Our company is highly specialised in the development and production of uninterruptible power supplies (UPS).
The device described in this manual is a high quality product that has been carefully designed and manufactured to guarantee
optimal performance.
This manual contains detailed instructions for product use and installation.
This manual must be stored in a safe place and CONSULTED BEFORE DEVICE USE for proper usage instructions as
well as maximum performance from the device itself.
NOTE: Some images contained in this document are for information purposes only and may not faithfully demonstrate the parts
of the product they represent.
ENVIRONMENTAL PROTECTION
Our company devotes abundant resources for analysing environmental aspects in the development of its products. All our
products pursue the objectives defined in the environmental management system developed by the company in compliance with
applicable standards.
Hazardous materials such as CFCs, HCFCs or asbestos have not been used in this product.
When evaluating packaging, the choice of material has been made favouring recyclable materials.
Please separate the different material of which the packaging is made and dispose of all material in compliance with applicable
standards in the country in which the product is used.
SAFETY
This part of the manual contains SAFETY precautions that must be followed scrupulously.
The device has been designed for professional use and is therefore not suitable for use in the home.
The device has been designed to operate only in closed environments. It should be installed in rooms where there are
no inflammable liquids, gas or other harmful substances.
Take care that no water or liquids and/or foreign bodies fall into the device.
In the event of a fault and/or impaired operation of the device, do not attempt to repair it but contact the authorized
service centre.
The device must be used exclusively for the purpose for which it was designed. Any other use is to be considered
improper and as such dangerous. The manufacturer declines all responsibility for damage caused by improper, wrong
and unreasonable use.
© The reproduction of any part of this manual, even in part, is prohibited unless authorised by the Manufacturer.
The manufacturer reserves the right to change the product described at any time without prior notice for improvement purposes.
CONTENTS
INTRODUCTION 15
INSTALLATION 15
PARALLEL CARD ASSEMBLY PROCEDURE 15
SIGNAL CONNECTION 17
UPS AC INPUT / OUTPUT POWER CONNECTION 18
POWER CONNECTIONS “BATTERY” SIDE 20
Our Company assumes no liability for damages caused by incorrect connections or operations not
contained in this manual.
INSTALLATION
1. Remove the “Parallel cover 1”, unscrewing the two screws from its slot at the back of UPS and cut the band around the flat
cable.
Note: please, make sure that the flat cable could not drop into the case.
2. Pull out the cable, taking care not to damage the cable’s protective covering.
3. Connect the flat cable to parallel card. Then insert the parallel card sub-assembly into the parallel slot on the rear panel.
Please, pay attention to the card orientation.
15
4. Fasten 2 pcs M3 screw to fix the parallel card as shown in the following picture.
16
SIGNAL CONNECTION
To perform the signal connection, follow the indications below. Use the Parallel cables supplied only.
The signal connection must remain there even after switching off one or more UPSs.
The system cannot be switched on without the ring closure connection.
1. Connect one of the parallel cable supplied to the COM1 of UPS1 and to the COM2 of the UPS2.
2. Connect one the other parallel cable supplied to the COM2 of UPS1 and to the COM1 of the UPS2.
3. After installing the two parallel cards with the respective cables, install 2 pcs “Parallel cover 2” to protect the parallel cable,
and fix the covers by 4 pcs M3 screw as shown in the picture.
17
UPS AC INPUT / OUTPUT POWER CONNECTION
In order to choose the cable section for each ups, refer to the chapter in the user manual entitled “Cables section”.
Connect the power cables L1, (L2, L3 if presents) and N to the input terminals L1, (L2, L3 if presents) and N of each
UPS.
Connect the load cables L1 and N to the output terminals L1 and N of each UPS.
SPM 6
18
SPH 8-20, 10 ER, 20 ER (SINGLE-PHASE INPUT)
19
MAGNETO-THERMAL SWITCHES:
To prevent a system failure from impacting on all of the machines present, it is essential that the input of each UPS be protected
by a completely independent magneto-thermal switch which is installed upstream of the machine (for rating of the switches, see
the indications of the UPS manual in the section “PROTECTION DEVICES”).
DIFFERENTIAL SWITCH:
To avoid false alarms, when there are various machines in parallel, one single differential switch upstream of the entire system
must be inserted as indicated in figure B.
Fig. A Fig. B
BAT BAT
UPS 1 UPS 2
OUT OUT
20
INITIAL START-UP
CAUTION: when operating SWMB follow these instructions:
SWMB must not be closed on a switched off UPS that is in parallel with other units operating normally. This
action might damage the UPSs and/or create dangerous voltage at the output.
1. Check that switches and isolators SWMB, SWIN, SWOUT on all the UPSs are open.
2. Close switch SWMB of only one UPS.
3. Ensure that no protection device up or downstream of the UPS has been triggered. If it has, check that the
connections are correct.
4. Check that the voltage between input and output terminals of all UPS units (L1_IN with L1_OUT, N_IN with N_OUT
and so on) is <5Vac. If this is not so, check connections are correct.
5. Open SWMB on all UPSs and close SWIN.
6. Wait for the pre-charge phase to finish, then check that all UPSs are STAND-BY status.
7. Check that all UPSs connected to the system have the same firmware version. To check the installed firmware
3
versions it is necessary the software PowerShield (refer to the UPS’s User Manual). If the firmware versions are
different it is necessary to upgrade all UPSs individually.
8. Start up the UPSs by pushing the ON button on the display of one UPS.
9. Wait for the end of the start-up phase and check that all UPSs are functioning on inverter. Then measure the output
voltage of each UPS to check if the voltage difference is less than 1V between them. If not, please calibrate the
output voltage , until the difference is less than 1V.
10. Close switch SWMB of one UPS to check that the whole system can switch to the bypass.
11. Open switch SWMB again. Wait a few seconds to check that all UPSs have returned to operating from inverter.
12. Repeat steps 10. and 11. for the other UPS in the system.
13. If the check is positive, close switches SWOUT of all UPSs.
14. After the start-up phase, check again that all UPSs are functioning on inverter.
15. After waiting approximately one minute, check there is no malfunction with the load disconnected.
16. When load is connected, wait for approximately one minute and then check that power distribution between the
various units is within ±3%.
21
BYPASS OPERATION CHECK
1. Connect an output load so that each unit indicates an output power greater than 5%.
2. Run the bypass command following the indications on UPS’s User Manual.
3. Wait a few seconds and verify that all UPSs switch onto the bypass line.
4. Verify through the display that power distribution between the various units is within ±5%.
During bypass operation the load distribution between the UPSs depends on the length of the cables only, so the rules
on the length of connections as indicated in the connections section must be followed.
If the imbalance between the various units is greater, the total power of the system has to be derated. For example if the
imbalance in bypass is 20% the maximum usable power of the system will be 90% of the rated total.
To return in Inverter mode from Manual Bypass for maintenance, open the SWMB switch of both UPSs in a quick sequence;
verify that the display does not show the code “C05” and then press the “ON” button to restart the system.