FIR Dt.08.06.2023
FIR Dt.08.06.2023
As per inspection call JSL/NSK/ PLNH/J1002/2023/138 Dt 04.06.2023 the under signed surveyor visited to
M/s. Deccan Enterprise Pvt Ltd works for inspection of 132KV 70 KN Long rod silicon composite Insulators
(1188 Nos) and found none of material against the inspection call is not ready for inspection. Hence visit on
08.06.2023 has been Aborted.
* Category: (1) Accepted (2) Conditionally Accepted (3) Re-inspection Required (4) Rejected (5) Advice/Instruction from client required
Inspection Date(s): * ANY NON Yes
08.06.2023 CONFORMITY
FOUND? No 08.06.2023
Inspection Place(s): Surveyor’s Stamp & Date
DEL, Sultanpur, * ORDER Complete Signature
Supplier’s Signature & Date Name: MSR Krishnamaraju
Sangareddy Dt TS STATUS Telephone no.
Balance Telephone no. 09885306345
* - Circle the relevant details OR strike out the non-relevant details
# - Include the reasons for rejection in the ‘details’ of the report Format FIR r5 – 19th Aug 2015