not defined.
7. HandOver Phase ..........................................................................................Error! Bookmark not defined.
8. Documentation For Completion , Commissionig & HandOver. ....................Error! Bookmark not defined.
9. FORMS......................................................................................................................................................... 19
10. ANNEXES
1. ANNEX 01: T & C for HVAC System
19
2. ANNEX 02: T & C for .............................................................................................................................. 19
3. ANNEX 03: T & C for .............................................................................................................................. 19
Document Ref#. HAC-xxxx-xxxx - Rev. 00 – Issued Date 15/08/2022
Quality Department Quality Management System
Issue Date: 16 August 2022 T & C Plan For: DESCRIPTION OF ACTIVITY Rev.: 00
Ref.# HAC-TCP-JOTUN-22-00 Project JOTUN PROJECT – PHASE 2 Pages: Page 4 of 19
1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All
previous revisions are hereby superseded and are to be destroyed.
Rev. Date By Checked. Approved Description of Revisions
Signature field
Rev. Number→ Rev.No. Revision Date→ 16-Aug-22
Position Name Signature Date
QA/QC
Prepared by→ Engineer
Sub-
contractor N\A N\A N\A
QA/QC
Checked by→
Manager
QA/QC
Segment
Reviewed Construction
By→ Manager
Technical
Manager
Project
Approved By→
Manager
I. INTRODUCTION
The commissioning plan is the reference document that identifies the strategies, aspects and outlines
the overall process, schedule, organization, responsibilities and documentation requirements of the
commissioning process for all commissioning team members.
Required commissioning plan components:
1. Brief overview of the commissioning process.
2. List of all systems and assemblies included in commissioning authority’s scope of work.
3. Identification of commissioning team and its responsibilities.
4. Description of management, communication and reporting Of commissioning process.
I.1. Overview of the commissioning process
The Commissioning authority will verify the installation and performance of the systems to be
commissioned, and will complete a commissioning report as part of the Fundamental commissioning
process.
The commissioning authority will document all commissioning review process, submittals, system
manual, verify O&M as a part of the commissioning report and final acceptance.
Below are the commissioning team members, along with their individual responsibilities in the
commissioning process during project phases.
F. Witness equipment, subsystem, and system start‐up and testing. Ensure the results
are documented, including a summary of deficiencies, and incorporated in the O&M
manuals.
G. Supervise the commissioning team members in the functional performance tests. The
test data will be part of the commissioning report.
H. Ensure that the O&M manuals and all other as‐built records have been updated to
include all modifications made during the construction phase.
I. Prepare the final commissioning report and the systems manual.
I.3.3. Design / Technical Control Consultants (COSMOS)
A. Provide system design parameters and revisions to the initial design intent document
as necessary, obtaining approval of the owner.
B. Prepare contract documents, including the commissioning specification and
description of the commissioned systems.
C. Attend construction‐phase coordination meeting.
D. Specify and verify adequate maintenance accessibility for each piece of equipment in
shop drawings and actual installation. Periodic inspections are part of the design
professional’s construction administration duties.
E. Develop an overview of system design and operation concepts for the Systems
Manual.
F. Review and accept as‐built records as required by contract documents and turn them
over to the commissioning authority.
I.3.4. Contractor / Sub-contractor / Supplier (HAC)
A. Include costs for commissioning requirements in the contract price.
B. Ensure cooperation and participation of specialty subcontractors and controls
contractors.
C. Ensure coordination, installation, and operation of interfaces between commissioning
team.
D. Prepare necessary preliminary schedule for commissioned system orientation and
inspections, O&M manual submission, equipment and systems’ testing, for use by
the commissioning authority.
E. Notify the commissioning authority when equipment and system start‐up and testing
can be witnessed.
F. Provide written notification to the construction manager and commissioning authority
that the following work has been completed in accordance with the contract
documents and that the equipment, systems, and subsystems are functioning as
required and ready for commissioning.
G. Demonstrate the operation of each piece of equipment to the commissioning
authority.
H. Schedule subcontractors as may apply to demonstrate the operation of the
equipment and systems.
I. Provide services of an engineer to participate in verification tests.
J. Turn over a set of as‐built records to the commissioning authority. (Hard and soft
copies).
K. Provide filled checklist data sheets to document verification tests for the
commissioning authority.
L. Submit verification test data to the design team and the commissioning authority for
review.
M. Conduct tests and verifications including opposite season tests, as required.
N. Retest if performance deficiencies are found and corrected and additional testing is
requested.
The commissioning Phase take place when mechanical completion is completed for a
commissioning package.
• Pre Commissioning .
• Commissioning Execution .
• Commissioning Documentation and Handover to operation
The startup and testing of systems may proceed prior to final completion of systems. However, the
commissioning authority shall not perform checkout services that are the primary responsibility of the
contractor vendor in advance of their testing and checkout, whom in return are responsible to inform
the commissioning team once their systems are ready to be verified and tested.
The following table including all systems to be commissioned can be updated during commissioning
process .
Systems to be commissioned
Pre‐functional Equipment Functional Sample
System: Target
checklists startup testing size
date:
Chilled Water System Y/N Y/N Y/N % N/A
Air Cooled Chiller
Equipment & Accessories Y/N Y/N Y/N % N/A
The commissioning authority will direct and witness some verification operating tests and checks.
The testing contractor’s technician will inspect and verify the position of each device and interlock that is
identified on the checklist. Each item shall be signed off as acceptable or failed.
Operating checks shall include all safety cutouts, alarms, and interlocks with smoke control and life safety
systems during all modes of operation of the system.
