Class-Notes 5 Tutorial Ms-Project
Class-Notes 5 Tutorial Ms-Project
MS Project Tutorial
MS Project in Labs:
Available in Siegal Hall Lab in Main Campus Prepared by
Available in Room 210 Rice Campus Milton Hurtado
How to get MS Project ?
6. To add a milestone the only difference is that the duration of the activity must be zero (below is an
example):
Note: By double clicking on a Task or milestone, you can modify its information with a form that prompts
Grouping Tasks in Logical Order (WBS Outline)
Outlining helps organize your tasks into more manageable chunks. You can indent related tasks under a more
general task, creating a hierarchy. The general tasks are called summary tasks; the indented tasks below the
summary task are subtasks. A summary task's start and finish dates are determined by the start and finish dates
of its earliest and latest subtasks.
1. Click once on the first activity of the group of activities you want to group. For the example Activities 4
and 5
2. Then click on the option “New Task” in the “Insert” Menu to insert a new task that will represent the
name of the group (“Group 1” for this example)
3. Then select the tasks below (4 and 5) and then click in the option “Outline-Indent” in the “Project”
Menu
Creating Relationships Between Tasks
A network of tasks in a project must be connecting activities from the start to the end, to establish these relationship
we need to use the field “Predecessors” of each task, where we can designate which activity will be preceding the one
we are updating, in the example below we will indicate MS project that “Activity 5” can start once “Activity 4” is
completed (Finish to Start relationship).
Notice that by establishing the relationship now the Group 1 takes 2 days to be completed, because before, the
activities were set to be performed in parallel, and now they are in series (Finish to Start relationship)
Note: MS project will calculate dates based on the durations of the tasks, their relationships and the start date
set for the project, however it is possible to change the starting date of a task (if necessary) By double clicking
on a Task or milestone, and using the fields related to the dates (Start or Finish)
Assigning Resources to Tasks
You can use the Resource Sheet in Microsoft Project to create a list of the people, equipment, and material resources
that make up your team and carry out the project tasks. Your resource list will consist of work resources or material
resources. Work resources are people or equipment; material resources are consumable materials or supplies, such as
concrete, wood, or nails.
6. Once the resources are created, you can go back to the View menu, and click Gantt Chart to see again
the tasks, and then when you double click a task you can add a resource to this task by using the tab
“Resources”
Note: The main goal of the resource assignment is to allocate properly the resources and to provide valuable
information regarding the effort of the team.
Find Critical Path
Critical Path Analysis (CPA) helps you to lay out all tasks that
must be completed as part of a project.
CPA helps you to identify the minimum length of time needed to
complete a project
For finding CP list all the activities and enter early start, late
start, early finish and late finish info of all the activities.
You can do this under insert/columns and selecting each terms.
Following screen shot demonstrates how to insert.
Project automatically calculates ES, EF, LS and LF based on the
starting/ending dates you have provided.
Slack Time For Scheduling
For viewing the schedule showing the slack go to Views Æ More views Æ
Detailed Gantt view Æ Apply.
In this click on View Æ Table Æ Schedule
Slack appears as thin bars to the right of a task, with slack values adjoining the
regular Gantt bars
You can also view the free slack and total slack of a task in the sheet.
You can move the activity within the available slack time, to balance the
resources, in the cases where over allocation is present.
Closing Project
When you are saving a file it asks you whether you want to
save with baseline/without baseline. You can choose either
options.
If you choose to save with baseline, a copy of your schedule
and other things will be saved and any changes when you are
making when the project progress can be viewed clearly using
the baseline.
If you choose to save without baseline, you will not be able to
view the changes.
