Work Plan - WS Bukhara
Work Plan - WS Bukhara
Work Plan - WS Bukhara
MONTHS
S. No. DELIVERABLES
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28 M-29 M-30 M-31 M-32 M-33 M-34 M-35 M-36 M-37 M-38 M-39 M-40 M-41 M-42 M-43 M-44 M-45 M-46 M-47 M-48 M-49 M-50 M-51 M-52 M-53 M-54 M-55 M-56 M-57 M-58 M-59 M-60
3 Identification of Raw Water Source and other structures locations and carrying out its
survey
4 Carrying out Topographical investigations in all the project towns to capture road levels
and other features of the project locations
5 Conducting Geotechnical Investigations
Conduct Initial Social Assessment and Environmental examinations based on the Initial
6 Environmental Assessment (IEE) and Review Framework (EARF). Reconfirm during detailed
design that the project activities do not include involuntary resettlement and/or land
acquisition.
7 Raw water Sample quality testing and analysis
8 Preparation of survey report including Site findings and features
3. Detail Design Stage
1 Fixing of Design basis for all Water Supply Components
2 Population Projection and Water Demand Estimation
3 Carrying out Source Sustainability of proposed raw water sources
New/Re-Construction of Intake works, WTP, Water Transmssion Lines, Storage Reservoirs
4 in Kagan, Karaulbazar, Ramitan, Peshku, Bukhara, Jandar districts and cities of Bukhara and
Kagan of Bukhara region
Hydraulic modeling of Distribution Network using WaterGems Software and network
5 optimization in Kagan, Karaulbazar, Ramitan, Peshku, Bukhara, Jandar districts and cities of
Bukhara and Kagan of Bukhara region
6 Surge Analsysis and providing appropiate surge protection devices
7 Provision of Water Metering as per National Metering Policy
Preparation of Conceptual design, Detailed Design & Drawings of Water Supply System in
8 Kagan, Karaulbazar, Ramitan, Peshku, Bukhara, Jandar districts and cities of Bukhara and
Kagan of Bukhara region
9 Preparation of Distribution Network, Intermediate Pumping Station and Structure
drawings
10 Preparation of Standard Drawings
11 Preparation of Final ESIA/ESMPF
Preparation of Resettlement Plans (RPs), and Gender Action Plan in accordance with
12 procedures described in the project Environment and Social Management Planning
Framework (ESMPF)
Preparation of Cost Estimates of all the Water Supply components using schedule of rates
13 for scheduled items while Rate Analysis/Vendor Quotation shall be used for Non-scheduled
Items.
14 Preparation of O & M Cost Estimates along with Cost Recovery Mechanism
15 Preparation of Tender Drawings for all the components of proposed Water Supply System
including standard drawings
17 Preparation of BoQ for all the items proposed in the Water Supply Components
18 Submission of Tender Document with Specifications, schedules, Data Sheet and BoQ
Page 1 of 2
MONTHS
S. No. DELIVERABLES
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18 M-19 M-20 M-21 M-22 M-23 M-24 M-25 M-26 M-27 M-28 M-29 M-30 M-31 M-32 M-33 M-34 M-35 M-36 M-37 M-38 M-39 M-40 M-41 M-42 M-43 M-44 M-45 M-46 M-47 M-48 M-49 M-50 M-51 M-52 M-53 M-54 M-55 M-56 M-57 M-58 M-59 M-60
5. Author's Supervision
1 Site Visit and review of construction progress
2 Checking of construction works at site and review whether the ongoing work is as per
design and drawing
Construction Supervision
9 Updating the client for any issues which might delay the site progress with possible
resolution measures
10 Submission of Monthly Progress Report (Interim)
11 Submission of Sub-Project Completion Report
Legends:
Main Activity
Sub-Activity
Main Report
Interim Report
Page 2 of 2