If, during a test, an operating deficiency is observed, appropriate comments shall be added to the checklist
data sheet.
The proper response of monitoring and control system controllers and sensors shall be verified.
Final verification:
JOTON Engineer will direct and witness the field verification of the final testing report.
JOTON Engineer will select at random percentage of the report data for verification.
• Failure of the final testing and balancing report shall require contractor to complete the
following work.
− Any system failing the verification procedure must be rechecked and corrected.
Document Ref#. HAC-xxxx-xxxx - Rev. 00 – Issued Date 15/08/2022
Quality Department Quality Management System
Issue Date: 16 August 2022 T & C Plan For: DESCRIPTION OF ACTIVITY Rev.: 00
Ref.# HAC-TCP-JOTUN-22-00 Project JOTUN PROJECT – PHASE 2 Pages: Page 11 of 19
2. SCOPE
2.1. To define the Preliminary Steps, principles and structures of mechanical completion ,
commissioning and Handing over for provisions of MEP Systems for JOTUN New solvent &
water Based factory Project – Phase II , 10th of Ramadan , Egypt , for Jotun paints
2.2. This plan is a general plan providing Direction for the commissioning process, providing
resolution for issues such as scheduling, roles and responsibilities, lines of communication and
reporting, approvals, and coordination ,explain on-site procedures and methods of testing and
commissioning for the different components of the MEP Systems, including the installation of
Main Systems, Sub-main Systems, Accessories, and all other components,
2.3. A separate detailed commissioning plan for each system shall be submitted in separate
annex
− .
3. REFERENCES
3.1. References / Code of Practices
1. (ECP) Egyptian Code of Practice.
12. IEC 60079 Explosive atmospheres. All standards under the 60079 series.
13. IEC 62305 Protection against lightning All standards under the 62305 series.
21. NFPA 20 Standard for the Installation of Stationary Pumps for Fire Protection.
22. NFPA 22 Standard for Water Tanks for Private Fire Protection.
23. NFPA 24 Standards for the Installation of Private Fire Service Mains and Their
Appurtenances.
24. NFPA 25 Standard for the Inspection, Testing, and Maintenance of Water-Based Fire
Protection Systems.
25. NFPA 30 Flammable and Combustible Liquids Code.
26. NFPA 33 Standard for Spray Application Using Flammable or Combustible Materials.
34. NFPA 110 Standard for Emergency and Standby Power Systems.
35. NFPA 170 Standards for Fire Safety and Emergency Symbols.
37. NFPA 291 Recommended Practice for Fire Flow Testing and Marking of Hydrants.
38. NFPA 329 Recommended Practice for Handling Releases of Flammable and
Combustible Liquids and Gases.
39. NFPA 432 Codes for the Storage of Organic Peroxide Formulations.
40. NFPA 484 Standards for Combustible Metals, Metal Powders, and Metal Dusts.
41. NFPA 650 Standard for Pneumatic Conveying Systems for Handling Combustible
Particulate Solids.
42. NFPA 654 Standards for the Prevention of Fire and Dust Explosions from the
Manufacturing, Processing, and Handling of Combustible Particulate Solids.
44. NFPA 780 Standards for the Installation of Lightning Protection Systems.
46. UL 142 Standard for Steel Aboveground for flammable and combustible liquids.
47. UL 58 Standard for Steel Underground Tanks for flammable and combustible.
8. Shop Drawings
Sr.
Description Shop Drawings Rev No. Date Remarks
No.
4. DEFINITIONS / ABBREVIATIONS
1. Commissioning Package : A practical scope of work unit within a system or subsystem
commissioning
2. Carry Over work register (COWR) : Register of incomplete items.
3. C : Commissioning .
4. CC : Commissionig certificate .
5. MC : Mechanical Completion .
6. MCC : Mechanical Completion Certificate .
7. RFCC : Ready for Commissioning Certificate .
Document Ref#. HAC-xxxx-xxxx - Rev. 00 – Issued Date 15/08/2022
Quality Department Quality Management System
Issue Date: 16 August 2022 T & C Plan For: DESCRIPTION OF ACTIVITY Rev.: 00
Ref.# HAC-TCP-JOTUN-22-00 Project JOTUN PROJECT – PHASE 2 Pages: Page 15 of 19
5. Completion Phase
• Mechanical completion means that the work is finished according to project specifications ,
Suppliers’ requirements and is ready to commissioning .
• Documentation for work completion include inspection requests & Test result submittals.
• MCC : Shall be issued by the executer and signed by the engineer prior the commencement
of commissioning.
6. Commissioning Phase
1- Inspection Requests , Test Results & material submittals are the evidence
Documents for mechanical completion.
2- MCC shall be issued and signed by all parties prior the commissioning.
3- RFCC shall be issued and signed by all parties once the MCC is signed and
the system is ready for commissioning ( start up & testing ).
4- CC shall be issued and signed by all parties after finishing the
commissioning of each system .
5- TOC shall finally be issued and signed attached with it all the above
mentioned documents and MUD
9. Forms
10. ANNEXES
10.1. ANNEX 01: T & C for HVAC System.
10.2. ANNEX 02: T & C for
10.3. ANNEX 03: T & C for
10.4. ANNEX 04: T & C for
10.5. ANNEX 05: T & C for
10.6. ANNEX 06: T & C for
10.7. ANNEX 07: T & C for
10.8. ANNEX 08: T & C for
10.9. ANNEX 09: T & C for
10.10. ANNEX 10: T & C for
10.11. ANNEX 11: T & C for
10.12. ANNEX 12: T & C for
10.13. ANNEX 13: T & C for
10.14. ANNEX 14: T & C for