7. Is combinations of ramps and grade separations designed as a system of interconnecting
roadways to separate the turning and through movements at the junction of two or more
roads.
A. Grade separated intersection
B. At-grade intersection
C. Channelization
D. Interchange
8. A project closeout does not constitute
A. Project planning
B. Contract closeout
C. Project Acceptance
D. Project completion
9. While designing a retaining wall, what remedial measure do you consider if the factor of
safety against sliding falls down below the requirement?
A. Increase the height of the wall.
B. Decrease the height of the wall.
C. Decrease the base width of the wall.
D. Increase the base width of the wall.
10. Minimum concrete cover is provided in RC members to provide except
A. Increased bond strength
B. Increased durability such as protecting the reinforcement from corrosion
C. Increased fire resistance
D. Increased flexural strength
11. One of the following is used for the computation of the volume of earthwork in a road
project.
A. Triangular formula
B. Spherical formula
C. Prismoidal formula
D. Simpson's 5/8 formula
Email – mulukenabel@gmail.com
Prepared by Abel Muluken Phone 0948552002
YouTube Channel - Engineering Solution by Abel M.
12. An effective and efficient procurement method ensures the following rights, except
A. The Right Quality
B. The Right Quantity
C. The Right profit
D. The Right Counterpart
13. The following is NOT considered as the main sources of dampness in buildings during
service
A. Water used for concrete curing
B. Moisture rising up the walls from the ground
C. Rain travel from wall tops
D. Rain Beating Against External Walls
14. One of the following is NOT an environmental issue related to soil boring during site
investigation.
A. Pneumatic caissons are less health hazard than other types of caissons
B. Construction of sheet pile walls can affect aquatic life
C. Deep excavation can cause damage on nearby buildings
D. A collapse of struts in cofferdams can cause life lose
15. One of the following tasks is NOT covered in quantity surveying
A. Preparation of approximate (preliminary) cost estimate at the very early stage
of the project
B. Preparation of Specification
C. Taking measurements of civil works
D. Preparation of construction drawing
16. There is a plan to construct a high-rise building on cast-in-situ pile foundation with about
50 m length. Geotechnical site investigation at the site dictates that ground water is located
at shallower depth and the top 10 m layer of the site is sand soil followed by clayey sand.
Using these data, which of the following is NOT true?
A. As the piles are cast-in-situ piles, the quality of construction of the piles can be reduced.
B. Use of casings during the construction of the piles is a must.
C. Caution must be made while pouring the concrete as concrete segregation can happen.
D. As there will be flow of water to the bore hole, it is a good idea to reduce the water
cement ratio during the concrete production.