Bentec Document No.

: EU 5-MC-PR-01-00
Issue
Bentec Project No.: B-05272 / 900663 01

CONTRACT TITLE

350 to Bentec AC Drilling Rig

For

DAFORA SA

DOCUMENT TITLE

Commissioning Documentation

Document No.: EU5-MC-PR-01_Rev. 04

04 Converted E IV GW Jan. 09
03 Converted E III GW Oct.02
02 Converted EII GW Aug.08
01 Updated GW GNK Aug.08
00 Issue GW Jul: 08

ISSUE ISSUE OR REVISION BY CHECK APP'D BY DATE APP'D BY DATE


REV. DESCRIPTION BENTEC BENTEC PROJECT CLIENT APPROVAL
ENGINEERING MANAGER
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

Table of Content:

1. Introduction

2. Terminology and Procédures in General

3. Layout Drawing

4. Piping and Instrumentation Diagrams (P&ID's)

5. Responsibilities / nominated personnel

6. Overview of Testing for Main Equipment

7. Mechanical Completion / Commissioning Check Sheets & Acceptance Certificates

8. Commissioning / Testing Time Table

2
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

1. Introduction

The Bentec "350 – t- AC Euro Rig" is a Drilling System designed and engineered to operate
under European conditions. All equipment and materials are in compliance with the current
ISO. DIN, and European standards including the ATEX specification.

The system is designed to be highly mobile; capable of being easily disassembled into truck
package sizes for easy transportation.

The whole package consists of:

- Main Rig Structure Models


- Special Drilling Machinery
- Drilling Instrumentation Package
- Special Drilling Enhanced Equipment
- Power Generation Plant

This comprehensive set of documents will demonstrate "completeness and functionality" of the
assembled and function tested drilling rig.

This document is part of Bentec's overall "Quality Management System".

3
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

2. Terminology and Procedures in General

Factory Acceptance Test (FAT)


The FAT is based on test protocols prepared by the sub-suppliers which might be witnessed
by DAFORA SA. The FAT certificate follows the sub-suppliers standard procedures.
Considering the use of standard drilling equipment – not all sub-suppliers are performing FAT
tests.

Mechanical Completion (MC)


Commissioning activities are based on mechanical completion checks to assure the
completeness of mechanical, electrical and instrumentation installation.
Additionally all required safety systems must be available.
- support structures, platforms, access structures
- safety precautions
- equipment – erection and alignment
- electrical wiring completion
- instrumentation installation completion
- loop check completion
- pressure tests

Cold Commissioning (CC)


Cold commissioning is split in activities first without energizing the equipment and second with
energizing the equipment.
- check of equipment tags and coding (if required)
- check of dimensions, clearness, movements
- check of equipment lubrication
- tests according to sub-suppliers requirements
- rotation testing
- data exchange to the Digital Control System (DCS)
- interlock testing
- functional test as far as possible (mud & high pressure system with water, etc.)

Hot Commissioning (HC)


Hot commissioning is performed under operation conditions as far as possible.
- re-adjustment of mechanical equipment (if necessary)
- adjustment and calibration of instruments and control loops (if necessary)
- vibration-, noise-performance tests under operating conditions as far as possible
- performance checks
- reliability checks
- as-built documentation update

4
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

3. Layout Drawings

• RIG LAYOUT DRILLING RIG : 1-97.98-1035981


• LOAD PLAN : 1-98.03-1039666
• HAZARDOUS ZONE CLASSIFICATION : 1-98.09-1039667

5
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

4. Piping and Instrumentation Diagrams (P&ID's)

• High Pressure Mud System 5000 PSI WP : 1-98.11-1035813


• LP-Mud Flow Scheme : 1-98.11-1035811
• Air Flow Scheme : is being revised
• Hydraulic Flow Scheme Drilling Equipment : is being revised
• Water Flow Scheme : is being revised

6
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

5. Responsibilities / Nominated Personnel

Key personnel for mechanical completion / commissioning and testing

Structural H. Fischer

Mechanical G. Niemeier-Krönke

Mud Systems H. Horstjan

Low & High Pressure Systems H. Horstjan

Electrical C. Klein

Instrumentation C. Klein

Rig Up R. Brüggemann
L. Kalmer
H. Ekelhoff

DAFORA SA can nominate their own responsible commissioning team to follow and
sign off activities as per contract.

7
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

6. Proposal / Test Program for Main Equipment

Please find attached a short list of activities during testing of main equipment (not all
equipment is described in detail)

VFD container FAT at Bentec. Testing and commissioning during rig up


Drawworks FAT at Bentec. Function testing and commissioning during rig-up
HPU Drilling Equipment FAT at manufacturer. Test run during start up of drilling equipment like
cathead, Iron Roughneck and mast raising system.
Cathead Functional test, pull test and commissioning
Rotary table Functional test and commissioning
Utility Winches FAT at manufacturer EMCE
Test run, load test and commissioning during rig up
BOP Lifting Hoists Load test at sub-supplier JDN
Test run without overload during rig up
Rig floor, mast and Functional test and commissioning during rig up
overhead drilling
equipment
Power Generation Plant FAT at manufacturer. Function testing, load testing and commissioning
during rig up period.
Mud pumps FAT at manufacturer. Function testing, load testing and commissioning
during rig-up
Mud System Assembling, function testing and commissioning during rig-up period.
Electric motors Installation, testing and commissioning
Mechanical equipment Installation, testing and commissioning

8
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

7. Mechanical Completion / Commissioning Check Sheets & Acceptance


Certificates

This chapter includes the different MCC-check sheets for the main equipment. Also the
acceptance certificates which have to be signed off by DAFORA SA. and Bentec are included.
Therefore DAFORA SA has not to sign off each individual activity shown in MCC-check
sheets.

The following MCC-check sheets are attached:

No. Section Description


1000 Main Rig Structure
01 1001 A Rig Structure
02. 1000,10001N Derrick and Substructure
03 1001 Mast Telescoping System
04 1111 Casing Stabbing Board
05. 1001 Mast Telescoping System
06 1001 I BOP Frame 13-5/8”
2000 Drilling Equipment installed in section 1000
07. 2001 Draw Works
08. 2002 Rotary Table
09. 2003 Traveling Block
10. 2004-A Drill Line Reel
11. 2005 Hydraulic Power Unit
12 2006 Top Drive System
13 2007 Spin Torue
14. 2008 Drill Floor Winch A
15. 2008 Drill Floor Winch B
16 2008 A Man Riding Winch
17 2009 Hydraulic Cathead
18. 2010 Monkey Board Air Hoist
19 2010 A Wireline Unit
20. 2011 Dead Line Anchor
21. 2012 Mast Telescoping Winch A
22 2013 Catwalk Winch
23. 2012 Mast Telescoping Winch B
24 2015 BOP Air Hoist A
25 2015 BOP Air Hoist B
26. 2016 Crown Block
3000 Power Equipment
27 3001 Main Generator Plant
28 3001 A Emergency Generator Set
29 3002-A Grass Hopper system
30 3003-5 Air Compressor System
4000 Mud System
31 4000 Mud Tank System
32 4001-A Emergency Shower

9
350 to Bentec AC Drilling Rig

Document No.: EU5-MC-PR-01_Rev.04


Project No. B-05272 / 900663 Rev. No. 04
Client DAFORA SA Date 07-01-2009
Fil Name
File N Commissioning Documentation D&S Originator GW

33 4003 Mud Agitators


34 4004 Desander Pump
35 4004 Desilter Pump
36 4004 Mixing Pumps 1 & 2
37 4004 Triptank Pump
38 4005 Mud Charging Pumps
39 4008 Shale Shaker Package
40 4011 Mud Gas Separator
41 4012 Vacuum Degasser

42 5002 Fuel Storage / Distribution System

43 9001 Triplex Mud Pumps

44 9002 High Pressure Mud System

10
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Derrick and Substructure

Discipline Electrical Mechanical Structural Piping No. 1000,1001A-N


SCOPE OF ACCEPTANCE

Operation and System of Derrick and Substructure (inkl. Accessories)

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Mast equipment


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP frames for 13-5/8" and / or 21-1/4" BOP

Discipline Electrical Mechanical Structural Piping No. 1001 I / 17003


SCOPE OF ACCEPTANCE

Operation and System of BOP storing frames

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of the BOP storing frames, equipment and operation
has been carried out
2.) Function test has been witnessed by: Darfora
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping System

Discipline Electrical Mechanical Structural Piping No. 1001


SCOPE OF ACCEPTANCE

Operation and System of Mast Telescoping System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Mast Erection System equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Rig Structure

Discipline Electrical Mechanical Structural Piping No. 1001 A


SCOPE OF ACCEPTANCE

Operation and System of Rig Structure (inkl. Accessories)

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of Rig Structure modules


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Casing Stabbing Board

Discipline Electrical Mechanical Structural Piping No. 1111


SCOPE OF ACCEPTANCE

Operation and System of Casing Stabbing Board

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of the installed Casing Stabbing Board, equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORE
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drawworks

Discipline Electrical Mechanical Structural Piping No. 2001


SCOPE OF ACCEPTANCE

Operation and System of Drawworks

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Drawworks equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Rotary Table

Discipline Electrical Mechanical Structural Piping No. 2002


SCOPE OF ACCEPTANCE

Operation and System of Rotary Table

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Rotary Table equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Traveling Block

Discipline Electrical Mechanical Structural Piping No. 2003


SCOPE OF ACCEPTANCE

Operation and System of Traveling Block

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Traveling Block equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drill Line Reel

Discipline Electrical Mechanical Structural Piping No. 2004A


SCOPE OF ACCEPTANCE

Operation and System of Drill Line Reel

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Drill Line Reel equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Hydraulic Power Unit

Discipline Electrical Mechanical Structural Piping No. 2005


SCOPE OF ACCEPTANCE

Operation and System of Hydraulic Power Unit

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed HPU "Drilling Equipment" equipment and operation has
been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Top Drive

Discipline Electrical Mechanical Structural Piping No. 2006


SCOPE OF ACCEPTANCE

Operation and System of Top Drive

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Top Drive equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Spin Torque

Discipline Electrical Mechanical Structural Piping No. 2007


SCOPE OF ACCEPTANCE

Operation and System of Spin Torque

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Iron Roughneck equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drillfloor Winch No.1

Discipline Electrical Mechanical Structural Piping No. 2008


SCOPE OF ACCEPTANCE

Operation and System of Drillfloor Winch No.1

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of the Drill Floor Winch No.1, equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora sa


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Drillfloor Winch No.2

Discipline Electrical Mechanical Structural Piping No. 2008


SCOPE OF ACCEPTANCE

Operation and System of Drillfloor Winch No.2

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all the Drill Floor Winch No.2, equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Manriding Winch

Discipline Electrical Mechanical Structural Piping No. 2008A


SCOPE OF ACCEPTANCE

Operation and System of Manriding Winch

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Manriding Winch equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Cathead

Discipline Electrical Mechanical Structural Piping No. 2009


SCOPE OF ACCEPTANCE

Operation and System of Cathead Serial No. 022

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Cathead equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Derrickman Hoist

Discipline Electrical Mechanical Structural Piping No. 2010


SCOPE OF ACCEPTANCE

Operation and System of Derrickman Hoist

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of the Derrickman Hoist, equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Wireline Unit

Discipline Electrical Mechanical Structural Piping No. 2010-A


SCOPE OF ACCEPTANCE

Operation and System of Wireline Unit.

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Wire Line Unit equipment and operation has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Dead Line Anchor

Discipline Electrical Mechanical Structural Piping No. 2011


SCOPE OF ACCEPTANCE

Operation and System of Dead Line Anchor.

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Dead Line Anchor equipment has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping Winch

Discipline Electrical Mechanical Structural Piping No. 2012


SCOPE OF ACCEPTANCE

Operation and System of Mast Telescoping Winch A

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Mast Telescoping Winch A equipment has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mast Telescoping Winch

Discipline Electrical Mechanical Structural Piping No. 2012


SCOPE OF ACCEPTANCE

Operation and System of Mast Telescoping Winch B

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Mast Telescoping Winch B equipment has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Catwalk Winch

Discipline Electrical Mechanical Structural Piping No. 2013


SCOPE OF ACCEPTANCE

Operation and System of Catwalk Winch

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Catwalk Winch equipment and operation has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP Hoist

Discipline Electrical Mechanical Structural Piping No. 2015


SCOPE OF ACCEPTANCE

Operation and System of BOP hoist A

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed BOP hoist equipment and operation has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: BOP Hoist

Discipline Electrical Mechanical Structural Piping No. 2015


SCOPE OF ACCEPTANCE

Operation and System of BOP hoist B

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed BOP hoist equipment and operation has been carried out

2.) Function test has been witnessed by: DARFORA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets

Discipline Electrical Mechanical Structural Piping No. 3001


SCOPE OF ACCEPTANCE

Operation and System of Main Generator Sets #1 - #3

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets

Discipline Electrical Mechanical Structural Piping No. 3001


SCOPE OF ACCEPTANCE

Operation and System of Main Generator Set No.2

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Main Generator Sets

Discipline Electrical Mechanical Structural Piping No. 3001


SCOPE OF ACCEPTANCE

Operation and System of Main Generator Set No.3

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Main Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: DARFORA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Emergency Generator

Discipline Electrical Mechanical Structural Piping No. 3001A


SCOPE OF ACCEPTANCE

Operation and System of Emergency Generator

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Emergency Generator Set equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Air Compressor System

Discipline Electrical Mechanical Structural Piping No. 3003,3004,3005


SCOPE OF ACCEPTANCE

Operation and System of Air Compressor System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Air Compressor equipment and operation has been carried out

2.) Function test has been witnessed by: DAFOR A SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Air Compressor System

Discipline Electrical Mechanical Structural Piping No. 3003,3004,3005


SCOPE OF ACCEPTANCE

Operation and System of Air Compressor No.2

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Air Compressor equipment and operation has been carried out

2.) Function test has been witnessed by: DAFOR A SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mud Tank System

Discipline Electrical Mechanical Structural Piping No. 4000


SCOPE OF ACCEPTANCE

Operation and System of Mud Tank System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Tank System equipment


has been carried out
2.) Function test has been witnessed by: Dafors SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Emergency Shower

Discipline Electrical Mechanical Structural Piping No. 4001E


SCOPE OF ACCEPTANCE

Operation and System of Emergency Shower

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed BOP Lifting Hoist equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.1 Degasser tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.10: Reserve tank No.1

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.11: Reserve tank No.1

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.12: Reserve tank No.2

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.13: Reserve tank No.2

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.2 Desilter tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.3 Desilter tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.4 Suction tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.5 Suction tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.6 Mix tank 2

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.7 Mix tank 1

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.8 Intermediate tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Agitators

Discipline Electrical Mechanical Structural Piping No. 4003


SCOPE OF ACCEPTANCE

Operation and System of Agitators

As per attached: Completion & Commissioning Records


COMMENTS No.9 Intermediate tank

1.) Successful testing of all installed Agitator equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump B

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORS SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump C

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORS SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Charging pump A

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafors SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Desander pump

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Desilter pump

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Mix pump A

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Mix pump B

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: LP Centrifugal Pumps

Discipline Electrical Mechanical Structural Piping No. 4004


SCOPE OF ACCEPTANCE

Operation and System of LP Centrifugal Pumps: Charge Pump A & B, Mix Pump A & B,
Desander & Desilter Pump, Triptank Pump
As per attached: Completion & Commissioning Records
COMMENTS Triptank pump

1.) Successful testing of all installed LP Centrifugal Pump equipment and operation
has been carried out
2.) Function test has been witnessed by: Jardboranir
Dafors SA

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package

Discipline Electrical Mechanical Structural Piping No. 4008


SCOPE OF ACCEPTANCE

Operation and System of Shale Shaker Package (incl. Mud Cleaner)

As per attached: Completion & Commissioning Records


COMMENTS Mud cleaner

1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package

Discipline Electrical Mechanical Structural Piping No. 4008


SCOPE OF ACCEPTANCE

Operation and System of Shale Shaker Package (incl. Mud Cleaner)

As per attached: Completion & Commissioning Records


COMMENTS Shale shaker No.1

1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora sa
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Shale Shaker Package

Discipline Electrical Mechanical Structural Piping No. 4008


SCOPE OF ACCEPTANCE

Operation and System of Shale Shaker Package (incl. Mud Cleaner)

As per attached: Completion & Commissioning Records


COMMENTS Shale shaker No.2

1.) Successful testing of all installed Shale Shaker Package equipment and operation
has been carried out
2.) Function test has been witnessed by: Dafora sa
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Mud Gas Separator

Discipline Electrical Mechanical Structural Piping No. 4011


SCOPE OF ACCEPTANCE

Operation and System Mud Gas Separator

As per attached: Completion & Commissioning Records


COMMENT. Mud Gas Separator

1.) Successful testing of all installed Degasser equipment and operation


has been carried out
2.) Function test has been witnessed by: Darfora
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Degasser

Discipline Electrical Mechanical Structural Piping No. 4012


SCOPE OF ACCEPTANCE

Operation and System of Degasser

As per attached: Completion & Commissioning Records


COMMENTS Rotary degasser

1.) Successful testing of all installed Degasser equipment and operation


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: Fuel Distribution System

Discipline Electrical Mechanical Structural Piping No. 5002A


SCOPE OF ACCEPTANCE

Operation and System of Fuel Distribution System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed BOP Lifting Hoist equipment and operation
has been carried out
2.) Function test has been witnessed by: Darfora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DARFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps

Discipline Electrical Mechanical Structural Piping No. 9001


SCOPE OF ACCEPTANCE

Operation and System of Mud Pump No.1

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps

Discipline Electrical Mechanical Structural Piping No. 9001


SCOPE OF ACCEPTANCE

Operation and System of Mud Pump No.2

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud Pumps

Discipline Electrical Mechanical Structural Piping No. 9001


SCOPE OF ACCEPTANCE

Operation and System of Mud Pump No.3

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed HP Mud Pump equipment and operation has been carried out

2.) Function test has been witnessed by: Dafora SA


Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date
TRIAL RUN AND PERFORMANCE TESTING
EQUIPMENT / SYSTEM ACCEPTANCE CERTIFICATE
SYSTEM: High Pressure Mud System

Discipline Electrical Mechanical Structural Piping No. 9002


SCOPE OF ACCEPTANCE

Operation and testing of High Pressure Mud System

As per attached: Completion & Commissioning Records


COMMENTS:

1.) Successful testing of all installed Piping System equipment


has been carried out
2.) Function test has been witnessed by: Dafora SA
Bentec

Punch List Items:

A-Items:

B-Items:

It is hereby certified that the equipment / system has been inspected, tested and accepted in
accordance with the attached records and other documents, but with the exception of outstanding
work detailed within the attached punch lists.
BENTEC DAFORA SA THIRD PARTY
(if applicable)

Name

Sign
Date

You might also like