Pipework
Pipework
Pipework
Workbook
Domestic Pipework Workbook
Instructions:
To enable you to work your way through this workbook answering the questions provided, you will
have firstly studied the gas safety training manual Section D
Work your way through all the questions, selecting one of the answers, either a,b,c or d
a. 28 mm copper.
b. 35 mm copper.
c. 1 inch steel.
d. DN 32 rigid stainless steel.
3. What is the minimum size of copper installation pipework required to supply a 35 kWnet
combi boiler, the pipe consists of 10m of copper pipe containing ten elbows?
a. 15 mm.
b. 22 mm.
c. 28 mm.
d. 35 mm.
4. What is the expected pressure absorption in a 5 m section of ¾ inch steel pipe conveying
?
sufficient natural gas for an appliance rated at 32 kWnet
a. 0.25 mbar.
b. 0.356 mbar.
c. 0.5 mbar.
d. 0.4 mbar.
Page 2 of 6
Domestic Pipework Workbook
a. 1.5 m.
b. 2 m.
c. 2.5 m.
d. 3 m.
a. Cut and sealed as close as practical to its connection with the live pipework.
Page 3 of 6
Domestic Pipework Workbook
b. Cut and sealed close to its terminal end i.e. appliance connection.
c. Removed and taken to the re-cycling facility.
d. Labelled “LIVE GAS”.
11. When the gas meter is externally located in a surface mounted box, the main
equipotential bond connection point should be?
12. When not separated by insulating material, what is the minimum separation distance
between installation pipework and a 13 amp socket outlet?
a. 150 mm.
b. 300 mm.
c. 25 mm.
d. 75 mm.
14. When cutting a notch in a solid timber joist which is 250 mm deep to accommodate a 22
mm pipe, the notch depth should be?
a. 22 mm.
b. 31.25 mm.
c. 37.5 mm.
d. 50 mm.
15. The annular space between a pipe and sleeve passing through an external cavity wall
must be?
Page 4 of 6
Domestic Pipework Workbook
16. Installation pipework installed in a vertical duct measuring 500 mm X 350 mm requires
the duct to have vents of what minimum size fitted at top and bottom?
a. Zero.
b. 0.12 m2.
c. 0.05 m2.
d. 0.175 m2.
17. If installation pipework is to be laid on a concrete slab and covered by a screed, which
specification listed below is correct?
a. Pipe painted (with undercoat and yellow gloss) on site with a minimum of 25 mm screed
cover.
b. Pipe wrapped with PTFE tape (50% overlap) with a minimum of 50 mm screed cover.
c. Pipework MUST be copper with a minimum of 25 mm screed cover.
d. Factory sheathed pipe with a minimum of 25 mm screed cover.
a. Is not permitted.
b. Is permitted provided the pipe is rigid steel.
c. Is permitted provided the pipe is installed within a continuous pipe sleeve.
d. Is permitted provided the pipe is encased in a timber or plaster channel.
a. Is not permitted.
b. Must be a minimum of 40 mm below the mono-blocks.
c. Must have at least 40 mm cover.
d. Must have at least 375 mm cover.
a. Is not permitted.
b. Can be copper with capillary fittings.
c. Can be steel with threaded fittings.
Page 5 of 6
Domestic Pipework Workbook
Page 6 of 6
Pipework Answers:
1: C
2: B
3: C
4: B
5: A
6: D
7: A
8: D
9: B
10: A
11: D
12: C
13: B
14: B
15: C
16: C
17: D
18: D
19: D
20: C
21: A