Rencana Anggaran Pelaksanaan PTL2
Rencana Anggaran Pelaksanaan PTL2
Rencana Anggaran Pelaksanaan PTL2
CIVIL WORKS
SUMMARY
HARGA SUBKON
NO. DESCRIPTION QTY UNIT AMOUNT
(Rp.)
A MILL BUILDING - Civil & Steel Structure
- Foundations 59.00 ttk 30,190,000.00
- Steel Structure 160,667.16 Kg -
- Roofing 6,035.15 m2 -
- Cladding 3,456.00 m2 -
- Wall power house and clarification station 168.00 m2 38,998,000.00
- Floor Ceramic power house and clarification station 636.54 m2 38,192,000.00
- Jalur Tamu 426.00 m 6,390,000.00
- Wall boier station 105.40 m2 19,545,000.00
- Floor 3,907.50 m2 252,229,000.00
- Perimeter Drain --> Include Washing Process Drain 326.00 m 65,631,000.00
- Roofing Over Loading Ramp Platform → full cover 1,188.00 m2 22,119,000.00
B MACHINERY FOUNDATIONS
- FOUNDATIONS - EMPTY BUNCH CONVEYOR → Include bak sampah 1.00 ls 9,018,000.00
- FOUNDATIONS - FFB CONV AT LOADING RAMP → Include bak sampah 1.00 ls 10,269,000.00
- FOUNDATIONS - STERILISER STATION 1.00 ls 28,658,000.00
- FOUNDATIONS - TRESSHING , PRESSING , AND CLARIFICATION STATIONS 1.00 ls 109,581,000.00
- FOUNDATION EFB PRESS 1.00 ls 8,032,000.00
- FOUNDATIONS - POWER HOUSE FDT 1.00 ls 44,083,000.00
- FOUNDATIONS - DEPERICARFER AND KERNEL RECOVERY STATION 1.00 ls 40,977,000.00
- SHELL DISPOSAL YARD ( 23 M X 24 M ) 552.00 m2 110,306,000.00
- FIBER AREA (15 M x 24 M) 360.00 ls 44,422,000.00
- FOUNDATIONS - PIT FOR BOILER FUEL RYCYCLING ELEVATOR AT BOILER STATION 1.00 ls 7,798,000.00
- FOUNDATIONS - BOILER FEED WATER TREATMENT PLANT FDT AT BOILER STATION 1.00 ls 23,346,000.00
- FOUNDATIONS - BAK ABU BOILER AT BOILER AREA 1.00 ls 9,525,000.00
- FOUNDATIONS - RAW WATER TREATMENT PLANT → Include domestic tank housing 1.00 ls 61,587,000.00
- FOUNDATIONS - BLOWDOWN SILENCER , CONDENSAT PIT , HEAVY DAN WASHING PIT 1.00 ls 89,846,000.00
- FOUNDATIONS - OIL STORAGE TANK FDT 1500 T ( 2 UNIT ) 1.00 ls 194,919,000.00
- FOUNDATIONS - TECHNICAL OIL TANK 500 TON ( 1 UNIT ) 1.00 ls 52,396,000.00
- FOUNDATIONS - WEIGHBRIDGE FDT ( 2 UNIT ) Hercules ls 13,560,000.00
- FOUNDATIONS - BUNKER KERNEL SILO FDT ( 1 UNIT ) 1.00 ls 15,149,000.00
- CABLE TRENCH 1.00 ls 77,550,000.00
- SUPPORT FOR PUMP , PIPE AND CONVEYOR → Inc. pondasi mesin workshop 1.00 ls 23,054,000.00
- BOILER FOUNDATION ( DESAIN MECH ) 1.00 ls 66,915,000.00
- PERKUATAN PONDASI DENGAN STRAUSS PILE Dia 25cm 1.00 ls 34,440,000.00
C ANCILLARY BUILDINGS
- Mill Workshop & Store (Uk. 14.00 M x 26.00 M) + INCLUDE Rak Baja Siku 1.00 unit 159,745,000.00
- Weighbridge House - Roof 12 M x 13 M (Uk. 3.00 M x 4.00 M) 1.00 unit 16,170,000.00
- Oil Loading Shed (Uk. 4.0 M x 9.0 M) 1.00 unit 1,276,000.00
- Bicycle Shed (Uk. 3.0 M x 10.0 M) 1.00 unit 2,232,000.00
- Shelter SPSI ( Uk 3.0 M x 5.0 M ) 1.00 unit 1,320,000.00
HARGA SUBKON
NO. DESCRIPTION QTY UNIT AMOUNT
(Rp.)
