ECM366 CHAPTER 1 DEFINITIONS INTRO TO SMM & myCSMM BQ
ECM366 CHAPTER 1 DEFINITIONS INTRO TO SMM & myCSMM BQ
ECM366 CHAPTER 1 DEFINITIONS INTRO TO SMM & myCSMM BQ
PREPARED BY:
WAN ZUKRI WAN ABDULLAH
Senior Lecturer
COURSE OUTCOME (CO) CHAPTER 1
CO1
Evaluate bill of quantities for major elements
WEEK 1
TOTAL CONTACT HOURS : 3
of building and civil engineering works in
accordance with Malaysian Civil Engineering
Standard Methods of Measurement
(myCESMM). 1.0 INTRODUCTION
BILL OF QUANTITIES
Consist of a schedule of the items of work to be
carried out under the contract with quantities and
unit cost rate entered against each item.
5
OTHER DEFINITIONS
TAKING-OFF
1
Process of Measuring from drawings and recording all
dimensions in recognized form on a special ruled paper
known as “Dimension Paper’ or ‘Taking-off Sheet’
SQUARING DIMENSION
2
Process of multiplication and/ or addition/
substraction of recorded dimension for the purposes
of obtaining the linear, square or cubic measurements.
OTHER DEFINITIONS
ABTRACTING OR WORKING UP
3 Process of collecting the measurements of identical
character and description, under different tracks and
reducing them to units as required by CESMM
TRADE
Work or practice of certain craft. Example:
Bricklayer, Plumber, Concreter, Carpenter etc. 4
CONDITION OF CONTRACT
5 Defines the terms under which the work is to be undertaken, the
relationship between the Promoter or employer, the engineer and
the contractor, the powers of the engineer and the term of payment.
OTHER DEFINITIONS
SPECIFICATION
6 Implies the information given in the Contract Drawings
and the Bill of Quantities. Describe in detail the work to be
executed under the contract and the nature and quality of
material and workmanship.
CONTRACT DRAWING
Despite the nature and scope of the work to be
carried out under the contract. They must be
prepared to a suitable scale and be insufficient to 7
permit a contractor to price the Bill of Quantities
and to carried out the work satisfactorily.
PROVISIONAL SUM
8 For work which cannot be described and given in items
which follows the measurement rules.
A sum provided for works or for the cost, which cannot
be entirely foreseen, defined or detailed at the time
tendering documents is issued.
PRIME COST
A sum provided for work or services to be executed by
the Nominated Sub-Contractor (NSC) for materials or
9 goods to be obtained from Nominated Supplier (NS)
Such sum shall be estimated to be exclusive of any profit
required by general contractor and provision shall be
made for the addition thereof.
1.2 Introduction to Standard
Method of Measurement of Building
Works (SMMM) and Malaysian Civil
Engineering Standard Methods of
Measurement (myCESMM).
Standard Method of Measurement of Building Works
SMMM
MyCESMM
www.website.com 11
Objective
To set forth the procedure
for the measurement of the
work according to which
the Bill of Quantities shall
be prepared and priced.
SMMM
Standard Method of
Measurement of Building Works
03 04 05 06
The details of Building work Building works mostly not Building work comprises
building works are generally covers subject to re-measurement many different trades
usually in a far more more work sections, due to rare occurrence in whereas civil engineering
precise stage at the
and is in designvariation while civil works consists of large
time of preparing the
BQ than is the case consequence subject engineer works subject to quantities of a
with civil engineering to more detailed design variation quite often comparatively small
works measurement range of items
17
8 MAIN SECTIONS IN MyCESMM
1 2 3 4
Definitions General Application Application
Principles of the Work of the Work
Classification Classification
5 6 7 8
Preparation
Completion, Method – Work
of Bill of
Pricing and Relates Classifications
Quantities
use of BQ Charges
(BQ)
18
SECTION 8 is further divided into 18 classes as follow:
MyCESMM CLASS A : General Items
CLASS B : Environmental Protection and Enhancement
CLASS C : Traffic Management and Control
CLASS D : Site Investigation Work
CLASS E : Demolition and Site Clearance
CLASS F : Earthworks
CLASS G : Geotechnical Work
CLASS H : Piling Work
CLASS I : Concrete Works
CLASS J : Brickwork, Blockwork and Masonry
19
SECTION 8 is further divided into 18 classes as follow: (Cont’nd)
MyCESMM CLASS K : Timber Work
CLASS L : Metal Work
CLASS M : Building Work
CLASS N : Painting Work
CLASS O : Pipe Work
CLASS P : Drainage Work
CLASS Q : Roads and Paving
CLASS R : Tunnel Work
CLASS S : Rail Track
CLASS T : Miscellaneous Work
20
MyCESMM SMMM
Covers a Large Variety Covers More Trade or
of Different Jobs Work Section
Less number of items because More number of items to be
most of the item are included NO. OF NO. OF measured separately
in the main job ITEMS ITEMS E.g.: Backfilling trenches,
E.g.: Backfilling trenches, levelling, levelling, compacting and
compacting and planking included planking are measured
in excavation rate. separately
CODING CODING
For convenient of refence NO Coding is required
AND AND
and computerization each
NUMBERING NUMBERING
item in the Work
OF ITEMS OF ITEMS
Classification has been
assigned code number
consisting of a letter and
not more than 3 digits
www.website.com 22
23
1.3 Procedure in Preparing
Bill of Quantities
PREPARATION BILL OF QUANTITIES
Stage 1
Taking-off
Stage 2
Abtracting
Stage 3
Writing a Bill of Quantities
STAGE 1
COLUMN A TAKING-OFF SHEET
TIMESING COLUMN
Used if the quantities to A B C D A B C D
be multiplied
COLUMN B
DIMENSION COLUMN
Dimensions of the item COLUMN C COLUMN D
are entered one below SQUARING COLUMN DESCRIPTION COLUMN
the other in this column. It is where the final Any figure, description
quantity is entered. and additional calculation
STAGE 2: ABSTRACTING
ABSTRACTING
ITEM NO. DESCRIPTION UNIT QUANTITY
ABSTRACT SHEET
It consists of transferring the description and quantity from the
taking-off sheet to the abstract sheet and collecting together
items, which can be, billed under one item. If the quantity has to
be converted from one unit to another unit this is done on the
abstract sheet.
STAGE 3: WRITING A BILL OF
QUANTITIES
QUANTITIES
BILL OF
ITEM DESCRIPTION UNIT QUANTITY UNIT AMOUNT
NO. RATE
BILL OF QUANTITIES
There are certain principles, which should always be followed
when writing a bill of quantities. It should be concise, accurate
and well written.
BILL OF
QUANTITIES
THANK
YOU