GIS Testing and Commissioning Checklist - SEC - CSD
GIS Testing and Commissioning Checklist - SEC - CSD
Substation
Bay/Panel
Equipment Serial No
schemes.
Check Minimum control voltage trip (60%) and close (80%)
7.
operations.
Check pump start stop trip/close lockout threshold values for
8.
CB mechanism.
GIS PTs to be included during AC HV tests on GIS when test
frequency is well above rated Frequency, otherwise test at
9. 1.5Un – one minute at rated frequency without secondary
load. PTs secondary output volts shall be measured
accordingly during the high voltage test.
Testing of All AC/DC MCBs tested by trip test through current
10.
injection.
11. Testing of all auxiliary relays and contactors.
12. Testing of meters, annunciators and metrosil resistors.
Measure current drawn by motor for CB and DS and check
13.
the results according to design.
Check & confirm the three-phase test adaptor and bushing for
14.
HV test on GIS have been provided.
Verify the alarms being initiated by SF6 density gauges on
15.
LCC and up to control room during calibration process.
Check that all cubicle space heaters and thermostats are
16.
functional and at correct temperature control settings.
Perform Mechanical Check and Visual Inspection and
17. Electrical test as per WI-NG-6460-002-023 for current
transformers
Perform Mechanical Check and Visual Inspection and
18. Electrical test as per WI-NG-6460-002-024 for voltage
transformers:-
19. Check gaps of protective flashover devices (if applicable).
Verify secondary circuits, terminal to terminal for correctness
20.
and tightness before energization.
21. High voltage test as per WI-NG-6460-002-028