II OUTSIDE FENCE
- Lining effluent Pond 1.00 ls 528,213,000.00
- Drain & overflow for effluent Ponds 621.00 m 101,140,000.00
- Main Drain to Discharge out 1.00 ls 60,000.00
TOTAL II 629,413,000.00
GRAND TOTAL ( I + II ) 5,736,779,000.00
NB :
1. Total Bahan Estimate 5,736,779,000.00
2. Upah Kerja All In (borongan Lumpsump) 1,400,000,000.00
3. Sewa Alat Berat 5 Bulan (all in Include Operator) 525,000,000.00
4. Mobil Mixer 3 Bulan, INCLUDE BBM 180,000,000.00
5. Overhead 5% 610,000,000.00
Page 2
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - STEEL STRUCTURE INCLUDE WORKSHOP
MILL BUILDING
- WF 300 Rafter 23,396.25 kg BY OTHERS
- WF 300 tiang 37,793.66 kg BY OTHERS
- WF 300 perkuatan rafter dan tiang 5,725.20 kg BY OTHERS
- WF 300 Bendera 1,548.74 kg BY OTHERS
- WF 300 over hang 1,156.05 kg BY OTHERS
- WF 300 canopy 1,5 m 1,266.15 kg BY OTHERS
- WF 300 canopy 2,5 m 2,064.38 kg BY OTHERS
Page 3
SUB TOTAL -
ROUNDED -
Page 4
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - ROOFING
SUB TOTAL -
ROUNDED -
2 Supply & install ceramic tiles, for flooring , 40x40 cm ex. Ikad/equiv 636.54 m² 60,000.00 38,192,292.00
SUB TOTAL 38,192,292.00
ROUNDED 38,192,000.00
Page 5
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - FLOOR
Page 6
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MILL BUILDING - ROOFING OVER PLATFORM LOADING RAMP
II PEKERJAAN PONDASI
1 Lean concrete 1:3:5 0.90 m³ 650,000.00 585,000.00
2 Cor K175 13.20 m³ 579,200.00 7,645,440.00
3 Besi Dia 12 mm 593.73 kg - -
4 Besi Dia 16 mm 325.00 kg - -
5 Besi Dia 8 mm 152.77 kg - -
6 Bekisting 54.30 m² 35,000.00 1,900,500.00
7 Pabrikasi Cover Tiang 4 mm, MS Plate 1,000.00 kg BY OTHERS
8 Cover Tiang 4 mm, MS Plate upah rol 1,000.00 kg BY OTHERS
B Tie Biem WF
1 WF 150 x 75 x 5 x 7 672.00 kg BY OTHERS
2 Plat Join, t = 12 mm (4" x 8") 41.93 kg BY OTHERS
E RAFTER
1 WF 400 x 200 x8 x 13 12,672.00 kg BY OTHERS
2 Plat Stiffner Span, t = 10mm (4" x 8") 603.33 kg BY OTHERS
3 Plat 12 mm Join Span - Tiang 160.00 kg BY OTHERS
4 Plat 8 mm untuk Pengaku Span - Tiang 70.00 kg BY OTHERS
5 Plat 12 mm Join Tiang - Over Stek 63.33 kg BY OTHERS
6 Plat 12 mm Join Span - Span 160.00 kg BY OTHERS
7 Plat 10 mm untuk Pengaku Span - Span dan kolom 26.67 kg BY OTHERS
8 Plat 8 mm untuk honeycomb dan pengaku kolom over stek 1,093.33 kg BY OTHERS
9 Plat 10 mm, untuk sambungan rafter 713.33 kg BY OTHERS
10 Plat 6 mm, 170.00 kg BY OTHERS
IV PEKERJAAN ATAP
1 CNP 150 x 50 x 20 x 2.3 5,506.20 kg BY OTHERS
2 Sagrod Ø12 mm - + mur 541.38 kg BY OTHERS
3 Ikatan Angin Ø20 mm 616.15 kg BY OTHERS
4 Plat 10 mm thk Ms Gusset, (4" x 8") 159.23 kg BY OTHERS
5 Atap Zincalumn, t = 0.45mm 1,188.00 m² BY OTHERS
6 Rabung, t = 0.45mm 27.00 m' BY OTHERS
7 Baja Siku L 40 x 40 x 4 263.08 kg BY OTHERS
8 Talang Horizontal (Seng Plat 0.4mm, Soft) 54.00 m' 50,000.00 2,700,000.00
9 Talang Vertikal (Pipa PVC 6") 108.00 m' 85,000.00 9,180,000.00
10 Ikatan Angin Ø20mm - 3200mm, untuk pengikat kolom - kolom 346.15 kg BY OTHERS
11 Besi Beton dia 12, untuk sokong pipa 150.00 kg BY OTHERS
BAK SAMPAH
1 Excavation 1.35 m³ - -
2 Removal surplus soil 1.35 m³ - -
3 Formwork 10.00 m² 35,000.00 350,000.00
4 Concrete 1:2:3 K 175- batu pecah 2.65 m³ 579,200.00 1,534,880.00
5 Wiremesh M6 36.80 m² - -
SUB TOTAL 9,018,238.00
ROUNDED 9,018,000.00
Page 7
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - FFB CONV AT LOADING RAMP
BAK SAMPAH ( 3M x 3 M)
1 Excavation 0.54 m³ - -
2 Removal surplus soil 0.54 m³ - -
3 Formwork 13.73 m² 35,000.00 480,375.00
4 Concrete 1:2:3 K 175- batu pecah 3.10 m³ 579,200.00 1,795,158.00
5 Besi 8mm 90.00 kg - -
6 Besi 6mm 67.50 kg - -