Step by Step Example
Now lets try a small example, step by step to practice each of the options we have seen so far about how to create a
project using MS Project. We are going to use a small set of tasks (Table Below) related to the initial phases of a
System Testing Plan (Definition and Design)
2.1
2.2
Step by Step Example (Step 2 – Add Tasks)
1. Write the name of each task in the spreadsheet using the column “Task Name”
2. Write the duration in days of each task in the spreadsheet using the column “Duration”
3. Group the tasks by the Phase according to the table of tasks shown before, and add a group that encloses the
phases named “System Testing Plan MCY-ADTT-ST-2002-01” this will represent the plan as a whole
4. Write the predecessors of each task in the spreadsheet using the column “Predecessors” (If you can’t see the
column, try to expand the vertical bar that divides the spreadsheet to the Gantt Chart)
5. To convert a Task in a Milestone, just double click the Task and go to the tab “Advanced” then check the box that
says “Mark Task as a Milestone”
2
Step by Step Example (Step 2 – Add Tasks Continued)
3.1
Insert a new task at the beginning that will group everything 3.3
Click on the option “Outline - Indent”
3.4
3.2
Highlight the tasks that are going to be added as subtasks The final result should look like this, now repeat this
steps to create the Subgroups that will represent the
phases (Definition and Design)
Step by Step Example (Step 2 – Add Tasks Continued)
3.5
Insert a new task at the beginning of the definition tasks 3.7
Click on the option “Outline - Indent”
3.6
3.8
Highlight the tasks that are going to be added as subtasks
The final result should look like this, now repeat this
steps to create the Subgroup that will represent the
phase “Design”
Step by Step Example (Step 2 – Add Tasks Continued)
3.9
Insert a new task at the beginning of the Design tasks
(Notice that the new task that will work as a group for the
“Design Phase” is inside the group “Definition Phase”,
therefore we need to Outdent one position to put it at
the same level as the Definition Phase)
3.11
3.10
Click on the option “Outline-Outdent” to move the
activity to the left
3.12
The final result should look like this
Step by Step Example (Step 2 – Add Tasks Continued)
4
Step by Step Example (Step 2 – Add Tasks Continued)
5
Step by Step Example (Step 3 – Add Resources)
2
1
3
Step by Step Example (Step 4 – Assign Resources)
1. Double click the task you want to link to resources available in the “Resource Sheet”
2. Then got to the Tab “Resources” and look up the resources you want to relate to the activity (For the example
lets keep the amount of effort of each Resources as 100%, Leveling Resources wont be covered in this tutorial),
finally Click the “Ok” button to finish the assignment.
3. Repeat steps 1 and 2 for the rest of the tasks
1 2
Step by Step Example (Step 5 – Adjust the Gantt Chart)
1. Adjust the length of the Gantt Chart such that it can be seen in one screen (If Possible), to do this perform a Right
Click on top of the Gantt Chart first, a pop-up menu will appear, select the option “Networking Time…”
2. In the form that will open go to the tab “Time Scale” and Change the Major Scale Units to “Months” and the
Minor Scale Units to “Weeks”, then press the “Ok” button to see the results in the Gantt Chart. (Adjust as
necessary the scales once you are familiar with them)
2
Step by Step Example (Step 6 – View the Critical Path)
1. For the example, we are going to use the Detailed Gantt Chart to view the Critical Path, because this option also
shows the Slack Time of the activities that don’t belong to the critical path, therefore first we have to select the
option “More Views”
2. Then we have to select the Detail Gantt to obtain the view desired (Adjust the Gantt Chart as explained before if is
necessary)
1. We can show more information, related to the tasks, in the spreadsheet, one column that might be of general
interest is the cost, to do this first perform a Right Click on top of the spread sheet (Specifically In the titles of the
Columns), a pop-up menu should appear showing several options, chose the one that says “Insert Column”
2. Then lookup the column named “Cost” and then press the “Ok” button
Now you should see the “Cost” Column, this cots is calculated
based on the resources allocated for each Task, notice also that
the groups automatically add up the cost of the subtasks making
the view even more interesting.
1
2
Step by Step Example (Step 8 – A Better View)
As explained before, you can add and hide columns from the Spread sheet, this lets you show exactly what the people
needs to see, below is a view with selected fields: Name, Cost, Duration, Resource initials and Start Date. The reader is
welcome to experiment with this features and to explore more views that are offered by MS Project, such as resources
usage, cost reports, etc.
Step by Step Example (Step 9 –Save the File)
1. For this example we are saving the file at the end, but it is recommended that you save the file frequently while
you are working to avoid losing data as a result of problems such as a Power Failure for instance.
2. You can chose between saving the file with or without Baseline (the difference was explained before in this
Tutorial)