001 - Pdfsam - Commissioning Documentation - Euro Rig 5
001 - Pdfsam - Commissioning Documentation - Euro Rig 5
001 - Pdfsam - Commissioning Documentation - Euro Rig 5
: EU 5-MC-PR-01-00
Issue
Bentec Project No.: B-05272 / 900663 01
CONTRACT TITLE
For
DAFORA SA
DOCUMENT TITLE
Commissioning Documentation
04 Converted E IV GW Jan. 09
03 Converted E III GW Oct.02
02 Converted EII GW Aug.08
01 Updated GW GNK Aug.08
00 Issue GW Jul: 08
Table of Content:
1. Introduction
3. Layout Drawing
2
350 to Bentec AC Drilling Rig
1. Introduction
The Bentec "350 – t- AC Euro Rig" is a Drilling System designed and engineered to operate
under European conditions. All equipment and materials are in compliance with the current
ISO. DIN, and European standards including the ATEX specification.
The system is designed to be highly mobile; capable of being easily disassembled into truck
package sizes for easy transportation.
This comprehensive set of documents will demonstrate "completeness and functionality" of the
assembled and function tested drilling rig.
3
350 to Bentec AC Drilling Rig
4
350 to Bentec AC Drilling Rig
3. Layout Drawings
5
350 to Bentec AC Drilling Rig
6
350 to Bentec AC Drilling Rig
Structural H. Fischer
Mechanical G. Niemeier-Krönke
Electrical C. Klein
Instrumentation C. Klein
Rig Up R. Brüggemann
L. Kalmer
H. Ekelhoff
DAFORA SA can nominate their own responsible commissioning team to follow and
sign off activities as per contract.
7
350 to Bentec AC Drilling Rig
Please find attached a short list of activities during testing of main equipment (not all
equipment is described in detail)
8
350 to Bentec AC Drilling Rig
This chapter includes the different MCC-check sheets for the main equipment. Also the
acceptance certificates which have to be signed off by DAFORA SA. and Bentec are included.
Therefore DAFORA SA has not to sign off each individual activity shown in MCC-check
sheets.
9
350 to Bentec AC Drilling Rig
10
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Derrick and Substructure
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP frames for 13-5/8" and / or 21-1/4" BOP
1.) Successful testing of the BOP storing frames, equipment and operation
has been carried out
2.) Function test has been witnessed by: Darfora
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping System
1.) Successful testing of all installed Mast Erection System equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Rig Structure
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Casing Stabbing Board
1.) Successful testing of the installed Casing Stabbing Board, equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORE
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drawworks
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Rotary Table
1.) Successful testing of all installed Rotary Table equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Traveling Block
1.) Successful testing of all installed Traveling Block equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drill Line Reel
1.) Successful testing of all installed Drill Line Reel equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Hydraulic Power Unit
1.) Successful testing of all installed HPU "Drilling Equipment" equipment and operation has
been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Top Drive
1.) Successful testing of all installed Top Drive equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Spin Torque
1.) Successful testing of all installed Iron Roughneck equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drillfloor Winch No.1
1.) Successful testing of the Drill Floor Winch No.1, equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drillfloor Winch No.2
1.) Successful testing of all the Drill Floor Winch No.2, equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Manriding Winch
1.) Successful testing of all installed Manriding Winch equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Cathead
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Derrickman Hoist
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Wireline Unit
1.) Successful testing of all installed Wire Line Unit equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Dead Line Anchor
1.) Successful testing of all installed Dead Line Anchor equipment has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping Winch
1.) Successful testing of all installed Mast Telescoping Winch A equipment has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping Winch
1.) Successful testing of all installed Mast Telescoping Winch B equipment has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Catwalk Winch
1.) Successful testing of all installed Catwalk Winch equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP Hoist
1.) Successful testing of all installed BOP hoist equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP Hoist
1.) Successful testing of all installed BOP hoist equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets
1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets
1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets
1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Emergency Generator
1.) Successful testing of all installed Emergency Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Air Compressor System
1.) Successful testing of all installed Air Compressor equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Air Compressor System
1.) Successful testing of all installed Air Compressor equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mud Tank System
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Emergency Shower
1.) Successful testing of all installed BOP Lifting Hoist equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps
Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump B
1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORS SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps
Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump C
1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORS SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps
Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump A
1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafors SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps
Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Desander pump
1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps
Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Desilter pump
1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps
Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Mix pump A
1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps
Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Mix pump B
1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps
Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Triptank pump
1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Jardboranir
Dafors SA
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package
1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package
1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora sa
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package
1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora sa
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mud Gas Separator
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Degasser
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Fuel Distribution System
1.) Successful testing of all installed BOP Lifting Hoist equipment and operation
has been carried out
2.) Function test has been witnessed by: Darfora SA
Bentec
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps
1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps
1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps
1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud System
A-Items:
B-Items:
It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)
Name
Sign
Date