7 Pas Bata 1/2 batu camp 1:4 10.80 m2 60,000.00 648,000.00
8 Plesteran camp 1:4 21.60 m2 15,000.00 324,000.00
9 Wiremesh M6 2 layer 9.00 m² - -
SUB TOTAL 10,269,297.35
ROUNDED 10,269,000.00
Page 8
10 Pocket hole 60.00 nos - -
11 Plastering for concrete works 5.92 m² 15,000.00 88,754.72
P6 1.00 UNIT -
- Excavation 3.12 m³ - -
- Removal surplus soil 3.12 m³ - -
- Lean concrete 0.20 m³ 650,000.00 126,750.00
- Formwork 9.31 m² 35,000.00 325,850.00
- Concrete 1:2:3 K 175- batu pecah 3.71 m³ 579,200.00 2,145,936.00
- Fabrication & install steel bar 10mm 70.32 kg - -
- Fabrication & install steel bar 6mm 13.05 kg - -
- Pocket hole - nos - -
- Plastering for concrete works 1.96 m² 15,000.00 29,400.00
-
CLARIFICATION STATION -
C1 1.00 UNIT -
- Excavation 26.97 m³ - -
- Backfill 10.79 m³ - -
- Removal surplus soil 16.18 m³ - -
- Lean concrete 1.42 m³ 650,000.00 922,736.10
- Formwork 33.27 m² 35,000.00 1,164,452.80
- Concrete 1:2:3 K 175- batu pecah 11.62 m³ 579,200.00 6,731,148.47
- Fabrication & install steel bar 16mm 343.50 kg - -
- Fabrication & install steel bar 12mm 118.97 kg - -
Page 10
- Fabrication & install steel bar 10mm 642.11 kg - -
- Fabrication & install steel bar 8mm 45.02 kg - -
- Pocket hole 6.00 nos - -
- Plastering for concrete works 3.82 m² 15,000.00 57,318.30
-
C2 8.00 UNIT -
- Excavation 17.02 m³ - -
- Backfill 8.51 m³ - -
- Removal surplus soil 8.51 m³ - -
- Lean concrete 1.22 m³ 650,000.00 790,400.00
- Formwork 40.08 m² 35,000.00 1,402,800.00
- Concrete 1:2:3 K 175- batu pecah 9.56 m³ 579,200.00 5,539,468.80
- Fabrication & install steel bar 16mm 242.42 kg - -
- Fabrication & install steel bar 10mm 722.54 kg - -
- Fabrication & install steel bar 8mm 113.63 kg - -
- Pocket hole 16.00 nos - -
- Plastering for concrete works 2.88 m² 15,000.00 43,200.00
-
-
C3 4.00 UNIT -
- Excavation 2.11 m³ - -
- Removal surplus soil 2.11 m³ - -
- Lean concrete 0.26 m³ 650,000.00 171,600.00
- Formwork 12.80 m² 35,000.00 448,000.00
- Concrete 1:2:3 K 175- batu pecah 2.46 m³ 579,200.00 1,427,148.80
- Fabrication & install steel bar 10mm 95.68 kg - -
- Fabrication & install steel bar 6mm 18.47 kg - -
- Plastering for concrete works 2.08 m² 15,000.00 31,200.00
-
C4 4.00 UNIT -
- Excavation 4.48 m³ - -
- Backfill 1.34 m³ - -
- Removal surplus soil 3.14 m³ - -
- Lean concrete 0.32 m³ 650,000.00 208,000.00
- Formwork 10.08 m² 35,000.00 352,800.00
- Concrete 1:2:3 K 175- batu pecah 2.30 m³ 579,200.00 1,334,476.80
- Fabrication & install steel bar 10mm 99.96 kg - -
- Fabrication & install steel bar 8mm 12.63 kg - -
- Pocket hole 4.00 nos - -
- Plastering for concrete works 0.64 m² 15,000.00 9,600.00
-
C5 1.00 UNIT -
- Excavation 0.36 m³ - -
- Removal surplus soil 0.36 m³ - -
- Lean concrete 0.09 m³ 650,000.00 59,231.25
- Formwork 2.97 m² 35,000.00 103,950.00
- Concrete 1:2:3 K 175- batu pecah 1.00 m³ 579,200.00 580,575.60
- Fabrication & install steel bar 10mm 42.17 kg - -
- Plastering for concrete works 1.35 m² 15,000.00 20,250.00
-
C6 7.00 UNIT -
- Excavation 34.19 m³ - -
- Removal surplus soil 6.19 m³ - -
- Lean concrete 1.55 m³ 650,000.00 1,010,100.00
- Formwork 117.60 m² 35,000.00 4,116,000.00
- Concrete 1:2:3 K 175- batu pecah 59.67 m³ 579,200.00 34,562,949.12
- Fabrication & install steel bar 10mm 1,398.41 kg - -
- Pocket hole 70.00 nos - -
- Plastering for concrete works 42.00 m² 15,000.00 630,000.00
- Pas 1/2 bata 45.93 m2 60,000.00 2,755,800.00
- Cor 1:2:3 bt pecah + acian 2.40 m3 579,200.00 1,387,321.56
- Earthfill ( ambil dari Excavation C6 ) 28.00 m3 - -
- Sika grouting 42.00 nos - -
Page 11
TO1 1.00 Unit
- Excavation 2.28 m³ - -
- Removal surplus soil 2.28 m³ - -
- Lean concrete 0.17 m³ 650,000.00 112,510.13
- Formwork 4.29 m² 35,000.00 150,013.50
- Concrete 1:2:3 K 175- batu pecah 2.08 m³ 579,200.00 1,203,062.11
- Fabrication & install steel bar 54.10 kg - -
- Plastering for concrete works 0.66 m² 15,000.00 9,891.00
Page 12
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - POWER HOUSE FDT
FOUNDATION OF TURBINE KE 2
1 Staking & pegging 22.26 m' 1,000.00 22,260.10
2 Excavation 14.19 m³ - -
3 Removal surplus soil 14.19 m³ - -
4 Sand fill 3.35 m³ 120,000.00 401,918.45
5 lean concrete 0.40 m³ 650,000.00 256,824.75
5 Formwork 18.03 m2 35,000.00 631,218.07
6 Concrete 1:2:3 K 175- batu pecah 11.85 m³ 579,200.00 6,864,354.83
7 MS bar 13mm 484.36 kg - -
8 Pocket Hole 10.00 nos - -
9 Asphalt 0.06 m3 800,000.00 48,000.00
10 Plastering for concrete works 3.20 m2 15,000.00 48,044.71
Page 13
11 Brickwall 33.00 m2 60,000.00 1,980,000.00
12 Plastering 66.00 m2 15,000.00 990,000.00
13 Wiremesh M6 - 1 layer 14.92 m2 - -
14 Tangga
Besi Dia 16mm 7.58 kg BY OTHERS
Plat Strip 50 x 6mm 34.15 kg BY OTHERS
TOTAL 44,083,930.54
ROUNDED 44,083,000.00
Page 14
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - FIBER AREA (15 M x 24 M)
Page 15
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - BAK ABU BOILER AT BOILER AREA INCLUDE FLOOR AREA BOILER
DRAINAGE
1 Excavation 14.11 m³ - -
2 Removal surplus soil 14.11 m³ - -
3 Sand fill - m³ 120,000.00 -
4 Concrete 1:3:5 2.02 m³ 650,000.00 1,313,000.00
5 Brickwall partition 1:4, 115 mm (ordinary) 43.80 m² 60,000.00 2,628,000.00
6 Plastering for brickwall t.15 mm (1:4) 65.70 m² 15,000.00 985,500.00
7 Concrete 1:2:3 for cover and sump pit- batu pecah 0.56 m³ 579,200.00 325,800.00
Page 17
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - BLOWDOWN SILENCER , CONDENSAT PIT , HEAVY DAN WASHING PIT
DRAINAGE
1 Staking & pegging 54.80 m' 1,000.00 54,800.00
2 Excavation 13.40 m³ - -
3 Removal surplus soil 13.40 m³ - -
4 sand fill 1.55 m3 120,000.00 186,000.00
5 Concrete 1:2:3 K 175- batu pecah 2.00 m³ 579,200.00 1,158,400.00
6 Concrete 1:3:5 1.00 m3 650,000.00 650,000.00
7 Pas 1/2 bata camp 1:4 39.50 m2 60,000.00 2,370,000.00
8 Plesteran camp 1:4 39.50 m2 15,000.00 592,500.00
9 Wiremesh M6 - 1 layer 16.50 m2 - -
10 Formwork 7.50 m² 35,000.00 262,500.00
COLLECTION PIT
1 Staking & pegging 33.60 m 1,000.00 33,600.00
2 Excavation 16.52 m³ - -
3 Removal surplus soil 16.52 m³ - -
4 Sand fill 0.62 m³ 120,000.00 74,520.00
5 Formwork 61.44 m² 35,000.00 2,150,400.00
6 Concrete 1:2:3 K 175 - batu pecah 6.40 m³ 579,200.00 3,704,346.00
7 Wiremesh M6 - 1 layer untuk pit 40.84 m2 - -
8 Wiremesh M6 - 1 layer untuk selasar 2.70 m2 - -
Page 18
- Wiremesh M6- 1 layer 400.00 m² - -
- Sandfill bawah lantai 20.00 m³ 120,000.00 2,400,000.00
- Formwork floor 9.20 m² 35,000.00 322,000.00
SUB TOTAL -
ROUNDED -
SUB TOTAL -
ROUNDED -
Page 19
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : MACHINERY FOUNDATIONS - WEIGHT BRIDGE FDT ( 2 UNIT )
Page 20
SCOPE : MACHINERY FOUNDATIONS - SUPPORT FOR PUMP , PIPE AND CONVEYOR
PUMP FOUNDATION
1 Staking & pegging 42.86 m' 1,000.00 42,860.00
2 Excavation 22.10 m³ - -
3 Removal surplus soil 21.05 m³ - -
4 Formwork 52.50 m² 35,000.00 1,837,500.00
5 Concrete 1:2:3 K 175- batu pecah 10.68 m³ 579,200.00 6,186,435.20
6 MS bar 8MM 300.00 kg - -
7 Pocket Hole 12.00 nos - -
PONDASI DI WORKSHOP
a. Pondasi Mesin Bubut
b. Pondasi Mesin Bor
c. Pondasi mesin Press
d. Pondasi mesin Scrap
1 Staking & pegging 19.38 m' 1,000.00 19,382.00
2 Excavation 3.63 m³ - -
3 Removal surplus soil 3.45 m³ - -
4 Formwork 9.44 m² 35,000.00 330,330.00
Page 21
5 Concrete 1:2:3 K 175- batu pecah 2.83 m³ 579,200.00 1,637,398.40
6 MS bar 10MM 268.14 kg - -
7 Pocket Hole 25.00 nos - -
SUB TOTAL 23,054,637.60
ROUNDED 23,054,000.00
CHIMNEY
- Staking & pegging 27.20 m' 1,000.00 27,200.00
- Excavation 61.00 m³ - -
- Back Fill 15.26 m³ - -
- Removal surplus soil 45.79 m³ - -
- Lean concrete/concrete 1 : 3 : 5 1.15 m³ 650,000.00 748,800.00
- Supply and install formwork 36.47 m² 35,000.00 1,276,303.46
- Concrete K225- batu pecah 37.59 m³ 579,200.00 21,772,128.00
- MS barD16- ulir 1,537.37 kg - -
- Install Anchor Bolt Ø 1 1/4 x 1500 mm 20.00 nos - -
- Grouting 20.00 nos - -
ID FAN
- Staking & pegging 12.64 m' 1,000.00 12,640.00
- Excavation 12.50 m³ - -
- Removal surplus soil 12.50 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.68 m³ 650,000.00 442,000.00
- Supply and install formwork 13.50 m² 35,000.00 472,500.00
- Concrete K225- batu pecah 12.24 m³ 579,200.00 7,089,408.00
- MS bar Ø 16 mm - Ulir 650.00 kg - -
- Pocket hole 13.00 nos - -
- Grouting pocket 14.00 nos - -
PONDASI FD FAN
- Staking & pegging 7.48 m' 1,000.00 7,479.00
- Excavation 0.75 m³ - -
- Removal surplus soil 0.75 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.07 m³ 650,000.00 45,500.00
- Supply and install formwork 2.88 m² 35,000.00 100,800.00
- Concrete K225- batu pecah 0.84 m³ 579,200.00 486,528.00
- MS bar Ø 16 mm 120.00 kg - -
Pocket hole 4.00 nos - -
- Grouting pocket 4.00 nos - -
BLOWDOWN PIT
- Staking & pegging 6.00 m' 1,000.00 6,000.00
- Excavation 1.70 m³ - -
- Removal surplus soil 1.70 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.10 m³ 650,000.00 65,000.00
- Supply and install formwork 10.50 m² 35,000.00 367,500.00
- Concrete K225- batu pecah 0.90 m³ 579,200.00 521,280.00
- MS bar Ø 10 mm - Polos 130.00 kg - -
Page 22
- Staking & pegging 15.00 m' 1,000.00 15,000.00
- Excavation 1.35 m³ - -
- Back Fill 0.40 m³ - -
- Removal surplus soil 0.95 m³ - -
- Lean concrete/concrete 1 : 3 : 5 0.13 m³ 650,000.00 83,200.00
- Supply and install formwork 7.90 m² 35,000.00 276,500.00
- Concrete K225- batu pecah 1.15 m³ 579,200.00 667,238.40
- MS bar Ø 10 mm - Polos 35.00 kg - -
- MS bar Ø 6 mm - Polos 20.00 kg - -
-
Page 23
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - PERKUATAN DENGAN STROUSS PILE
1 BUILDING FOUNDATION
- Strauss pile f 25 cm -5 M 7.00 Nos 70,000.00 490,000.00
- Strauss pile f 25 cm -3 M 52.00 Nos 70,000.00 3,640,000.00
2 MACHINARY FOUNDATION
FOUNDATIONS - EMPTY BUNCH CONVEYOR
- Strauss pile f 25 cm -2 M (EP1) 15.00 Nos 70,000.00 1,050,000.00
12 ANCILLARY BUILDING
a. Workshop
- Strauss pile f 25 cm -3 M 19.00 Nos 70,000.00 1,330,000.00
b. Loading Shed
- Strauss pile f 25 cm -2 M 4.00 Nos 70,000.00 280,000.00
c. Rumah Jembatan Timbang
- Strauss pile f 25 cm -2 M 4.00 Nos 70,000.00 280,000.00
Page 24
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : ANCHILLARY BUILDING - MILL WORKSHOP AND STORE
Page 25
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : ANCHILLARY BUILDING - WEIGHBRIDGE HOUSE Ukuran 3 x 4 M (bangunan) / 13,2 M x 14,2 M (Atap)
Jendela kaca mati 3 lobang aluminium ex. Alexindo/Damai Abadi ukuran sesuai gambar
- 2@115x105+ ventilasi 2 @115x40 cm + 1@120x105 cm ventilasi kaca mati 40x115 cm 2.00 unit 750,000.00 1,500,000.00
+accessories (lihat gambar) J2
Page 26
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : ANCHILLARY BUILDING - OIL LOADING SHED Ukuran 4M x 9 M
Page 27
Pipa 3" 37.86 kg BY OTHERS
Plat 12mm 12.72 kg BY OTHERS
Plat 6mm 6.36 kg BY OTHERS
Plat 8mm 2.50 kg BY OTHERS
CNP125 108.00 kg BY OTHERS
Sagrot 12mm 7.46 kg BY OTHERS
Tali anging 16mm 14.21 kg BY OTHERS
11 Anchor bolt D16 - 600 8.00 nos -
12 Roofing installation 21.93 m² BY OTHERS
TEMPAT DUDUK
1 Pas 1/2 batu camp 1:4 1.08 m2 60,000.00 64,800.00
2 Plesteran bata/ batako camp 1:4 2.16 m2 15,000.00 32,400.00
3 Cor 1:2:3 ( kerikil ) 7cm 0.14 m3 650,000.00 91,455.00
4 Wiremesh M6 - 1 layer 2.01 m2 - -
5 Formwork 2.56 m2 35,000.00 89,705.00
TYPE A1
- Staking & pegging 6.00 m' 1,000.00 6,000.00
- Excavation 1.44 m³ - -
- Removal surplus soil 1.44 m³ - -
- Cor 1:3:5 0.58 m³ 650,000.00 374,400.00
- Formwork 4.32 m² 35,000.00 151,200.00
- TYPE B
- Staking & pegging 151.00 m' 1,000.00 151,000.00
- Excavation 52.85 m³ - -
- Removal surplus soil 52.85 m³ - -
- Cor 1:3:5 19.93 m³ 650,000.00 12,955,800.00
- Formwork 169.12 m² 35,000.00 5,919,200.00
TYPE B1
- Staking & pegging 48.00 m' 1,000.00 48,000.00
- Excavation 16.80 m³ - -
- Removal surplus soil 16.80 m³ - -
- Cor 1:3:5 5.18 m³ 650,000.00 3,369,600.00
- Formwork 39.36 m² 35,000.00 1,377,600.00
TYPE D
- Staking & pegging 812.28 m' 1,000.00 812,278.49
- Excavation 365.53 m³ - -
- Removal surplus soil 365.53 m³ - -
- Cor 1:3:5 100.17 m³ 650,000.00 65,111,250.67
Beton K175 batu pecah 4.81 m³ 579,200.00 2,786,653.78
- Formwork 998.73 m² 35,000.00 34,955,709.30
- Rebar 8mm dan 6 mm 419.66 kg - -
TYPE E
- Staking & pegging 198.00 m' 1,000.00 198,000.00
- Excavation 170.28 m³ - -
- Removal surplus soil 170.28 m³ - -
- Beton K175 batu pecah 42.73 m³ 579,200.00 24,748,289.28
- Formwork 429.00 m² 35,000.00 15,015,000.00
- Rebar 8mm dan 6 mm 190.08 kg - -
- Wiremesh 534.60 m² - -
TYPE F
- Staking & pegging 30.00 m' 1,000.00 30,000.00
- Excavation 30.00 m³ - -
- Removal surplus soil 30.00 m³ - -
- Beton K175 batu pecah 8.37 m³ 579,200.00 4,847,904.00
Page 28
- Formwork 77.50 m² 35,000.00 2,712,500.00
- Rebar 8mm dan 6 mm 36.00 kg - -
- Wiremesh 87.00 m² - -
TYPE G DAN G1
- Staking & pegging 52.00 m' 1,000.00 52,000.00
- Excavation 42.12 m³ - -
- Removal surplus soil 42.12 m³ - -
- Concrete 1:2:3- batu pecah 13.06 m³ 579,200.00 7,565,742.08
- Formwork 261.25 m² 35,000.00 9,143,680.00
- Rebar 8MM 687.19 kg - -
Page 29
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS - IPAL DOMESTIC
-
SUB TOTAL ( 1 UNIT) 163,792,209.56
ROUNDED 163,792,000.00
Page 30
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS -GATE AND FENCING
2. Personal Gate
- MS Pipe 2" 38.76 kg BY OTHERS
- Plate 2mm 10.70 kg BY OTHERS
- L 40.40.4 26.14 kg BY OTHERS
- Gerendel/kunci 1.00 bh 150,000.00 150,000.00
- Barbed wire 2,721.60 m' 25,000.00 68,040,000.00
- Sign board/name board 1.00 ls 20,000,000.00 20,000,000.00
SUB TOTAL 300,892,080.00
ROUNDED 300,892,000.00
Page 31
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : INSIDE FENCE - OTHER CIVIL WORKS -FRUIT LOADING RAMP
E SLAB / FLOOR
1 Staking & pegging 144.00 m' 1,000.00 144,000.00
2 Laterit/Sirtu fill t. 20 cm + compacted 243.40 m³ 560,000.00 136,304,000.00
3 Construct concrete K-225 for floor t. 20 cm 243.40 m³ 579,200.00 140,977,280.00
4 Supply and install formwork 18.99 m² 35,000.00 664,482.00
5 Install wiremesh m-6 (2 layers) 1,217.00 m² - -
6 Pipa PVC 6" AW 72.00 m 120,000.00 8,640,000.00
7 Curb menuju loading ramp
- Construct concrete 1:2:3 -batu pecah 34.00 m³ 579,200.00 19,692,800.00
- Fabrications and install steel bar 10mm 1,726.20 kg - -
- Supply and install formwork 110.00 m² 35,000.00 3,850,000.00
G TANGGA
1 Wiremesh 60.00 m2 - -
2 Supply and install formwork 45.00 m² 35,000.00 1,575,000.00
3 Construct concrete 1:2:3 for stair & foundation- batu pecah 4.00 m3 579,200.00 2,316,800.00
4 Railing, pipa dia 2" 35.00 m BY OTHERS
5 Tanah timbun dipadatkan 12.00 m3 - -
Page 32
3 Concrete 1:2:3 K 175- batu pecah t. 12 cm + ACIAN 75.00 m³ 579,200.00 43,440,000.00
4 Install Wiremesh M6 ( 1 layer) 625.00 m² - -
Page 33
5 Formwork 37.50 m² 35,000.00 1,312,500.00
SUB TOTAL 44,752,500.00
ROUNDED 44,752,000.00
Page 34
RENCANA ANGGARAN PELAKSANAAN (RAP)
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
SCOPE : OUTSIDE FENCE - -EFFLUENT TREATMENT PLANT -MAIN DRAIN TO DISCHARGE OUT
Page 35
HARGA SATUAN BAHAN
60 TONNES FFB / HR PALM OIL MILL
PT. PERMATA TIMUR LESTARI 2
DESA BANGKAL, KEC. SERUYAN RAYA, KAB. SERUYAN, PROV. KALIMANTAN TENGAH
5,736,779,000.00
RATE BAHAN YANG DISUPPLY OLEH PT THB
No DESCRIPTION Volume Unit
Rp.
A BANGUNAN MILL DAN PONDASI MESIN
- Staking & pegging 1.00 m 1,000.00
- Trimming 1.00 m² 1,000.00
- Excavation 1.00 m³ Include Sewa alat berat
- Bakcfill+ compacted 1.00 m³ Include Sewa alat berat
- Removal surplus soil 1.00 m³ Include Sewa alat berat
- Compacted sand /sand fill 1.00 m³ 120,000.00 Include Borong Mandor
- Laterit / Sirtu fill + compacted 1.00 m³ 560,000.00
- Grouting flat, ±2cm thk, "SIKA" 1.00 lot Sika Grout, Include Borong Mandor
- Inctall anchor bolt 1.00 nos Anchor,Include Borong Mandor
- Install anchor bolt 7/8" - 400 atau untuk pondasi mesin lainnya 1.00 nos Anchor,Include Borong Mandor
- Lean concrete/concrete 1:3:5 1.00 m³ 650,000.00 Semen,Include Borong Mandor
- Concrete K175 Foundations & Road (Batu Kerikil) 1.00 m³ 579,200.00 Semen
- Concrete K175 Foundations & Road (Batu Pecah) 1.00 m³ 579,200.00 Semen
- Concrete K175 for slab & floor + acian (Batu Kerikil) 1.00 m³ 579,200.00 Semen
- Concrete K175 for slab & floor + acian (Batu Pecah) 1.00 m³ 579,200.00 Semen
- Concrete K225 batu pecah (untuk L. ramp & Boiler) 1.00 m³ 579,200.00 Semen
- Fabrications and install steel bar 1.00 kg Besi beton dan kawat beton
- Supply and install formwork for foundation 1.00 m² 35,000.00
- Supply and install formwork for drainage 1.00 m² 35,000.00
- Supply and install formwork for road 1.00 m² 35,000.00
- Install pocket hole 1.00 nos
- Strauss pile dia 250 mm x 1000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Strauss pile dia 250 mm x 2000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Strauss pile dia 250 mm x 3000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Strauss pile dia 250 mm x 4000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Strauss pile dia 250 mm x 5000 mm 1.00 nos 70,000.00 Semen, besi , kawat beton
- Pecah kepala MINI pile 1.00 nos
- Install & supply wiremesh 1 layer M6 1.00 m² Wiremesh dan kawat beton
- Install wiremesh m-6 (2 layers) 1.00 m² Wiremesh dan kawat beton
- Wiremesh M8 + Frame 1.00 m² Wiremesh dan cat baja
- Expanded mesh 1.2x2.4m 1.00 m² Expanded mesh dan cat baja
- Brickwall partition 1:4, 115 mm for ordinary works 1.00 m² 60,000.00 Semen
- Brickwall partition 1:4, 115 mm for ordinary works 1.00 m² 60,000.00 Semen
- Brickwall 3 m high 230 mm, fibre storage include cover column WF 1.00 m² 60,000.00
Semen
- Plastering for brickwall t.15 mm (1:4) 1.00 m² 15,000.00 Semen
- Plastering for concrete work 1.00 m² 15,000.00 Semen
- Aspalt sand mix 1.00 m³ 800,000.00
- Ventilation Block/Hollow block (batu kerawang) 1.00 m² 60,000.00 Semen
- Painting for door & fascia: enamel paint, Bee Brand 1.00 m² 12,000.00
- Painting for wall : emulsion paint, ex Vinilex 1.00 m² 12,000.00
- Ceiling triplex t. 6 mm + frame / Gypsum 9mm 1.00 m² 75,000.00
- Cable installation 1.00 nos 120,000.00
- Supply & install lamp LED 18 W Ex Hannocs/Philips 1.00 nos 50,000.00
- Supply & install lamp LED 12 W Ex. Hannocs/Philips 1.00 nos 50,000.00
- Supply & install lamp LED 9 W 1.00 nos 50,000.00
- Supply & install switch and outlet 1.00 nos 30,000.00
- Fabrications and install steel structure
- WF 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- WF 400 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- H. Beam 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- UNP 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Besi CNP 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Besi Siku 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Plate 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Plate Strip 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Pipa Besi Hitam 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Besi Round Bar 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Instal Plat + tekuk 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
Upah Roll Plate 1.00 kg BY OTHERS Baja , Cat baja , Tbuckledan baut
- Railing (pipe dia 1 1/2" & 1 1/4") + painting 1.00 m BY OTHERS Baja , Cat baja , Tbuckledan baut
- Railing stair 1.00 m BY OTHERS Baja , Cat baja , Tbuckledan baut
- Drain dia 50mm PVC+ plam fibre 1.00 unit 20,000.00
- Install roofing ( aluzinc t.0,45 mm) ( incld biaya potong seng ) 1.00 m² BY OTHERS Seng dan paku seng
- Install cladding (aluzinc t.0,35 mm) ( incld biaya potong seng ) 1.00 m² BY OTHERS Seng dan paku seng
- Install cladding TRANSPARANT 2MM ( incld biaya potong seng ) 1.00 M2 BY OTHERS Seng dan paku seng
- Install Ridge capping 0.45mm ( incld biaya potong seng ) 1.00 m BY OTHERS Seng dan paku seng
- Install Ridge capping 0.3mm ( incld biaya potong seng ) 1.00 m BY OTHERS Seng dan paku seng
- Install flashing ( incld biaya potong seng ) 1.00 m BY OTHERS Seng dan paku seng
- Install gutter horizontal 1.00 m BY OTHERS Seng plat
- Pekerjaan talang- PVC pipe for gutter vertical, pipa 8" AW 1.00 m BY OTHERS
Pekerjaan talang- PVC pipe for gutter vertical, pipa 4" AW 1.00 m BY OTHERS
- Pasangan batu kali lining cooling pond 1.00 m² 185,000.00 Semen
- Pipa PVC AW -cross jalan dia 4" 1.00 m 85,000.00
Pipa PVC AW -Slba l. ramp dia 6" 1.00 m 120,000.00
B ANCHILLARY
Pekerjaan Umum
- Supply & install ceramic tiles for flooring ex. Ikad/ Mulia ukuran 40x40 cm 1.00 m² 60,000.00
semen
- Supply & install ceramic tiles for wall ex. Ikad/ Mulia 1.00 m² 60,000.00 semen
- Supply & install ceramic plinth for flooring ex. Ikad/ Mulia 1.00 m 60,000.00 semen
- Supply & install ceramic tiles for bath room ex. Ikad/ Mulia 1.00 m² 60,000.00 semen
- Supply & install ceramic tiles for kitchen 1.00 m² 60,000.00 semen
- Supply & install ceramic tiles for laboratorium's table 1.00 m² 60,000.00 semen
- Supply & install fix wood trim K3 1.00 m 7,000.00
- Fascia /listplank kayu+cat minyak 1.00 m 12,000.00
- Rangka baja ringan untuk office 1.00 m² 75,000.00
2 Weighbridge House
Lain-lain
- Talang horizontal seng plate 0,4 mm 1.00 m 50,000.00 Seng plat
- Talang vertical PVC 6"/8" + accessories 1.00 m 85,000.00
- Jalur tamu 1.00 m 15,000.00 Semen
- earthfill + compacted 1.00 m3
- Gali , Buang tanah, dan merapikan tanah buangan 1.00 m3
- Air bersih pipa PVC 1/2" (3 Titik) 1.00 LOT 300,000.00
- Triplek 9mm Rak workshop 1.00 m2 85,000.00
- Meja cor , beton 1:2:3 + Wiremesh 1.00 ls 500,000.00
- MCB 1.00 unit 75,000.00
- AC 2 PK 1.00 nos 6,500,000.00
VOLUME BASE
Kg Unit Price Rp/m3 Rp/Kg/Ltr
K-175 A B C D AXD
Pasir 692 875,000.00 175000 125 86,500.00
Split 1039 3,750,000.00 750000 535.7143 556,607.14
Semen 384 0.00 0 0.00
Air 215 1,200,000.00 150 32,250.00
Total 675,357.14
TOTAL (B) 675,357.14
TONASE BASE
beton 1700000
semen 720000
Selisih 980000
Split 700000
Pasir 175000
875000
Beton
K175