Concrete Pumping Risk Assessment
Concrete Pumping Risk Assessment
Concrete Pumping Risk Assessment
Assessment Team:
Client: Contractor Representatives: Page 1 of 5
General Guidelines:
1. Task Risk Assessment (also called Job Safety Analysis) is a qualitative hazard identification technique used for identifying, assessing and controlling major hazard(s) associated with a
specific task or operation where Permit to Work (PTW) precautions are deemed insufficient to execute the job safely.
2. No such work should be allowed to proceed until Risk Assessment has been completed and approved by a competent authority (normally Site Manager/Superintendent).
3. Risk Assessment should be carried out by a competent person and conducted in a team environment, involving all relevant parties.
4. Only trained and experienced staff should be deployed to execute high-risk jobs.
5. Conduct TRA well in advance as part of the work planning process.
6. Address all direct and indirect hazards associated with the task.
7. This TRA shall be conducted in conjunction with the above referenced PTW. A copy of the approved Risk Assessment must be attached to the permit throughout the work duration.
8. Use 5x5 Risk Assessment Matrix (provided separately) to assess the potential risks.
9. When determining safeguards, consider the ‘Hierarchy of Hazard Controls’ provided on this page.
10. Communicate TRA to all relevant personnel through meetings/toolbox talks before starting work.
11. Record Risk Assessment and revise if necessary.
15. Potential blockages Operator, Only “single-ended” hoses shall be used – double Supervisor/CPO Only competent
at start or restart of Workers, / steel collared ended hoses shall personals should be
pump, use of suspended Visitors, not be used “off the boom”. assigned the tasks,
hose “of the boom” Others The CPO shall request that all persons remain follow complete,
resulting in hose clear (a radial distance of at least twice the length Safety personnel
whipping into danger 3 2 6 1 2 2
of the hose) of the suspended hose at each start surveillance, giving
area or restart of the pump and until “smooth flow” first aid, & proper
has been achieved. Also, see Blockages section toolbox talk.
below training
Full PPE to be worn.
16. Bursting of pipelines / Operator, Only pipes, hoses, clips of sufficient safety rating Supervisor/CPO
hoses under pressure Workers, shall be used. Wear and damage
Visitors, shall be monitored by the CPO and checked
4 3 12 1 2 2
Others during scheduled services. Excessively
damaged/worn components shall be withdrawn.
Also, see Blockages section below
17. Forceful ejection of air / Operator, Pipe jointing seals shall be clean and in good Supervisor/CPO
concrete from the end Workers, order. Concrete level in the pump hopper O, S
of the pipeline. Air sucked Visitors, must be maintained at the required
into line and compressed Others level, where the CPO is required to
3 4 12 position himself remote of the 1 3 3
pump appoint a competent person
to monitor deliveries and hopper
level (to ensure air is not pumped into the pipe
system).
18. Pressurised concrete Operator, CPO to ensure the pipeline is depressurized Supervisor/CPO
release – dismantling Workers, before freeing jointing clips, hirer personnel must
4 4 16 1 3 3
of line Visitors, not uncouple pipes without the express
Others permission of the CPO
19. Pipeline cleaning with Operator, A demarcated and access restricted area shall be Supervisor/CPO
compressed air – Workers, provided at the end of the pipeline that is to be
pressurised release / Visitors, 2 3 6 air cleansed. 1 3 3
ejection of sponge ball / Others
concrete / water / air
Segregation of concrete / aggregates as it is pressurised through the pipeline with It shall be ensured that the appropriate grout mix is used. Maximum pipeline and delivery hose length shall be
the primer / grout considered – grouting may be more successful in shorter sections
Inappropriate concrete mix design or consistency – not suitable for pumping Only concrete that is of “pump mix design” and appropriate quality should be specified for delivery to
Hardening of the concrete in boom / pipeline from standing too long (usually when CPO shall circulate or move the concrete in the hopper / boom / pipeline. Deliveries shall be time managed and
awaiting delivery of fresh concrete) planned appropriately
Flexible placing hose become kinked The hose should never become kinked, it should be suspended vertically when used “off the boom”
Foreign objects delivered from visiting mixer drums The quality of the concrete should be monitored
Blockages – Reacting To
Where possible the CPO will stop the pump action and reverse the pumping direction (this may free the blockage). Before the CPO restarts the pumping action, he should ensure all persons retreat to a safe
distance away from the boom / pipeline. Should the blockage persist, the CPO will stop the pump, depressurize the line and investigate the location of the blockage before taking appropriate action (ie
disconnecting pipework to locate and remove the blockage).
A momentary blockage may occur that frees immediately this is often accompanied by increased engine / pump revs and noise. The CPO shall endeavour where possible to warn persons in the vicinity to
stand clear. However, the release is likely to cause the delivery hose and/or boom to move or “kick” before the pump action can be stopped.
Severity
disability
3-Likely Major injury or health effects (long Major damage Major Effect Major impact 2 0 2 4 6 8 10
term or permanent partial disability)
1 0 1 2 3 4 5
2- Unlikely Minor injury or health effects leading Minor effect Minor Effect Minor impact
to LTI/RWC/MTC 0 0 0 0 0 0 0
1- Very Unlikely Single injury or health effects, Slight effect Slight Effect Slight impact 0 1 2 3 4 5
requiring first aid
Risk=Likelihood x Severity
0- Zero to Very
Low
Date: