8.2.1. Monthly Report
8.2.1. Monthly Report
8.2.1. Monthly Report
Provision of Engineering
Services for Pangkah
Development
Author's Organization Validation
-
PT. Depriwangga Expired Date
Engineering -
Monthly Report
Sep-15
Approval Sheet
Name Title Date Signature
- Project Lead
- Engineering Lead
- Project Control
PT. Depriwangga
Rev Issue Date Engineering Issue Purpose Owner Signature
By Chk App
TABLE OF CONTENT
1. EXECUTIVE SUMMARY
2. MANAGEMENT SUMMARY
6. LOCAL CONTENT
Project Title Document Number
Provision of Engineering
Services for Pangkah
Development
Author's Organization Validation
-
PT. Depriwangga Engineering Expired Date
-
1. Executive Summary
Activity had been done in this month period :
- Site survey for Shutdown Panel Facilities 12 -18 September 2015
- Issued Rev. 1 RFQ for ESD Panel Facilities
- Issued Rev. 0 TBE
- Issued some drawings for Instrument
- PDMS Model Review
- Process Study in issued
2. Management Summary
2.1 GENERAL
- -
2.2 DETAIL DESIGN AND PROCUREMENT SUPPORT for LONG LEAD ITEMS
- -
- -
2.3 PIPING
- -
- -
- -
2.4 INSTRUMENTATION
- -
- -
- -
2.5 PDMS
- -
2.6 DEBOTLENECKING STUDY AT FACILITIES
- Issued Rev B Process Study
Project Title Document Number
Provision of Engineering
Services for Pangkah
Development
Author's Organization Validation
-
PT. Depriwangga Expired Date
Engineering -
5. Recovery Plan
- Conduct PDMS Review regularly to finalize model
7. Local Content
- NTR (this project is 100% local content no expatriate involvement)
Project Title Document Number
Provision of Engineering
Services for Pangkah
Development
Author's Organization Validation
-
PT. Depriwangga Expired Date
Engineering -
ATTACHMENT 1
Progress Table, MDR and S- curves
Provision of Engineering Services for Pangkah Development
MONTHLY PROGRESS REPORT
COD : -
1 GENERAL 2.16% 100.00% 100.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 0.00%
3 PIPING 9.74% 93.64% 93.64% 0.00% 6.36% 6.36% 0.00% 100.00% 100.00% 0.00%
4 INSTRUMENT 25.04% 100.00% 94.95% -5.05% 0.00% 0.50% 0.50% 100.00% 95.45% -4.55%
5 PDMS 38.12% 94.75% 47.38% -47.38% 2.62% 33.16% 30.54% 97.38% 80.54% -16.84%
6 DEBOTLENECKING STUDY AT BRAVO 5.71% 100.00% 15.00% -85.00% 0.00% 35.00% 35.00% 100.00% 50.00% -50.00%
Overall 100.00% 97.23% 72.70% -24.53% 1.77% 15.88% 14.11% 99.00% 88.58% -10.41%
P
IDR/IFD
IFB/AFC/AFP/IFP A
(Internal Discipline Review/ IFR IFA
WEIGHT FACTOR
Start/Draft Prepared (Approve for Construction/Approve for PHYSICAL PROGRESS Y
Issued for Design)/ (Issued for Review) (Issued for Approval)
Purchase/Issued for Purchase) M
Draft Completed
Doc./Dwg. Number EEngineering Client Approval
REVISION
O
Deliverables EACH DELIVERABLE OVERALL
V
0% 15% 50% 85% 100%
ACTUAL PLAN VAR ACTUAL PLAN VAR
T
Plan Actual Plan Actual Plan Actual Return Plan Actual Return Plan Actual Return LAST THIS Mo TODATE TODATE TODATE TODATE TODATE TODATE
DETAIL DESIGN AND PROCUREMENT SUPPORT for LONG LEAD ITEMS 19.24%
PIPELINE
DATA SHEET
Document Number Document Name 2 0.94% 11-Jun-12 11-Jun-12 19-Jun-12 19-Jun-12 29-Jun-12 100% 0% 100% 100% 0% 0.94% 0.94% 0.00%
MTO
Document Number Document Name 2 0.94% 11-Jun-12 11-Jun-12 19-Jun-12 19-Jun-12 29-Jun-12 100% 0% 100% 100% 0% 0.94% 0.94% 0.00%
RFQ
Document Number Document Name 0 1.89% 11-Jun-12 11-Jun-12 25-Jun-12 25-Jun-12 100% 0% 100% 100% 0% 1.89% 1.89% 0.00%
MECHANICAL
SPECIFICATION, DATA SHEET AND RFQ
Document Name 2 5.70% 1-Jun-12 1-Jun-12 4-Jun-12 4-Jun-12 11-Jun-12 100% 0% 100% 100% 0% 5.70% 5.70% 0.00%
TBE
Document Number Document Name 0 3.56% 2-Aug-12 28-Aug-12 16-Aug-12 29-Aug-12 3-Sep-12 100% 0% 100% 100% 0% 3.56% 3.56% 0.00%
VENDOR CLARIFICATION
Document Name 1.42% 2-Aug-12 28-Aug-12 16-Aug-12 29-Aug-12 100% 0% 100% 100% 0% 1.42% 1.42% 0.00%
STRUCTURE
MTO
Document Number Document Name 2 0.94% 8-Jun-12 8-Jun-12 15-Jun-12 15-Jun-12 26-Jun-12 100% 0% 100% 100% 0% 0.94% 0.94% 0.00%
Document Number Document Name 2 0.94% 8-Jun-12 8-Jun-12 15-Jun-12 15-Jun-12 26-Jun-12 100% 0% 100% 100% 0% 0.94% 0.94% 0.00%
RFQ
Document Number Document Name A 0.94% 15-Jun-12 15-Jun-12 22-Jun-12 22-Jun-12 26-Jun-12 100% 0% 100% 100% 0% 0.94% 0.94% 0.00%
Document Number Document Name 1 0.94% 25-Jun-12 25-Jun-12 2-Jul-12 22-Jul-12 9-Jul-12 100% 0% 100% 100% 0% 0.94% 0.94% 0.00%
INSTRUMENT
Document Number Document Name 1 0.50% 6-Aug-12 6-Aug-12 7-Aug-12 7-Aug-12 8-Aug-12 8-Aug-12 3-Sep-12 22-Aug-12 11-Sep-12 5-Sep-12 26-Sep-12 50% 50% 100% 100% 0% 0.50% 0.50% 0.00%
Document Number Document Name 1 0.50% 6-Aug-12 6-Aug-12 7-Aug-12 7-Aug-12 8-Aug-12 8-Aug-12 3-Sep-12 22-Aug-12 11-Sep-12 5-Sep-12 26-Sep-12 50% 50% 100% 100% 0% 0.50% 0.50% 0.00%
PIPING 9.74%
SURVEY
Document Number Document Name 0 0.62% 15-Sep-12 12-Sep-12 24-Sep-12 24-Sep-12 0% 100% 100% 100% 0% 0.62% 0.62% 0.00%
DATA SHEET
Document Number Document Name 2 1.18% 27-Jan-12 29-Feb-12 3-Feb-12 17-Feb-12 22-Feb-12 100% 0% 100% 100% 0% 1.18% 1.18% 0.00%
Document Number Document Name 1 1.18% 29-Feb-12 27-Jan-12 7-Mar-12 7-Mar-12 15-Mar-12 100% 0% 100% 100% 0% 1.18% 1.18% 0.00%
CALCULATION
Document Number Document Name 1 3.40% 4-May-12 4-May-12 11-May-12 11-May-12 14-May-12 100% 0% 100% 100% 0% 3.40% 3.40% 0.00%
LIST
Document Number Tie-In List 1 0.52% 21-Mar-12 21-Mar-12 28-Mar-12 28-Mar-12 10-Apr-12 100% 0% 100% 100% 0% 0.52% 0.52% 0.00%
