MasterEmaco® S 346
applying MasterEmaco S 346 ensure all water is ESTIMATING DATA
removed from formwork prior to installation and
formwork is resealed. MasterEmaco S 346 should Each bag of MasterEmaco S 346 when mixed
be pumped or poured into the prepared formwork with 3.5L of water yields 12.5L.
until the void is filled. Pumping is recommended for PACKAGING
larger pours. Do not vibrate MasterEmaco S 346 MasterEmaco S 346 is available in 25kg bags.
as it could lead to segregation.
SHELF LIFE
The formwork should be removed after 1-3 days
and a curing compound applied. If subsequent MasterEmaco S 346 has a shelf life of 6 months.
coats are to be applied the use of clear polythene Store out of direct sunlight, clear of the ground on
is recommended for the first three days after pallets protected from rainfall.
removal of formwork. For repairs beyond 80m m PRECAUTIONS
to 100mm in thickness, extend MasterEmaco S
346 with up to 25kg of 5-12mm sized washed, It is highly recommended to use necessary PPE
saturated surface-dry (SSD), graded low (Gloves, mask etc.,) during installation of the
absorption, high density aggregates. Please product. In case of Incidents of direct inhalation,
consult your local Master Builders Solutions causing dizziness/giddiness, loss of
consciousness, contact with eyes etc, seek
representative for advice.
immediate medical advice. The requirements may
vary depending on the application areas. Please
ensure to have proper ventilation while working in
Protective coatings confined areas. Contact Master Builders Solutions
Subsequent coatings of MasterProtect anti- representative in case you need further details or
carbonation barriers or silane impregnations refer to the material safety datasheet of the
should be applied as recommend on the individual product to know more.
datasheets.
CURING
MasterEmaco S 346/01/0313
MasterEmaco S 346 should be cured after
formwork removal by MasterKure 181
The technical information and application advice given in this Master Builders Solutions publication are based on the
STATEMENT OF present state of our best scientific and practical knowledge. As the information herein is of a general nature, no
RESPONSIBILITY assumption can be made as to a product's suitability for a particular use or application and no warranty as to its
(Disclaimer) accuracy, reliability or completeness either expressed or implied is given other than those required by law. The user
is responsible for checking the suitability of products for their intended use.
Field service where provided does not constitute supervisory responsibility. Suggestions made by Master Builders
NOTE Solutions either orally or in writing may be followed, modified or rejected by the owner, engineer or contractor since
they, and not Master Builders Solutions, are responsible for carrying out procedures appropriate to a specific
application.