DRAWING
Document Number Document Name 1 1.24% 11-Jul-12 11-Jul-12 18-Jul-12 18-Jul-12 25-Jul-12 100% 0% 100% 100% 0% 1.24% 1.24% 0.00%
Document Number Document Name 2 0.00% 18-Sep-12 18-Sep-12 19-Sep-12 24-Sep-12 0% 100% 100% 100% 0% 0.00% 0.00% 0.00%
Document Number Document Name 2 0.00% 18-Sep-12 18-Sep-12 19-Sep-12 24-Sep-12 0% 100% 100% 100% 0% 0.00% 0.00% 0.00%
MTO
Document Number Document Name 2 0.60% 7-Mar-12 7-Mar-12 14-Mar-12 14-Mar-12 27-Mar-12 100% 0% 100% 100% 0% 0.60% 0.60% 0.00%
Document Number Document Name 1 1.00% 28-May-12 28-May-12 4-Jun-12 4-Jun-12 11-Jun-12 100% 0% 100% 100% 0% 1.00% 1.00% 0.00%
INSTRUMENTATION 25.04%
SPECIFICATION
Document Number Document Name 4 0.74% 27-Feb-12 27-Feb-12 5-Mar-12 11-May-12 22-May-12 100% 0% 100% 100% 0% 0.74% 0.74% 0.00%
Document Number Document Name 1 1.14% 18-Jun-12 18-Jun-12 22-Jun-12 22-Jun-12 25-Jun-12 25-Jun-12 9-Jul-12 12-Jul-12 12-Jul-12 2-Aug-12 26-Jul-12 6-Aug-12 6-Sep-12 100% 0% 100% 100% 0% 1.14% 1.14% 0.00%
DATA SHEET
Document Number Document Name 1 0.84% 25-Jun-12 25-Jun-12 29-Jun-12 29-Jun-12 2-Jul-12 2-Jul-12 2-Aug-12 16-Jul-12 9-Aug-12 6-Sep-12 26-Jul-12 6-Sep-12 6-Sep-12 85% 15% 100% 100% 0% 0.84% 0.84% 0.00%
DRAWING
Document Number Document Name 1 2.42% 23-Mar-12 23-Mar-12 26-Mar-12 26-Mar-12 30-Mar-12 30-Mar-12 5-Apr-12 5-Apr-12 10-Apr-12 10-Apr-12 100% 0% 100% 100% 0% 2.42% 2.42% 0.00%
Document Number Document Name 1 2.81% 20-Mar-12 30-May-12 23-Mar-12 2-Jun-12 27-Mar-12 19-Jun-12 5-Jul-12 5-Jul-12 18-Jul-12 19-Jul-12 8-Aug-12 100% 0% 100% 100% 0% 2.81% 2.81% 0.00%
Document Number Document Name 1 1.74% 20-Mar-12 30-May-12 23-Mar-12 2-Jun-12 27-Mar-12 25-Jun-12 12-Jul-12 12-Jul-12 18-Jul-12 26-Jul-12 8-Aug-12 100% 0% 100% 100% 0% 1.74% 1.74% 0.00%
Document Number Document Name 0 3.51% 26-Jun-12 30-May-12 29-Jun-12 2-Jun-12 3-Jul-12 3-Jul-12 12-Jul-12 17-Jul-12 8-Aug-12 31-Jul-12 85% 0% 85% 100% -15% 2.98% 3.51% -0.53%
Document Number Document Name 1 1.84% 14-May-12 14-May-12 17-May-12 17-May-12 21-May-12 21-May-12 12-Jul-12 12-Jul-12 18-Jul-12 26-Jul-12 8-Aug-12 100% 0% 100% 100% 0% 1.84% 1.84% 0.00%
Document Number Document Name 1 2.81% 3-May-12 3-May-12 6-May-12 6-May-12 10-May-12 19-Jun-12 29-Jun-12 5-Jul-12 5-Jul-12 18-Jul-12 19-Jul-12 8-Aug-12 100% 0% 100% 100% 0% 2.81% 2.81% 0.00%
Document Number Document Name 0 4.09% 14-May-12 14-May-12 17-May-12 17-May-12 21-May-12 3-Jul-12 12-Jul-12 4-Jun-12 8-Aug-12 18-Jun-12 85% 0% 85% 100% -15% 3.47% 4.09% -0.61%
Document Number Document Name 2 1.55% 3-May-12 3-May-12 6-May-12 6-May-12 10-May-12 10-May-12 24-May-12 19-Jun-12 29-Jun-12 5-Jul-12 8-Aug-12 100% 0% 100% 100% 0% 1.55% 1.55% 0.00%
Document Number Document Name 1 1.55% 12-Jun-12 12-Jun-12 15-Jun-12 15-Jun-12 19-Jun-12 19-Jun-12 3-Jul-12 5-Jul-12 18-Jul-12 17-Jul-12 8-Aug-12 100% 0% 100% 100% 0% 1.55% 1.55% 0.00%
PDMS 38.12%
3D Model
Document Name B 16.00% 13-Jun-12 13-Jun-12 27-Jun-12 27-Jun-12 18-Jul-12 6-Sep-12 8-Aug-12 50% 35% 85% 100% -15% 13.60% 16.00% -2.40%
Document Name B 4.36% 13-Jun-12 13-Jun-12 27-Jun-12 27-Jun-12 18-Jul-12 6-Sep-12 8-Aug-12 50% 35% 85% 100% -15% 3.70% 4.36% -0.65%
Document Name B 1.64% 13-Jun-12 13-Jun-12 27-Jun-12 27-Jun-12 18-Jul-12 6-Sep-12 8-Aug-12 50% 35% 85% 100% -15% 1.39% 1.64% -0.25%
Document Name B 5.65% 13-Jun-12 13-Jun-12 27-Jun-12 27-Jun-12 18-Jul-12 6-Sep-12 8-Aug-12 50% 35% 85% 100% -15% 4.80% 5.65% -0.85%
Document Name B 8.47% 13-Jun-12 13-Jun-12 27-Jun-12 27-Jun-12 18-Jul-12 6-Sep-12 8-Aug-12 50% 35% 85% 100% -15% 7.20% 8.47% -1.27%
Document Number Document Name 2.00% 3-Sep-12 6-Sep-12 11-Sep-12 2-Oct-12 23-Oct-12 0% 0% 0% 50% -50% 0.00% 1.00% -1.00%
DEBOTLENECKING STUDY AT BRAVO 5.71%
PROCESS STUDY
Document Number Document Name B 5.71% 16-Jul-12 1-Jul-12 23-Jul-12 23-Jul-12 30-Jul-12 19-Sep-12 13-Aug-12 27-Aug-12 15% 35% 50% 100% -50% 2.85% 5.71% -2.85%
PROCESS DRAWING
Document Number Document Name 0.00% 16-Jul-12 1-Jul-12 23-Jul-12 23-Jul-12 30-Jul-12 13-Aug-12 27-Aug-12 14-Sep-12 15% 85% 100% 100% 0% 0.00% 0.00% 0.00%
Document Number Document Name 0.00% 16-Jul-12 1-Jul-12 23-Jul-12 23-Jul-12 30-Jul-12 13-Aug-12 27-Aug-12 14-Sep-12 15% 85% 100% 100% 0% 0.00% 0.00% 0.00%
OVERALL PROJECT 72.70% 15.88% 88.58% 99.00% -10.41% 88.58% 99.00% -10.41%
100%
90%
80%
70%
Progress (%)
60%
50%
40%
30%
20%
10%
0%
25-May 29-Jun 27-Jul 31-Aug 28-Sep 26-Oct 30-Nov 28-Dec
0 1 2 3 4 5 6 7
DESCRIPTION
25-May 29-Jun 27-Jul 31-Aug 28-Sep 26-Oct 30-Nov 28-Dec
PLAN CUMMULATIVE (REV. 0) 0.00% 55.57% 80.60% 97.23% 99.00% 100.00% 100.00% 100.00%
8/16/2015
Project Title Document Number
Provision of Engineering
Services for Pangkah
Development
Author's Organization Validation
-
PT. Depriwangga Expired Date
Engineering -
ATTACHMENT 2
Manpower Loading Chart
PT. Depriwangga Engineering
MANPOWER LOADING
PROJECT : Provision of Engineering Services for Pangkah Development
CLIENT : SAHA INDONESIA PANGKAH LIMITED
JOB No. :-
REVISION :0
Project Manager Project Control Document Control PR Lead/Senior PR Eng PR Designer PR Drafter CS Lead/Senior CS Eng
5
Manpower
0
Plan Actual Plan Actual Plan Actual Plan Actual Plan Actual
S Curve Plan 15.7% 24.5% 36.2% 41.0% 60.5% 62.3% 84.8% 83.6% 100.0%